B.02 - BIH Solicitation AMD 0001 - W912HN25B5007 (Updated Drawings & Specs).pdf

PDF 10 MB Posted

Attached to
Solicitation - FY25 Brunswick Inner Harbor Maintenance Dredging Project Federal contract opportunity
Solicitation number
W912HN25B5007
Issued by
Department of the Army Corps of Engineers Engineering District Savannah

About this file

This document is an Amendment (AMD 0001) to a federal solicitation for the FY25 Brunswick Inner Harbor Maintenance Dredging project (Solicitation Number W912HN25B5007) issued by the U.S. Army Corps of Engineers Savannah District. The amendment updates technical specifications and contract drawings for a maintenance dredging project in Brunswick Harbor, Glynn County, Georgia. The project involves removing up to 835,000 cubic yards of material from multiple waterways including East River, Brunswick River, South Brunswick River, and Lower Turtle River, with dredging depths ranging from 36 to 41 feet Mean Lower Low Water (MLLW). Dredged materials will be deposited in the Andrews Island disposal area, and the project is expected to be completed within 120 days of notice to proceed.

The solicitation includes detailed specifications covering work requirements, environmental protections, safety procedures, quality control, and survey methodologies. Key project elements include using a hydraulic cutterhead dredge, implementing extensive environmental protection measures for endangered species and marine habitats, maintaining strict water quality standards, and conducting comprehensive pre- and post-dredging surveys. The project will require careful coordination with government agencies, adherence to environmental regulations, and detailed reporting on operations, safety, and environmental compliance throughout the dredging process.

View the file

Other files for this federal contract opportunity

Other files attached to Solicitation - FY25 Brunswick Inner Harbor Maintenance Dredging Project, newest first.
File Type Posted
C.04 BID ABSTRACT - FY25 Brunswick Inner Harbor (signed).pdf PDF
B.02 - FY25 BIH Solicitation with Drawings & Specs- W912HN25B5007.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

See changes below .

1. CONTRACT ID CODE PAGE OF PAGES

J 1 2

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 14-Jul-2025

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912HN25B5007

X 9B. DATED (SEE ITEM 11)

30-Jun-2025

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

14-Jul-2025

CODE

USACE - SAVANNAH DISTRICT

100 W. OGLETHORPE AVE

SAVANNAH GA 31401

W912HN 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912HN25B5007

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION 00 00 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

The following have been added by full text:

AMD 0001

SUMMARY OF CHANGES

A. CONTRACT CHANGES: There are no Contract Changes with this amendment.

B. TECHNICAL SPECIFICATION CHANGES: The technical specification has been updated with this amendment.

C. CONTRACT DRAWINGS: The contract drawings has been updated with this amendment.

(End of Summary of Changes)

Glynn County, Georgia

Solicitation Number

W912HN-25-B-5007

FY25 Brunswick Inner Harbor Maintenance Dredging Specifications Divisions 01 - 35 and Appendices

PN CWK0650

May 2025

U.S. ARMY ENGINEER DISTRICT, SAVANNAH

CORPS OF ENGINEERS

100 WEST OGLETHORPE AVENUE

SAVANNAH, GEORGIA 31401-3640

US Army Corps Of Engineers Savannah District

FY25 Brunswick Inner Harbor Maintenance Dredging 25B5007 Glynn County, Georgia

PROJECT TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

01 11 00 SUMMARY OF WORK

01 14 00 WORK RESTRICTIONS

01 33 00 SUBMITTAL PROCEDURES

01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS

01 42 00 SOURCES FOR REFERENCE PUBLICATIONS

01 45 00 QUALITY CONTROL

01 45 00.15 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)

01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS

DIVISION 35 - WATERWAY AND MARINE CONSTRUCTION

35 20 23 DREDGING

APPENDICES

APPENDIX A STANDARD FORMS

-- End of Project Table of Contents --

PROJECT TABLE OF CONTENTS Page 1

FY25 Brunswick Inner Harbor Maintenance Dredging CWK0650

SECTION 01 11 00

SUMMARY OF WORK

PART 1 GENERAL

1.1 WORK COVERED BY CONTRACT DOCUMENTS

1.1.1 Project Description

The work includes providing construction services, including personnel, transportation, mobilization/demobilization, equipment, and materials, required in connection with maintenance dredging in East River, South Brunswick River, Lower Turtle River, and Brunswick River and disposal of the dredged materials. Perform these services in accordance with the Contract. Services not specifically described are nevertheless required if they can be identified as an item commonly a part of normally expected and/or professional grade work of a comparable nature.

The dredging is located in the Brunswick Inner Harbor in Glynn County, Georgia. Disposal shall be in the Andrews Island disposal area in Glynn County, Georgia.

The units of measure will be U.S. standard units.

Horizontal control shall be NAD 83 Georgia East state plane coordinate system. Vertical control shall be Mean Lower Low Water (MLLW) EPOCH 1983-2001. Coordinate with the Contracting Officer to ensure that surveys are consistent with Government standards and accepted datum.

The limits of construction are as shown in the Contract Drawings.

Construction work described applies to the excavation and disposal of dredged material in the designated areas, and survey before and after construction.

1.1.2 Location

The work is located at Brunswick Harbor in Glynn County, Georgia, approximately as indicated. The exact location will be shown by the Contracting Officer.

1.2 CONTRACTOR REQUIREMENTS

a. Project Involves Handling of Asbestos: No

b. Occupancy During Construction: yes

c. Phasing of Work: No

d. Construction Schedule: Bar Chart

e. CQC System Requirements: CQC Manager, Superintendent, and Site Safety Health Officer.

1.3 PRE-BID SITE VISIT

Prior to the submission of bids, it is recommended that bidders visit the project site location to become familiar with the project requirements.

SECTION 01 11 00 Page 1

Failure to visit the project site will not disqualify a bid; however, the bidder is required to comply with the terms and conditions of the resultant Contract by reason of such failure. In no event will a failure to inspect the site constitute grounds for a claim after award of Contract.

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

Not used.

-- End of Section --

SECTION 01 11 00 Page 2

SECTION 01 14 00

WORK RESTRICTIONS

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

U.S. ARMY CORPS OF ENGINEERS (USACE)

ER 1110-1-5 (1984) Plant Pest Quarantined Areas and Foreign Soil Samples

U.S. COAST GUARD (USCG)

COMDTINST M16672.2 Navigation Rules, International-Inland

U.S. CODE (USC)

46 USC 33 Inspection Generally

46 USC 51 Load Lines

U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)

33 CFR 64 Marking of Structures, Sunken Vessels and other Obstructions

33 CFR 66 Private Aids to Navigation

33 CFR 67 Aids to Navigation on Artificial Islands and Fixed Structures

33 CFR 67.01 General Requirements

33 CFR 67.40-1 Notification to District Commander

33 CFR 81 Implementing Rules

33 CFR 84 Annex I: Positioning and Technical Details of Lights and Shapes

33 CFR 89 Inland Navigation Rules: Implementing Rules

46 CFR 7 Boundary Lines

1.2 WORK IN QUARANTINED AREA

The U.S. Army Corps of Engineers (USACE) and the U.S. Department of Agriculture (USDA) have a compliance agreement requiring measures to prevent the spread of certain plant pests that may be present in the soil ( ER 1110-1-5 ). Major portions of the southeastern states are in a quarantine area for such pests, including the imported fire ant. In addition, adjacent states to the north have introduced infestations

SECTION 01 14 00 Page 1 resulting from movement of soil from infested southeastern states.

Thoroughly clean the construction equipment and tools at the previous job site in a manner that ensures that these implements are free from residual soil, egg deposits from plant pests, noxious weeds, and plant seeds.

Equipment shall be cleaned using water under pressure, and hand tools shall be thoroughly cleaned by brushing or other means to remove soil. In addition, thoroughly clean construction equipment used for this Contract before it is removed from this job site. Consult with the USDA jurisdictional office for additional cleaning requirements.

1.3 COORDINATION WITH OTHER CONTRACTORS

Cooperate with other contractors performing work in the project area and designated disposal areas to avoid conflicts and delays. Provide and bury pipelines (with caution signs saying "buried pipeline") below grade of the dike to a sufficient depth to prevent damage during motor grading and to avoid the hindrance of traffic.

1.4 DATUM AND BENCHMARKS

The plane of reference of mean lower low water (MLLW) is that determined by benchmarks for Brunswick Harbor, which is available in the office of the District Engineer, U.S. Army Engineer District, Savannah, 100 West Oglethorpe Avenue , Savannah, Georgia 31401-3640. Access to this data may be obtained through:

U.S. Army Corps of Engineers ATTENTION: Miles Saunders Hydro-Survey Section (OPN-CS) 100 West Oglethorpe Ave.

Savannah, Georgia 31401

(912) 652-5783 Miles.G.Saunders@usace.army.mil

1.5 PLANT

a. Keep sufficient plant on the job to meet the requirements of the work.

The plant must be in satisfactory operating condition, capable of safely and efficiently performing the work as set forth in the Contract, and is subject to Government inspections. The plant listed on the Contractor's Plant Data Sheet (see form in Appendix A) is the minimum which the Contractor agrees to place on the job, unless otherwise determined by the Government, and its listing is not to be construed as an agreement on the part of the Government that it is adequate for the performance of the work.

b. Scows must be kept in good condition, coamings repaired, and the pockets provided with proper doors or appliances to prevent leakage of material.

c. Keep pipelines for hydraulic machines in good condition and promptly and properly repair items and leaks or breaks along their lengths. Repair damages to dikes and riverbanks, including pot-holes, for easy driving access. Report such leaks and breaks to the Contract Officer's Representative.

d. No reduction in the capacity of the plant employed on the work shall be made except by written permission of the Contracting Officer. The measure of the "capacity of the plant" shall be its actual performance on the work.

SECTION 01 14 00 Page 2

e. In the event of collision, fire, major breakdown, or other actions that prevent continuation of dredging operations for more than 48 hours and are anticipated to continue for 30 days or more, provide additional dredging plant. If additional plant as directed by the Contracting Officer is not delivered and placed in operation within the allowable 30 days, the Contract will be terminated under FAR 52.249 10 DEFAULT (FIXED PRICE

CONSTRUCTION).

1.6 NAVIGATION AIDS AND PERMITS

1.6.1 Navigation Aids

Navigation aids located within or near the areas required to be dredged will be removed, if necessary, by the U.S. Coast Guard in advance of dredging operations. Do not remove, change the location of, obstruct, willfully damage, make fast to, or interfere with aids to navigation. If the Contracting Officer determines the aids will interfere with the dredging process, the Government will request the U.S. Coast Guard to relocate the aids.

1.6.2 Dredging Aids

Dredging aid markers and lights must not be colored or placed in a manner that obstructs or confuses them with navigation aids.

Mark submerged pipelines with signs, buoys, and lights. Post appropriate signs and lights at the entry and exit points. In-water lines (rope, chain, and cable, including the lines to secure turbidity curtains) must be stiff, taut, and non-looping. Examples of such lines are heavy metal chains and heavy cables that do not easily loop and tangle.

1.7 SIGNAL LIGHTS

Lights and day signals displayed by towing vessels with tows on which no signals can be displayed, vessels working on wrecks, dredges and vessels engaged in laying cables or pipes or in submarine or bank protection operations, lights displayed on dredge pipeline and day signals displayed by vessels of more than 65 feet in length moored or anchored in a fairway or channel and the passing by other vessels or floating plant working in navigable channels, shall be as set forth in COMDTINST M16672.2 or 33 CFR 81 Appendix A (International) and 33 CFR 84 through 33 CFR 89 (Inland) as applicable.

1.8 NOTICE TO MARINERS

If the Contractor, during dredging operations, encounters objects on the channel bottom which could be a hazard to navigation, notify the Government and the USCG Marine Safety Office (912-652-4353) of the location of said object immediately so the Coast Guard may put out a Notice to Mariners. Furnish a description of said object, the latitude and longitude of the reported object, and other pertinent information necessary to alert shippers in the area.

1.9 COAST GUARD CERTIFICATION OF PLANT

Furnish evidence that the floating plant (or self-propelled dredge) has the proper and necessary U.S. Coast Guard certifications under the following laws and regulations:

SECTION 01 14 00 Page 3

Vessels, their cargo and miscellaneous 46 USC 33

Inland Water Rules 46 CFR 7

Coastwise vessels, certificated Oceans, and load line exemptions

46 USC 51

1.10 ADVANCE NOTICE REQUIREMENT

Give the Contracting Officer 15 days written notice of the intended date of completion in each reach so that the next assigned area may be surveyed sufficiently in advance of the Contractor's operations.

1.11 COMPLIANCE WITH APPLICABLE NAVIGATION RULES AND REGULATIONS, EQUIPMENT

a. Ensure that the vessels used in project operations are commanded, equipped, navigated, and operated in strict compliance with the general regulations of the Department of the Army and of the Coast Guard, including applicable section, safety, environmental and navigational rules and regulations of the Code of Federal Regulations (CFR), parts 33 and 46.

b. Equipment placed by the Contractor on or over the seabed of the work area, i.e., pipeline, pipeline risers and booster stations, are obstructions or structures in accordance with 33 CFR 67.01 . Such equipment or portions thereof are subject to regulations set forth in 33 CFR 64 , 33 CFR 66 , and 33 CFR 67 .

c. Notifying Commander, Seventh Coast Guard District, per 33 CFR 67.40-1 , and secure the necessary project work approvals. Maintain and operate job site equipment and vessels in accordance with applicable laws.

1.12 AUTOMATIC IDENTIFICATION SYSTEM (AIS) VESSEL TRACKING

Dredges, tug boats, crew boats, survey vessels, dive team vessels, and other attendant plants working on this project must have working AIS tracking on board vessels. The large plants (i.e. the dredge) must have Class A AIS Systems. The smaller, more maneuverable attendant plants may have Class B AIS Systems.

1.13 Submerged Pipelines

There are additional restrictions for submerged pipeline as detailed in 35 20 23.

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

Not used.

SECTION 01 14 00 Page 4

SECTION 01 33 00

SUBMITTAL PROCEDURES

PART 1 GENERAL

1.1 SUMMARY

1.1.1 Submittal Information

The Contracting Officer may request submittals in addition to those specified when deemed necessary to adequately describe the work covered in the respective sections. Each submittal is to be complete and in sufficient detail to allow ready determination of compliance with contract requirements.

Units of weights and measures used on all submittals are to be the same as those used in the contract drawings.

1.1.2 Project Type

The Contractor's Quality Control (CQC) Manager is to check and approve all items before submittal and stamp, sign, and date indicating action taken.

Proposed deviations from the Contract requirements are to be clearly identified. Include within submittals items such as: Contractor's, manufacturer's, or fabricator's drawings; descriptive literature including (but not limited to) catalog cuts, diagrams, operating charts or curves;

test reports; test cylinders; samples; O&M manuals (including parts list);

certifications; warranties; and other such required submittals.

1.1.3 Submission of Submittals

Schedule and provide submittals requiring Government approval before acquiring the material or equipment covered thereby. Pick up and dispose of samples not incorporated into the work in accordance with manufacturer's Safety Data Sheets (SDS) and in compliance with existing laws and regulations.

1.2 DEFINITIONS

1.2.1 SUBMITTAL DESCRIPTIONS (SD)

Submittal requirements are specified in the technical sections. Examples and descriptions of submittals identified by the Submittal Description (SD) numbers and titles follow:

SD-01 Preconstruction Submittals

Submittals that are required prior to or at the start of construction (work) or the next major phase of the construction on a multiphase contract.

Preconstruction Submittals include schedules and a tabular list of locations, features, and other pertinent information regarding products, materials, equipment, or components to be used in the work.

Certificates Of Insurance

SECTION 01 33 00 Page 1

Surety Bonds

List Of Proposed Subcontractors

List Of Proposed Products

Baseline Network Analysis Schedule (NAS)

Submittal Register

Schedule Of Prices Or Earned Value Report

Accident Prevention Plan

Work Plan

Quality Control (QC) plan

Environmental Protection Plan

SD-06 Test Reports

Report signed by authorized official of testing laboratory that a material, product or system identical to the material, product or system to be provided has been tested in accord with specified requirements. Unless specified in another section, testing must have been within three years of date of contract award for the project.

Report that includes findings of a test required to be performed on an actual portion of the work or prototype prepared for the project before shipment to job site.

Report that includes finding of a test made at the job site or on sample taken from the job site, on portion of work during or after project completion.

Investigation reports

Daily logs and checklists

Final acceptance test and operational test procedure

SD-07 Certificates

Statements printed on the manufacturer's letterhead and signed by responsible officials of manufacturer of product, system or material attesting that the product, system, or material meets specification requirements. Must be dated after award of project contract and clearly name the project.

Document required of Contractor, or of a manufacturer, supplier, installer or Subcontractor through Contractor. The document purpose is to further promote the orderly progression of a portion of the work by documenting procedures, acceptability of methods, or personnel qualifications.

Confined space entry permits

Text of posted operating instructions

SECTION 01 33 00 Page 2

SD-11 Closeout Submittals

Documentation to record compliance with technical or administrative requirements or to establish an administrative mechanism.

Submittals required for Guiding Principle Validation (GPV) or Third Party Certification (TPC).

Special requirements necessary to properly close out a construction contract. For example, Record Drawings and as-built drawings. Also, submittal requirements necessary to properly close out a major phase of construction on a multi-phase contract.

1.2.2 Approving Authority

Office or designated person authorized to approve the submittal.

1.2.3 Work

As used in this section, on-site and off-site construction required by contract documents, including labor necessary to produce submittals, construction, materials, products, equipment, and systems incorporated or to be incorporated in such construction. In exception, excludes work to produce SD-01 submittals.

1.3 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with this section.

SD-01 Preconstruction Submittals

Submittal Register ; G, RO

Form ENG 4025 ; G, RO

1.4 SUBMITTAL CLASSIFICATION

1.4.1 Government Approved (G)

Government approval is required for extensions of design, critical materials, variations, equipment whose compatibility with the entire system must be checked, and other items as designated by the Government.

Within the terms of the Contract Clause SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION, submittals are considered to be "shop drawings."

1.4.2 For Information Only

Submittals not requiring Government approval will be for information only. Within the terms of the Contract Clause SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION, they are not considered to be "shop drawings".

SECTION 01 33 00 Page 3

1.5 PREPARATION

1.5.1 Transmittal Form

Use the ENG Form 4025-R transmittal form for submitting both Government-approved and information-only submittals. Submit in accordance with the instructions on the reverse side of the form. These forms are included in the RMS CM software that the Contractor is required to use for this contract. Properly complete this form by filling out all the heading blank spaces and identifying each item submitted. Exercise special care to ensure proper listing of the specification paragraph and sheet number of the contract drawings pertinent to the data submitted for each item.

1.5.2 Submittal Format

1.5.2.1 Format of SD-01 Preconstruction Submittals

When the submittal includes a document that is to be used in the project, or is to become part of the project record, other than as a submittal, do not apply the Contractor's approval stamp to the document itself, but to a separate sheet accompanying the document.

Provide data in the unit of measure used in the Contract. Unless otherwise specified, submit two sets of administrative submittals..

1.5.2.2 Format of SD-06 Test Reports

By prominent notation, indicate each report in the submittal. Indicate the specification number and paragraph number to which each report pertains.

1.5.2.3 Format of SD-07 Certificates

Provide design data and certificates on 8 1/2 by 11 inch paper.

1.5.2.4 Format of SD-11 Closeout Submittals

When the submittal includes a document that is to be used in the project or is to become part of the project record, other than as a submittal, do not apply the Contractor's approval stamp to the document itself, but to a separate sheet accompanying the document.

Provide data in the unit of measure used in the contract documents.

1.5.3 Source Drawings for Shop Drawings

1.5.3.1 Source Drawings

The entire set of source drawing files (DWG) will not be provided to the Contractor. Request the specific Drawing Number for the preparation of shop drawings. Only those drawings requested to prepare shop drawings will be provided. These drawings are provided only after award.

1.5.3.2 Terms and Conditions

Data contained on these electronic files must not be used for any purpose other than as a convenience in the preparation of construction data for the referenced project. Any other use or reuse is at the sole risk of the Contractor and without liability or legal exposure to the Government. The

SECTION 01 33 00 Page 4

Contractor must make no claim, and waives to the fullest extent permitted by law any claim or cause of action of any nature against the Government, its agents, or its subconsultants that may arise out of or in connection with the use of these electronic files. The Contractor must, to the fullest extent permitted by law, indemnify and hold the Government harmless against all damages, liabilities, or costs, including reasonable attorney's fees and defense costs, arising out of or resulting from the use of these electronic files.

These electronic source drawing files are not construction documents.

Differences may exist between the source drawing files and the corresponding construction documents. The Government makes no representation regarding the accuracy or completeness of the electronic source drawing files, nor does it make representation to the compatibility of these files with the Contractor hardware or software. The Contractor is responsible for determining if any conflict exists. In the event that a conflict arises between the signed and sealed construction documents prepared by the Government and the furnished source drawing files, the signed and sealed construction documents govern. Use of these source drawing files does not relieve the Contractor of the duty to fully comply with the contract documents, including and without limitation the need to check, confirm and coordinate the work of all contractors for the project. If the Contractor uses, duplicates or modifies these electronic source drawing files for use in producing construction data related to this contract, remove all previous indication of ownership (seals, logos, signatures, initials and dates).

1.5.4 Electronic File Format

Provide submittals in electronic format, with the exception of material samples required for SD-04 Samples items, in RMS 3.0. Compile the submittal file as a single, complete document, to include the Transmittal Form described within. Name the electronic submittal file specifically according to its contents, and coordinate the file naming convention with the Contracting Officer. Electronic files must be of sufficient quality that all information is legible. Use PDF as the electronic format, unless otherwise specified or directed by the Contracting Officer. Generate PDF files from original documents with bookmarks so that the text included in the PDF file is searchable and can be copied. If documents are scanned, optical character resolution (OCR) routines are required. Index and bookmark files exceeding 30 pages to allow efficient navigation of the file. When required, the electronic file must include a valid electronic signature or a scan of a signature.

1.6 INFORMATION ONLY SUBMITTALS

Submittals without a "G" designation must be certified by the CQC Manager and submitted to the Contracting Officer for information-only. Approval of the Contracting Officer is not required on information only submittals. The Contracting Officer will mark "receipt acknowledged" on submittals for information and will return only the transmittal cover sheet to the Contractor. Normally, submittals for information only will not be returned. However, the Government reserves the right to return unsatisfactory submittals and require the Contractor to resubmit any item found not to comply with the contract. This does not relieve the Contractor from the obligation to furnish material conforming to the plans and specifications; will not prevent the Contracting Officer from requiring removal and replacement of nonconforming material incorporated in the work; and does not relieve the Contractor of the requirement to

SECTION 01 33 00 Page 5 furnish samples for testing by the Government laboratory or for check testing by the Government in those instances where the technical specifications so prescribe.

1.7 PROJECT SUBMITTAL REGISTER

A sample Project Submittal Register showing items of equipment and materials for when submittals are required by the specifications is provided as "Attachment A - Submittal Register".

1.7.1 Submittal Management

Prepare and maintain a submittal register, as the work progresses. Do not change data that is output in columns (c), (d), (e), and (f) as delivered by Government; retain data that is output in columns (a), (g), (h), and

(i) as approved. As an attachment, provide a submittal register showing items of equipment and materials for which submittals are required by the specifications. This list may not be all-inclusive and additional submittals may be required. Maintain a submittal register for the project in accordance with Section 01 45 00.15 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE(RMS CM). The Government will provide the initial submittal register in electronic format with the following fields completed, to the extent that will be required by the Government during subsequent usage.

Column (c): Lists specification section in which submittal is required.

Column (d): Lists each submittal description (SD Number. and type, e.g., SD-02 Shop Drawings) required in each specification section.

Column (e): Lists one principal paragraph in each specification section where a material or product is specified. This listing is only to facilitate locating submitted requirements. Do not consider entries in column (e) as limiting the project requirements.

Thereafter, track the submittals by maintaining a complete list, including completion of all data columns and all dates on which submittals are received by and returned by the Government.

1.7.2 Preconstruction Use of Submittal Register

Submit the submittal register. Include the QC plan and the project schedule. Verify that all submittals required for the project are listed and add missing submittals. Coordinate and complete the following fields on the register submitted with the QC plan and the project schedule:

Column (a) Activity Number: Activity number from the project schedule.

Column (g) Contractor Submit Date: Scheduled date for the approving authority to receive submittals.

Column (h) Contractor Approval Date: Date that Contractor needs approval of submittal.

Column (i) Contractor Material: Date that Contractor needs

SECTION 01 33 00 Page 6 material delivered to Contractor control.

1.7.3 Contractor Use of Submittal Register

Update the following fields with each submittal throughout the contract.

Column (b) Transmittal Number: List of consecutive, Contractor-assigned numbers.

Column (j) Action Code (k): Date of action used to record Contractor's review when forwarding submittals to QC.

Column (l) Date submittal transmitted.

Column (q) Date approval was received.

1.7.4 Approving Authority Use of Submittal Register

Update the following fields:

Column (b) Transmittal Number: List of consecutive, Contractor-assigned numbers.

Column (l) Date submittal was received.

Column (m) through (p) Dates of review actions.

Column (q) Date of return to Contractor.

1.7.5 Delivery of Copies

Submit an updated electronic copy of the submittal register to the Contracting Officer with each invoice request. Provide an updated Submittal Register monthly regardless of whether an invoice is submitted.

1.8 VARIATIONS

Variations from contract requirements require Contracting Officer approval pursuant to contract FAR 52.236-21 "Specifications and Drawings for Construction", and will be considered where advantageous to the Government.

1.8.1 Considering Variations

Discussion of variations with the Contracting Officer before submission will help ensure that functional and quality requirements are met and minimize rejections and resubmittals. When contemplating a variation that results in lower cost, consider submission of the variation as a Value Engineering Change Proposal.

Specifically point out variations from contract requirements in transmittal letters. Failure to point out variations may cause the Government to require rejection and removal of such work at no additional cost to the Government.

1.8.2 Proposing Variations

When proposing variation, deliver a written request to the Contracting

SECTION 01 33 00 Page 7

Officer (CO), with documentation of the nature and features of the variation and why the variation is desirable and beneficial to Government.

Include the DOR's written analysis and approval. If lower cost is a benefit, also include an estimate of the cost savings. In addition to documentation required for variation, include the submittals required for the item. Clearly mark the proposed variation in all documentation.

1.8.3 Warranting that Variations are Compatible

When delivering a variation for approval, the Contractor warrants that this contract has been reviewed to establish that the variation, if incorporated, will be compatible with other elements of work.

1.8.4 Review Schedule Extension

In addition to the normal submittal review period, a period of 14 days will be allowed for the Government to consider submittals with variations.

1.9 SCHEDULING

Schedule and submit concurrently product data and shop drawings covering component items forming a system or items that are interrelated. Submit pertinent certifications at the same time. No delay damages or time extensions will be allowed for time lost in late submittals.

a. Coordinate scheduling, sequencing, preparing, and processing of submittals with performance of work so that work will not be delayed by submittal processing. The Contractor is responsible for additional time required for Government reviews resulting from required resubmittals. The review period for each resubmittal is the same as for the initial submittal.

b. Submittals required by the contract documents are listed on the submittal register. If a submittal is listed in the submittal register but does not pertain to the contract work, the Contractor is to include the submittal in the register and annotate it "N/A" with a brief explanation. Approval by the Contracting Officer does not relieve the Contractor of supplying submittals required by the contract documents but that have been omitted from the register or marked "N/A."

c. Resubmit the submittal register and annotate it monthly with actual submission and approval dates. When all items on the register have been fully approved, no further resubmittal is required.

Contracting Officer review will be completed within 15 days after the date of submission.

1.10 GOVERNMENT APPROVING AUTHORITY

When the approving authority is the Contracting Officer, the Government will:

a. Note the date on which the submittal was received.

b. Review submittals for approval within the scheduling period specified and only for conformance with project design concepts and compliance with contract documents.

SECTION 01 33 00 Page 8

c. Identify returned submittals with one of the actions defined in paragraph REVIEW NOTATIONS and with comments and markings appropriate for the action indicated.

Upon completion of review of submittals requiring Government approval, stamp and date submittals.

1.10.1 Review Notations

Submittals will be returned to the Contractor with the following notations:

a. Submittals marked "approved" or "accepted" authorize proceeding with the work covered.

b. Submittals marked "approved as noted" or "approved, except as noted, resubmittal not required," authorize proceeding with the work covered provided that the Contractor takes no exception to the corrections.

c. Submittals marked "not approved," "disapproved," or "revise and resubmit" indicate incomplete submittal or noncompliance with the contract requirements or design concept. Resubmit with appropriate changes. Do not proceed with work for this item until the resubmittal is approved.

d. Submittals marked "not reviewed" indicate that the submittal has been previously reviewed and approved, is not required, does not have evidence of being reviewed and approved by Contractor, or is not complete. A submittal marked "not reviewed" will be returned with an explanation of the reason it is not reviewed. Resubmit submittals returned for lack of review by Contractor or for being incomplete, with appropriate action, coordination, or change.

e. Submittals marked "receipt acknowledged" indicate that submittals have been received by the Government. This applies only to "information-only submittals" as previously defined.

1.11 DISAPPROVED SUBMITTALS

Make corrections required by the Contracting Officer. If the Contractor considers any correction or notation on the returned submittals to constitute a change to the contract drawings or specifications, give notice to the Contracting Officer as required under the FAR clause titled CHANGES. The Contractor is responsible for the dimensions and design of connection details and the construction of work. Failure to point out variations may cause the Government to require rejection and removal of such work at the Contractor's expense.

If changes are necessary to submittals, make such revisions and resubmit in accordance with the procedures above. No item of work requiring a submittal change is to be accomplished until the changed submittals are approved.

1.12 APPROVED SUBMITTALS

The Contracting Officer's approval of submittals is not to be construed as a complete check, and indicates only that the general method of construction, materials, detailing, and other information are satisfactory.

SECTION 01 33 00 Page 9

Approval or acceptance by the Government for a submittal does not relieve the Contractor of the responsibility for meeting the contract requirements or for any error that may exist, because under the Quality Control (QC) requirements of this contract, the Contractor is responsible for ensuring information contained with in each submittal accurately conforms with the requirements of the contract documents.

After submittals have been approved or accepted by the Contracting Officer, no resubmittal for the purpose of substituting materials or equipment will be considered unless accompanied by an explanation of why a substitution is necessary.

1.13 APPROVED SAMPLES

Approval of a sample is only for the characteristics or use named in such approval and is not be construed to change or modify any contract requirements. Before submitting samples, provide assurance that the materials or equipment will be available in quantities required in the project. No change or substitution will be permitted after a sample has been approved.

Match the approved samples for materials and equipment incorporated in the work. If requested, approved samples, including those that may be damaged in testing, will be returned to the Contractor, at its expense, upon completion of the contract. Unapproved samples will also be returned to the Contractor at its expense, if so requested.

Failure of any materials to pass the specified tests will be sufficient cause for refusal to consider, under this contract, any further samples of the same brand or make as that material. The Government reserves the right to disapprove any material or equipment that has previously proved unsatisfactory in service.

Samples of various materials or equipment delivered on the site or in place may be taken by the Contracting Officer for testing. Samples failing to meet contract requirements will automatically void previous approvals. Replace such materials or equipment to meet contract requirements.

1.14 WITHHOLDING OF PAYMENT

Payment for materials incorporated in the work will not be made if required approvals have not been obtained.

1.15 STAMPS

Certify the submittal data as follows on Form ENG 4025 : "I certify that the above submitted items had been reviewed in detail and are correct and in strict conformance with the contract drawings and specifications except as otherwise stated.

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

Not used.

SECTION 01 33 00 Page 10

SECTION 01 33 00 Page 11

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 1 OF 3 PAGES

FY25 BRUNSWICK INNER HARBOR MAINTENANCE DREDGING

01 33 00 SD-01 Preconstruction Submittals

1.7 G ROSubmittal Register

1.15 G ROForm ENG 4025

01 35 26 SD-01 Preconstruction Submittals

1.16 G RODive Operations Plan

1.8 G ROAccident Prevention Plan (APP)

3.2 G RODiving Safe Practices Manual

1.8.3.7 G ROSafe Access Plan

1.7.1.2 G ROENG Form 6282

1.7.2 G ROENG Form 6282

1.8.3.3 G ROENG FORM 6213

SD-06 Test Reports

1.5Monthly Exposure Reports

1.13Notifications and Reports

1.13.2 G ROAccident Reports

1.13.3LHE Inspection Reports

SD-07 Certificates

1.7.8Crane Operators/Riggers

1.8.3.2 G ROStandard Lift Plan

1.13.4 G ROStandard Lift Plan

1.8.3.3 G ROCritical Lift Plan

1.8.3.4 G RONaval Architecture Analysis

1.9Activity Hazard Analysis (AHA)

1.10.1Confined Space Entry Permit

1.10.1Hot Work Permit

1.14Hot Work Permit

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P H

C L A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

AUTH REMARKS

(a) (b) (c) (d) (e) (f) (g) (h) (i) (j) (k) (l) (m) (n) (o) (p) (q) (r)

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 2 OF 3 PAGES

01 35 26 1.13.4Certificate of Compliance

01 45 00 SD-01 Preconstruction Submittals

3.2 G ROContractor Quality Control (CQC)

Plan

SD-06 Test Reports

3.9.2Verification Statement

01 57 19 SD-01 Preconstruction Submittals

1.6.1Preconstruction Survey

1.8 G ROSolid Waste Management Permit

1.6.2 G RORegulatory Notifications

1.7 G ROEnvironmental Protection Plan

1.5 G ROEndangered Species Watch Plan

1.6.5 G ROEmployee Training Records

1.6.4 G ROEnvironmental Manager

Qualifications

SD-06 Test Reports

1.8.1 G ROMonthly Solid Waste Disposal

Report

SD-07 Certificates

1.6.5 G ROEmployee Training Records

SD-11 Closeout Submittals

3.5.2.1 G ROWaste Determination

Documentation

3.5.2.4 G RODisposal Documentation for

Hazardous and Regulated Waste

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 3 OF 3 PAGES

01 57 19 1.6.5 G ROAssembled Employee Training

Records

3.5.2.1 G ROHazardous Waste/Debris

Management

1.6.2 G RORegulatory Notifications

35 20 23 SD-01 Preconstruction Submittals

1.6 G DODredging and Disposal Plan

SD-07 Certificates

1.9.7Stoplogs

1.20 G DOProgress Chart

1.14.2.3Daily Report of Operations

1.23Man-Hour Report

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SECTION 01 35 26

GOVERNMENTAL SAFETY REQUIREMENTS

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only. Additional references can be found in EM 385-1-1.

AMERICAN SOCIETY OF MECHANICAL ENGINEERS (ASME)

ASME B30.3 (2020) Tower Cranes

ASME B30.5 (2021) Mobile and Locomotive Cranes

ASME B30.8 (2020) Floating Cranes and Floating Derricks

ASME B30.9 (2021) Slings

ASME B30.20 (2021) Below-the-Hook Lifting Devices

ASME B30.22 (2023) Articulating Boom Cranes

ASME B30.26 (2015; R 2020) Rigging Hardware

AMERICAN SOCIETY OF SAFETY PROFESSIONALS (ASSP)

ASSP A10.44 (2020) Control of Energy Sources (Lockout/Tagout) for Construction and Demolition Operations

ASSP Z244.1 (2024) The Control of Hazardous Energy Lockout, Tagout and Alternative Methods

ASSP Z359.2 (2023) Minimum Requirements for a Comprehensive Managed Fall Protection Program

ASSP Z359.4 (2022) Safety Requirements for Assisted-Rescue and Self-Rescue Systems, Subsystems and Components

ASTM INTERNATIONAL (ASTM)

ASTM F855 (2023) Standard Specifications for Temporary Protective Grounds to Be Used on De-energized Electric Power Lines and Equipment

INSTITUTE OF ELECTRICAL AND ELECTRONICS ENGINEERS (IEEE)

IEEE 1048 (2016) Guide for Protective Grounding of Power Lines

SECTION 01 35 26 Page 1

INTERNATIONAL SAFETY EQUIPMENT ASSOCIATION (ISEA)

ANSI/ISEA Z89.1 (2014; R 2019) American National Standard for Industrial Head Protection

NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)

NFPA 10 (2022; ERTA 1 2021) Standard for Portable Fire Extinguishers

NFPA 70 (2023) National Electrical Code

NFPA 70E (2024) Standard for Electrical Safety in the Workplace

NFPA 241 (2022) Standard for Safeguarding Construction, Alteration, and Demolition Operations

NFPA 51B (2024) Standard for Fire Prevention During Welding, Cutting, and Other Hot Work

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1 (2024) Safety -- Safety and Occupational Health (SOH) Requirements

U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)

29 CFR 1910 Occupational Safety and Health Standards

29 CFR 1910.147 The Control of Hazardous Energy (Lock Out/Tag Out)

29 CFR 1910.333 Selection and Use of Work Practices

29 CFR 1915 Confined and Enclosed Spaces and Other Dangerous Atmospheres in Shipyard Employment

29 CFR 1915.89 Control of Hazardous Energy (Lockout/Tags-Plus)

29 CFR 1926 Safety and Health Regulations for Construction

29 CFR 1926.500 Fall Protection

29 CFR 1926.1400 Cranes and Derricks in Construction

CPL 2.100 (1995) Application of the Permit-Required Confined Spaces (PRCS) Standards, 29 CFR 1910.146

1.2 DEFINITIONS

The following definitions are for the convenience of the reader. If there is a referenced document in the text of this specification section, that

SECTION 01 35 26 Page 2 is the document that should define terms for that paragraph. If further clarification is needed, contact the Contracting Officer. Additional definitions are in EM 385-1-1 .

1.2.1 Site Safety and Health Officer (SSHO)

A Contractor Employee that is responsible for overseeing and ensuring implementation of the prime Contractor's Safety and Occupational Health (SOH) program according to the Contract, EM 385-1-1 , applicable federal, state, and local requirements.

1.2.1.1 Level One SSHO

A designated employee with full-time SOH responsibility that meets and follows the requirements of EM 385-1-1 .

1.2.1.2 Level Two SSHO

A designated employee with Level Two SSHO responsibility that meets and follows the requirements of EM 385-1-1 . Level Two SSHOs cannot be assigned to projects that have a residual Risk Assessment Code (RAC) of high or extremely high.

1.2.1.3 Level Three SSHO

A designated Qualified Person or Competent Person with SOH responsibility that meets and follows the requirements of EM 385-1-1 . Level 3 SSHOs cannot be assigned to projects that have a residual RAC of high or extremely high.

1.2.1.4 Alternate SSHO

An employee that meets the definition of the contract-required level SSHO, but is not the primary SSHO.

1.2.2 Competent Person (CP)

The CP is a person designated in writing, who, through training, knowledge and experience, is capable of identifying, evaluating, and addressing existing and predictable hazards in the working environment or working conditions that are unsanitary, hazardous, or dangerous to personnel, and who has authorization to take prompt corrective measures to eliminate them.

1.2.3 Qualified Person (QP)

The QP is a person designated in writing, who, by possession of a recognized degree, certificate, or professional standing, or extensive knowledge, training, and experience, has successfully demonstrated their ability to solve or resolve problems related to the subject matter, the work, or the project.

1.3 SUBMITTALS

Government Acceptance or Approval does not remove responsibility from the Contractors for their actions or liability.

Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for information only. When used, a code following the "G" classification

SECTION 01 35 26 Page 3 identifies the office that will review the submittal for the Government.

Submit the following in accordance with Section 01 33 00 SUBMITTAL

PROCEDURES:

SD-01 Preconstruction Submittals

Dive Operations Plan ; G, RO

Accident Prevention Plan (APP) ; G, RO

Diving Safe Practices Manual ; G, RO

Safe Access Plan ; G, RO

ENG Form 6282 ; G, RO

ENG FORM 6213; G, RO

SD-06 Test Reports

Monthly Exposure Reports

Notifications and Reports

Accident Reports ; G, RO

LHE Inspection Reports

SD-07 Certificates

Crane Operators/Riggers

Standard Lift Plan ; G, RO

Critical Lift Plan ; G, RO

Naval Architecture Analysis ; G, RO

Activity Hazard Analysis (AHA)

Confined Space Entry Permit

Hot Work Permit

Certificate of Compliance

1.4 PUBLIC HEALTH EMERGENCIES

In the event of a declared public health emergency, follow safety precautions as required by the Occupational Safety and Health Administration (OSHA) www.osha.gov , the Centers for Disease Control and Prevention (CDC) www.cdc.gov , and as required by federal, state and local requirements.

1.5 MONTHLY EXPOSURE REPORTS

Provide a Monthly Exposure Report by the fifth of each month. This report is a compilation of employee-hours worked each month for all site workers, both Prime and subcontractor. Failure to submit the report may result in

SECTION 01 35 26 Page 4 retention of up to 10 percent of the progress payment.

1.6 REGULATORY REQUIREMENTS

In addition to the detailed requirements included in the provisions of this Contract, comply with the most recent edition of USACE EM 385-1-1 , and the following federal, state, and local laws, ordinances, criteria, rules and regulations at the date of the Solicitation for this Contract.

Submit matters of interpretation of standards to the…