Phase 1 Preproposal Conference - Unrestricted.pdf
PDF 235 KB Posted
- Solicitation number
- W912HY-09-R-0023
About this file
Pre-proposal Conference Slides for W912HY-09-R-0023
View the file
Other files
| File | Type | Posted |
|---|---|---|
| No AMD 0004 Notice.doc | DOC document | |
| AMD0003.pdf | ||
| W912HY-09-R-0023 Pre-Proposal Conference Sign In Sheet.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PRE-PROPOSAL CONFERENCE
Galveston District – Building Strong!
IDIQ MATOC for Design-Build and Design Bid Build Horizontal
Construction Services Southwestern Division
Unrestricted Pool of Contractors RFP No. W912HY-09-R-0023
7 Oct 2009
FOR INFORMATION ONLY
ALL CHANGES MUST BE EXECUTED BY
FORMAL AMENDMENT TO THE SOLICITATION
AGENDA
Galveston District – Building Strong!
•Introductions •Brief Program Overview •Solicitation Overview •Questions
PROGRAM OVERVIEW
This requirement is part of the total MATOC program requirements for Horizontal Construction in the Southwestern Division (SWD) of approximately $950M all contracts combined, to provide capacity to support the execution of SWD's horizontal construction, workload missions, including horizontal construction missions associated with the American Recovery and Reinvestment Act of 2009 (ARRA) signed into law on February 20, 2009. The government intends to create a pool under each of the following categories:
Unrestricted Historically Under-Utilized Business Zone SB (HUBZone), 8(a) Small Disadvantaged Business (SDB) Small Disadvantaged Veteran Owned Small Business (SDVOSB)
There must be two or more awardable offers within each category, in order to create a pool.
OVERVIEW OF THE SOLICITATION
SOLICITATION PROCESS SOLICITATION PROCESS
SECTION 00 90 00 SECTION 00 90 00 –– DESCRIPTION/SPECS/WORK DESCRIPTION/SPECS/WORK
STATEMENT STATEMENT
SECTION 00 22 10 SECTION 00 22 10 –– PHASE 1 OF 2 DESIGN BUILD PHASE 1 OF 2 DESIGN BUILD
SELECTION PROCEDURES SELECTION PROCEDURES –– PROPOSAL PROPOSAL
SUBMITTAL INSTRUCTIONSSUBMITTAL INSTRUCTIONS
SECTION 00 22 20 SECTION 00 22 20 -- PROPOSAL EVALUATION AND PROPOSAL EVALUATION AND
CONTRACT AWARD BEST VALUE TRADE OFF CONTRACT AWARD BEST VALUE TRADE OFF
PROCEDURESPROCEDURES
DESCRIPTION/SPECS/WORK STATEMENT
SECTION 00 90 00
This Contract is intended for multi-tasking of horizontal construction services for a wide variety of new construction, maintenance, repair, and alteration projects. The work will include, but not limited to abutment, asphalt and concrete paving, bridge, culverts, curbs, and street gutters, elevated highway construction, overpass, road and street surfacing, trestle, water and sewer, mains, pumping stations, treatment plants and storage tanks, anchored earth retention, breakwater, spillways, floodwater, bulkhead wall or embankment, channel canal, dams, related projects, repair, maintain, and build marine related structures, levees, flood control and jetties, anti-terrorism and force protection, outdoor recreation facilities, park and recreational open space improvements.
DESCRIPTION/SPECS/WORK STATEMENT
SECTION 00 90 00
Any work executed under the SWD UNRESTRICTED MATOC is generally limited to the geographic boundaries of the Southwestern Division, U.S. Army Corps of Engineers, however, it is anticipated that the Unrestricted MATOC pool will execute up to an estimated 15% of the total MATOC capacity outside of the established SWD geographical area, if capacity permits.
The boundaries for Southwestern Division are identified at http://www.usace.army.mil/about/Pages/Locations.aspx. For more detailed district boundary information go to each district’s Regulatory boundary maps.
SOLICITATION PROCESS
This is a "Best Value", Two-Phase competitive selection process.
PHASE 1
The first phase consists of a process known in the commercial design-build industry as the Request for Qualifications or acronym: RFQ. (This solicitations refers to it as Phase 1.) In Phase 1, interested firms or joint venture entities (referred to as Offeror's) shall submit performance capability proposals in accordance with this Section 00 22 10, demonstrating their capability to successfully execute the design-build construction IDIQ MATO contract resulting from this solicitation. The Government will evaluate the performance capability proposal in accordance with Section 00 22 20 of this solicitation and will select between 2 to 10 Contractors from Phase 1, for consideration in Phase 2, in anticipation of awarding 2 or more MATOC contracts in Phase 2.
Phase 2 In Phase 2, the selected Offeror's will submit the remainder of the technical/performance capability proposals and a price proposal for a seed project.
The Government will evaluate the Phase 2 proposals in accordance with the criteria described for Phase 2 in the solicitation and award 2 or more MATO contracts to the responsible Offerors whose proposals conform with all terms and conditions of the solicitation and whose proposals are determined to represent the overall best value to the Government considering technical design quality, performance capability and/or cost.
Phase 2 In Phase 2, the short-listed offerors will submit the remaining technical proposal portions as required by Section 00 22 10A, to be provided by amendment for the seed project and price. The government will review and evaluate the Phase 2 proposals as set forth in Section 00 22 20A.
Phase 2 of this process permits tradeoffs among cost or price and non-cost factors and allows the Government to accept other than the lowest priced proposal.
SECTION 00 22 10
PHASE 1 - VOLUME 1 - PROPOSAL CONTENTS
Volume 1 Contents: PHASE 1 DOES NOT INVOLVE PRICING SUBMISSION.
Galveston District – Building Strong!
N/ACoordination with SBA Joint Venture (if applicable)
TAB H
N/ASmall Business Subcontracting Plan (applicable to Large Business only)
TAB G
N/AExtent of Small Business Participation (1) Small Business Participation (2) Past Performance in Utilization of Small Business
Factor 6 (1) (2) TAB F
N/A Financial CapabilityFactor 5TAB E
N/A Evidence of ability to obtain Bonding: TAB D
N/AProposal Data Sheet TAB C
N/ASection 00 45 00 Representation and Certifications or ORCA
TAB B
N/A
SF 1442
TAB A
Page LimitDescription Factor/Subfactor
Number Location
SECTION 00 22 10
PHASE 1 - VOLUME 2 - PROPOSAL CONTENTS
PHASE 1, VOLUME 2 CONTENTS:
Galveston District – Building Strong!
10 pgOrganization and Management Approach – 1) Organization, 2) Processes during Design and Construction, 3) Planning and Scheduling, 4) Self-Performed Work, 5 ) Quality Control
Factor 4 (1)(2)(3) (4)(5)
TAB D
10 pgKey Project Personnel – Capabilities and Experience
Factor 3TAB C
20 pg excluding past performance Questionnaires
Past PerformanceFactor 2 TAB B
50 pg including Project List
Specialized Experience (1) Prime/construction contractor (2) Design firm(s) and subcontractor design consultants
Factor 1 (1) (2)TAB A
Page LimitDescriptionFactor/Subfactor Number
Location
SECTION 00 22 20
PHASE 1 - VOLUME 1 – EVALUATIONS FACTORS AND RELATIVE
IMPORTANCE OF EACH
Galveston District – Building Strong!
Go/No-GoJoint Venture Agreement (if applicable)TAB H
Go/No-GoSmall Business Subcontracting Plan (applicable to Large Business only)
TAB G
5th (Slightly less than 4th) (Subfactor 2 is more important than Subfactor
Extent of Small Business Participation
(1) Small Business Participation (2) Past Performance in Utilization of Small Business
Factor 6 (1) (2) TAB F
4th (Slightly less than 3rd)Financial CapabilityFactor 5TAB E
Go/No-GoEvidence of ability to obtain Bonding: TAB D
Not RatedProposal Data Sheet TAB C
Not RatedSection 00 45 00 Representation and Certifications or ORCA
TAB B
Not Rated
SF 1442
TAB A
Relative ImportanceDescription Factor/Subfactor Number Location
SECTION 00 22 20
PHASE 1 - VOLUME 2 - EVALUATIONS FACTORS AND RELATIVE
IMPORTANCE OF EACH :
Galveston District – Building Strong!
3rd (Slightly less tan 2nd) Subfactors equal in importance to each other
Organization and Management Approach – 1) Organization, 2) Processes during Design and Construction, 3) Planning and Scheduling, 4) Self-Performed Work, 5 ) Quality Control
Factor 4 (1)(2)(3) (4)(5)
TAB D
2nd (Slightly less than 1st)Key Project Personnel – Capabilities and Experience
Factor 3TAB C
1st (Equal to Factor 1)Past PerformanceFactor 2 TAB B
1st (equal to Factor 2) Subfactor (1) is slightly more important than Subfactor (2)
Specialized Experience (1) Prime/construction contractor (2) Design firm(s) and subcontractor design consultants
Factor 1 (1) (2)TAB A
Relative ImportanceDescriptionFactor/Subfactor Number
Location
Solicitation Overview
• Central Contractor Registration (CCR)
• Bonding
• Joint Ventures & DUNS
• Evaluation Preference for HUBZone Small Business
• ARRA Reporting Requirements
• E-Verify Requirements
• CENTRAL CONTRACTOR REGISTRATION (CCR)
– FAR 4.11 Requires all DOD Contractors to be registered Prior to Award
– A DUN And BRADSTREET (DUNS) Number will be assigned and a
Contractor And Government Entity (CAGE)
– Update a minimum of Once a Year
• BONDING
– Surety company must be listed on the Department of the Treasury's
Listing of Approved Sureties (Department Circular 570) at http://www.fms.treas.gov/c570/c570.html
– Bid Guarantee
• Joint Ventures must be registered in the CCR with a separate Duns number and CAGE Code
• 8(a) Joint Ventures must be pre-approved by the Small Business Administration (SBA) prior to Proposal Due Date
• Evaluation Preference for HUBZone Small Business concerns in accordance with FAR 52.219-4. HUBZone SB concerns may elect to waive the evaluation preference, in which case the agreements in para (d) of this clause will not apply, i.e. contract performance of work requirement.
• Performance of Work by the Contractor (FAR 52.236-1):
– The contractor shall perform on the site, and with its own organization, work equivalent to at least 15% of the total amount of work to be performed under the contract.
• American Recovery and Reinvestment Act of 2009 (ARRA) signed into law on February 20, 2009 – task orders utilizing ARRA funds will be identified as such and will require special reporting and compliance with the Buy American Act provisions identified in this solicitations.
• Employment Eligibility Verifications (52.222-54):
applicable to all task orders valued at greater than $3000.00
Offeror’s Responsibility
• Read RFP thoroughly
• Submit Questions using Bidding Inquiry System
• Do not wait until last minute to ask questions. Cut off period in
Bidding Inquiry System – cut off date is 21 Oct 09
• Follow the format for the submission
• Stay within the Technical Proposal Page Limitation as set forth in
Section 00 22 10
• Consider the Relative Importance of the Rating Factors
• Proactive Partnership
QUESTIONS