AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04 EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
Multiple Award Task Order Contract (MATOC) for Design-Build (D-B) and Design-Bid-Build (D-B-B) Construction Services Japan Wide, U.S. Army Corps of Engineers (USACE), Japan District (POJ)
See next page.
1. CONTRACT ID CODE PAGE OF PAGES
1 2
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY
16B. UNITED STATES OF AMERICA 15C. DATE SIGNED 15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer) (Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912HV-16-R-0003
X 9B. DATED (SEE ITEM 11)
18-Mar-2016
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
AM-0002
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
13 Apr 2016
CODE
U.S. ARMY ENGINEER DISTRICT, JAPAN
CONTRACTING DIVISION
APO AP96338-5010
UNITED STATES (THE)
W912HV 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODE CODE
EMAIL: TEL:
Am-0002 Standard Form 30 RFP No. W912HV-16-R-0003 Page 2 of 2 Item No. 14 (Continued)
14. DESCRIPTION OF AMENDMENT (continued)
A. CHANGES TO SPECIFICATIONS – The amendment mark “(Am-0002)” is shown on each page of the amended specification section(s).
Revised Page(s)/ Paragraph(s) to Project Specifications. Attached hereto are the following revised page(s)/paragraph(s) to the specifications. Revised paragraph(s) will replace like-numbered page(s)/paragraph(s) in the subject specifications. Revisions are highlighted in yellow.
Section Page No(s) / Paragraph No(s).
00 22 00 Page 3, para 2.3.1
B. The following page contains questions that were submitted by potential offerors.
Answers provided to the respective questions do not amend the solicitation (specifications, drawings, etc.) unless revision to the specifications or drawings is specifically noted and incorporated into the solicitation. Please see attached list of questions.
C. Proposal due date and time remains unchanged.
Multiple Award Task Order Contract (MATOC) for Design-Build (D-B) and Design-Bid-Build (D-B-B) Construction Services Japan Wide, U.S. Army Corps of Engineers (USACE), Japan District (POJ)
W912HV-16-R-0003 (Am-0002)
RFI Sheet No. or Specs Contractor Question Government Response
1 RFP
00 22 00 -7
It says "Offerors may submit Contract Performance Assessment Report (CPAR) generated from the Past Performance Information Retrieval System (PPIRS) in lieu of Attachment C for any project." ; however, for several projects, we only have CCASS evaluations such as DD2626. We believe that CCASS evaluations are recognized equal to CPAR. Kindly accept CCASS form for this section.
The DD2626 is one of the CPARS generated forms from PPIRS.
2 AM-0001 In Amendment No. 0001, dated April 5, 2016, it indicates “Section 00 10 00 Contract. Line Item Number (CLIN) Schedule, but we cannot find the “CLIN Schedule". How could we handle this?
The proposal schedule (CLIN schedule) will be issued in Phase 2 and will replace this section.
3 Regarding past experience of an entity(prime contractor), would you consider a teaming agreement(not as JV partner) between prime contractor(offeror) and its subcontractor utilizing subcontractors past experiences as the offeror's experience in order to give its subcontractor opportunity to participate in this solicitation?
No, please see Section 00 22 16, para 4.1.1.1.1. notes (a) - (d).
4 In reference to Section 00 22 00 - 6, par 2.3.1.1.1 item d - "The government will not consider prior projects completed by a joint venture prime contractor as construction experience by the prime contractor unless the offeror is the same joint venture entity that performed the work as the prime contractor on the prior project"... If its the entity's first time to be JV with other company, would you consider using past experiences of each JV entity?
Yes, refer to Section 00 22 00, para 2.3.5.1.1 note (a).
5 Section 2.3.1 states “The total pages submitted shall not exceed 100 pages.”
Due to the length of the PPIRS and PPQ forms, and to allow room for all of the required information, please consider excluding Tab 1 Cover Sheet, Tab 2 SF 1442, Tab 3 Section 00 45 00 Representations and Certifications, and Tab 4 Joint Venture Agreement from the page count.
No, please follow AM-0002, Section 00 22 00, para 2.3.1.*
*(AM-0002 revises Section 00 22 00, para 2.3.1 but does not revise the total page count).
6 Section 00 22 00 - Proposal Submission Requirements Pg3, Item
2.3.1 Size of Proposal
Page
It states that "Proposal pages should be letter size (8-1/2" x 11" or equivalent Japanese letter size). Is it acceptable to use A4 size?
See AM-0002, Section 00 22 00, para 2.3.1.
7 RFP, 00 22 00
2.3.5.1.1.1 (3) Were completed within (5) years from the date of this solicitation
We would like to confirm the requirement of "within 5 years from the date of this solicitation". If the contract completion date of a relevant construction project is 1st April 2011, does the Government evaluate the project?
The Government will not evaulate the contract completion date of a relevant construction project before receipt of proposals. See SF 1442, Block 3 for issuance date of the solicitation.
8 P27/137, 00 22 00, Attachment B, Item C.
Item C.
Location/Site of Project (Include Country and City where the project was or will be constructed):
Can we assume projects currently under construction may also be submitted to demonstrate the Designer’s experience?
No, please see Section 00 22 16, para 4.1.1.2.1.(2).
00 22 00 – 3
(AM-0002)
that they will be contacted or afforded an opportunity to clarify, discuss or revise their proposals.
1.4. Proposals received by the Government after the date and time set for receipt of proposals will be handled in accordance with the requirements of Provision “52.215-1, Instructions to Offerors – Competitive Acquisition”.
1.5. Offerors are required to provide information addressing all stated factors and subfactors in a clear and understandable format. If an Offeror does not have information relating to a specific factor or subfactor, the Offeror shall clearly state so in the proposal. Proposals that do not clearly address all factors and subfactors may be considered unacceptable and may not receive further consideration.
2. PHASE ONE PROPOSAL SUBMISSION INSTRUCTIONS:
2.1. Proposals may be submitted by firms formally organized as design-build entities, or by construction contractors and design firms that have associated specifically for this contract. For the purpose of this solicitation, no distinction is made between formally organized design-build entities and contract-specific design-build associations. Both are referred to as the design-build offeror (or simply “Offeror”), or the design/build contractor, (or simply, “Contractor”), after award of the contract.
2.2. General Requirements: The proposal shall be clear, concise, and shall include sufficient detail for effective evaluation and for substantiating the validity of stated claims. The proposal shall not simply rephrase or restate the Government’s requirements, but rather shall provide convincing rationale to address how the Offeror intends to meet the requirements. Offerors shall assume that the Government has no prior knowledge of their facilities or experience, and will base its evaluation on the information presented in the Offeror’s proposal.
2.3. Phase One Proposal Format
2.3.1. Size of Proposal Pages: Proposal pages should be standard letter size (8-1/2” x 11” or equivalent Japanese letter size, A4); however, if drawings or other graphics are submitted, Offerors should reduce them only to the extent that legibility is not lost. The total pages submitted shall not exceed 100 pages. Font size Arial 12 or larger is preferred. All pages should be numbered. Any pages over the prescribed limit will not be considered for evaluation.
2.3.2. Number of copies.
2.3.2.1. Submit the original and five (5) hard copies.
2.3.2.2. An electronic copy of the proposal shall be submitted on CD or DVD, and shall accompany the hard copy submittals. The disc shall be externally labeled with the solicitation number, date, and the offeror’s name. If the electronic files are of a size at which they must be compressed (zipped), they shall be compressed into one file using WinZip version 6.2 or later. Self-extracting exe files will not be accepted.
Electronic files shall be in their native format (i.e. doc, xls, ppt, etc.), or if in pdf format, shall be in searchable text. In the event of any conflicts or differences between the original sealed offer and any paper copy or electronic copy of the
| A.2.9 Preproposal Powerpoint.pdf |
| MATOC for Design-Build & Design-Bid-Build Construction Services Japan Wide �U.S. Army Corps of Engineers, Japan District |
| Welcome |
| Rules for the Conference |
| Highlights |
| Geographic Area |
| Japan District �Area of Operations |
| Potential Types of Work�(Vertical & Horizontal Construction) |
| US Funded Construction |
| US Funded Construction |
| Contractor Required Information |
| Sam.gov |
| FBO.GOV |
| FBO.GOV |
| Quick Tips for all solicitations |
| Contract Period of Performance |
| Task Order Types �D-B-B |
| Task Order Types�D-B |
| Task Order Limitations �(Section 00 70 00, 52.216-19 Order Limitations) |
| Task Order Award Procedures �(Section 00 73 00, Paragraph 17) |
| Bonding Requirements |
| Contract Maximum and Minimum �(Section 00 10 00, Note 2) |
| Two-Phase Design-Build Selection Procedures �(Section 00 22 16, Paragraph 1.1) |
| Phase One Evaluation Factors �(Section 00 22 16 Paragraph 3.0) |
| Proposal Submission Instructions |
| Solicitation |
| Division 01 |
| Questions? |
| Thank you |
| RFI _am2.pdf |
| Consolidted |
| RFI _am2.pdf |
| Consolidted |
| RFI _am2.pdf |
| Consolidted |
File details come from the government source that posted it. Updated .