1. SOLICITATION NUMBER 2. DATE ISSUED 3. DATE OPENED

31-Aug-18 2-Oct-18

4. ISSUING OFFICE NAME AND TITLE OF CERTIFYING OFFICIAL

Department of the Army, Corps of Engineers Bruce A. Helms

SIGNATURE

5. PROJECT TITLE: 8. GOVERNMENT ESTIMATE

FY18 Atlantic Intracoastal Waterway (AIWW) Jekyll Creek Beneficial Use of Dredged Material Pilot Project and Selective Sites Maintenance Dredging Contract

(Check A, B or C and complete D, E and F.)

A. OFFEROR

A. HIRED LABOR

(Without Profit) 100% Small Business Set-Aside

(Including Profit) 7A.

ITEM 7B. DESCRIPTION OF OFFERED ITEM 7C. EST

QTY. D. UNIT E. UNIT PRICE F. ESTIMATED

AMOUNT E. UNIT PRICE F. ESTIMATED

AMOUNT

0001 MOBILIZATION AND DEMOBILIZATION

0001AA FIRST MOBILIZATION AND DEMOBILIZATION 1 EA $ 1,872,000.00 1,872,000.00$ 5,892,000.00$ 5,892,000.00$ 0001AB ALL OVER 1 MOBILIZATION AND DEMOBILIZATION 1 EA 115,000.00$ 115,000.00$ 400,000.00$ 400,000.00$

MAINTENANCE DREDGING, JEKYLL CREEK OPEN WATER

PLACEMENT

0002AA FIRST 112,000 CUBIC YARDS 112,000 CY 11.20$ 1,254,400.00$ 14.59$ 1,634,080.00$ 0002AB ALL OVER 112,000 CUBIC YARDS 108,000 CY 11.20$ 1,209,600.00$ 14.59$ 1,575,720.00$

0003 MAINTENANCE DREDGING, JEKYLL CREEK, THIN LAYER

PLACEMENT 5,000 CY 42.25$ 211,250.00$ 14.59$ 72,950.00$

0004 TURBIDITY MONITORING 1 JB 135,410.00$ 135,410.00$ 50,000.00$ 50,000.00$

0005 PLACEMENT CONTROL (COIR LOGS) 2,000 LF 220.00$ 440,000.00$ 100.00$ 200,000.00$

0006 MOVES (JEKYLL CREEK TO BUTTERMILK SOUND) 1 EA 54,600.00$ 54,600.00$ 250,000.00$ 250,000.00$

0007 MAINTENANCE DREDGING, BUTTERMILK SOUND

0007AA FIRST 121,200 CUBIC YARDS 121,200 CY 6.20$ 751,440.00$ 8.39$ 1,016,868.00$ 0007AB ALL OVER 121,200 CUBIC YARDS 138,000 CY 6.20$ 855,600.00$ 8.39$ 1,157,820.00$

0008 MOVES (BUTTERMIL SOUND TO HELLS GATE 1 EA 70,000.00$ 70,000.00$ 250,000.00$ 250,000.00$

0009 MAINTENANCE DREDGING, HELLS GATE

0009AA FIRST 112,600 CUBIC YARDS 112,600 CY 5.80$ 653,080.00$ 5.31$ 597,906.00$

0009AB ALL OVER 112,600 CUBIC YARDS 105,600 CY 5.80$ 612,480.00$ 5.31$ 560,736.00$

0010 MOVES (HELLS GATE TO FIELDS CUT) 1 EA 60,800.00$ 60,800.00$ 450,000.00$ 450,000.00$

0011 MAINTENANCE DREDGING, FIELDS CUT

0011AA FIRST 84,000 CUBIC YARDS 84,000 CY 6.05$ 508,200.00$ 21.00$ 1,764,000.00$

0011AB ALL OVER 84,000 CUBIC YARDS 44,200 CY 6.05$ 267,410.00$ 21.00$ 928,200.00$

BASE CLINS (ITEMS 0001 THROUGH 0005) 5,237,660.00$ 9,824,750.00$

OPTION CLINS (ITEMS 0006 THROUGH 0011AB) 3,833,610.00$ 6,975,530.00$

TOTAL BID (ITEMS 0001 THROUGH 0011AB) 9,071,270.00$ 16,800,280.00$

ABSTRACT OF OFFERS - CONSTRUCTION W912HN18B5005

I CERTIFY that I have opened, read, and recorded on this abstract all offers received In response to this solicitation.

Savannah District Contracting Office Contracting Officer 100 W Oglethorpe Ave.

Savannah, GA 31401

9. OFFERS

NO. 1

Cottrell Contracting Corporation 328 N. Battlefield Blvd.

Chesapeake VA 23320

X B. REASONABLE CONTRACT B. BID SECURITY (Type and Amount)

20%

C. REASONABLE CONTRACT C. AMENDMENTS ACKNOWLEDGED

Yes

2018-10-02T16:39:55-0400