FINAL_BID_ABSTRACT___FOR_GIWW,FREEPORT_HARBOR_TO_UPPER_MATAGORDA_BAY__19....pdf

PDF 311 KB Posted

Attached to
GIWW, Texas Freeport Harbor to Upper Matagorda Bay Pipeline Dredging
Solicitation number
W912HY19B0024
Issued by

About this file

BID ABSTRACT OF OFFERS-WW912HY19B0024

View the file

Other files

File Type Posted
W912HY19B0024-Plans_-_SIGNED_-_2019-07-23.pdf PDF
W912HY19B0024-Specs_-_SIGNED.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

QUANTITY SUM UNIT PRICE TOTAL

1 JOB SUM $1,500,000.00

1 JOB SUM $250,000.00

283,000 CY 3.28 $928,240.00

226,000 CY 3.03 $684,780.00

410,000 CY 3.02 $1,238,200.00

525,000 CY 2.47 $1,296,750.00

1,970 CY 15.00 $29,550.00

2,060 CY 15.00 $30,900.00

$5,958,420.00

QUANTITY UNIT UNIT PRICE TOTAL

1 JOB SUM $330,000.00

1 JOB SUM $55,000.00

162,000 CY $588,060.00

$973,060.00

$6,931,480.00

Dredging - COE Boathouse, Colorado River

Locks, Section 17

ITEM OPTION NO. 1

CURTIS COLE, JR.

CONTRACTING OFFICER

* The apparent low bidder is ORION MARINE CONSTRUCTION, INC who is 5.11% BELOW the Government's Estimate.

I CERTIFY THAT I HAVE OPENED, READ, AND RECORDED ON THIS ABSTRACT ALL OFFERS RECEIVED IN RESPONSE TO THIS SOLICITATION.

NO. DESCRIPTION

0009 Mobilization and Demobilization

TOTAL SCHEDULE 1 & OPTION 1

TOTAL SCHEDULE NO. 1

TOTAL OPTION NO. 1

0010 Pipeline Management

0011 Dredging- GIWW Sections 1-3

Pipeline Management0002

Number of Amendments Issued: 0 Government Estimate (Without Profit)

NO.

SCHEDULE NO. 1ITEM

DESCRIPTION

ABSTRACT OF OFFERS Page 1 of 2

Solicitation No.: W912HY19B0024 Date Issued: 23 JULY 2019 Date Opened: 22 AUGUST 2019

Issuing Office: USAED-Galveston Project Title: Maintenance Dredging Of Gulf Intracoastal Waterway, Texas Freeport Harbor To Upper Matagorda Bay, In Brazoria and Matagorda Counties, Texas. Unrestricted Procurement.

Dredging - COE Boathouse, Brazos River Floodgates, Section 16

0004 Dredging -GIWW Sections 7-9

Dredging -GIWW Sections 4-6

Dredging -GIWW Sections 10-12

Dredging - GIWW Sections 13-15

Mobilization and Demobilization

3.63

QUANTITY SUM UNIT PRICE TOTAL

1 JOB SUM $1,150,000.00

1 JOB SUM $490,000.00

283,000 CY 4.25 $1,202,750.00

226,000 CY 3.50 $791,000.00

410,000 CY 2.00 $820,000.00

525,000 CY 2.00 $1,050,000.00

1,970 CY 40.00 $78,800.00

2,060 CY 45.00 $92,700.00

$5,675,250.00

QUANTITY UNIT UNIT PRICE TOTAL

1 JOB SUM $225,000.00

1 JOB SUM $110,000.00

162,000 CY 3.50 $567,000.00

$902,000.00

$6,577,250.00

Dredging- GIWW Sections 1-3

Mobilization and Demobilization

TOTAL OPTION NO. 1

TOTAL SCHEDULE 1 & OPTION 1

Issuing Office: USAED-Galveston Project Title: Maintenance Dredging Of Gulf Intracoastal Waterway, Texas Freeport Harbor To Upper Matagorda Bay, In Brazoria and Matagorda Counties, Texas. Unrestricted Procurement.

Number of Amendments Issued: 0

OFFEROR # 1: ORION MARINE CONSTRUCTION, INC. TAMPA, FL (OTHER THAN SMALL BUSINESS)

ITEM SCHEDULE NO. 1

0009 Mobilization and Demobilization

0010 Pipeline Management

ABSTRACT OF OFFERS Page 1 of 2

Solicitation No.: W912HY19B0024 Date Issued: 23 JULY 2019 Date Opened: 22 AUGUST 2019

Dredging - COE Boathouse, Brazos

River Floodgates, Section 16

0005 Dredging -GIWW Sections 10-12

NO. DESCRIPTION

Dredging -GIWW Sections 4-6

NO. DESCRIPTION

Pipeline Management

Dredging - COE Boathouse, Colorado River Locks, Section 17

ITEM OPTION NO. 1

0004 Dredging -GIWW Sections 7-9

TOTAL SCHEDULE NO. 1

Dredging - GIWW Sections 13-15

2019-08-22T18:26:18-0500
COLE.CURTIS.JR.1231025746