This document is an amendment to a solicitation for the Brunswick Harbor Entrance Channel Maintenance Dredging Contract (Solicitation # W912HN25B5002). The purpose of the amendment is to change the permitted hopper dredge use period within Brunswick Harbor from 15 December 2024 to 30 June 2025, to 15 December 2024 to 31 March 2025. There are no other technical changes or contract drawing changes included in this amendment. The contract provides construction services for maintenance dredging, including furnishing personnel, transportation, mobilization/demobilization, equipment, and materials. Up to 1 million cubic yards of material is expected to be removed from the entrance channel and up to 100,000 cubic yards from the Cedar Hammock Range, to be placed in the offshore dredged material disposal site (ODMDS). The work is located in the Brunswick Harbor, Georgia deep draft navigation project in Glynn County.

View the file

Other files for this federal contract opportunity

Other files attached to W912HN25B5002 - Solicitation for Brunswick Harbor Entrance Channel Maintenance Dredging, newest first.
File Type Posted
C.04 BID ABSTRACT - Brunswick Entrance Channel Maintenance Dredging_KO signed.pdf PDF
B.02 - Solicatation AMD 0002 - W912HN25B5002.pdf PDF
A.03 - W912HN-25-B-5002_SPECS.pdf PDF
A.03 - W912HN-25-B-5002_DRAWINGS.pdf PDF
B.02 - Solicatation - W912HN25B5002.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

1. CONTRACT CHANGES: The purpose of this amendment is to change the Hopper dredge use w ithin Brunsw ick from 15 December 2024 to 30 June 2025, to 15 December 2024 to 31 March 2025.

2. TECHNICAL SPECIFICATION CHANGES: There are no technical changes with this amendment.

3. CONTRACT DRAWINGS: There are no contract drawing changes with this amendment.

NOTE: All amendments issued under this solicitation should be signed, and the signed copy turned in along with your bid.

1. CONTRACT ID CODE PAGE OF PAGES

1 2

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 11-Oct-2024

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912HN25B5002

X 9B. DATED (SEE ITEM 11)

10-Oct-2024

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

11-Oct-2024

CODE

USACE - SAVANNAH DISTRICT

100 W. OGLETHORPE AVE

SAVANNAH GA 31401

W912HN 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912HN25B5002

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION 01 00 00 - GENERAL REQUIREMENTS

The following have been modified:

STATEMENT OF WORK

Statement of Work FY25 Brunswick Harbor Entrance Channel Maintenance Dredging

The Brunswick Harbor Entrance Channel Maintenance Dredging Contract provides construction services, including furnishing personnel, transportation, mobilization and demobilization, equipment and materials required in connection with maintenance dredging. This contract is traditionally performed with a trailing suction hopper dredge. Up to one million cubic yards of maintenance material is expected to be removed from the entrance channel and up to one hundred thousand cubic yards from the Cedar Hammock Range.

The work is located in Brunswick Harbor Georgia deep draft navigation project. Brunswick Harbor is located in Glynn County, Georgia, 70 statute miles south of the Savannah Harbor, Georgia, and 25 statute miles north of Fernandina Harbor, Florida. The Brunswick Entrance Channel is 38 ft. deep MLLW and 400 ft.

wide from the Atlantic Ocean through St. Simons Range. The Brunswick Harbor Inner Harbor channel is 36 ft. deep MLLW and 400 ft. wide through Cedar Hammock Range, Brunswick River, Turtle River, South Brunswick River, and East River.

The dredging scope includes the entrance channel stations 0+000 to -45+000 and inner harbor Cedar Hammock Range stations 12+750 to 22+000. The maintenance material removed from during this contract is to be placed within the offshore dredged material disposal site (ODMDS). Hopper dredge use within the Brunswick Harbor is restricted to 15 December to 31 March 2025.

(End of Summary of Changes)