AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
W912HP-14-R-0033 Holly Hill to Harleyville Reach.
The purpose of this amendment is to revise the Scope of Work. See block 14 continuation page.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 3
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 28-Aug-2014
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912HP-14-R-0033
X 9B. DATED (SEE ITEM 11)
04-Aug-2014
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
28-Aug-2014
CODE
US ARMY CORPS OF ENGINEERS, CHARLESTON
69-A HAGOOD AVENUE
CHARLESTON SC 29403
W912HP 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912HP-14-R-0033
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE
The following have been added by full text:
AMENDMENT 0001
The Scope of Work was revise as follows:
a. APPENDICES, replaced in their entirety with the attached Pages 1-252.
b. Appendix C, added approximate soil boring locations.
c. 00 41 00, replaced Pages 2 and 3 with new Pages 6 and 7.
d. 02 25 00 Page 164, paragraph 1.3, deleted “steel and” from the sentence.
e. 02 25 00 Page 165, 1.4 Submittals, SD-01, third submittal changed to say “Submit additional soil test data prior to commencement of drilling/excavation work; FIO”.
f. 02 25 00, page 168, 1.6 General Job Requirements, first paragraph, added the following sentence to the end “HDD installation shall be guaranteed regardless of subsurface materials encountered.”
g. 02 25 00, Page 179, 3.12.1, deleted 4th paragraph beginning “Steel pipe welds…”
h. 02 30 00, Page 189, paragraph 2.1.2. 2nd paragraph, deleted ML from the list of unsuitable materials.
i. 02 30 00, page 194, section 3.3, bedding table. Revised table to the following: Type A bedding 25 percent, Type B bedding, 25 percent, Type C bedding 50 percent.
SECTION 00010 - SOLICITATION CONTRACT FORM
The required response date/time has changed from 04-Sep-2014 02:00 PM to 08-Sep-2014 11:00 AM.
(End of Summary of Changes)
W912HP-14-R-0033
LAKE MARION REGIONAL WATER AGENCY
HARLEYVILLE REACH
WATER TRANSMISSION MAIN
TECHNICAL SPECIFICATIONS
SOLICITATION NO. W912-HP-14-R-0033
JULY 2014
Prepared by:
K2PMPJDP
Typewritten Text Revision 1
LAKE MARION REGIONAL WATER AGENCY
HARLEYVILLE REACH
WATER TRANSMISSION MAIN
TECHNICAL SPECIFICATIONS
SOLICITATION NO.
JULY 2014
PREPARED BY:
HAZEN AND SAWYER, P.C.
CHARLOTTE, NC
U.S. ARMY CORPS OF ENGINEERS SANTEE COOPER
CHARLESTON DISTRICT MONCKS CORNER, SC
HARLEYVILLE REACH WATER TRANSMISSION MAIN COE
W912-HP-14-R-0033 JULY 2014
SECTION TABLE OF CONTENTS
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
DOCUMENT 00 01 15
LIST OF DRAWINGS
PART 1 GENERAL
1.1 SUMMARY
1.2 CONTRACT DRAWINGS
1.3 SUPPLEMENTARY DRAWINGS
1.3.1 Subsurface Data
-- End of Section Table of Contents --
DOCUMENT 00 01 15 Page 2
08/27/14 -9:36 AM
DOCUMENT 00 01 15
LIST OF DRAWINGS
PART 1 GENERAL
1.1 SUMMARY
This section lists the drawings for the project pursuant to contract clause "DFARS 252.236-7001, Contract Drawings, Maps and Specifications."
1.2 CONTRACT DRAWINGS
Contract drawings are as follows:
DRAWING SHEET
NO. NO. TITLE
1 COVER
X1 2 INDEX SHEET
X2 3 LEGEND AND NOTES
C1 4 MASTER METER SITE PLAN
M1 5 MASTER METER VAULT DETAILS
E1 6 MASTER METER ELECTRICAL SITE PLAN
E2 7 MASTER METER ELECTRICAL DETAILS
E3 8 MASTER METER GENERAL SCADA SCHEMATICS
P01 9 STA 0+00 TO STA 13+00
P02 10 STA 13+00 TO STA 26+00
P03 11 STA 26+00 TO STA 39+00
P04 12 STA 39+00 TO STA 52+00
P05 13 STA 52+00 TO STA 65+00
P06 14 STA 65+00 TO STA 78+00
P07 15 STA 78+00 TO STA 91+00
P08 16 STA 91+00 TO STA 104+00
P09 17 STA 104+00 TO STA 117+00
P10 18 STA 117+00 TO STA 130+00
P11 19 STA 130+00 TO STA 142+00
P12 20 STA 142+00 TO STA 155+50
P13 21 STA 155+50 TO STA 169+00
P14 22 STA 169+00 TO STA 182+00
P15 23 STA 182+00 TO STA 195+00
P16 24 STA 195+00 TO STA 208+00
P17 25 STA 208+00 TO STA 221+00
P18 26 STA 221+00 TO STA 234+00
P19 27 STA 234+00 TO STA 247+00
P20 28 STA 247+00 TO STA 260+00
P21 29 STA 260+00 TO STA 273+00
P22 30 STA 273+00 TO STA 286+00
P23 31 STA 286+00 TO STA 299+00
P24 32 STA 299+00 TO STA 312+50
P25 33 STA 312+50 TO STA 325+00
P26 34 STA 325+00 TO STA 338+00
P27 35 STA 338+00 TO STA 349+20
P28 36 WATER TANK ALTITUDE VALVES
P29 37 CROSS SECTIONS
DOCUMENT 00 01 15 Page 3
DRAWING SHEET TITLE
NO. NO.
D1 38 MISCELLANEOUS DETAILS
D2 39 MISCELLANEOUS DETAILS
D3 40 MISCELLANEOUS DETAILS
D4 41 MISCELLANEOUS DETAILS
D5 42 MISCELLANEOUS DETAILS
D6 43 MISCELLANEOUS DETAILS
1.3 SUPPLEMENTARY DRAWINGS
1.3.1 Subsurface Data
Subsurface data, contained in the soils report is included as part of the solicitation and attached as a reference in these documents.
-- End of Document --
DOCUMENT 00 01 15 Page 4
SECTION TABLE OF CONTENTS
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
DOCUMENT 00 41 00
BID SCHEDULES
PART 1 GENERAL
1.1 BASIS OF BIDS
1.1.1 Unit Price Schedule
-- End of Section Table of Contents --
DOCUMENT 00 41 00 Page 5
DOCUMENT 00 41 00
BID SCHEDULES
PART 1 GENERAL
1.1 BASIS OF BIDS
1.1.1 Unit Price Schedule
This contract will be awarded as one lump sum. A schedule of the unit price work (if applicable) is contained in Standard Form SF 1442, "Solicitation, Offer and Award." See Contract Clauses, "FAR 52.211-18, Variation in Estimated Quantity" and "FAR 52.236-16, Quantity Surveys," "DFARS.252.236-7008, Contract Prices - Bidding Schedules." The Unit Prices Form below is for informational purposes only.
Unit Prices Form
(i) Basis of Bid for Item 0001 shall be the Total Amount for Item 1 (Items 1AA through 1AM), complete in accordance with the drawings and specifications.
Item Description Estimated Quantity
Unit Amount
0001 All work complete in accordance with the drawings and specifications.
1 LS $(_____)
0001AA Mobilization 1 LS $(_____)
0001AB Temporary Construction Facilities
1 LS $(_____)
0001AC Erosion Control 1 LS $(_____)
0001AD Clearing/Grubbing Easements
1 LS $(_____)
0001AE Boring and Jacking 1 LS $(_____)
0001AF Horizontal Directional Drilled Pipe
1 LS $(_____)
0001AG Water Main Pipe (All Sizes & Materials)
1 LS $(_____)
0001AH Blow-Offs/Hydrants 1 LS $(_____)
0001AI Air Release Valves/Manholes
1 LS $(_____)
DOCUMENT 00 41 00 Page 6
Unit Prices Form
0001AJ Site Restoration/Seeding 1 LS $(_____)
0001AK Traffic Control 1 LS $(_____)
0001AL Demobilization/Project Closeout
1 LS $(_____)
0001AM Pavement Repair 1 LS $(_____)
0001AN Underground Packaged - Meter Station
1 LS $(_____)
0001AO Associated Sitework Underground Packaged Meter Station
1 LS $(_____)
0001AP Disinfection of Adjacent Pipeline
1 LS $(_____)
-- End of Document --
DOCUMENT 00 41 00 Page 7
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 11 00
SUMMARY OF WORK
PART 1 GENERAL
1.1 REFERENCES
1.2 WORK COVERED BY CONTRACT DOCUMENTS
1.2.1 Project Description
1.2.2 Location
1.3 EXISTING WORK
1.4 LOCATION OF UNDERGROUND FACILITIES
1.5 GOVERNMENT-FURNISHED MATERIAL AND EQUIPMENT
PART 2 PRODUCTS
PART 3 EXECUTION
-- End of Section Table of Contents --
SECTION 01 11 00 Page 8
SECTION 01 11 00
SUMMARY OF WORK
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. DEPARTMENT OF DEFENSE (DOD)
FAR 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements
1.2 WORK COVERED BY CONTRACT DOCUMENTS
1.2.1 Project Description
The Harleyville Reach Water Transmission Main contract consists of the furnishing, installing and placing into successful operation approximately 34,870 LF of 16-inch diameter pipe, a master meter station, and all associated work. This contract includes all pipe, valves, appurtenances, roadway bores, horizontally directionally drilled pipe, testing, quality control, safety and all other related work. This contract will be a portion of the Lake Marion Regional Water System and will be owned, operated and maintained by Santee Cooper, South Carolina's electric and water utility. The Contractor will be responsible for coordinating work with local utility owners, property owners, Lake Marion Water Treatment Plant personnel, the Town of Holly Hill water personnel, Town of Harleyville water personnel, Orangeburg County Personnel, and Dorchester County, (Intersection of Boyer Road and Gardner Blvd S-453) to Harleyville (Intersection of N. Railroad Ave and Dotson St.).
1.2.2 Location
The work shall be located along roadways, private easements and power line rights-of-way between the Town of Holly Hill, Orangeburg County, and the Town of Harleyville, Dorchester County, approximately as indicated. The exact location will be as indicated on the drawings and verified by Contractor's location survey.
1.3 EXISTING WORK
Contractor shall adhere to the requirements of FAR 52.236-9 , Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements".
a. As required to complete the Contract, Contractor shall only remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.
b. Contractor shall repair or replace portions of existing work which have been altered during construction operations to match existing
SECTION 01 11 00 Page 9 or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work shall be in a condition equal to or better than that which existed before new work started.
1.4 LOCATION OF UNDERGROUND FACILITIES
Contractor to obtain all required permits and notify Government. Scan the construction site with electromagnetic or sonic equipment, and mark the surface of the ground where existing underground utilities are discovered.
Verify the elevations of existing piping, utilities, and any type of underground obstruction not indicated or specified to be removed but indicated or discovered during scanning in locations to be traversed by piping,ducts, and other work to be installed. Verify elevations at each manhole or other structure at a minimum and adjust pipeline grade as necessary . Contractor shall contact Palmetto Utility Protection Service (PUPS) at 1-888-721-7877 or 811 at least 48 hours prior to digging.
1.5 GOVERNMENT-FURNISHED MATERIAL AND EQUIPMENT
All materials required by this contract are to be furnished by the Contractor and included in the lump sum price bid.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
-- End of Section --
SECTION 01 11 00 Page 10
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 22 00.00 10
MEASUREMENT AND PAYMENT
PART 1 GENERAL
1.1 SUBMITTALS
1.2 LUMP SUM PAYMENT ITEMS
1.2.1 Mobilization
1.2.1.1 Payment
1.2.1.2 Unit of Measure
1.2.2 Temporary Construction Facilities
1.2.2.1 Payment
1.2.2.2 Unit of Measure
1.2.3 Erosion Control
1.2.3.1 Payment
1.2.3.2 Unit of Measure
1.2.4 Clearing/Grubbing Easements
1.2.4.1 Payment
1.2.4.2 Unit of Measure
1.2.5 Boring and Jacking
1.2.5.1 Payment
1.2.5.2 Unit of Measure
1.2.6 Horizontal Directional Drilled Pipe
1.2.6.1 Payment
1.2.6.2 Unit of Measure
1.2.7 Water Main Pipe (All Sizes and Materials)
1.2.7.1 Payment
1.2.7.2 Unit of Measure
1.2.8 Blow-offs/Hydrants
1.2.8.1 Payment
1.2.8.2 Unit of Measure
1.2.9 Air Release Valves/Manholes
1.2.9.1 Payment
1.2.9.2 Unit of Measure
1.2.10 Site Restoration/Seeding
1.2.10.1 Payment
1.2.10.2 Unit of Measure
1.2.11 Traffic Control
1.2.11.1 Payment
1.2.11.2 Unit of Measure
1.2.12 Demobilization/Project Closeout
1.2.12.1 Payment
1.2.12.2 Unit of Measure
1.2.13 Pavement Repair
1.2.13.1 Payment
1.2.13.2 Unit of Measure
1.2.14 Underground Packaged Master Meter Station
1.2.14.1 Payment
1.2.14.2 Unit of Measure
SECTION 01 22 00.00 10 Page 11
1.2.15 Underground Packaged Master Meter Station - Site Work
1.2.15.1 Payment
1.2.15.2 Unit of Measure
1.2.16 Disinfection of Water Mains
1.2.16.1 Unit of Measure
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION (Not Applicable)
-- End of Section Table of Contents --
SECTION 01 22 00.00 10 Page 12
SECTION 01 22 00.00 10
MEASUREMENT AND PAYMENT
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals which do not have a "G" designation are for information only.
When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
SCHEDULE OF WORK ITEMS/COSTS; G
1.2 LUMP SUM PAYMENT ITEMS
Payment items for the work of this contract for which contract lump sum payments will be made are listed in the BIDDING SCHEDULE and described below. All costs for items of work, which are not specifically mentioned are to be included in the lump sum price. The lump sum price and payment made for all work shall constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided.
1.2.1 Mobilization
1.2.1.1 Payment
Payment for lump sum item 0001AA will be made for the costs associated with mobilization to the project location. This item is for the costs incurred on this contract, including any local permits, licenses, fees, insurance, bonds, equipment mobilization to the project site, and temporary facilities required for start-up. The project sign costs shall be included in this payment item.
1.2.1.2 Unit of Measure
Unit of measure: lump sum.
1.2.2 Temporary Construction Facilities
1.2.2.1 Payment
Item 0001AB includes furnishing all materials, equipment and labor required to install and maintain the temporary construction facilities and associated supplies, as specified until final acceptance of the project by the Corps.
SECTION 01 22 00.00 10 Page 13
1.2.2.2 Unit of Measure
Unit of measure: lump sum.
1.2.3 Erosion Control
1.2.3.1 Payment
Item 0001AC includes furnishing all materials, equipment and labor required to install and maintain erosion control devices, as specified and as shown on the Drawings. This item shall also include, but is not limited to, the following:
a. All temporary construction barrier fencing
b. All storm water pollution prevention measures, as specified in the specification and on the drawings.
c. Furnishing and installing silt fence, rip rap check dams, control barriers, filter fabrics, geotextiles and sediment control fences, as specified.
1.2.3.2 Unit of Measure
Unit of measure: lump sum.
1.2.4 Clearing/Grubbing Easements
1.2.4.1 Payment
Item 0001AD includes furnishing all materials, equipment and labor required to clear, grub and dispose of all cleared debris on the permanent and temporary easements.
1.2.4.2 Unit of Measure
Unit of measure: lump sum.
1.2.5 Boring and Jacking
1.2.5.1 Payment
Item 0001AE includes furnishing all materials, equipment and labor required for boring and jacking, as specified and between the stations indicated on the Drawings. This item shall also include bore pit, casing pipe, casing spacers, masonry walls, concrete cradles, brick bulkheads, and all other necessary appurtenances required to install the pipe between the bore and jack stations indicated on the drawings. All pipe material costs including transport, delivery, and storage shall be included in Item 0001AG Ductile Iron Pipe.
1.2.5.2 Unit of Measure
Unit of measure: lump sum.
SECTION 01 22 00.00 10 Page 14
1.2.6 Horizontal Directional Drilled Pipe
1.2.6.1 Payment
Item 0001AF includes furnishing all materials, equipment, and labor required to excavate, install and backfill 16" diameter pipe, and associated appurtenances, complete, as specified and as indicated on the contract drawings using horizontal directional drilling methods. This item shall also include:
a. Furnishing and installing all, stell casing HDPE piping, fittings, bends, DIP to HDPE adapters and connections, stiffeners, drill fluids, and all other necessary appurtenances, temporary or permanent, to place pipe installed by HDD into successful operation.
b. Complying with all applicable OSHA regulations.
c. Restoration of drill pits to original grade.
d. Removal and disposal of all drill fluids.
e. Joining of HDPE pipe joints together by heated butt-fusion or electro-fusion.
f. Any additional HDD lengths of HDPE required to successfully install HDD pipe to the minimum radius and cover requirements indicated on the contract drawings.
g. Cutting/removal and disposal of HDPE pipe to allow for connections.
h. Any and all work other than erosion control to ensure drill fluid does not enter wetlands areas or leaves the site.
1.2.6.2 Unit of Measure
Unit of measure: lump sum.
1.2.7 Water Main Pipe (All Sizes and Materials)
1.2.7.1 Payment
Item 0001AG includes furnishing all materials, equipment and labor required to excavate, install and backfill all water main pipe complete, as specified and as shown on the drawings. This item shall also include:
a. Furnishing and installing all piping, line valves, valve markers, plugs, fittings, bends, reducers, tangential outlets, gradient control mats and other necessary appurtenances to place pipe complete.
b. Complying with all applicable OSHA regulations.
c. Locating underground utilities and protecting existing utilities.
d. Installing temporary watertight plugs in the new line.
e. Furnishing, placing and compacting suitable backfill materials as required.
SECTION 01 22 00.00 10 Page 15
f. Stone bedding and all other fill materials.
g. Testing of water lines, as specified.
h. Testing of trench bottom, stockpiled materials and compaction as specified under earthwork.
i. Complying with regulations for construction within wetlands;
including stripping, storing and replacing topsoil, placing and removing temporary access roads, and anti-seepage collars.
j. Furnishing and installing polywrap, as specified and indicated on the drawings.
h. All other work not indicated in other items required to place new water main and appurtenances into successful operation.
Note : At specified locations, if existing piping is present, Contractor shall connect to piping and all costs therto shall be included in this line item. If existing piping is not where shown, Contractor shall furnish restrained plug and mark with a wood post, to be included in this line item.
1.2.7.2 Unit of Measure
Unit of measure: lump sum.
1.2.8 Blow-offs/Hydrants
1.2.8.1 Payment
Item 0001AH includes furnishing all materials, equipment and labor required to install blow-offs and hydrants as shown on drawings (See Detail Sheet D2). This item includes all piping, fittings, valves, rip up dissipater pad, and appurtenances at all locations indicated on Contract Drawings.
1.2.8.2 Unit of Measure
Unit of measure: lump sum.
1.2.9 Air Release Valves/Manholes
1.2.9.1 Payment
Item 0001AI includes furnishing all materials, equipment and labor required to install manhole as shown on typical manhole section (See Detail Sheet D3 of the drawings). This item also includes cone section, risers, frame and cover, steps, pipe connectors, air release valve and associated piping, valve markers and other appurtenances as applicable.
1.2.9.2 Unit of Measure
Unit of measure: lump sum.
SECTION 01 22 00.00 10 Page 16
1.2.10 Site Restoration/Seeding
1.2.10.1 Payment
Item 0001AJ includes furnishing all materials, equipment and labor required to prepare the seed bed, fertilize, seed and mulch the disturbed areas, as specified. This item shall also include the following:
a. Restoring the site to a condition equal to or better than original condition.
b. Temporary patching of driveways, walkways, and roadways immediately following construction and maintaining same until final or permanent repairs can be made.
c. Installing concrete sidewalks and curbs and gutters, as specified.
d. Temporary seeding, fertilizing and mulching
e. Shrub replacement and relocation.
1.2.10.2 Unit of Measure
Unit of measure: lump sum.
1.2.11 Traffic Control
1.2.11.1 Payment
Item 0001AK includes furnishing all materials, equipment and labor required to install and maintain traffic control devices and procedures, as specified and as shown in the Drawings.
1.2.11.2 Unit of Measure
Unit of measure: lump sum.
1.2.12 Demobilization/Project Closeout
1.2.12.1 Payment
Item 0001AL includes furnishing all costs incurred by the Contractor for removing all equipment, excess materials, refuse and other items from the project site once the project has been accepted by the Corps of Engineers. This item also includes furnishing of all operations and maintenance manuals, training and equipment startup.
1.2.12.2 Unit of Measure
Unit of measure: lump sum.
1.2.13 Pavement Repair
1.2.13.1 Payment
Item 0001AM includes furnishing all materials, equipment and labor required to remove and replace with new bituminous pavement in all areas indicated on the Contract Drawings. This work includes saw cut of existing pavements (roads or driveways), removal of debris to subgrade, SECTION 01 22 00.00 10 Page 17 compaction of subgrade, replacement of unsuitable materials with flowable fill, and installation of new bituminous pavement.
1.2.13.2 Unit of Measure
Unit of measure: lump sum.
1.2.14 Underground Packaged Master Meter Station
1.2.14.1 Payment
Item 0001AN includes furnishing all materials, equipment and labor required to excavate for, backfill for and install meter station and appurtenances as indicated on the Drawings. Includes all testing and disinfection of meter station piping.
1.2.14.2 Unit of Measure
Unit of measure: lump sum.
1.2.15 Underground Packaged Master Meter Station - Site Work
1.2.15.1 Payment
Item 0001AO includes furnishing all materials, equipment and labor required to excavate for, backfill for and install all site work associated with meter station and appurtenances as indicated on the Drawings.
1.2.15.2 Unit of Measure
Unit of measure: lump sum.
1.2.16 Disinfection of Water Mains
Item 0001AP includes furnishing all materials, equipment and labor required to flush and disinfect new water mains as well as approximately 73,000 linear feet of 24 to 30-inch diameter pipeline adjacent to the Harleyville Water Transmission Main (known as the Wells Crossroads Reach and the Holly Hill Reach). Laboratory testing and reporting to SCDHEC, coordination and dechlorinating all in accordance with the latest SCDHEC regulations.
Shall include all chemicals and temporary piping, sample ports on existing pipeline. Water shall be provided by Santee Cooper at minimum 1 ppm residual chlorine. Shall reimburse utility owner for all water used, not to exceed $1.00 per 1,000 gallons as metered at the plant. As-built drawings may be obtained from the water utility.
1.2.16.1 Unit of Measure
Unit of measure: lump sum.
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION (Not Applicable)
-- End of Section --
SECTION 01 22 00.00 10 Page 18
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 30 00
ADMINISTRATIVE REQUIREMENTS
PART 1 GENERAL
1.1 SUBMITTALS
1.2 MINIMUM INSURANCE REQUIREMENTS
1.3 SUPERVISION
1.4 PRECONSTRUCTION CONFERENCE
1.5 ELECTRONIC MAIL (E-MAIL) ADDRESS
PART 2 PRODUCTS
PART 3 EXECUTION
-- End of Section Table of Contents --
SECTION 01 30 00 Page 19
SECTION 01 30 00
ADMINISTRATIVE REQUIREMENTS
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
1.2 MINIMUM INSURANCE REQUIREMENTS
Procure and maintain during the entire period of performance under this contract the following minimum insurance coverage:
a. Comprehensive general liability: $500,000 per occurrence
b. Automobile liability: $200,000 per person, $500,000 per occurrence for bodily injury, $20,000 per occurrence for property damage
c. Workmen's compensation as required by Federal and State workers' compensation and occupational disease laws.
d. Employer's liability coverage of $100,000, except in States where workers compensation may not be written by private carriers,
e. Others as required by State law .
1.3 SUPERVISION
Have at least one qualified supervisor capable of reading, writing, and conversing fluently in the English language on the job site during working hours. In addition, if a Quality Control (QC) representative is required on the contract, then that individual shall also have fluent English communication skills.
1.4 PRECONSTRUCTION CONFERENCE
After award of the contract but prior to commencement of any work at the site, meet with the Contracting Officer to discuss and develop a mutual understanding relative to the administration of the value engineering and safety program, preparation of the schedule prices, shop drawings, and other submittals, scheduling programming, prosecution of the work, and clear expectations of the "Interim DD Form 1354" Submittal. Major subcontractors who will engage in the work shall also attend.
1.5 ELECTRONIC MAIL (E-MAIL) ADDRESS
The Contractor shall establish and maintain electronic mail (e-mail) capability along with the capability to open various electronic
SECTION 01 30 00 Page 20 attachments in Microsoft, Adobe Acrobat, and other similar formats.
Within 10 days after contract award, the Contractor shall provide the Contracting Officer a single (only one) e-mail address for electronic communications from the Contracting Officer related to this contract including, but not limited to contract documents, invoice information, request for proposals, and other correspondence. The Contracting Officer may also use email to notify the Contractor of base access conditions when emergency conditions warrant, such as hurricanes, terrorist threats, etc.
Multiple email address will not allowed.
It is the Contractor's responsibility to make timely distribution of all Contracting Officer initiated e-mail with its own organization including field office(s). The Contractor shall promptly notify the Contracting Officer, in writing, of any changes to this email address.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
-- End of Section --
SECTION 01 30 00 Page 21
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 32 01.00 10
PROJECT SCHEDULE
PART 1 GENERAL
1.1 REFERENCES
1.2 SUBMITTALS
1.3 QUALITY ASSURANCE
PART 2 PRODUCTS
PART 3 EXECUTION
3.1 GENERAL REQUIREMENTS
3.1.1 Approved Project Schedule
3.1.2 Schedule Status Reports
3.1.3 Default Terms
3.2 BASIS FOR PAYMENT AND COST LOADING
3.3 PROJECT SCHEDULE DETAILED REQUIREMENTS
3.3.1 Critical Path Method
3.3.2 Level of Detail Required
3.3.2.1 Activity Durations
3.3.2.2 Procurement Activities
3.3.2.3 Mandatory Tasks
3.3.2.4 Government Activities
3.3.2.5 Activity Responsibility Coding (RESP)
3.3.2.6 Activity Work Area Coding
3.3.2.7 Contract Changes/Requests for Equitable Adjustment (REA)
Coding (MODF)
3.3.2.8 Contract Line Item (CLIN) Coding (BIDI)
3.3.2.9 Phase of Work Coding (PHAS)
3.3.2.10 Category of Work Coding (CATW)
3.3.2.11 Definable Features of Work Coding (FOW1, FOW2, FOW3)
3.3.3 Scheduled Project Completion and Activity Calendars
3.3.3.1 Project Start Date
3.3.3.2 Schedule Constraints and Open Ended Logic
3.3.3.3 Early Project Completion
3.3.4 Interim Completion Dates
3.3.4.1 Start Phase
3.3.4.2 End Phase
3.3.4.3 Phase "X" Hammock
3.3.5 Default Progress Data Disallowed
3.3.6 Out-of-Sequence Progress
3.3.7 Negative Lags and Start to Finish Relationships
3.3.8 Calculation Mode
3.3.9 Milestones
3.4 PROJECT SCHEDULE SUBMISSIONS
3.4.1 Preliminary Project Schedule Submission
SECTION 01 32 01.00 10 Page 22
3.4.2 Initial Project Schedule Submission
3.4.3 Periodic Schedule Updates
3.4.4 Standard Activity Coding Dictionary
3.5 SUBMISSION REQUIREMENTS
3.5.1 Data CD's
3.5.2 Narrative Report
3.5.3 Approved Changes Verification
3.5.4 Schedule Reports
3.5.4.1 Activity Report
3.5.4.2 Logic Report
3.5.4.3 Total Float Report
3.5.4.4 Earnings Report by CLIN
3.5.5 Network Diagram
3.5.5.1 Continuous Flow
3.5.5.2 Project Milestone Dates
3.5.5.3 Critical Path
3.5.5.4 Banding
3.5.5.5 S-Curves
3.6 PERIODIC SCHEDULE UPDATE MEETINGS
3.6.1 Update Submission Following Progress Meeting
3.6.2 Status of Activities
3.6.2.1 Start and Finish Dates
3.6.2.2 Remaining Duration
3.6.2.3 Percent Complete
3.6.2.4 Logic Changes
3.6.2.5 Other Changes
3.7 REQUESTS FOR TIME EXTENSIONS
3.7.1 Justification of Delay
3.7.2 Submission Requirements
3.7.3 Additional Submission Requirements
3.8 DIRECTED CHANGES
3.9 WEEKLY PROGRESS MEETINGS
3.10 OWNERSHIP OF FLOAT
3.11 TRANSFER OF SCHEDULE DATA INTO RMS/QCS
-- End of Section Table of Contents --
SECTION 01 32 01.00 10 Page 23
SECTION 01 32 01.00 10
PROJECT SCHEDULE
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
ECB 2005-10 (2005) Scheduling Requirements for Testing of Mechanical Systems in Construction Contracts
ER 1-1-11 (1995) Administration -- Progress, Schedules, and Network Analysis Systems
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Project Schedule; G
1.3 QUALITY ASSURANCE
Designate an authorized representative to be responsible for the preparation of the schedule and all required updating (activity status) and preparation of reports. The authorized representative shall have previously developed, created, and maintained at least 2 electronic schedules for projects similar in nature and complexity to this project and shall be experienced in the use of the scheduling software that meets the requirements of this specification.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
3.1 GENERAL REQUIREMENTS
Prepare for approval a Project Schedule, as specified herein, pursuant to the Contract Clause, SCHEDULE FOR CONSTRUCTION CONTRACTS. Show in the schedule the sequence in which the Contractor proposes to perform the work and dates on which the Contractor contemplates starting and completing all
SECTION 01 32 01.00 10 Page 24 scheduled activities. The scheduling of construction is the responsibility of the Contractor. Contractor management personnel shall actively participate in its development. Subcontractors and suppliers working on the project shall also contribute in developing and maintaining an accurate Project Schedule. Provide a schedule that is a forward planning as well as a project monitoring tool.
3.1.1 Approved Project Schedule
Use the approved Project Schedule to measure the progress of the work and to aid in evaluating time extensions. Make the schedule cost loaded and activity coded. The schedule will provide the basis for all progress payments. If the Contractor fails to submit any schedule within the time prescribed, the Contracting Officer may withhold approval of progress payments until the Contractor submits the required schedule.
3.1.2 Schedule Status Reports
Provide a Schedule Status Report on at least a monthly basis. If, in the opinion of the Contracting Officer, the Contractor falls behind the approved schedule, take steps necessary to improve its progress including those that may be required by the Contracting Officer, without additional cost to the Government. In this circumstance, the Contracting Officer may require the Contractor to increase the number of shifts, overtime operations, days of work, and/or the amount of construction plant, and to submit for approval any supplementary schedule or schedules as the Contracting Officer deems necessary to demonstrate how the approved rate of progress will be regained.
3.1.3 Default Terms
Failure of the Contractor to comply with the requirements of the Contracting Officer shall be grounds for a determination, by the Contracting Officer, that the Contractor is not prosecuting the work with sufficient diligence to ensure completion within the time specified in the contract. Upon making this determination, the Contracting Officer may terminate the Contractor's right to proceed with the work, or any separable part of it, in accordance with the default terms of the contract.
3.2 BASIS FOR PAYMENT AND COST LOADING
Use the schedule as the basis for determining contract earnings during each update period and therefore the amount of each progress payment.
Lack of an approved schedule update, or qualified scheduling personnel, will result in the inability of the Contracting Officer to evaluate contract earned value for the purposes of payment. Failure of the Contractor to provide all required information will result in the disapproval of the preliminary, initial and subsequent schedule updates.
In the event schedule revisions are directed by the Contracting Officer and those revisions have not been included in subsequent revisions or updates, the Contracting Officer may hold retainage up to the maximum allowed by contract, each payment period, until such revisions to the Project Schedule have been made. Activity cost loading shall be reasonable, as determined by the Contracting Officer. The aggregate value of all activities coded to a contract CLIN shall equal the value of the CLIN on the Schedule.
SECTION 01 32 01.00 10 Page 25
3.3 PROJECT SCHEDULE DETAILED REQUIREMENTS
The computer software system utilized to produce and update the Project Schedule shall be capable of meeting all requirements of this specification. Failure of the Contractor to meet the requirements of this specification will result in the disapproval of the schedule.
3.3.1 Critical Path Method
Use the Critical Path Method (CPM) of network calculation to generate the Project Schedule. Prepare the Project Schedule using the Precedence Diagram Method (PDM).
3.3.2 Level of Detail Required
Develop the Project Schedule to an appropriate level of detail. Failure to develop the Project Schedule to an appropriate level of detail, as determined by the Contracting Officer, will result in its disapproval.
The Contracting Officer will consider, but is not limited to, the following characteristics and requirements to determine appropriate level of detail:
3.3.2.1 Activity Durations
Reasonable activity durations are those that allow the progress of ongoing activities to be accurately determined between update periods. Less than 2 percent of all non-procurement activities shall have Original Durations (OD) greater than 20 work days or 30 calendar days. Procurement activities are defined herein.
3.3.2.2 Procurement Activities
The schedule must include activities associated with the submittal, approval, procurement, fabrication and delivery of long lead materials, equipment, fabricated assemblies and supplies. Long lead procurement activities are those with an anticipated procurement sequence of over 90 calendar days. A typical procurement sequence includes the string of activities: submit, approve, procure, fabricate, and deliver.
3.3.2.3 Mandatory Tasks
The following tasks must be included and properly scheduled:
a. Submission of mechanical systems layout drawings.
b. Submission and approval of O & M manuals.
c. Submission and approval of as-built drawings.
d. Submission and approval of 1354 data and installed equipment lists.
e. Submission and approval of testing and air balance (TAB).
f. Submission of TAB specialist design review report.
g. Submission and approval of fire protection specialist.
h. Submission and approval of testing and balancing of HVAC plus commissioning plans and data. Develop the schedule logic
SECTION 01 32 01.00 10 Page 26 associated with testing and commissioning of mechanical systems to a level of detail consistent with ECB 2005-10 .
i. Air and water balancing.
j. HVAC commissioning.
k. Controls testing plan submission.
l. Controls testing.
m. Performance Verification testing.
n. Other systems testing, if required.
o. Contractor's pre-final inspection.
p. Correction of punchlist from Contractor's pre-final inspection.
q. Government's pre-final inspection.
r. Correction of punch list from Government's pre-final inspection.
s. Final inspection.
3.3.2.4 Government Activities
Show Government and other agency activities that could impact progress.
These activities include, but are not limited to: approvals, approvals, design reviews, environmental permit approvals by State regulators, inspections, utility tie-in, Government Furnished Equipment (GFE) and Notice to Proceed (NTP) for phasing requirements.
3.3.2.5 Activity Responsibility Coding (RESP)
Assign responsibility Code for all activities to the Prime Contractor, Subcontractor or Government agency responsible for performing the activity. Activities coded with a Government Responsibility code include, but are not limited to: Government approvals, Government design reviews, environmental permit approvals by State regulators, Government Furnished Equipment (GFE) and Notice to Proceed (NTP) for phasing requirements.
Code all activities not coded with a Government Responsibility Code to the Prime Contractor or Subcontractor responsible to perform the work.
Activities shall not have more than one Responsibility Code. Examples of acceptable activity code values are: DOR (for the designer of record);
ELEC (for the electrical subcontractor); MECH (for the mechanical subcontractor); and GOVT (for USACE). Unacceptable code values are abbreviations of the names of subcontractors.
3.3.2.6 Activity Work Area Coding
Assign Work Area code to activities based upon the work area in which the activity occurs. Define work areas based on resource constraints or space constraints that would preclude a resource, such as a particular trade or craft work crew, from working in more than one work area at a time due to restraints on resources or space. Examples of Work Area Coding include different areas within a floor of a building, different floors within a building, and different buildings within a complex of buildings.
Activities shall not have more than one Work Area Code. Not all
SECTION 01 32 01.00 10 Page 27 activities are required to be Work Area coded. A lack of Work Area coding will indicate the activity is not resource or space constrained.
3.3.2.7 Contract Changes/Requests for Equitable Adjustment (REA) Coding
(MODF)
Assign Activity code to any activity or sequence of activities added to the schedule as a result of a Contract Modification, when approved by the Contracting Officer, with a Contract Changes/REA Code. Key all Code values to the Government's modification numbering system. Any activity or sequence of activities added to the schedule as a result of alleged constructive changes made by the Government may be added to a copy of the current schedule, subject to the approval of the Contracting Officer.
Assign Activity codes for these activities with a Contract Changes/REA Code. Key the code values to the Contractor's numbering system. Approval to add these activities does not necessarily mean the Government accepts responsibility and, therefore, liability for such activities and any associated impacts to the schedule, but rather the Government recognizes such activities are appropriately added to the schedule for the purposes of maintaining a realistic and meaningful schedule. Such activities shall not be Responsibility Coded to the Government unless approved. An activity shall not have more than one Contract Changes/REA Code.
3.3.2.8 Contract Line Item (CLIN) Coding (BIDI)
Code all activities to the CLIN on the Contract Line Item Schedule to which the activity belongs. An activity shall not contain more than one CLIN Item Code. CLIN Item code all activities, even when an activity is not cost loaded.
3.3.2.9 Phase of Work Coding (PHAS)
Assign Phase of Work Code to all activities based upon the phase of work in which the activity occurs. Code activities to either a Design Phase or a Construction Phase a Construction Phase . Code fast track design and construction construction phases proposed by the Contractor to allow filtering and organizing the schedule by fast track design and construction packages. If the contract specifies construction phasing with separately defined performance periods, identify a Construction Phase Code to allow filtering and organizing the schedule accordingly. Each activity shall be identified with a single project phase and have only one Phase of Work code.
3.3.2.10 Category of Work Coding (CATW)
Assign Category of Work Code to all Activities based upon the category of work to which the activity belongs. Category of Work Code must include, but is not limited to: design, design submittal, design reviews, review conferences, permits, construction submittals, construction submittal approvals, Acceptance, Procurement, Fabrication, Delivery, Weather Sensitive Installation, Non-Weather Sensitive Installation, Start-Up, Test and Turnover. Assign a Category of Work Code to each activity. Each activity shall have only one Category of Work Code.
3.3.2.11 Definable Features of Work Coding (FOW1, FOW2, FOW3)
Assign a Definable Feature of Work Code to appropriate activities based on the definable feature of work to which the activity belongs. Definable Feature of Work is defined in Specification Section 01 45 00.00 10 QUALITY
SECTION 01 32 01.00 10 Page 28
CONTROL. An activity shall not have more than one Definable Feature of Work Code. Not all activities are required to be Definable Feature of Work Coded.
3.3.3 Scheduled Project Completion and Activity Calendars
The schedule interval shall extend from NTP date to the required contract completion date. The contract completion activity (End Project) shall finish based on the required contract duration in the accepted contract proposal, as adjusted for any approved contract time extensions. The first scheduled work period shall be the day after NTP is received by the Contractor. Schedule activities on a calendar to which the activity logically belongs. Activities may be assigned to a 7 day calendar when the contract assigns calendar day durations for the activity such as a Government Acceptance activity. If the Contractor intends to perform physical work less than seven days per week, schedule the associated activities on a calendar with non-work periods identified including weekends and holidays. Assign the Category of Work Code - Weather Sensitive Installation to those activities that are weather sensitive.
Original durations must account for anticipated normal adverse weather.
The Government will interpret all work periods not identified as non-work periods on each calendar as meaning the Contractor intends to perform work during those periods.
3.3.3.1 Project Start Date
The schedule shall start no earlier than the date on which the NTP was acknowledged. Include as the first activity in the project schedule an activity called "Start Project"( or NTP). The "Start Project" activity shall have an "ES" constraint date equal to the date that the NTP was acknowledged, and a zero day duration.
3.3.3.2 Schedule Constraints and Open Ended Logic
Constrain completion of the last activity in the schedule by the contract completion date. Schedule calculations shall result in a negative float when the calculated early finish date of the last activity is later than the contract completion date. Include as the last activity in the project schedule an activity called "End Project". The "End Project" activity shall have an "LF" constraint date equal to the contract completion date for the project, and with a zero day duration or by using the "project must finish by" date in the scheduling software. The schedule shall have no constrained dates other than those specified in the contract. The use of artificial float constraints such as "zero fee float" or "zero total float" are typically prohibited. There shall only be 2 open ended activities: Start Project (or NTP) with no predecessor logic and End Project with no successor logic.
3.3.3.3 Early Project Completion
In the event the Preliminary or Initial project schedule calculates an early completion date of the last activity prior to the contract completion date, identify those activities that it intends to accelerate and/or those activities that are scheduled in parallel to support the Contractor's "early" completion. The last activity shall have a late finish constraint equal to the contract completion date and the schedule will calculate positive float. The Government will not approve an early completion schedule with zero float on the longest path. The Government is under no obligation to accelerate activities for which it is
SECTION 01 32 01.00 10 Page 29 responsible to support a proposed early contract completion.
3.3.4 Interim Completion Dates
Constrain contractually specified interim completion dates to show negative float when the calculated early finish date of the last activity in that phase is later than the specified interim completion date.
3.3.4.1 Start Phase
Include as the first activity for a project phase an activity called "Start Phase X" where "X" refers to the phase of work. The "Start Phase X" activity shall have an "ES" constraint date equal to the date on which the NTP was acknowledged, and a zero day duration.
3.3.4.2 End Phase
Include as the last activity for a project phase an activity called "End Phase X" where "X" refers to the phase of work. The "End Phase X" activity shall have an "LF" constraint date equal to the specified completion date for that phase and a zero day duration.
3.3.4.3 Phase "X" Hammock
Include a hammock type activity for each project phase called "Phase X" where "X" refers to the phase of work. The "Phase X" hammock activity shall be logically tied to the earliest and latest activities in the phase.
3.3.5 Default Progress Data Disallowed
Do not automatically update Actual Start and Finish dates with default mechanisms that may be included in the scheduling software. Activity Actual Start (AS) and Actual Finish (AF) dates assigned during the updating process shall match those dates provided from Contractor Quality Control Reports. Failure of the Contractor to document the AS and AF dates on the Daily Quality Control report for every in-progress or completed activity, and failure to ensure that the data contained on the Daily Quality Control reports is the sole basis for schedule updating shall result in the disapproval of the Contractor's updated schedule and the inability of the Contracting Officer to evaluate Contractor progress for payment purposes. Updating of the percent complete and the remaining duration of any activity shall be independent functions. Disable program features which calculate one of these parameters from the other.
3.3.6 Out-of-Sequence Progress
Activities that have progressed before all preceding logic has been satisfied (Out-of-Sequence Progress) will be allowed only on a case-by-case basis subject to approval by the Contracting Officer.
Propose logic corrections to eliminate all out of sequence progress or justify not changing the sequencing for approval prior to submitting an updated project schedule. Correct out of sequence progress that continues for more than two update cycles by logic revision, as approved by the Contracting Officer.
3.3.7 Negative Lags and Start to Finish Relationships
Lag durations contained in the project schedule shall not have a negative value. Do not use Start to Finish (SF) relationships.
SECTION 01 32 01.00 10 Page 30
3.3.8…