Pre-Bid Site Visit Minutes.pdf

PDF 75 KB Posted

Attached to
Tybee Island Shoreline Protection Project
Solicitation number
W912HN27BA001
Issued by

About this file

This is a Pre-Bid Site Visit Summary for federal procurement W912HN27BA001, the Tybee Island Shoreline Protection Project (TISPP), held on November 19, 2026.

The project involves shoreline protection and beach nourishment work at Tybee Island, Georgia, with two primary work areas: the North Beach area near the North Terminal Groin and the 19th Street area featuring the South Terminal Groin and existing T-groins. The contract duration is 90 calendar days, with all construction activities, including demobilization, required to be completed by April 30, 2027, before the sea turtle nesting season begins on May 1. Work scope includes sand placement operations that may require pumping around T-groins, and contractors must maintain access to existing driveways along the 19th Street staging area throughout construction. The Government confirmed that concurrent construction activities by other contractors are possible within the project area, with potential overlap areas identified on contract drawings. All contract options will be awarded at the time of contract award, not separately. Key procurement deadlines are the Bidder Inquiry Deadline of November 30, 2026, and Bid Opening on December 10, 2026. Prospective bidders are directed to submit all solicitation questions through the Bidder Inquiry module in ProjNet for official Government responses, and any solicitation changes or clarifications will be issued through formal solicitation amendments; verbal discussions during the site visit do not modify solicitation requirements.

View the file

Other files

File Type Posted
Site Visit Sign In Sheet.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Pre-Bid Site Visit

W912HN27BA001

Tybee Island Shoreline Protection Project (TISPP)

Date: 19 November 2026

• The pre-bid site visit commenced at 10:00 at the North Beach Parking Lot, near the Gulick Street beach access.

• Attendees signed in, and introductions were made.

• MSG Francisco, Contracting Division, opened the meeting with an overview of the project and discussed the pre-bid site visit procedures and expectations.

• MSG Francisco emphasized that all questions concerning the solicitation must be submitted through the Bidder Inquiry module in ProjNet for an official Government response. Any changes or clarifications to the solicitation will be issued through a formal solicitation amendment, and verbal discussions during the site visit do not modify the solicitation requirements.

• MSG Francisco identified the following procurement dates:

o Bidder Inquiry Deadline: 30 November 2026 o Bid Opening: 10 December 2026

• Ms. Courtney Messer and Mr. Spencer Davis, Project Management, discussed the contract duration of 90 calendar days and the environmental construction window, emphasizing that all construction activities (including demobilization) must be completed no later than 30 April 2027 (sea turtle nesting season begins 1 May).

NORTH BEACH SITE VISIT:

• All attendees proceeded down the boardwalk at the North Beach Parking Lot near Gulick Street to the beach.

• The Government identified the North Terminal Groin and discussed the project area.

• A prospective bidder inquired whether another contractor could potentially be performing work within the project area concurrently. The Government confirmed that concurrent construction activities were possible and identified the potential area of overlap on the contract drawings.

• A prospective bidder requested clarification regarding the base bid and optional bid items.

The Government stated that all contract options would be awarded at the time of contract award.

19TH STREET SITE VISIT:

• The site visit continued to the 19th Street beach access, where all attendees proceeded down the boardwalk to the beach.

• The Government identified the South Terminal Groin and the existing T-groins within the project area.

• The Government explained that, if the applicable option were awarded, sand placement operations would require pumping around the T-groins in this area.

• The Government also emphasized that the Contractor would be required to maintain access to the existing driveways along the 19th Street staging area throughout construction.

• Mr. Spencer Davis concluded the pre-bid site visit at 10:35.