Questions:

1. Is the Government off loading the equipment or are we to do so?

2. Are their to be no Bouncy animals in the site? If not the site will be smaller then the 82' x 62' site.

3. I saw on page 6 of 30 Ground Surface Material is responsibility of purchaser, are they also going to supply the Borders to contain the ground surfacing or should we quote borders for the sites as well?

4. If equipment is to be delivered by Aug 31st 2009 will a PO be issued by July 31st?

Answers:

1. Contractors are to provide complete delivery, to include off loading their own trucks.

2. We did not include Bouncy Animals in specifications.

3. We will provide our own borders.

4. The scheduled award date is 7/31/09, if that does not happen, the delivery date will be adjusted to 30 days after contract award.