CODE
(Hour)
PAGE(S)
until 02:00 PM local time 05 Jun 2020
X
A X B X C
D
EX
X G F 78 - 90
91 - 101 H 102 - 109 lucille.r.smith@usace.army.mil
RATING PAGE OF PAGES
7. ISSUED BY
(Date)
IMPORTANT - Award will be made on this Form, or on Standard Form 26, or by other authorized official written notice.
Previous Edition is Unusable 33-134 STANDARD FORM 33 (REV. 9-97)
Prescribed by GSA FAR (48 CFR) 53.214(c)
1 109
(If other than Item 7)
15A. NAME 16. NAME AND TITLE OF PERSON AUTHORIZED TO
AND
ADDRESS
SIGN OFFER (Type or print)
OF
OFFEROR
AMENDMENT NO. DATE
15B. TELEPHONE NO (Include area code) 17. SIGNATURE15C. CHECK IF REMITTANCE ADDRESS
IS DIFFERENT FROM ABOVE - ENTER
SUCH ADDRESS IN SCHEDULE.
18. OFFER DATE
1. THIS CONTRACT IS A RATED ORDER
UNDER DPAS (15 CFR 700)
2. CONTRACT NO.
W912HY 8. ADDRESS OFFER TO
See Item 7
9. Sealed offers in original and 0 copies for furnishing the supplies or services in the Schedule will be received at the place specified in Item 8, or if handcarried, in the depository located in
CAUTION - LATE Submissions, Modifications, and Withdrawals: See Section L, Provision No. 52.214-7 or 52.215-1. All offers are subject to all terms and
Electronic Proposals Only conditions contained in this solicitation.
10. FOR INFORMATION
CALL:
A. NAME (NO COLLECT CALLS)
LUCILLE R SMITH 409 766 3845
11. TABLE OF CONTENTS
SOLICITATION/ CONTRACT FORM
SUPPLIES OR SERVICES AND PRICES/ COSTS
2 - 6
X I CONTRACT CLAUSES
DESCRIPTION/ SPECS./ WORK STATEMENT X
PACKAGING AND MARKING
7 - 28 J LIST OF ATTACHMENTS
INSPECTION AND ACCEPTANCE
DELIVERIES OR PERFORMANCE
30 - 31 X K
REPRESENTATIONS, CERTIFICATIONS AND
OTHER STATEMENTS OF OFFERORS
CONTRACT ADMINISTRATION DATA 32 - 36 X
SPECIAL CONTRACT REQUIREMENTS
OFFER (Must be fully completed by offeror) X M
L INSTRS., CONDS., AND NOTICES TO OFFERORS
EVALUATION FACTORS FOR AWARD
NOTE: Item 12 does not apply if the solicitation includes the provisions at 52.214-16, Minimum Bid Acceptance Period.
is inserted by the offeror) from the date for receipt of offers specified above, to furnish any or all items upon which prices are offered at the price set opposite each item, delivered at the designated point(s), within the time specified in the schedule.
13. DISCOUNT FOR PROMPT PAYMENT
(See Section I, Clause No. 52.232-8)
14. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments
AMENDMENT NO. DATE
to the SOLICITATION for offerors and related documents numbered and dated):
FACILITY
12. In compliance with the above, the undersigned agrees, if this offer is accepted within calendar days (60 calendar days unless a different period
SOLICITATION, OFFER AND AWARD
X
(X) SEC. DESCRIPTION (X) SEC. DESCRIPTION PAGE(S)
PART I - THE SCHEDULE
26. NAME OF CONTRACTING OFFICER (Type or print) 27. UNITED STATES OF AMERICA 28. AWARD DATE
EMAIL:TEL: (Signature of Contracting Officer)
CODE CODE
B. TELEPHONE (Include area code) C. E-MAIL ADDRESS
AWARD (To be completed by Government)
19. ACCEPTED AS TO ITEMS NUMBERED 20. AMOUNT 21. ACCOUNTING AND APPROPRIATION
22. AUTHORITY FOR USING OTHER THAN FULL AND OPEN COMPETITION:
10 U.S.C. 2304(c)( ) 41 U.S.C. 253(c)( ) (4 copies unless otherwise specified)
23. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM
24. ADMINISTERED BY (If other than Item 7) CODE 25. PAYMENT WILL BE MADE BY CODE
PART IV - REPRESENTATIONS AND INSTRUCTIONS
PART III - LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS
37 - 51
PART II - CONTRACT CLAUSES
USAED, GALVESTON
CONTRACTING DIVISION
2000 FORT POINT ROAD
GALVESTON TX 77553-1229 409 766 3845
FAX:
TEL:
FAX:
TEL:
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
SOLICITATION
52- 73
6. REQUISITION/PURCHASE NO.5. DATE ISSUED
21 Apr 2020
4. TYPE OF SOLICITATION
SEALED BID (IFB)
NEGOTIATED (RFP)
[ X ]
3. SOLICITATION NO.
W912HY20R0008
RFP No. W912HY20R0008
Section B - Supplies or Services and Prices
PRICING SCHEDULE
Indefinite Delivery Contract (IDC) Multiple Award Task Order Contract (MATOC)
Geotechnical Field Exploration and Laboratory Testing Services of the U.S. Army Corps of Engineers, Galveston District and the Southwestern Division
1. This contract is an unrestricted MATOC with a Small Business (SB) reserve for professional geotechnical services for field exploration, core drilling, soil sampling and laboratory testing projects within the boundaries of Galveston District and the Southwestern Division, executed through Solicitation No. W912HY-20-R-0008. The collective ceiling for this contract is $20,000,000. The minimum guaranteed amount for this contract is $2,500.
There is no minimum guaranteed amount for any subsequent option period.
Requirements under $100,000 will be reserved for the small businesses, with the exception of the following:
The requirements are so complex that only the unrestricted firms would be able to successfully complete the requirement;
The small businesses will not be able to meet the self-performance requirements due to the limits of small business subcontracting; and
The small business reserve is currently under contract and is unable to take on additional work.
2. The Contract Line Item Number structure shall be established at the Task Order level. Pricing of Task Orders shall be pursuant to the instructions and limitations in accordance with FAR Clause 52.216-19, Order Limitation.
The Contractor shall complete the Rate Schedule in Table 3 for the 3-year Base Period, and the 2-year Option Period. The rates must be provided for each item of the Base and Option Periods. Failure to provide a rate for line items will result in the Offeror’s proposal being deemed ineligible for further consideration for contract award.
These rates will apply to the prime contractor and all teaming subcontractors. A list of all teaming subcontractors must be submitted with the proposal (Factor 1).
3. All costs associated with travel shall be in accordance with the Joint Travel Regulations (JTR).
4. The Period of Performance for the contract’s Base Period will be 3 years from the date of contract award. In addition, there will be one (1) 2-year Option Period, not guaranteed, exercised at the Government’s discretion.
FAR Clause 52.217-9, Option to Extend the Term of the Contract, will be the authority to exercise the 2-year Option Period at the Government’s discretion and would be accomplished via contract modification no later than midnight of the last day of the IDC’s 3-year Base Period.
FAR Clause 52.217-8, Option to Extend Services, will be the authority to extend the IDC’s period of Performance an additional 6 months beyond the 2-year Option Period, if necessary. In accordance with this contract clause, the rates during this 6-month extension period would be the “existing rates”, which would be those identified in Option Period 1, Year 5 and no escalation will be applied.
5. This is a firm-fixed price type contract for geotechnical services specified in Section C, Performance Work Statement, which may be required during the contract period. The Government is setting forth its anticipated requirements and its obligation under this contract. If the Government has any requirements for the type of work described in Section C, Performance Work Statement, during the contract period, the Government will procure said services on Task Orders under this IDC contract on a per requirement basis. Task Order request for proposals will generally be evaluated using Lowest Price Technically Acceptable (LPTA).
RFP No. W912HY20R0008
6. Ordering. Services will be ordered by the Government in accordance with Contract Clause 52.216-18 – Ordering.
All services shall be charged at the unit prices, or lower, set forth in this Section B, Pricing Schedule.
In addition to DFARS Clause 252.216-7006, Ordering, the following will also apply:
(a) Services for each task order will be requested either verbally or in writing. A letter request for proposal will be issued by the Contracting Officer (KO). Oral or telecommunications requests will be issued only by the KO.
(b) The Government request for proposal will delineate (1) Performance Work Statement, (2) Location of Work, (3) Character and Extent of Services, (4) Technical Requirements in addition to those already contained in Section C of this basic contract, (5) Time period(s) within which the work must be performed and (6) Method to be used for evaluation of proposals received.
(c) The Contractor will prepare a proposal to perform the work, and submit their proposal in writing to the KO within the time specified. Verbal proposals, when so requested and authorized, will be directed only to the KO.
Itemized cost proposals will strictly correspond to the units contained in Section B of this contract.
(d) Each task order will include:
(1) Performance Work Statement with type(s) of service(s) to be performed.
(2) Specific Deliverables.
(3) A Period of Performance.
(4) Existing site conditions, survey control, and other available data.
(5) A fair and reasonable price to perform the work.
7. The Contractor will not accept instructions issued by any person employed by the U.S. Government or otherwise, other than the Contracting Officer or the Authorized Representative of the Contracting Officer acting within the limits of his authority.
8. The Contractor’s Project Manager Key Personnel will be responsible for ensuring successful performance during the course of this contract and function as the key liaisons between contract forces and the KO and COR. These designations with their express authorities shall be submitted in writing to the KO and COR within 5 calendar days of contract award.
9. Accounting and appropriation data will be established at the time of award for each task order. At no point will the capacity used for both military and Interagency and International Services (IIS) exceed more than $10,000,000 of the total capacity of this IDC.
10. Payments will be made on the Contractor’s estimate of work accomplished upon submission of Engineer Form 93, “Payment Estimate-Contract Performance.” No partial payment will be made for task orders of less than 30 calendar day’s duration. Each task order will include payment information.
11. Table 1 – Annual Escalation Rates, Table 2 – Contractor Pre-Established Markups, and Table 3 – Key Personnel must be completed and submitted with the proposal. Rates will be binding for all task orders executed within that year. Rates will not be renegotiated during their periods.
Table 1 – Annual Escalation Rates
Base Period Year 1
Base Period Year 2
Base Period Year 3
Option Period 1 Year 4
Option Period 1 Year 5
Annual Escalation – Labor
NA % % % %
Annual Escalation – Other
NA % % % %
Table 2 – Contractor Pre-Established Markups
Markup Item Markup Rate (%) G&A on Other Direct Costs (ODCs) _____________ % Subcontractor Markup (if applicable) _____________ %
NOTE: Other Direct Costs and Subcontractor costs shall be determined on a task order basis, plus the prime contractor’s pre-established markups identified in Table 2.
Any additional ODCs not included in Table 2, will be determined on a Task Order basis.
Subcontractor Markup is a fixed percentage that is lower than the Prime’s negotiated profit and applied by the Prime on a Task order basis to subcontracted costs. Neither the prime’s profit nor G&A is included in this percentage. The Prime’s profit will be determined on a Task Order basis and applied only to costs incurred by the Prime. The profit shall not be applied to subcontracted costs in addition to the Subcontractor markup.
Table 3 – Key Personnel
ITE
M
DESCRIPTION
U/I
Base Period Year 1
Base Period Year 2
Base Period Year 3
Option Period
Year 4
Optio n
Period
Year 5
Labor – Fully Burdened, Without Profit
0001 Principal HR $ $ $ $ $
Project/Task Order Manager
HR $ $ $ $ $
Sr. Geotechnical Engineer
(PE)
HR $ $ $ $ $
Staff Geotechnical Engineer
HR $ $ $ $ $
Professional Sr. Geologist
(PG)
HR $ $ $ $ $
0006 Staff Geologist HR $ $ $ $ $
0007 Engineering Technician HR $ $ $ $ $
0008 CADD/gINT Technician HR $ $ $ $ $
0009 Clerical HR $ $ $ $ $
Survey Crew (including
RPLS)
DA $ $ $ $ $
NOTE: For each line item in Table 3, the offeror shall annotate whether the personnel provided is Prime or Subcontractor by entering “(SUB)” after the CLIN description. There should be only one rate per labor discipline, including those provided by subcontractors. The offeror may not have all capabilities.
The labor discipline categories in Table 3 are the Government’s anticipated categories to be used over the life of the contract. All offerors must include and price all of these labor discipline categories whether through the use of the Prime or through subcontractors.
12. Department of Labor Wage Rates. For individual task orders written against the contract, the appropriate Department of Labor Wage Determination will be provided.
13. If during the Contract Period of Performance, the Contractor’s original subcontractor is no longer available to the Prime, the Prime shall find a subcontractor that has at a minimum, the same capabilities and qualifications as the previous subcontractor and shall submit a substitution request to the Contracting Officer for approval. The Prime shall be responsible for negotiating the rates for the work items that have been provided in its proposal. The rates provided in Table 3 are the maximum that will be paid by the Government for any replacement subcontractor.
14. This Section B Pricing Schedule (Tables 1, 2, and 3) are only one part of the contents of the required Cost/Price Proposal. The complete Pricing Schedule for the sample task order must also be submitted in the proposal.
15. Subcontractors. “Team Subcontractors” are subcontractors that the Prime used in their proposal to the Government to qualify for this contract. The subcontractors included in Table 3 – Key Personnel will be considered “Team Subcontractors.”
16. All Other Direct Costs (ODCs) that may vary, including but not limited to, reproduction, mailing, mobilization, equipment, level of effort, etc. will be determined as required, on each Task Order and not pre-priced or listed on the Pricing Schedule. The Contractor will be allowed to apply indirect cost rates as proposed (the multiplier identified as appropriate to ODCs and consistent with the accounting system), and profit on each Task Order to equipment, testing, material, and supply costs.
17. Per Diem (lodging and MI & E expenses) shall be paid at the current Government rates in accordance with the Joint Travel Regulation (JTR) per person per calendar day spent in travel status. No per diem will be paid for travel less than the number of hours per day stated in the current JTR. Per Diem rate information may be obtained at https://secureapp2.hqda.pentagon.mil/perdiem/. Actual cost of transportation by public conveyance (plane, limited to coach class) shall be paid. Privately owned vehicles shall be paid at the current Government mileage rate in accordance with the JTR. If required by a Task Order under this contract, cost for travel, lodging, meals, vehicle rental, and mileage are allowable subject to the limitations of FAR 31.205-46. These costs will be negotiated on each Task Order. The contractor is not allowed to apply indirect costs (G&A) to travel costs.
18. Any services or other direct costs for the prime or subcontractors that are needed during the life of the contract, but were not included in the Pricing Schedule, will be negotiated on the Task Order and may be added by modification to the contract as necessary. However, the fully burdened line items entered on the Pricing Schedule and, thereby, proposed by the Contractor will be the contract’s binding rates and prices for the periods for which they are proposed (Base and Option periods) and will not be renegotiated during those periods.
19. Allowable markups on a Task Order basis:
Profit will be allowable on:
(a) Total fully burdened labor cost
(b) Other Direct Costs (ODCs)
ODC Markup – This percentage is the Prime’s Overhead (OH) or G&A
20. Non-allowable markups on a Task Order basis:
Profit cannot be applied to travel costs.
Profit cannot be applied to subcontractor costs. The subcontractor markup in Section 12 above is applied in lieu of profit.
G&A or OH cannot be applied to travel costs. The Prime must include an adequate number of hours for the Clerical Specialist labor disciplines for scheduling travel and paying travel invoices.
G&A or OH cannot be applied to subcontractor costs. The Prime must include an adequate number of hours for the appropriate labor disciplines to source, compete, and schedule subcontractors, as well as Clerical Specialist labor disciplines to pay subcontractor invoices.
Section C - Descriptions and Specifications
PERFORMANCE WORK STATEMENT
INDEFINITE DELIVERY CONTRACT (IDC)
MULTIPLE AWARD TASK ORDER CONTRACT (MATOC)
Geotechnical Field Exploration and Laboratory Testing Services of the U.S. Army Corps of Engineers, Galveston District and the Southwestern Division
1. GENERAL. The intent of the work specified herein to be performed by the Contractor is to determine the type, nature, and characteristics of the subsurface materials at existing and proposed project sites under investigation by the United States Government, principally the U.S. Army Corps of Engineers (USACE), Galveston District, Galveston, Texas. The required work will normally be located within the boundaries of the Galveston District, shown on Plate 1 (Section J); however, work may occur outside these boundaries within the Southwestern Division (shown on Plates 2 and 3, Section J, for civil works and military boundaries, respectively). Services may be performed in connection with both military and civil projects assigned to any entity of the United States Government. Project locations will be identified in each task order. The Contractor, operating as an independent contractor and not as an agent of the Government, shall provide all labor, equipment, transport of equipment and personnel to the site necessary to determine the type, nature, and characteristics of the subsurface materials at the specified locations, utilizing procedures for geotechnical field exploration (sampling using various drilling, direct push, or excavation equipment, and field testing) and laboratory testing, which are acceptable to the U. S. Army Corps of Engineers, and provide the required products with supporting data. The Contractor must adhere to USACE Engineering Regulations and Manuals, and be capable of providing proper equipment and experienced personnel, and developing and following field exploration procedures that comply with the established requirements. All work shall be performed in accordance with the terms and conditions of the contract and this Performance Work Statement (PWS). During the prosecution of the work, the Contractor shall provide adequate supervision and quality control to assure the accuracy, quality, completeness, and progress of the work. In addition, supplemental PWS will be provided at the task order level.
2. DIRECTION OF WORK. The Contractor will initiate field exploration operations at designated work areas and to perform related laboratory testing through the issuance of either one or multiple task orders. Task orders will identify the purpose and location of the required field exploration, the location, number, and depth of soil borings, Cone Penetrometer Tests (CPTs), vibracores, or other field sampling or test procedures, the frequency of soil samples to be obtained, the laboratory tests to be performed on the samples, the required completion date of the work, and any special requirements or conditions. The Contractor shall begin the field exploration at the designated work site in accordance with the task order scope requirements. The Contractor shall develop and provide a site-specific safety plan to the Safety Officer for review prior to issuance of an NTP for each task order as specified in Section H of this contract. A drilling plan, if required for a task order, shall be developed and provided to the Safety Officer for review prior to issuance of notice to proceed (NTP). If laboratory testing is directed by a separate task order, then the Contractor shall begin laboratory testing of the soil samples within five (5) calendar days after receipt of the NTP for that task order. The Government reserves the right to set aside a certain portion of field exploration work to be performed by Government personnel or other commercial sources which would be reflected in the task order PWS or edited via modification. Testing of samples obtained by Government personnel may be designated for testing by the Contractor or may be tested at a Government and/or other commercial laboratory as selected by the Government.
3. SUPERVISION OF WORK. The Contractor shall be responsible for supervision of geotechnical field exploration and laboratory testing of soil samples. The Contractor shall assign a professional engineer or a professional geologist to supervise the work to be performed under each individual task order. The Contractor’s representative shall be responsible for coordinating the field operations to ensure that field procedures and directions specified in this contract are being followed. In addition, the Contractor shall be responsible for ensuring that the soil samples are being properly obtained and handled and that the samples are representative of the subsurface materials being encountered. The Contractor's representative shall communicate with the Contracting Officer’s Representative (COR) during the field operations and advise of any difficulties encountered in the performance of the work. Upon receipt of the Field logs, described in paragraph 14, RECORDS, the Contractor's representative shall review the logs for completeness and for agreement with the samples obtained. Upon receipt of directions for laboratory testing, the Contractor's representative shall inform laboratory personnel of the tests to be performed and shall supervise the testing to ensure that proper testing procedures are followed and that test results are properly recorded. The presence of the COR during the drilling operations and/or the laboratory testing shall not relieve the Contractor of the responsibilities specified in this paragraph.
4. LOCATION OF WORK. The location of the field exploration to be performed will be identified in each task order. Locations will include terrain of varying types, steepness, and consistencies ranging from hard-surfaced dry land to soft marsh lands, including swamps and dredged material placement areas, lands with excessive moisture or soft to very soft surface and subsurface conditions, partially to fully submerged areas with varying depths of ponded or standing water, and areas which may be covered by heavy vegetation or brush.
Locations may also include inland waterways and channels, portions of other bodies of water, and waters of and in close proximity of deep draft navigation channels including entrance channels offshore. The locations of the projects will, at times, be on islands that are only accessible by water. The exact location of each field boring, vibracore, CPT, or other field sampling or testing to be performed will either be provided to the contractor in the form of horizontal coordinates, be staked by the COR, be provided in relation to an existing physical or topographic feature, or be positioned in accordance with other instructions provided in the individual task orders.
The locations of borings specified in the task order or task order attachments shall not be changed unless the contract is modified.
5. ACCESS TO BORING LOCATIONS. The Contractor shall be required to perform clearing of vegetation where necessary to provide access for field exploration equipment. Where clearing is needed as determined by the Government, one or more of the equipment types listed in paragraph 13, EARTHWORK may be ordered by the Government for use in a task order. Rights-of-Entry or assurances that field exploration and associated clearing and earthwork activities are permitted in the designated areas will be furnished to the Contractor by the Government prior to the initiation of the field work. Access to the project sites accessible only by water may be obtained via public or private boat ramps or other launching sites identified by the Contractor. The Contractor shall exercise care in the use of the public ramps to avoid disturbance to the area and shall be responsible for leaving the area in a condition comparable to condition prior to the work. If private ramps are used, the Contractor is responsible to make arrangements with the owners for their use.
6. INCLEMENT WEATHER AND UNFORESEEN SITE CONDITIONS. Due to the nature of the field work required under this PWS, it is anticipated that inclement weather and unforeseen site conditions may cause field work delays.
a. Weather Delays. Routine inclement weather is considered to be any inclement weather that would reasonably be anticipated for the project site location and season during which the work is planned to be performed. Every effort will be made to accommodate the possibility of routine inclement weather delays in the work schedule for each task order. Full or partial days when field work cannot be accomplished due to routine inclement weather will not be paid for separately. The Contractor should take into account the potential for delays to field work schedules and costs due to the effects of routine inclement weather. The exception to routine inclement weather is the occurrence of unusual weather that causes extended limitations to site access and field operations, for example hurricanes, flooding, winter freezing storms, or other unusual events. Should unusual weather events occur that create extended periods of time whereby the work cannot continue, the Contractor shall notify the Government at the earliest possible time after these conditions are anticipated or encountered so that a determination can be made whether to pursue a task order modification. No additional time or work will be paid for without a formal task order modification issued in advance of the additional time or work.
b. Unforeseen Site Conditions. The term “unforeseen site conditions” is defined as conditions that could not reasonably be foreseen by the Government or the Contractor prior to task order award. The Contractor is responsible for visiting the proposed exploration site, determining access requirements for the exploration sites, including for challenging locations, becoming familiar with existing utilities at the project site, and estimating the field work schedule and costs, based on sound judgment and experience, prior to task order award. Should unforeseen site conditions that result in work delays and/or additional cost to the Contractor be encountered after task order award, the Contractor shall notify the Government at the time of discovery of the related site conditions so that a determination can be made whether to pursue a task order modification. Other field work included in the task order, and not affected by the unforeseen site condition, should be continued in order to maintain the completion schedule as closely as possible. No additional time or work will be paid for without a formal task order modification issued.
7. FIELD EQUIPMENT. Equipment to be furnished and utilized by the Contractor for geotechnical sampling shall be dependable equipment in good condition and of sufficient size to efficiently perform the sampling and testing to the required depths, at the required locations, and within the approved time period specified for the work. All equipment is subject to approval by the COR prior to the commencement of the required work and shall be maintained in good working condition by the Contractor throughout the drilling operations. Global Position Systems (GPS) and survey equipment shall conform to the requirements in paragraph 20.
SURVEYING EXPLORATION LOCATIONS.
a. Land-Based Site Exploration.
(1) Drilling equipment shall be of the hydraulic feed or chain pulldown type, and mounted on a self-propelled vehicle having the capability to access the drilling sites. Varied conditions at the investigation sites may require the drilling equipment be truck-mounted with regular road tires, or marsh buggy-mounted with rice or cane tires, or terra or floatation tires, or be track-mounted.
Supplies shall include, but not be limited to, all casing, pipes, pumps, power, and supplemental equipment necessary to accomplish the required drilling and sampling. All equipment is subject to approval in writing by the Government prior to the commencement of the required work and shall be maintained in good working condition by the Contractor throughout the drilling operations.
(2) Cone Penetrometer Test (CPT) Equipment to be furnished and utilized by the Contractor for CPT testing shall be dependable equipment in good condition and of sufficient size to efficiently perform the CPT testing to the required depths at the required locations and within the approved time period specified for the work. CPT equipment shall be of the electronic type, suitable for obtaining the data requested herein in accordance with ASTM D5778, “Electronic Friction Cone and Piezocone Testing of Soils”. CPT equipment shall be mounted on a self-propelled vehicle capable of accessing various investigation sites as described in (1) above for drilling equipment. All equipment is subject to approval in writing by the Government prior to commencement of the required work and shall be maintained in good working condition by the Contractor throughout the CPT operations.
b. Water-Based Site Explorations
All floating plants shall conform to U.S. Coast Guard Regulations and shall provide a working environment that will comply with Corps of Engineers safety and health requirements. All pertinent provisions of the latest edition of Engineer Manual (EM) 385-1-1, U.S. Army Corps of Engineers Safety and Health Requirements Manual, shall govern the prosecution of the work. Drilling equipment shall be of the hydraulic feed or chain pulldown type. Vibracore equipment shall be of the type required to penetrate and sample the sediments anticipated at the investigation site(s). GPS electronic positioning equipment used for positioning of drilling, CPT, vibracore, or other specified sampling and testing rigs, shall be as stated above and suitable for use in positioning of vessels or floating plant in areas as required by this contract.
(1) Floating Plant (normal setup). The Floating Plant with normal setup shall consist of a collapsible drilling rig having hydraulic or chain-drive mounted on a self-propelled (any vessels or their crew required to maneuver plants that are not self-propelled shall be included in this rate) boat, skiff, or small barge limited to a maximum of 40 feet in length and capable of being trailered to and launched from a public boat ramp near the work area, then sailed (or towed - cost included) to the work area under its own power. The floating plant shall be capable of maintaining horizontal and vertical stability during drilling operations on inland waters of up to 20-foot depth at locations having minimal exposure to wave, tidal, and current influences. The floating plant should be capable of drilling and obtaining soil samples in predominantly cohesive to cohesionless soils to a maximum depth of 60 feet below the sea floor.
(2) Floating Plant (extra stability 4 point anchor spread & heavy duty casing). The Floating Plant with extra stability capabilities shall consist of a collapsible drilling rig having hydraulic or chain-drive mounted on a self-propelled (any vessels or their crew required to maneuver plants that are not self- propelled shall be included in this rate) boat, skiff, or small barge limited to a maximum of 40 feet in length and capable of being trailered to and launched from a public boat ramp near the work area, then sailed to the work area under its own power. The floating plant shall be capable of maintaining horizontal and vertical stability during drilling operations on inland waters of up to 20-foot depth at locations having moderate exposure to wave, tidal, and current influences. The floating plant may be stabilized using spuds or other reliable methods such as multipoint anchors. Heavy duty casing is typically required to protect the drill string from breakage due to stresses imposed by moderate wave, tidal, and/or current influences. The floating plant should be capable of drilling and obtaining soil samples in predominantly cohesive to cohesionless soils to a maximum depth of 60 feet below the sea floor.
(a) Signal Lights. When working with floating plants, the Contractor shall display signal lights and conduct his operations in accordance with the General Regulations of the Department of the Army and of the U.S. Coast Guard governing lights and day signals to be displayed by towing vessels with tows on which no signals can be displayed, vessels working on wrecks, dredges, and vessels engaged in laying cables or pipe or in submarine or bank protection operations, lights to be displayed on dredge pipe lines, and day signals to be displayed by vessels of more than 65 feet in length moored or anchored in a fairway or channel, and the passing by other vessels of floating plant working in navigable channels, as set forth in Commandant U.S. Coast Guard Instruction M16672.2, Navigation Rules: International - Inland (COMDTINST M16672.2) or 33 CFR 81 Appendix A (International) and 33 CFR 84 through 33 CFR 89 (Inland), as applicable.
(b) Obstruction of Channel. The Government will not undertake to keep the channel free from vessels or other obstructions, except to the extent of such regulations, if any, as may be prescribed by the Secretary of the Army, in accordance with the provisions of Section 7 of the River and Harbor Act approved 8 August 1917. The Contractor will be required to conduct the work in such manner as to obstruct navigation as little as possible, and in case the Contractor’s plant so obstructs the channel as to make difficult or endanger the passage of vessels, said plant shall be promptly moved on the approach of any vessel to such an extent as may be necessary to afford a practicable passage. Upon completion of the work, the Contractor shall promptly remove his plant, including ranges, buoys, piles, and other marks placed by him under the contract.
8. FIELD PERSONNEL. The Contractor shall have experienced and thoroughly competent core drillers, soil boring loggers, CPT operators, vibracore operators, earthmoving and clearing equipment operators, and helpers performing the field work at all times. Written approval from the Government is required to substitute any Key Personnel.
9. ORDER OF WORK. The Government may designated the order of work to be performed on a task order basis. Unless otherwise specified in the individual task orders, the Contractor may perform the field work in whatever order deemed best for completion in accordance with the task order schedule, and in a well-organized, and cost efficient manner.
10. EXISTING UTILITIES. The Contractor is advised to clear existing utilities by referring to available maps of gas and oil pipelines, visual inspection of all field exploration sites, and calling appropriate utility locating services before commencing field exploration and earthwork operations as described herein. If a pipeline is detected at a proposed field exploration element (boring, CPT, vibracore, or other exploration type), then the Contractor shall relocate the element 100-feet away from such pipeline and identify the revised locations on the exploration layout. Approval for relocation of an element shall be obtained from the Government prior to performing the work.
11. BORING TYPES AND SAMPLING METHODS. Required boring and sampling methods will be specified in the individual task orders as undisturbed, disturbed, and/or environmental sample borings. Borings, as defined in this document, include field exploration that requires drilling or direct push to advance sampling equipment used to obtain subsurface samples for examination and testing. Field borings and sampling procedures and equipment shall be appropriate for the type, depth, and purpose of the samples required. Field work shall be performed in accordance with the criteria and guidance provided in EM 1110-1- 1804 and the procedures outlined in the applicable ASTM standards (latest edition) for the methods used. When drilling in and near flood embankment dams and levees and/or their earth and rock foundations the Contractor will comply with ER 1110-1-1807.
a. Undisturbed Sample Borings.
(1) General Requirements for Continuous and Intermittent Sampling. Undisturbed sample borings shall be either manually or mechanically driven via industry standard drilling equipment in good working order and shall exhibit properties as close to the in-situ properties as can practically be obtained through use of ASTM sampling methods cited herein. Drilling personnel shall exercise care during the drilling operations to assure that changes in materials are detected and that samples are obtained at start of each new material layer and at the prescribed intervals thereafter according to the sampling methods prescribed herein. Sample containers shall be labeled with project name, location, boring number, sample number, depth of sample, and date sample was obtained.
(2) Continuous Sampling.
(a) Cohesive Materials. Where cohesive materials are encountered, continuous sampling shall be performed in accordance with ASTM D1587, “Standard Practice for Thin-Walled Tube Sampling of Soils for Geotechnical Purposes”, using 3-inch diameter thin-walled tube samplers, or as specified in the task orders. Continuous sampling within cohesive materials using thin-walled tubes shall be performed at the rate of one sample every two (2) feet of depth. As cohesive samples are retrieved, they shall be extruded from sample tubes by a mechanical jack or hydraulic piston designed in a manner to minimize disturbance or distortion of the sample during extrusion. The sample shall be supported during the extruding process and shall be moved from the extruder to the wrapping table by a rigid sample supporting device. Pocket penetrometer tests shall be made on each cohesive undisturbed sample after removing all loose disturbed material from the sample. The tests shall be performed according to the standard procedures using a pocket penetrometer in good working order and having a scale range of
0.25 to 4.5 tons per square foot (tsf) in scale divisions of 0.25 tsf. Where pocket penetrometer results yield 0.25 tsf or less, the Contractor shall also perform a field torvane test using the appropriate torvane attachment for soft materials. For every 2-feet of continuous sampling in cohesive soils, and after removal of loose disturbed material, the remaining intact undisturbed sample shall be a minimum of 1-foot in length to the extent practicable for the consistency of the materials sampled by experience and competent drillers. Cohesive samples shall be wrapped with aluminum foil, placed in containers, to be furnished by the Contractor, and encased and sealed with paraffin or approved equal sample sealing method.
(b) Non-cohesive Materials. Standard Penetration Tests (SPTs) shall be performed in accordance with ASTM D1586, “Standard Test Method for Penetration Test (SPT) and Split- Barrel Sampling of Soils”, where cohesionless materials are encountered (such as sands, clayey sands, silty sands, etc.), at the start of each cohesionless layer and at 5-foot intervals thereafter within the cohesionless layer(s) to the required depth of the boring. For each SPT test, the number of blows required to drive the sampler shall be recorded for every 6 inches driven until driven a full 18 inches to complete the test. The cohesionless materials from the sampler shall be placed in quart jars or approved equal sample container, to be furnished by the Contractor, for follow-up lab testing. Sample jars or other approved containers shall be equipped with moisture tight screw caps or approved sealing method.
(3) Intermittent Sampling. Sampling methods and procedures for intermittent sampling shall be the same as that prescribed for continuous sampling above. Unless otherwise directed, sampling intervals for intermittent sampling shall be as follows:
(a) Cohesive materials. Starting at the ground surface, maintain an interval of one sample every two (2) feet to the 10-foot depth, then below the 10-foot depth, the sampling interval shall be one sample every five (5) feet or change in material type, whichever is less.
(b) Non-Cohesive Materials. If non-cohesive materials are encountered at the surface and/or within the top 10 feet of an intermittent boring, then samples shall be obtained at the surface, then at five (5) intervals thereafter within the non-cohesive layer(s) using the SPT procedure.
b. Disturbed Sample Borings. A disturbed sample boring is any boring advanced with, and samples obtained with, either a manually or mechanically operated auger, in accordance with ASTM D1452, “Standard Practice for Soil Exploration and Sampling by Auger Borings”. Disturbed soil samples shall be obtained at the existing ground surface and at each 5-foot interval thereafter, or change in material type, whichever is the lesser interval, or at the interval required by the task order (not to exceed one every two
(2) feet) to the required depth of the boring. Disturbed soil samples shall be placed in quart jars or approved equal sample container, to be furnished by the Contractor, for follow-up lab testing. Sample jars or other approved containers shall be equipped with moisture tight screw caps or approved sealing method.
Larger grab bag samples may be required for obtaining materials for laboratory compaction tests.
Samples for compaction tests shall consist of bag samples of specified weight that are composed of representative composite samples obtained from designated depths in the boring. In addition to the disturbed samples described above, a jar sample that is representative of the material composing each bag sample shall also be obtained for material identification purposes. All sample containers shall be furnished by the Contractor. Each sample obtained shall be clearly marked or labeled with the project name, location, boring number, sample number, depth of sample, and date the sample was obtained.
c. Vibracore. Vibracore sampling is a specialized method for obtaining continuous samples of unconsolidated soils underwater or on land in relatively soft soils. The sampler uses a vibratory unit to drive a continuous sample tube (or barrel) through the soil and retrieve samples. The vibratory unit may by electric, pneumatic, or hydraulic; however, must be appropriate for the soil conditions and required sampling depths at the vibracore locations. A core retaining device shall be used to ensure full core recovery. The vibracore apparatus shall include a method to evacuate water from the barrel to create a vacuum in the barrel as it penetrates the soil.
12. CONE PENETROMETER TESTS. The CPTs shall be performed at the locations and pushed hydraulically to the depths specified in the task order. CPTs shall be performed in accordance with the requirements outlined in ASTM D5778. Plotted results of each test shall include as a minimum, the depth versus the cone resistance (qc), the depth versus the cone side friction (fsc), the depth versus the pore water pressure, and the depth versus the friction ratio (Rf). Depth versus the soil behavior type using an accepted friction ratio classification chart shall also be provided. Plotted results of cone resistance, cone side friction, and porewater pressure shall be provided in units of tons per square feet (tsf), and depth shall be provided in feet. In addition to plotted results, raw data files from which the plots are based on shall be provided with the final deliverables, with raw data labeled according to type of information and units. The Contractor shall record the coordinates and elevation (X, Y & Z) of CPT locations with reference to the horizontal and vertical datums specified in paragraph
20. SURVEYING EXPLORATION LOCATIONS, or as otherwise specified in the individual task orders. The Contractor shall have experienced and competent personnel and helpers performing the CPT operations at all times.
13. EARTHWORK.
a. Earthmoving Equipment. Earthmoving equipment furnished and utilized by the Contractor shall meet the minimum requirements shown below and be dependable equipment in good condition and of sufficient size to efficiently perform the earthmoving operations in order to support the drilling operations in heavily vegetated areas or challenging terrain and within the approved time period specified for the work. All equipment is subject to approval by the COR prior to the commencement of the required work and shall be maintained in good working condition by the Contractor throughout the drilling operations.
(1) Small Bulldozer. The small bulldozer shall have a minimum net engine or flywheel power rating of 70 horsepower, be furnished with an angle type blade and power operated controls, and have a track width and configuration setup for optimal performance for the type of foundation and terrain at the site specific project location.
(2) Large Bulldozer. The large bulldozer shall have a minimum net engine or flywheel power rating of 150 horsepower, be furnished with an angle type blade and power operated controls, and have a track width and configuration setup for optimal performance for the type of foundation and terrain at the site specific project location.
(3) Track-hoe. The track-hoe shall have a minimum net engine or flywheel power rating of 135 horsepower, have a hydraulic system configuration capable of operating up to a 1.8 cubic yard bucket filled with soil, and capable of placing and picking up the matting described below.
The track width and configuration shall be setup for optimal performance for the type of foundation and terrain at the site specific project location.
(4) Matting. Each matt shall be of sufficient size and configuration to support operations of the earth moving equipment, drilling rig, or other vehicle as required. Matting shall be configured to allow earthmoving and drilling equipment to pass over the matting when used to bridge over trenches, small to medium size ditches, small dips, or depressions, soft areas, other challenging locations, or when being used as a base from which to operate the earthmoving equipment in soft areas. Matting shall be configured and capable of being disassembled and reassembled to the extent necessary to allow the matting to be placed or picked up with the track-hoe equipment included herein. Matting shall be of sufficient quantity to allow the track-hoe equipment to operate on the matting while also placing another set of matting to complete the earthwork operations and create access necessary for complete drilling operations.
b. Earthmoving Locations. Locations for which earthmoving equipment will be used will be determined by the Government on a case by case basis for a given site and be included in the task order PWS. In all cases where the use of the small bulldozer, large bulldozer, track-hoe, matting, or some combination thereof is identified for a given task order, the Contractor shall be responsible for notifying the Government of the extent, scope, and locations and will not proceed with the work until the appropriate written approvals and rights of entry have been obtained. Factors which may be the basis for the Government considering the use of the clearing and earthmoving equipment for approved sites may include, but not be limited to, heavily vegetated sites with no pathways, locations where the digging of test pits are requested, or sites with uneven terrain whereby the use of other land based, marsh terrain, or floating plant equipment covered under the main contract will not allow for successfully traversing, accessing, or navigating the investigation site to the specified boring locations.
c. Selection of Equipment. Depending on the extent and nature of the earthwork and clearing, the Government may require any combination of the small bulldozer, large bulldozer, track-hoe, and matting be used, but not necessarily all these items for a given project and will be identified in the task order PWS.
Once a task order is awarded, any deviations from the types or combination of equipment require a modification in advance, otherwise, the use of additional equipment will be at the expense of the Contractor.
d. Equipment Operators and Duration of Operation. The Contractor shall have experienced and thoroughly competent operators performing the earthmoving and clearing operations with equipment specified herein. Costs for qualified operators shall be included in the overall daily rates for using the various types of equipment.
e. Preservation and Restoration. Any earthwork permitted under a given task order shall be done in a manner that is kept to the “bare minimum” necessary to facilitate getting the drilling equipment through to the investigation locations, or facilitate other types of investigations. The Contractor shall exercise care and reasonable judgment in order to ensure any property at the site is not damaged, such as, but not limited to, structures, utilities, pipelines, fences, gates, roads, pathways, landscaped areas, ditches, levees, vehicles, livestock, etc. Property damaged by the Contractor shall be repaired at the Contractor’s expense. Additionally, after the earthwork operations are no longer needed to assist the soil investigations, the Contractor shall restore the soil topography to a condition comparable to the condition before any earthwork at the site began, unless this requirement is specifically waived by the land owner in written documentation.
This is the start of the file's text. The full file is on GovTribe.