B08.03 Answers to Questions - W912HQ22R0006.docx
DOCX document 14 KB Posted
- Solicitation number
- W912HQ22R0006
About this file
This document contains a federal contract opportunity announcement and related questions and answers. The U.S. Army Corps of Engineers, National Capitol Region Humphreys Engineer Center Support Activity is seeking proposals for a single-award IDIQ contract to provide Water Management Enterprise System and Corps Water Management System software development, security compliance requirements, and software support services for a five-year period of performance. Task orders will be firm-fixed price. Proposals are due by July 1, 2022. To be eligible, offerors must be registered in SAM.gov. The NAICS code is 541511. Questions were due by June 13, 2022. Proposals must address both the IDIQ and an initial task order.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| B08.03 W912HQ22R0006 (Amendment 002) - IWR HEC CWMS-WMES.pdf | ||
| W912HQ22R0006 - IWR HEC CWMS-WMES.pdf | ||
| Attachment 3 - PWS TO1 - CAVI Support for Web Data Write Access.docx | DOCX document | |
| Attachment 1 - SCA Wage Determination No. 15-5631.txt | TXT text file | |
| Attachment 2 - NAVFAC USACE Past Performance Questionnaire.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1. A page limit was mentioned for the sub-contractor competition plan. Is there an overall page limit for the proposal, or page limits on any other sections?
Answer: Yes, please see the revised Instructions to Offerors in the RFP. Page limits and breakdown of what should be submitted per each volume is now included.
2. Can we include rates in our proposal for additional labor categories beyond those directly requested in the solicitation?
Answer: Yes. Other labor categories may be proposed.
3. Should the SATOC technical proposal, SATOC price proposal, and PWS proposal volumes be submitted as a single electronic document, or should these be separate electronic documents?
Answer: These should be separate. See the revised Instructions to Offerors in the RFP.
4. Can the three (3) relevant contracts in the past 3 years include a combination of prime and major subcontractor(s) or do the prime and each major subcontractor each require 3 such contracts individually?
Answer: They may include a combination.