C.04 - Bid Abstract W912HN23B4002.pdf
PDF 194 KB Posted
- Solicitation number
- W912HN23B4002
About this file
This bid abstract document summarizes five bids received in response to Solicitation Number W912HN23B4002 issued by the Department of the Army Corps of Engineers Engineering District Savannah. The solicitation sought bids for the Convert Warehouse for PMEL project at Building 4312 at Seymour Johnson Air Force Base in North Carolina. Bidder 1 proposed to complete the required conversion work for $8,638,000. Bidder 2 bid $9,659,654.51, Bidder 3 bid $9,880,770.63, Bidder 4 bid $9,857,572, and Bidder 5 bid $5,944,637. All bids were above the independent government estimate of $5,374,719. Bid amounts were provided for two contract line items, to convert Warehouse 1 and develop the RASCAL Yard, along with total proposed prices. No further award details or required products and services were included in this bid abstract document.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Site Visit Attendees 20230726.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Yes/No/NA Yes/No/NA Yes/No/NA Yes/No/NA Yes/No/NA Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes
CLIN Quantity Unit of Issue Unit Price Quantity Grand Total Unit Price Quantity Grand Totals Unit Price Quantity Grand Totals Unit Price Quantity Grand Totals Unit Price Quantity Grand Totals Unit Price Grand Totals
CLIN 0001 - Convert Warehouse 1 Job $8,396,353.00 1 $8,396,353.00 $8,937,557.55 1 $8,937,557.55 $8,677,151.81 1 $8,677,151.81 $8,980,212.00 1 $8,980,212.00 $8,638,000.00 1 $8,638,000.00 $5,374,719.00 $5,374,719.00 CLIN 0002 - RASCAL Yard 1 Job $833,099.00 1 $833,099.00 $722,096.96 1 $722,096.96 $1,203,618.82 1 $1,203,618.82 $877,360.00 1 $877,360.00 $995,000.00 1 $995,000.00 $569,918.00 $569,918.00
SUB-TOTAL $9,229,452.00 SUB-TOTAL $9,659,654.51 SUB-TOTAL $9,880,770.63 SUB-TOTAL $9,857,572.00 SUB-TOTAL $9,633,000.00 SUB-TOTAL $5,944,637.00
TOTAL $9,229,452.00 TOTAL $9,659,654.51 TOTAL $9,880,770.63 TOTAL $9,857,572.00 TOTAL $9,633,000.00 TOTAL $5,944,637.00 155.26% 162.49% 166.21% 165.82% 162.05%
DATE:
Percent of IGE:
Bidder/Offeror #4:
Phillips C&C
Bid Signed?
Amendments Acknowledged?
Bid Bond Furnished?
Remarks:
Project No: VKAG 12-1020 CONVERT WAREHOUSE FOR PMEL, BLDG 4312 Bid Time: 11:00 a.m. Bid Opening 12:00pm
Bid Signed?
Bid Bond Furnished?
Remarks:
Bid Signed?
Remarks:
Percent of IGE:
Gregory M. Graham
I CERTIFY THAT I HAVE OPENED, READ AND RECORDED ON THIS ABSTRACT
(AND CONTINUATION SHEETS, IF ANY) ALL OFFERS RECEIVED IN RESPONSE
TO THE SOLICITATION
SIGNATURE:
Percent of IGE:Percent of IGE:
Remarks: Remarks:
TYPED NAME OF BID OPENING OFFICIAL:
Independent Government Estimate
(IGE)
Amendments Acknowledged?
Bidder/Offeror #2:
Bid Bond Furnished?
Amendments Acknowledged?
Brantley Construction Howard Pence
Bid Signed?
Amendments Acknowledged?
Bid Bond Furnished?
Solicitation Number:
W912HN23B4002
Project Description:
Bid Signed?
Bidder/Offeror #1:
Remarks:
Percent of IGE:
Bidder/Offeror #3:
Midnight Sun-Centennial Sunnliaq JV
Bidder/Offeror #5:
Sea Wolf Construction Corp
Remarks:
Percent of IGE:
Amendments Acknowledged?
Bid Bond Furnished?
File details come from the government source that posted it. Updated .