Scope of Work

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Scope of work: Procurement of a Self Propelled Articulating Boom Lift.

1. Location:

Richard B. Russell Project 4144 Russell Dam Drive Elberton, Ga. 30635 1-706-213-3400

2. Work To Be Performed:

2. A. Vendor shall provide a new self propelled articulating boom lift for the Richard B.

Russell Project as described in section 3.B.

2. B. The vendor will supply training for up to 15 employees on the proper operation, safety precautions, and maintenance necessary for the boom lift. Training shall be scheduled as close as possible to the delivery date of the equipment. Training shall be coordinated with the plant manager so that it does not interfere with plant operation or plant maintenance. Arrangements to schedule the on-site training shall be coordinated with Timmy Thomas, at 706-213-3463.

3. Self Propelled Articulating Boom:

3. A. The vendor shall provide a new self propelled articulating boom lift. The vendor shall test and inspect the self propelled articulating boom lift for proper operation prior to delivery. Inspection report shall be included with the lift.

3. B. The following is a list of minimum specifications for the articulating boom:

Must have a platform height of at least 60 ft.

Must have at least a 39 ft horizontal reach.

Must have a 26 ft, up and over clearance.

Must have a self-leveling platform.

Must have a platform width of 8 ft.

Must have a platform length of 3 feet.

Must have an unrestricted lift capacity of 500 lbs.

Must have hydraulic platform rotation.

Must have a platform rotation of 180 deg.

Must have a Jib with a range of articulation of 130 deg.

Must have a turntable with 360 deg. Continuous rotation.

Must have proportional controls.

Must have an outside turning radius of less than 12ft.

Must have a duel fuel engine of gasoline/liquid propane gas.

Must have a 12v auxiliary power unit.

Must have four-wheel drive.

Must have four wheel steering.

Must have rough terrain tires.

Must have AC power cord to platform.

Must have a tilt alarm.

Must have a descent alarm.

Must meet or exceed all OSHA standards as well as ANSI A92.5, CSA standard B354.4

Must have at minimum one copy of Operation and maintenance manuals with the lift.

Must have at minimum one CD that contains an electronic copy of the Operation and maintenance. NO flash drives.

3. C. Accessories and Options:

Must have self closing platform gate.

Must have self closing platform gate.

Flashing Amber Beacon

Foam Filled Tires

Must have 43.5 lb. propane tank.

4. Warranty:

4. A. Articulating boom lift shall be covered under a manufacture standard warranty having minimum one year on all parts and labor and a five year structural warranty on all structural components.

5. Recommended Lift or equivalent:

5. A. JLG 600AJ self propelled articulating boom lift or equivalent.

6. Delivery:

6. A. Method of delivery is at contractor’s discretion, but must be within 45 days of award of contract. The contractor shall coordinate delivery with Timmy Thomas timmy.a.thomas@usace.army.mil, 706-213 3463 or Anthony Bergeron anthony.j.bergeron@usace.army.mil, 706-213-3471 at least three days prior to units being delivered.

6. B. Delivery shall be to the Richard B. Russell Dam and Powerhouse at 4144 Russell Dam Drive, Elberton, GA 30635. Delivery shall be made on Monday – Thursday from 07:00 am to 3:00 pm with the exception of federal holidays.

7. Security Requirments:

7. A. Requirements to be accomplished by Savannah District Security Office.

Contractor workforce must comply with all personal identity verification requirements as mailto:timmy.a.thomas@usace.army.mil mailto:anthony.j.bergeron@usace.army.mil directed by DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition

(FPCON) at any individual facility change, the Government may require changes in contractor security matters or processes.

7. B. The contractor must pre-screen Candidates using the E-verify Program

(http://www.dhs.gov/E-Verify) website to meet the established employment eligibility requirements. The vendor must ensure that the Candidate has two valid forms of

Government issued identification prior to ensure the correct information is entered into the E-verify system. An initial list of verified/eligible Candidates must be provided to the

COR no later than 3 business days after the initial contract award http://www.dhs.gov/E-Verify

File details come from the government source that posted it. Updated .