This document provides details on a federal solicitation for emergency repairs along Brays Bayou in Harris County, Texas. The U.S. Army Corps of Engineers is seeking contractors to perform repairs to damage caused by Hurricanes Harvey and Imelda along Brays Bayou Flood Control District in Harris County. Services required include repairing bank stabilization measures, debris removal, and repairing drainage structures. The solicitation number is W912HY20B0009 and responses are due by the specified deadline. The agency listed is the Department of the Army Corps of Engineers Engineering District Galveston.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
W45VAK20201216 469941
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
Project: HARRIS COUNTY FLOOD CONTROL DISTRICT BRAYS BAYOU, HARRIS COUNTY, TEXAS
HURRICANE HARVEY AND T.S. IMELDA EMERGENCY REPAIRS
1. CONTRACT ID CODE PAGE OF PAGES
J 1
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912HY20B0009
X 9B. DATED (SEE ITEM 11)
16-Jun-2020
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO.
5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE:
13-Aug-2020
CODE
CONTRACTING DIVISION
US ARMY CORPS OF ENGINEERS
2000 FT. POINT RD.
GALVESTON TX 77550
W912HY 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
X
W912HY20B0009
A0001-2
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
1. The specifications for Solicitation No. W912HY20B0009, HARRIS COUNTY FLOOD
CONTROL DISTRICT BRAYS BAYOU HARRIS COUNTY, TEXAS HURRICANE HARVEY
AND T.S. IMELDA EMERGENCY REPAIRS PROJECT SPECIFICATIONS FOR
CONSTRUCTION are hereby amended as follows:
*THE BID DUE DATE IS HEREBY RESCHEDULED FOR 20 AUG 2020 AT 2:00 P.M. CST.
CALL IN INFORMATION IS AS FOLLOWS:
Dial-in Number: 1-866-390-1828 Access Code: 1361602 Pass Code: 1234
a) Specifications.
(1) SECTION 00 11 00.00 45, BID SCHEDULE – The enclosed SECTION 00 11 00.00 45 entitled BID SCHEDULE supersedes that issued with this Solicitation.
(2) SECTION 01 00 10, SUMMARY OF WORK – The enclosed SECTION 01 00 10 entitled SUMMARY OF WORK supersedes that issued with this Solicitation.
(3) SECTION 01 32 01.01 45, PROJECT SCHEDULE – The enclosed SECTION 01 32 01.01 45 entitled PROJECT SCHEDULE supersedes that issued with this Solicitation.
(4) SECTION 01 45 01.00, QUALITY CONTROL – The enclosed SECTION 01 45 01.00 entitled QUALITY CONTROL supersedes that issued with this Solicitation.
(5) SECTION 01 57 24.00 45, STORM WATER POLLUTION PREVENTION PLAN – The enclosed SECTION 01 57 24.00 45 entitled STORM WATER POLLUTION PREVENTION PLAN supersedes that issued with this Solicitation.
(6) SECTION 35 41 00.01 45, EMBANKMENT CONSTRUCTION – The enclosed SECTION 35 41 00.01 45 entitled EMBANKMENT CONSTRUCTION supersedes that issued with this Solicitation.
b) Drawings.
(1) DRAWINGS NO. G-001 through G-004, C-317 through C-321 and C-501 - The enclosed Drawings No. G-001 through G-004, C-317 through C-321 and C-501, supersedes that issued with this Solicitation.
(2) DRAWINGS HARRIS COUNTY BRAYS BAYOU HIKE & BIKE TRAIL/
CONSTRUCTION – 160 PAGES
(3) DRAWINGS CITY OF HOUSTON, BRAYS BAYOU TIGER #6 TRAIL IMPROVEMENTS
(MLK TO OST) – 115 PAGES
2. This amendment shall be attached to and become a part of the solicitation.
18 Encls:
1. SECTION 00 11 00.00 45, BID SCHEDULE
2. SECTION 01 00 10, SUMMARY OF WORK
3. SECTION 01 32 01.01 45, PROJECT SCHEDULE
4. SECTION 01 45 01.00, QUALITY CONTROL
W912HY20B0009
A0001-3
5. SECTION 01 57 24.00 45 STORM WATER POLLUTION PREVENTION PLAN
6. SECTION 35 41 00.01 45 EMBANKMENT CONSTRUCTION
7. DRAWING NO. G-001
8. DRAWING NO. G-002
9. DRAWING NO. G-003
10. DRAWING NO. G-004
11. DRAWING NO. C-317
12. DRAWING NO. C-318
13. DRAWING NO. C-319
14. DRAWING NO. C-320
15. DRAWING NO. C-321
16. DRAWING NO. C-501
17. DRAWINGS HARRIS COUNTY BRAYS BAYOU HIKE & BIKE TRAIL/ CONSTRUCTION
18. DRAWINGS CITY OF HOUSTON, BRAYS BAYOU TIGER #6 TRAIL IMPROVEMENTS
(MLK TO OST)
SWG FILE NO.: FCCE 410-067 SOLICITATION NO.: W912HY20B0009
SECTION TABLE OF CONTENTS
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
SECTION 00 11 00.00 45
BID SCHEDULE AMENDMENT No. 0001
PART 1 GENERAL
1.1 BID SCHEDULE
1.1.1 Schedule No. 1AM#1
1.2 MODIFICATIONS (CESWG)
-- End of Section Table of Contents --
DOCUMENT 00 11 00.00 45 Page 1
TO ACCOMPANY AMENDMENT NO. 0001 OF SOLICITATION: W912HY20B0009
THIS PAGE INTENTIONALLY LEFT BLANK
DOCUMENT 00 11 00.00 45 Page 2
SECTION 00 11 00.00 45
BID SCHEDULE
AMENDMENT No. 0001
PART 1 GENERAL
1.1 BID SCHEDULE
(TO BE ATTACHED TO STANDARD FORM 1442)
1.1.1 Schedule No. 1 AM#1
Item No. Description Estimated Quantity
Unit Unit Price Estimated Amount
SCHEDULE NO. 1
0001 Mobilization and Demobilization 1 JOB SUM $___________
0002 Clearing, Grubbing, and Debris Removal
1 JOB SUM $___________
0003 Stripping
1 JOB SUM $___________
0004 Geotextile 16,029 S.Y. $___________ $___________
0005 Blanket Stone
5,660 TON $_________ $___________
0006 Riprap
29,060 TON $_________ $___________
0007 Compacted Fill
5,762 C.Y. $___________ $___________
0008 Sod 6,541 3,985
S.Y. $___________ $___________
0009 Excavation of Existing Embankments
7,309 7,306
C.Y. $___________ $___________
DOCUMENT 00 11 00.00 45 Page 3
Item No. Description Estimated Quantity
Unit Unit Price Estimated Amount
SCHEDULE NO. 1
TOTAL SCHEDULE NO. 1 $___________
NOTE: Completion time stated in SECTION 00 73 00.00 45 SPECIAL CONTRACT REQUIREMENTS, STANDARD is for Schedule No. 1 work.
1.2 MODIFICATIONS (CESWG)
If a modification to a bid based on unit prices is submitted, which provides for a lump sum adjustment to the total estimated cost, the application of the lump sum adjustment of each unit price in the bid schedule must be stated. If it is not stated, the bidder agrees that the lump sum adjustment shall be applied on a pro rate basis to unit price in the bid schedule.
-- End of Document --
DOCUMENT 00 11 00.00 45 Page 4
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 00 10
SUMMARY OF WORK AMENDMENT No. 0001
PART 1 GENERAL
1.1 SUMMARY
1.2 SITE LOCATION
1.3 GENERAL DESCRIPTION OF WORKAM#1
1.3.1 Zones 3 through 5,
1.3.2 Zones 1, 2, 6, 7, and 12
1.3.3 Zones 8 through 10, 13, and 14
PART 2 PRODUCTS (Not Used)
PART 3 EXECUTION
3.1 GENERAL
-- End of Section Table of Contents --
SECTION 01 00 10 Page 1
SECTION 01 00 10 Page 2
SECTION 01 00 10
SUMMARY OF WORK
AMENDMENT No. 0001
PART 1 GENERAL
1.1 SUMMARY
The work in this project includes the retoration of channel slopes, and placement of stone protection.
1.2 SITE LOCATION
The work in this Contract is to be performed at the locations specified in Harris County, Texas.
1.3 GENERAL DESCRIPTION OF WORKAM#1
1.3.1 Zones 3 through 5, and 11
The work will consist of clearing, stripping, grubbing and removal of debris. Once all clearing and grubbing operations are completed, the contractor shall then excavate, backfill, and compact and grade the slope according to typical cross sections. Once earthwork is completed, then the contractor shall place sodding according to typical cross sections.
1.3.2 Zones 1, 2, 6, 7, and 12
The work will consist of clearing, stripping, grubbing and removal of debris. Once all clearing and grubbing operations are completed, the contractor shall then place bedding stone and riprap according to typical cross sections.
1.3.3 Zones 8 through 10, 13, and 14
The work will consist of clearing, stripping, grubbing and removal of debris. Once all clearing and grubbing operations are completed, the contractor shall then excavate, backfill, and compact and grade the slope according to typical cross sections.Once earthwork is completed,the contractor shall then place bedding stone and riprap according to typical cross sections. After all rock placement has been completed, then the contractor shall place sodding according to typical cross sections.
PART 2 PRODUCTS (Not Used)
PART 3 EXECUTION
3.1 GENERAL
Project features are to be constructed as shown, specified, and according to manufacturer supplied instructions. .
SECTION 01 00 10 Page 3
-- End of Section --
SECTION 01 00 10 Page 4
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 32 01.01 45
PROJECT SCHEDULE AMENDMENT No. 0001
PART 1 GENERAL
1.1 SUBMITTALS
1.2 QUALITY ASSURANCE
PART 2 PRODUCTS (Not Used)
PART 3 EXECUTION
3.1 GENERAL REQUIREMENTS
3.1.1 Sequence of WorkAM#1
3.1.2 Approved Project Schedule
3.1.3 Updated Progress Schedule
3.1.4 Default Terms
3.2 BASIS FOR PAYMENT AND COST LOADING
3.3 PROJECT SCHEDULE DETAILED REQUIREMENTS
-- End of Section Table of Contents --
SECTION 01 32 01.01 45 Page 1
SECTION 01 32 01.01 45 Page 2
SECTION 01 32 01.01 45
PROJECT SCHEDULE
AMENDMENT No. 0001
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with the SECTION 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Project Schedule ; G
Submit to the Contracting Officer no later than 10 calendar days after acknowledgement of the Notice To Proceed.
1.2 QUALITY ASSURANCE
Designate an authorized representative to be responsible for the preparation of the Schedule and the required updating (activity status) and preparation of reports. The authorized representative must be experienced in scheduling projects similar in nature and complexity to this project and be experienced in the use of the scheduling software that meets the requirements of this specification.
PART 2 PRODUCTS (Not Used)
PART 3 EXECUTION
3.1 GENERAL REQUIREMENTS
Prepare for approval a Project Schedule , as specified herein, pursuant to FAR Clause 52.236-15, SCHEDULE FOR CONSTRUCTION CONTRACTS. Show in the schedule the proposed sequence to perform the work and dates contemplated for starting and completing all schedule activities. The scheduling of the entire project, including the construction sequences, is required.
The scheduling of construction is the responsibility of the Contractor.
Contractor management personnel must actively participate in its development. Subcontractors and suppliers working on the project must also contribute in developing and maintaining an accurate Project Schedule. Provide a Schedule that is forward planning and is a project monitoring tool.
3.1.1 Sequence of Work AM#1
This contract will be executed in accordance with criteria and general sequence specified herein. The sequence was developed, in part, to return the damaged areas of the Brays Bayou in Harris County, Texas to the pre-Hurricane Harvey conditions prior to the next hurricane event. The
SECTION 01 32 01.01 45 Page 3 project repair construction sequence priority is as follows:
1) Repairs at Zones 1 and 2
2) Repairs at Zones 3 and 4
3) Repairs at Zone 5
4) Repairs at Zone 6
5) Repairs at Zones 7 and 12
6) Repairs at Zone 8
7) Repairs at Zone 11
8) Repairs at Zone 9, 10, 13, and 14
3.1.2 Approved Project Schedule
The approved Project Schedule will be used to measure the progress of the work and to aid in evaluating time extensions. The Schedule must depict activity durations, be based on the percentage of physical completion, and provide the basis for progress payments. Use ENG Form 2454 or equivalent produced by a scheduling program to depict the Progress Schedule and ensure that the Schedule conforms with the requirements outlined in the FAR 52.236-15 SCHEDULES FOR CONSTRUCTION CONTRACTS.
Schedule will show anticipated earnings per Contract Line Item Number (CLIN) for each pay period, and total earnings per pay period. If the Contractor fails to submit a schedule within the time prescribed, the Contracting Officer may withhold approval of progress payments until the Contractor submits the required Schedule. Once approved, the Contractor may not change the schedule for any reason without permission from the Contracting Officer or the ACO.
3.1.3 Updated Progress Schedule
Provide an updated Progress Schedule on at least a monthly basis and submit this updated Schedule along with the monthly pay request. The Government may request the Contractor to provide the Government with an updated Schedule as a result of a change in order of work, activity sequences, or activity duration prior to the monthly pay request. If, in the opinion of the Contracting Officer, the Contractor falls behind the approved Schedule, the Contractor must take steps necessary to improve its progress including those that may be required by the Contracting Officer, without additional cost to the Government and submit an updated Progress Schedule to the Government. In this circumstance, the Contracting Officer may require the Contractor to increase the number of shifts, overtime operations, days of work, or the amount of construction plant, and to submit for approval supplementary Schedule or Schedules as the Contracting Officer deems necessary to demonstrate how the approved rate of progress will be regained.
3.1.4 Default Terms
Failure of the Contractor to comply with the requirements of the Contract will be grounds for a determination, by the Contracting Officer, that the Contractor is not prosecuting the work with sufficient diligence to ensure
SECTION 01 32 01.01 45 Page 4 completion within the time specified in this Contract. Upon making this determination, the Contracting Officer may terminate the Contractor's right to proceed with the work, or separable parts of it, in accordance with the default terms of the Contract.
3.2 BASIS FOR PAYMENT AND COST LOADING
The schedule is the basis for determining Contract earnings during each update period and therefore the amount of each progress payment. Lack of an approved Schedule update, or qualified scheduling personnel, will result in the inability of the Contracting Officer to evaluate Contract earned value for the purposes of payment. Failure of the Contractor to provide required information will result in the disapproval of the preliminary, initial, and subsequent Schedule updates. If Schedule revisions are directed by the Contracting Officer and those revisions have not been included in subsequent revisions or updates, the Contracting Officer may hold retainage up to the maximum allowed by this Contract, each payment period, until revisions to the Project Schedule have been made. Activity cost loading shall be reasonable, as determined by the Contracting Officer.
3.3 PROJECT SCHEDULE DETAILED REQUIREMENTS
A computer software system utilized to produce and update the Project Schedule must be capable of meeting the requirements of this specification. Failure of the Contractor to meet the requirements of this specification will result in the disapproval of the Schedule.
-- End of Section --
SECTION 01 32 01.01 45 Page 5
SECTION 01 32 01.01 45 Page 6
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 45 01.00
QUALITY CONTROL AMENDMENT No. 0001
PART 1 GENERAL
1.1 REFERENCES
1.2 PAYMENT
1.3 SUBMITTALS
PART 2 PRODUCTS (Not Used)
PART 3 EXECUTION
3.1 GENERAL REQUIREMENTS
3.2 CONTRACTOR QUALITY CONTROL (CQC) PLAN
3.2.1 Content of the CQC Plan
3.2.2 Acceptance of Plan
3.2.3 Notification of Changes
3.3 COORDINATION MEETING
3.4 PROGRESS MEETINGS
3.5 QUALITY CONTROL ORGANIZATION
3.5.1 Personnel Requirements
3.5.2 CQC System Manager AM#1
3.5.3 CQC Personnel
3.5.4 Additional Requirement
3.5.5 Organizational Changes
3.6 SUBMITTALS AND DELIVERABLES
3.7 CONTROL
3.7.1 Preparatory Phase
3.7.2 Initial Phase
3.7.3 Follow-up Phase
3.7.4 Additional Preparatory and Initial Phases
3.8 TESTS
3.8.1 Laboratory Validation Requirements
3.8.2 Laboratory Validation Procedures
3.8.3 Coordination
3.9 COMPLETION INSPECTION
3.9.1 Punch-out Inspection
3.9.2 Pre-final Inspection
3.9.3 Final Acceptance Inspection
3.10 DOCUMENTATION
3.11 NOTIFICATION OF NON-COMPLIANCE
-- End of Section Table of Contents --
SECTION 01 45 01.00 Page 1
SECTION 01 45 01.00 Page 2
SECTION 01 45 01.00
QUALITY CONTROL
AMENDMENT No. 0001
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
ASTM INTERNATIONAL (ASTM)
ASTM E329 (2018) Standard Specification for Agencies Engaged in Construction Inspection, Testing, or Special Inspection
U.S. ARMY CORPS OF ENGINEERS (USACE)
ER 1110-1-261 (1999) Quality Assurance of Laboratory Testing Procedures
1.2 PAYMENT
Separate payment will not be made for providing and maintaining an effective Quality Control program. Include all associated costs in the applicable Bid Schedule item.
1.3 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with SECTION 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Contractor Quality Control Plan ; G
Verification Statement
PART 2 PRODUCTS (Not Used)
PART 3 EXECUTION
3.1 GENERAL REQUIREMENTS
Establish and maintain an effective Quality Control (QC) system that complies with the CONTRACT CLAUSE titled INSPECTION OF CONSTRUCTION. QC consists of plans, procedures, and organization necessary to produce an end product which complies with the Contract requirements. The QC system
SECTION 01 45 01.00 Page 3 will cover all construction operations, both onsite and offsite, and be keyed to the proposed construction sequence. The project superintendent will be held responsible for the quality of work and is subject to removal by the Contracting Officer for non-compliance with the quality requirements specified in the Contract. In this context the highest level manager responsible for the overall construction activities at the site, including quality and production, is the project superintendent. The project superintendent will maintain a physical presence at the site at all times and is responsible for all construction and related activities at the site, except as otherwise acceptable to the Contracting Officer.
3.2 CONTRACTOR QUALITY CONTROL (CQC) PLAN
Submit no later than 10 calendar days from the award date, the Contractor Quality Control Plan proposed to implement the requirements of the CONTRACT CLAUSE titled INSPECTION OF CONSTRUCTION. Construction will be permitted to begin only after acceptance of the CQC Plan.
3.2.1 Content of the CQC Plan
Include, as a minimum, the following to cover all construction operations, both onsite and offsite, including work by subcontractors, fabricators, suppliers, and purchasing agents:
a. A description of the quality control organization, including a chart showing lines of authority and acknowledgment that the CQC staff will implement the three phase control system for all aspects of the work specified. Include a CQC System Manager who reports to the project superintendent.
b. The name, qualifications (in resume format), duties, responsibilities, and authorities of each person assigned a CQC function.
c. A copy of the letter to the CQC System Manager signed by an authorized official of the firm which describes the responsibilities and delegates sufficient authorities to adequately perform the functions of the CQC System Manager, including authority to stop work which is not in compliance with the contract. Letters of direction to all other various quality control representatives outlining duties, authorities, and responsibilities will be issued by the CQC System Manager. Copies of these letters will be furnished to the Government.
d. Procedures for scheduling, reviewing, certifying, and managing submittals, including those of subcontractors, offsite fabricators, suppliers, and purchasing agents. These procedures will be in accordance with SECTION 01 33 00 SUBMITTAL PROCEDURES.
e. Control, verification, and acceptance testing procedures for each specific test to include the test name, specification paragraph requiring test, feature of work to be tested, test frequency, and person responsible for each test. Laboratory facilities approved by the Contracting Officer will be used.
f. Procedures for tracking preparatory, initial, and follow-up control phases and control, verification, and acceptance tests including documentation.
g. Procedures for tracking construction deficiencies from identification through acceptable corrective action. Establish verification
SECTION 01 45 01.00 Page 4 procedures that identified deficiencies have been corrected.
h. Reporting procedures, including proposed reporting formats.
i. A list of the definable features of work. A definable feature of work is a task which is separate and distinct from other tasks, has separate control requirements, and may be identified by different trades or disciplines, or it may be work by the same trade in a different environment. Although each section of the specifications may generally be considered as a definable feature of work, there are frequently more than one definable features under a particular section. This list will be agreed upon during the coordination meeting.
3.2.2 Acceptance of Plan
Acceptance of the Contractor's Plan is required prior to the start of construction. Acceptance is conditional and will be predicated on satisfactory performance during the construction. The Government reserves the right to require the Contractor to make changes in the CQC Plan and operations including removal of personnel, as necessary, to obtain the quality specified.
3.2.3 Notification of Changes
After acceptance of the CQC Plan, notify the Contracting Officer in writing of proposed change. Proposed changes are subject to acceptance by the Contracting Officer.
3.3 COORDINATION MEETING
After the and prior to acceptance by the Government of the CQC Plan, meet with the Contracting Officer or Authorized Representative and discuss the CQC System. During the meeting, a mutual understanding of the system details will be developed, including the forms for recording the CQC operationsoperations, control activities, testing, administration of the system for both onsite and offsite work, and the interrelationship of Contractor's Management and control with the Government's Quality Assurance. Minutes of the meeting will be prepared by the Government, signed by both the Contractor and the Contracting Officer and will become a part of this Contract file. There may be occasions when subsequent conferences will be called by either party to reconfirm mutual understandings and/or address deficiencies in the CQC system or procedures which may require corrective action by the Contractor.
3.4 PROGRESS MEETINGS
A progress meeting will be held weekly during active construction. The meetings will occur on-site, in the Contractor's field office or by teleconference, as conditions allow. The day for conducting meetings will be mutually agreed to between the Contractor, the Government and the Local Sponsors at the preconstruction conference. The Contractor will prepare meeting agendas and meeting minutes for each meeting and provide to all parties, unless the Contracting Officer's Representative (COR) specifically indicates otherwise in writing.
Progress meeting will consist of a written agenda of topics and issues to
SECTION 01 45 01.00 Page 5 be discussed during the meeting and followed up with draft meeting minutes prepared by the Contractor. The draft meeting minutes will be emailed out to all attendees one day after the meeting for review and approval. The review and approval process will allow for mutual acceptance of the draft minutes as written, or editing to add, delete, and/or correct items that were covered in the weekly meeting. The edited draft meeting minutes will be published and handed out by the Contractor at each following week's progress meeting. If all attendees agree the minutes have been properly edited; then those minutes become the official final minutes of the previous week's progress meeting. All attendees will be required to sign an attendance sheet that will become an attachment to the official final meeting minutes.
The progress meeting agendas will at a minimum contain the following items (Italic wording represents example input per item):
1. Contract Schedule and S-curve status
a. Dollar driven schedule how much will the Contractor need in the next three months
b. Status of the Contract and funds
2. Weather days for the last two weeks
3. Go over Punch/Discrepancy list Items
a. Not in Contract compliance
b. Methods of correction
c. Where does it fit in the schedule?
d. Is it holding up a critical path item?
e. Is it a critical path item?
4. Status of stored materials
a. When to fund stored materials and when to subtract materials from the stored state
b. Where is the item on the scheduled?
5. Work performed since last progress meeting
a. Last week did we do what we said we were going to do?
b. Is there some slippage according to schedule?
6. Two week look ahead.
7. Submittal register open / closed items
a. Status of needed submittals
b. Missing/overdue
8. Visit any open items from previous week's agenda.
9. Pay estimate
a. Questions
b. Concerns
c. Progress
10. Status of safety plan and accident prevention
11. Review of the QCS program
a. Questions
b. Problems
c. Observations
d. Review Reports (Contractor Action Items, Submittals in Review, SECTION 01 45 01.00 Page 6
Submittals due in 30 days, etc)
12. Status and review of testing
a. Concrete
b. Soil
c. Asphalt
13. RFI's / RFC's
a. New
b. Unanswered
14. RFP's
a. New
b. Unanswered
15. Differing Site Conditions
16. Security issues
a. Status of coordination with the Others/Local Sponsor, Any Item
17. Other
During the first progress meeting the agenda format will be reviewed and agreed to by all parties in attendance.
Contractor will conduct all progress meetings as well as prepare the updated agenda for the meeting prior to the scheduled day, and any information in dispute will be addressed at the meeting.
3.5 QUALITY CONTROL ORGANIZATION
3.5.1 Personnel Requirements
The requirements for the CQC organization are a Safety and Health Manager, CQC System Manager, and sufficient number of additional qualified personnel to ensure safety and Contract compliance. The Safety and Health Manager will report directly to a senior project (or corporate) official independent from the CQC System Manager. The Safety and Health Manager will also serve as a member of the CQC Staff Personnel identified in the technical provisions as requiring specialized skills to assure the required work is being performed properly will also be included as part of the CQC organization. The Contractor's CQC staff maintains a presence at the site at all times during progress of the work and have complete authority and responsibility to take actions necessary to ensure Contract compliance. The CQC staff will be subject to acceptance by the Contracting Officer. Provide adequate office space, filing systems and other resources as necessary to maintain an effective and fully functional CQC organization. Promptly complete and furnish all letters, material submittals, shop drawing submittals, schedules, and all other project documentation to the CQC organization. The CQC organization is responsible to maintain these documents and records at the site at all times, except as otherwise acceptable to the Contracting Officer.
3.5.2 CQC System Manager AM#1
Identify as CQC System Manager an individual within the on-site work organization who is responsible for overall management of CQC and has the authority to act in every CQC issue for the Contractor. The CQC System Manager is required to be a graduate engineer, graduate architect, or a
SECTION 01 45 01.00 Page 7 graduate of construction management, with a minimum of 5 years construction experience on construction similar to this Contract , or a const r uct i on per son wi t h a mi ni mum of 10 year s i n r el at ed wor k. .
This CQC System Manager is on the site at all times during construction and be employed by the prime Contractor. The CQC System Manager is assigned no other duties. Identify in the Plan an alternate to serve in the event of the CQC System Manager's absence. The requirements for the alternate are the same as the CQC System Manager.
3.5.3 CQC Personnel
In addition to CQC personnel specified elsewhere in the Contract, provide as part of the CQC organization specialized personnel to assist the CQC System Manager for the following areas: civil, environmental, and materials technician. These individuals or specialized technical companies are directly employed by the prime Contractor and can not be employed by a supplier or subcontractor on this project; be responsible to the CQC System Manager; be physically present at the construction site during work on the specialized personnel's areas of responsibility; have the necessary education and/or experience in accordance with the experience matrix listed herein. These individuals have no other duties other than quality control
Experience Matrix
Area Qualifications
Civil Graduate Civil Engineer or Construction Manager with 2 years experience in the type of work being performed on this project or technician with 5 years related experience
Environmental Graduate Environmental Engineer with 3 yrs experience
3.5.4 Additional Requirement
In addition to the above experience and education requirements, the CQC System Manager and Alternate CQC System Manager are required to have completed the Construction Quality Management (CQM) For Contractors course. If the CQC System Manager does not have a current certification, obtain the CQM for Contractors course certification within 90 days of award. This course is periodically offered by the Army Corps of Engineers. More information can be obtained from the web site:
Construction Quality Management (CQM) for Contractors .
The Construction Quality Management Training certificate expires after 5 years. If the CQC System Manager's certificate has expired, retake the course to remain current.
3.5.5 Organizational Changes
Maintain the CQC staff at full strength at all times. When it is necessary to make changes to the CQC staff, revise the CQC Plan to reflect the changes and submit the changes for acceptance.
SECTION 01 45 01.00 Page 8
3.6 SUBMITTALS AND DELIVERABLES
Submittals, if needed, have to comply with the requirements in SECTION 01 33 00 SUBMITTAL PROCEDURES. The CQC organization is responsible for certifying that all submittals and deliverables are in compliance with the Contract requirements.
3.7 CONTROL
CQC is the means by which the Contractor ensures that the construction, to include that of subcontractors and suppliers, complies with the requirements of the Contract. At least three phases of control are required to be conducted by the CQC System Manager for each definable feature of the construction work as follows:
3.7.1 Preparatory Phase
This phase is performed prior to beginning work on each definable feature of work, after all required plans/documents/materials are approved/accepted, and after copies are at the work site. This phase includes:
a. A review of each paragraph of applicable specifications, reference codes, and standards. Make available during the preparatory inspection a copy of those sections of referenced codes and standards applicable to that portion of the work to be accomplished in the field. Maintain and make available in the field for use by Government personnel until final acceptance of the work.
b. Review of the Contract drawings.
c. Check to assure that all materials and/or equipment have been tested, submitted, and approved.
d. Review of provisions that have been made to provide required control inspection and testing.
e. Examination of the work area to assure that all required preliminary work has been completed and is in compliance with the contract.
f. Examination of required materials, equipment, and sample work to assure that they are on hand, conform to approved shop drawings or submitted data, and are properly stored.
g. Review of the appropriate activity hazard analysis to assure safety requirements are met.
h. Discussion of procedures for controlling quality of the work including repetitive deficiencies. Document construction tolerances and workmanship standards for that feature of work.
i. Check to ensure that the portion of the plan for the work to be performed has been accepted by the Contracting Officer.
j. Discussion of the initial control phase.
k. The Government needs to be notified at least 72 hours in advance of beginning the preparatory control phase. Include a meeting conducted
SECTION 01 45 01.00 Page 9 by the CQC System Manager and attended by the superintendent, other CQC personnel (as applicable), and the foreman responsible for the definable feature. Document the results of the preparatory phase actions by separate minutes prepared by the CQC System Manager and attach to the daily CQC report. Instruct applicable workers as to the acceptable level of workmanship required in order to meet contract specifications.
3.7.2 Initial Phase
This phase is accomplished at the beginning of a definable feature of work. Accomplish the following:
a. Check work to ensure that it is in full compliance with contract requirements. Review minutes of the preparatory meeting.
b. Verify adequacy of controls to ensure full contract compliance.
Verify required control inspection and testing are in compliance with the contract.
c. Establish level of workmanship and verify that it meets minimum acceptable workmanship standards. Compare with required sample panels as appropriate.
d. Resolve all differences.
e. Check safety to include compliance with and upgrading of the safety plan and activity hazard analysis. Review the activity analysis with each worker.
f. The Government needs to be notified at least 24 hours in advance of beginning the initial phase for definable feature of work. Prepare separate minutes of this phase by the CQC System Manager and attach to the daily CQC report. Indicate the exact location of initial phase for definable feature of work for future reference and comparison with follow-up phases.
g. The initial phase for definable feature of work should be repeated for each new crew to work onsite, or any time acceptable specified quality standards are not being met.
3.7.3 Follow-up Phase
Perform daily checks to assure control activities, including control testing, are providing continued compliance with Contract requirements, until completion of the particular feature of work. Record the checks in the CQC documentation. Conduct final follow-up checks and correct deficiencies prior to the start of additional features of work which may be affected by the deficient work. Do not build upon nor conceal non-conforming work.
3.7.4 Additional Preparatory and Initial Phases
Conduct additional preparatory and initial phases on the same definable features of work if: the quality of on-going work is unacceptable; if there are changes in the applicable CQC staff, onsite production supervision or work crew; if work on a definable feature is resumed after a substantial period of inactivity; or if other problems develop.
SECTION 01 45 01.00 Page 10
3.8 TESTS
3.8.1 Laboratory Validation Requirements
Propose the minimum number of laboratories that can attain or have attained U.S. Army Corps of Engineers (USACE) validation in accordance with ER 1110-1-261 Quality Assurance of Laboratory Testing Procedures and consistent with the testing requirements in this Contract. The Contractor may propose laboratories that will be subsequently validated by the USACE, or select currently validated USACE laboratories.
3.8.2 Laboratory Validation Procedures
If not currently validated, the laboratory will be validated by the Engineering Research and Development Center, Materials Testing Center (MTC) .
The MTC may be contacted at (601) 634-2142. The laboratory validation fee will be paid directly to the MTC by the Contractor. The validation process requires 45 days to complete for laboratories without significant deficiencies. Validation will be accomplished by one of the following processes:
(1) Inspection will be performed by the MTC in accordance with
ASTM E329.
(2) A laboratory may be validated by auditing if it has been inspected by the Concrete and Cement Reference Laboratory (CERL) or AASHTO Materials Reference Laboratory (AMRL) within the past 2 years in accordance with ASTM E329. The audit is to be performed by the MTC. Inspection by the MTC may be required after auditing if one or more of the critical testing procedures required in this project specification were not included in the CCRL or AMRL inspection report or if there is a concern that the laboratory may not be able to provide the required services.
3.8.3 Coordination
Each specific test, exact delivery location, and dates will be coordinated with the Contracting Officer.
3.9 COMPLETION INSPECTION
3.9.1 Punch-out Inspection
Conduct an inspection of the work by the CQC System Manager near the end of the work, or any increment of the work established by a time stated in the SPECIAL CONTRACT REQUIREMENTS, STANDARD Clause, "Commencement, Prosecution, and Completion Of Work", or by the specifications. Prepare and include in the CQC documentation a punch list of items which do not conform to the approved drawings and specifications, as required by Paragraph: DOCUMENTATION. Include within the list of deficiencies the estimated date by which the deficiencies will be corrected. Make a second inspection by the CQC System Manager or staff to ascertain that deficiencies have been corrected. Once this is accomplished, notify the Government that the facility is ready for the Government Pre-final inspection.
3.9.2 Pre-final Inspection
The Government will perform the pre-final inspection to verify that the
SECTION 01 45 01.00 Page 11 construction work is complete. A Government Pre-final Punch List may be developed as a result of this inspection. Ensure that all items on this list have been corrected before notifying the Government, so that a Final inspection with the customer can be scheduled. Correct any items noted on the Pre-final inspection in a timely manner. These inspections and any deficiency corrections required by this paragraph need to be accomplished within the time slated for completion of the entire work or a particular increment of the work if the project is divided into increments by separate completion dates.
3.9.3 Final Acceptance Inspection
The Contractor's Quality Control Inspection personnel, plus the superintendent or other primary management person, and the Contracting Officer's Representative is required to be in attendance at the final acceptance inspection. Additional Government personnel including, but not limited to, those from user groups and the Contracting Officer may also be in attendance. The final acceptance inspection will be formally scheduled by the Contracting Officer based upon results of the Pre-final inspection. Notify the Contracting Officer at least 14 days prior to the final acceptance inspection and include the Contractor's assurance that all specific items previously identified to the Contractor as being unacceptable, along with the remaining work performed under this Contract, will be complete and acceptable by the date scheduled for the final acceptance inspection. Failure of the Contractor to have the Contract work acceptably complete for this inspection will be cause for the Contracting Officer to bill the Contractor for the Government's additional inspection cost in accordance with the CONTRACT CLAUSE titled "Inspection Of Construction".
3.10 DOCUMENTATION
Maintain current records providing factual evidence that required quality control activities and/or tests have been performed. Include in these records the work of subcontractors and suppliers on an acceptable form that includes, as a minimum, the following information:
a. The name and area of responsibility of the Contractor/Subcontractor.
b. Operating plant/equipment with hours worked, idle, or down for repair.
c. Work performed each day, giving location, description, and by whom.
When Network Analysis (NAS) is used, identify each phase of work performed each day by NAS activity number.
d. Test and/or control activities performed with results and references to specifications/drawings requirements. Identify the control phase (Preparatory, Initial, Follow-up). List of deficiencies noted, along with corrective action.
e. Quantity of materials received at the site with statement as to acceptability, storage, and reference to specifications/drawings requirements.
f. Submittals and deliverables reviewed, with contract reference, by whom, and action taken.
g. Offsite surveillance activities, including actions taken.
SECTION 01 45 01.00 Page 12
h. Job safety evaluations stating what was checked, results, and instructions or corrective actions.
i. Instructions given/received and conflicts in plans and/or specifications.
k. Contractor's Verification Statement
Indicate a description of trades working on the project; the number of personnel working; weather conditions encountered; and any delays encountered. Cover both conforming and deficient features and include a statement that equipment and materials incorporated in the work and workmanship comply with the contract. Furnish the original and one copy of these records in report form to the Government daily within 24 hours after the date covered by the report, except that reports need not be submitted for days on which no work is performed. As a minimum, prepare and submit one report for every 7 days of no work and on the last day of a no work period. All calendar days will be accounted for throughout the life of the Contract. The first report following a day of no work will be for that day only. Reports will be signed and dated by the CQC System Manager. Include copies of test reports and copies of reports prepared by all subordinate quality control personnel within the CQC System Manager Report.
3.11 NOTIFICATION OF NON-COMPLIANCE
The Contracting Officer will notify the Contractor of any detected noncompliance with the foregoing requirements. Take immediate corrective action after receipt of this notice. This notice, when delivered to the Contractor at the worksite, will be deemed sufficient for the purpose of notification. If the Contractor fails or refuses to comply promptly, the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to such stop orders will be made the subject of claim for extension of time or for excess costs or damages by the Contractor.
-- End of Section --
SECTION 01 45 01.00 Page 13
SECTION 01 45 01.00 Page 14
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 57 24.00 45
STORM WATER POLLUTION PREVENTION PLAN AMENDMENT No. 0001
PART 1 GENERAL
1.1 SUMMARY
1.2 REFERENCES
1.3 SUBMITTALS
1.4 PROJECT IDENTIFICATION
1.5 PROJECT DESCRIPTION
1.6 STANDARD INDUSTRIAL CLASSIFICATION (SIC)
1.7 LOCATION AM#1
1.8 RECEIVING WATERS
PART 2 SITE DESCRIPTION
2.1 EXISTING CONDITIONS
2.2 FINAL CONDITIONS
2.3 CONSTRUCTION ACTIVITIES
2.4 SOILS DATA
2.5 STORM WATER POLLUTION PREVENTION DRAWINGS
PART 3 BEST MANAGEMENT PRACTICES (BMPs)-EROSION AND SEDIMENT CONTROLS
3.1 TEMPORARY STABILIZATION
3.2 PERMANENT STABILIZATION
3.3 SEDIMENT BASIN
3.4 STRUCTURAL CONTROLS
3.5 NON-STRUCTURAL CONTROLS
3.5.1 Construction Practices
3.5.2 Material Management
3.5.3 Waste Management
3.5.4 Vehicle and Equipment Management
3.5.5 Employee and Subcontractor Training
3.5.6 Storm Water Pollution Prevention Plan Maintenance
PART 4 STORM WATER MANAGEMENT AND PERMANENT CONTROLS
4.1 SURFACE DISCHARGE QUALITY
4.2 PERMANENT EROSION CONTROL STRUCTURES AND STORM WATER TREATMENT UNIT
4.3 OUTLET PROTECTION OR OUTFALL VELOCITY DISSIPATION DEVICES
PART 5 TIMING OF CONTROLS AND ACTIVITIES
PART 6 COMPLIANCE WITH FEDERAL, STATE, AND LOCAL REGULATIONS
PART 7 MAINTENANCE AND INSPECTION PROCEDURES AND QUALIFICATION OF
SECTION 01 57 24.00 45 Page 1
DESIGNATED INSPECTOR
PART 8 PROHIBITION ON NON-STORM WATER DISCHARGES
PART 9 CONTRACTOR COMPLIANCE AND CERTIFICATION
9.1 CONSTRUCTION SWPPP GUIDELINES
9.1.1 On-Site Construction Document, Signage, and Record-keeping
9.1.2 Storm Water Discharge General Permit Fees and Fines for
Non-compliance
9.1.3 Regulatory Inspector Visits
9.2 NOTICE OF TERMINATION (NOT) [COMPLETION REPORT]
-- End of Section Table of Contents --
SECTION 01 57 24.00 45 Page 2
SECTION 01 57 24.00 45
STORM WATER POLLUTION PREVENTION PLAN
AMENDMENT No. 0001
PART 1 GENERAL
1.1 SUMMARY
http://www.tceq.state.tx.us/nav/permits/sw_permits.html (PERMIT NO.
TXR150000 for large or small construction site)
The Contractor must verify that the most current forms (e.g., NOI, NOC, NOT, etc.) are submitted with the SWPPP.
There is no separate payment for work required in this Section.
1.2 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by basic designation only.
U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)
40 CFR 110 Title 40: Protection of Environment, Part 110 - Discharge of Oil
40 CFR 112 Oil Pollution Prevention
40 CFR 122 EPA Administered Permit Programs: The National Pollutant Discharge Elimination System
TEXAS COMMISSION ON ENVIRONMENTAL QUALITY (TCEQ)
1.3 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following must be submitted in accordance with the SECTION 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Stormwater Notice Of Intent ; G
Copy of the submitted Notice of Intent to the Texas Commission for Environmental Quality.
Storm Water Pollution Prevention Plan (SWPPP or SWP3); G
SECTION 01 57 24.00 45 Page 3
a. Submit a copy of the TECQ approved Contractor's Storm Water Pollution Prevention Plan (SWPPP) for the project prior to the commencement of work. The SWPPP must meet the requirements of the State of Texas general permit for storm water discharges from construction sites.
Submit the SWPPP along with any required Notice of Intents, Notice of Termination, and appropriate permit fees to the Texas Commission of Environmental Quality (TCEQ) agency for approval, while meeting the required waiting periods for document submission and land disturbance commencement. Maintain an approved copy of the SWPPP at the construction on-site office, and continually update as regulations require, to reflect current site conditions. Include within the SWPPP:
(1) Identify potential sources of pollution which may be reasonably expected to affect the quality of storm water discharge from the site.
(2) Describe and ensure implementation of practices which will be used to reduce the pollutants in storm water discharge from the site.
(3) Ensure compliance with terms of the State of Texas general permit for storm water discharge.
(4) Select applicable best management practices from EPA 832-R-92-005.
(5) Include a completed copy of the Registration Statement, BMP Inspection Report Template and Notice of Termination except for the effective date.
b. The construction Contractor site specific SWPPP must prevent erosion, sediment loss from the construction site, and erosion down gradient of the developed property. To the maximum extent possible, the SWPPP must (i) limit the area of disturbance to minimize soil loss and prevent the discharge of water quality impaired water from the construction site and (ii) incorporate staged stabilization measures as work progresses throughout the duration of the project. The Contractor must use the current forms (e.g., NOI, NOT, NOC, etc.)
required by the TXR150000 Construction General Permit issued by the Texas Commission on Environmental Quality (TCEQ). Additionally, the Contractor must maintain compliance with the Construction General Permit at all times (even when the Construction General Permit is revised by the issuing agency).
(1) The SWPPP must comprise of 3 major parts: (a) narrative, (b) drawings depicting structural and non-structural best management practices (BMPs), and (c) permit required documentation…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .