AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this amendment is to make various changes to the specifications (see Summary Changes).
1. CONTRACT ID CODE PAGE OF PAGES
1 4
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 15-Sep-2017
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912HP17R0022
X 9B. DATED (SEE ITEM 11)
16-Aug-2017
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
15-Sep-2017
CODE
US ARMY CORPS OF ENGINEERS, CHARLESTON
69-A HAGOOD AVENUE
CHARLESTON SC 29403
W912HP 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912HP17R0022
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SECTION 00 00 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
SUMMARY OF CHANGES
SECTION 00 21 16 - INSTRUCTIONS TO PROPOSERS
The following have been added by full text:
AMENDMENT 0002
Dorchester Reach, Lake Marion RWS (Amendment 0002)
AMENDMENT CONTINUATION PAGE
SUMMARY OF CHANGES
1) PIPE MATERIAL CHANGE. Poly Vinyl Chloride (PVC) shall be replaced with Ductile Iron
Pipe (DIP) everywhere indicated throughout both the contract plans [drawings] and specifications.
DELETE: “PVC” throughout all documents REPLACE: with “DIP”
Reference Pipe Bedding cross sections A & B, Plans Sheet 53 and specification Section 02 60 00 for correct bedding procedures associated with DIP.
2) Section 02 24 00, 1.5.1
DELETE: Contractor shall have successfully completed at least 5 projects of the same scope and size or larger within the last 5 years totaling a minimum of 5000 LF. Contractor shall demonstrate specific experience in regard to the system installation to be performed.
REPLACE: Contractor shall have successfully completed at least 3 projects of the same scope and size or larger within the last 3 years totaling a minimum of 5000 LF. Contractor shall demonstrate specific experience in regard to the system installation to be performed.
3) Section 02 25 00, Paragraph 1.5.1
DELETE: A minimum of three construction contracts which have been successfully completed (within the last 3 years), which are of similar pipe type (includes diameter, material AND length), scope and complexity to the work of this Contract. Include the names of the contracts, the contact award amounts, the names, addresses and telephone numbers of the owners, the length of time required for the completion of each segment of directional drill (include setup, drilling and pullback), the location(s), pipe type, size of pipe, manufacturer of equipment, and other information relevant to the successful completion of the project.
Horizontal directional drilling ("HDD") Supervisor shall have (within the last years) direct experience in successfully completing HDD projects of a similar pipe size, length, and complexity.
Operators of the drill rig shall demonstrate a minimum of 12 months experience in the operation of the proposed drill rig.
REPLACE: A minimum of three construction contracts which have been successfully completed (within the last 5 years), which are of similar pipe type (includes diameter, material AND length), scope and complexity to the work of this Contract. Include the names of the contracts, the contact award amounts, the names, addresses and telephone numbers of the owners, the length of time required for the completion of each segment of directional drill (include setup, drilling and pullback), the location(s), pipe type, size of pipe, manufacturer of equipment, and other information relevant to the successful completion of the project.
Horizontal directional drilling ("HDD") Supervisor shall have (within the last years) direct experience in successfully completing HDD projects of a similar pipe size, length, and complexity.
Operators of the drill rig shall demonstrate a minimum of 12 months experience in the operation of the proposed drill rig.
4) SECTION 02 24 00, Paragraph 1.2:
DELETE “CLIN 0001D”
REPLACE with “Bid Item 0001AD"
5) SECTION 02 25 00, Paragraph 1.2:
ADD: “with under line item Bid Item 0001AE in Section 00 41 00, BID SCHEDULES”
6) SECTION 02 37 00, Paragraph 1.4:
ADD: “under line item Bid Item 0001AB in Section 00 41 00, BID SCHEDULES.”
7) SECTION 02 57 00, Paragraph 1.6:
ADD: “under line item Bid Item 0001AH in Section 00 41 00, BID SCHEDULES.”
8) SECTION 02 71 30, Paragraph 1.2:
ADD: “under line item Bid Item 0001AL in Section 00 41 00, BID SCHEDULES.”
9) SECTION 02 72 30, Paragraph 1.1:
ADD: “with under line item Bid Item 0001AL in Section 00 41 00, BID
SCHEDULES.”
10) SECTION 02 73 20, Paragraph 1.2:
DELETE: "0001AO"
REPLACE: with “Bid Item 0001AA.”
11) SECTION 02 74 10, Paragraph 1.5:
ADD: with “under line item Bid Item 0001AL in Section 00 41 00, BID
SCHEDULES.”
DELETE: "Section 02 74 10 HOT-MIX ASPHALT (HMA) FOR ROADS/DRIVEWAYS" in specification “02 74 10 HOT-MIX ASPHALT (HMA) FOR ROADS/DRIVEWAYS" REPLACE: with "02 71 30 BITUMINOUS BASE COURSE".
12) SECTION 02 83 10 CHAIN LINK FENCES AND GATES:
DELETE the Section in its entirety.
13) SECTION 02 92 10, Paragraph, 1.3:
ADD: with under line item Bid Item 0001AL in Section 00 41 00, BID
SCHEDULES.
14) SECTION 33 40 00:
ADD: New Paragraph 1.1.1
“1.1.1 Measurement and Payment Measurement and payment will be based on completed work performed in accordance with the drawings, specifications and the contract payment schedules and shall be included in the Contractor's lump sum price bid, under line item Bid Item 0001AL in Section 00 41 00, BID
SCHEDULES.”
15) SECTION 02 71 30, Para. 1.2.1:
ADD: Measurement Paragraph has changed to Lump Sum.
16) SECTION 0272 30, Para, 1.1.1:
17) SECTION 02 74 10, Para.1.4:
(End of Summary of Changes)