Text version

W81LJ891737911

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

SOLICITATION NUMBER W912HN-09-B-0030, ENTITLED PAVING AND GRADING, JOHN H. KERR DAM AND RESERVOIR, MECKLENBURG

COUNTY, VIRGINIA IS AMENDED AS FOLLOWS:

1. THE TIME AND DATE SET FOR BID OPENING REMAINS UNCHANGED.

2. SEE SUMMARY OF CHANGES.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 2

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 16-Nov-2009

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912HN-09-B-0030

X 9B. DATED (SEE ITEM 11)

27-Oct-2009

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 2 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

16-Nov-2009

CODE

U.S. ARMY ENGINEER DISTRICT SAVANNAH

ATTN: DANNY KISSAM

69 DARLINGTON AVENUE

910-251-4424 (FAX) 910-251-4454

WILMINGTON NC 28403

W912HN 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

Page 2 of 2 Pages

SECTION 01 35 26 – GOVERNMENTAL SAFETY REQUIREMENTS

(1) Delete existing Table of Contents Page 1 and Page 2 in their entirety and replace with enclosed revised Pages.

(2) Delete existing SECTION Page 6 thru Page 9 in their entirety and replace with enclosed revised Pages.

(3) ADD Attachment 3 – COVER and Enclosure in their entirety.

SECTION 32 12 10.00 38 – BITUMINOUS PRIME COAT

(1) Delete existing Table of Contents Page 1 in its entirety and replace with enclosed revised Page.

(2) Delete existing SECTION Page 1 and Page 2 in their entirety and replace with enclosed revised Pages.

SECTION 32 12 10.01 38 BITUMINOUS TACK COAT

Delete existing SECTION Page 1 and Page 2 in their entirety and replace with enclosed revised Pages.

NOTE:

Text that is added or revised by this amendment is replaced in its entirety and underlined and/or printed in bold and/or stamped appropriately.

The text changes may have necessitated reformatting of subsequent text or pages. If this is the case, those pages have also been issued as amended pages but are not underlined or bold text.

(End of Summary of Changes)

Encls As stated

Paving and Grading W912HN-09-B-0030 John H. Kerr Dam and Reservoir, Mecklenburg County, VA

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 35 26

GOVERNMENTAL SAFETY REQUIREMENTS

PART 1 GENERAL

1.1 REFERENCES

1.2 SUBMITTALS

1.3 DEFINITIONS

1.4 REGULATORY REQUIREMENTS

1.5 SITE QUALIFICATIONS, DUTIES AND MEETINGS

1.5.1 Personnel Qualifications

1.5.1.1 Site Safety and Health Officer (SSHO)

1.5.2 Personnel Duties

1.5.2.1 Site Safety and Health Officer (SSHO)

1.5.3 Meetings

1.5.3.1 Preconstruction Conference

1.5.3.2 Safety Meetings

1.6 ACCIDENT PREVENTION PLAN (APP)

1.6.1 USACE EM 385-1-1 Contents

1.7 ACTIVITY HAZARD ANALYSIS (AHA)

1.8 DISPLAY OF SAFETY INFORMATION

1.9 SAFETY PERFORMANCE SIGN

1.10 SITE SAFETY REFERENCE MATERIALS

1.11 EMERGENCY MEDICAL TREATMENT

1.12 REPORTS

1.12.1 Accident Reports

1.12.2 Accident Notification

1.12.3 Monthly Exposure Reports

1.13 FACILITY OCCUPANCY CLOSURE

1.14 SEVERE STORM PLAN

PART 2 PRODUCTS

PART 3 EXECUTION

3.1 CONSTRUCTION AND/OR OTHER WORK

3.1.1 Hazardous Material Use

3.1.2 Hazardous Material Exclusions

3.1.3 Unforeseen Hazardous Material

3.2 PRE-OUTAGE COORDINATION MEETING

3.3 EQUIPMENT

3.3.1 Material Handling Equipment

3.3.2 Equipment and Mechanized Equipment

3.4 EXCAVATIONS

3.4.1 Utility Locations

3.4.2 Utility Location Verification

3.4.3 Shoring Systems

3.4.4 Trenching Machinery

SECTION TABLE OF CONTENTS 01 35 26 Page 1 (Revised by Amendment No. 0001)

3.5 UTILITIES WITHIN CONCRETE SLABS

3.6 ELECTRICAL

3.6.1 Portable Extension Cords

ATTACHMENTS:

Attachment 1 - Minimum Basic Outline for Accident Prevention Plan

Attachment 2 - Safety Performance Sign

Attachment 3 - Work Sheet for Preliminary Accident Notification

-- End of Section Table of Contents --

SECTION TABLE OF CONTENTS 01 35 26 Page 2 contractor, supplier or subcontractor and provided to the prime contractor for submittal to the Contracting Officer.

1.8 DISPLAY OF SAFETY INFORMATION

Within 5 calendar days after commencement of work, erect a safety bulletin board at the job site. Include and maintain information on safety bulletin board as required by USACE EM 385-1-1, section 01.A.06. Additional items required to be posted include: Hot work permit.

1.9 SAFETY PERFORMANCE SIGN

Within 5 calendar days after commencement of work, erect a safety performance sign at the job site as shown in Attachment 2 - Safety Performance Sign.

1.10 SITE SAFETY REFERENCE MATERIALS

Maintain safety-related references applicable to the project, including those listed in the article "References." Maintain applicable equipment manufacturer's manuals.

1.11 EMERGENCY MEDICAL TREATMENT

Contractors will arrange for their own emergency medical treatment.

Government has no responsibility to provide emergency medical treatment.

1.12 REPORTS

1.12.1 Accident Reports

Conduct an accident investigation for recordable injuries and illnesses, and property damage accidents resulting in at least $2,000 in damages, to establish the root cause(s) of the accident, complete the USACE Accident Report Form 3394 and provide the report to the Contracting Officer within 5 calendar day(s) of the accident. The Contracting Officer will provide copies of any required or special forms.

1.12.2 Accident Notification

Notify the Contracting Officer of all accidents as soon as practical, but not later than four hours after occurrence. The notification shall be done by completing the Work Sheet for Preliminary Accident Notification form (see Attachment 3 - Work Sheet for Preliminary Accident Notification) and providing it to the Contracting Officer. For major accidents, preserve the conditions and evidence on the accident site until the Government investigation team arrives on-site and the Government's investigation is complete. Major accidents are defined as accidents that result in fatalities, permanent total or permanent partial disabilities, three or more admitted to the hospital, and $200,000 or more in property damage.

1.12.3 Monthly Exposure Reports

Monthly exposure reporting to the Contracting Officer is required to be submitted by the fifth of the month for the previous month. This report is a compilation of employee-hours worked each month for all site workers, both prime and subcontractor. The Contracting Officer will provide copies of any special forms.

SECTION 01 35 26 Page 6

1.13 FACILITY OCCUPANCY CLOSURE

Streets, walks, and other facilities occupied and used by the Government shall not be closed or obstructed without written permission from the Contracting Officer.

1.14 SEVERE STORM PLAN

In the event of a severe storm warning, the Contractor must:

a. Secure outside equipment and materials and place materials that could be damaged in protected areas.

b. Check surrounding area for loose material, equipment, debris, and other objects that could be blown away or against existing facilities.

c. Ensure that temporary erosion controls are adequate.

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

3.1 CONSTRUCTION AND/OR OTHER WORK

Comply with USACE EM 385-1-1, NFPA 241, the APP, AHA, Federal and/or State OSHA regulations, and other related submittals and activity fire and safety regulations. The most stringent standard prevails.

3.1.1 Hazardous Material Use

Each hazardous material must receive approval prior to being brought onto the job site or prior to any other use in connection with this contract.

Allow a minimum of 10 working days for processing of the request for use of a hazardous material.

3.1.2 Hazardous Material Exclusions

Notwithstanding any other hazardous material used in this contract, radioactive materials or instruments capable of producing ionizing/non-ionizing radiation (with the exception of radioactive material and devices used in accordance with USACE EM 385-1-1 such as nuclear density meters for compaction testing and laboratory equipment with radioactive sources) as well as materials which contain asbestos, mercury or polychlorinated biphenyls, di-isocynates, lead-based paint are prohibited. The Contracting Officer, upon written request by the Contractor, may consider exceptions to the use of any of the above excluded materials.

3.1.3 Unforeseen Hazardous Material

The design should have identified materials such as PCB, lead paint, and friable and non-friable asbestos. If material, not indicated, that may be hazardous to human health upon disturbance during construction operations is encountered, stop that portion of work and notify the Contracting Officer immediately. Within 14 calendar days the Government will determine if the material is hazardous. If material is not hazardous or poses no

SECTION 01 35 26 Page 7 danger, the Government will direct the Contractor to proceed without change. If material is hazardous and handling of the material is necessary to accomplish the work, the Government will issue a modification pursuant to "FAR 52.243-4, Changes" and "FAR 52.236-2, Differing Site Conditions."

3.2 PRE-OUTAGE COORDINATION MEETING

Contractors are required to apply for utility outages at least 15 days in advance. As a minimum, the request should include the location of the outage, utilities being affected, duration of outage and any necessary sketches. Special requirements for electrical outage requests are contained elsewhere in this specification section. Once approved, and prior to beginning work on the utility system requiring shut down, attend a pre-outage coordination meeting with the Contracting Officer and Public Utilities representative to review the scope of work and the lock-out/tag-out procedures for worker protection. No work will be performed on energized electrical circuits unless proof is provided that no other means exist.

3.3 EQUIPMENT

3.3.1 Material Handling Equipment

a. Material handling equipment such as forklifts shall not be modified with work platform attachments for supporting employees unless specifically delineated in the manufacturer's printed operating instructions.

b. The use of hooks on equipment for lifting of material must be in accordance with manufacturer's printed instructions.

c. Operators of forklifts or power industrial trucks shall be licensed in accordance with OSHA.

3.3.2 Equipment and Mechanized Equipment

a. Proof of qualifications for operator shall be kept on the project site for review.

b. Manufacture specifications or owner's manual for the equipment shall be on-site and reviewed for additional safety precautions or requirements that are sometimes not identified by OSHA or USACE EM 385-1-1. Incorperate such additional safety precautions or requirements into the AHAs.

3.4 EXCAVATIONS

Perform soil classification by a competent person in accordance with

29 CFR 1926.

3.4.1 Utility Locations

Prior to digging, the appropriate digging permit must be obtained. All underground utilities in the work area must be positively identified by a private utility locating service in addition to any station locating service and coordinated with the station utility department. Any markings made during the utility investigation must be maintained throughout the contract.

SECTION 01 35 26 Page 8

3.4.2 Utility Location Verification

The Contractor must physically verify underground utility locations by hand digging using wood or fiberglass handled tools when any adjacent construction work is expected to come within three feet of the underground system. Digging within 2 feet of a known utility must not be performed by means of mechanical equipment; hand digging shall be used. If construction is parallel to an existing utility expose the utility by hand digging every

30.5 m (100 feet) if parallel within 1.5 m (5 feet) of the excavation.

3.4.3 Shoring Systems

Trench and shoring systems must be identified in the accepted safety plan and AHA. Manufacture tabulated data and specifications or registered engineer tabulated data for shoring or benching systems shall be readily available on-site for review. Job-made shoring or shielding must have the registered professional engineer stamp, specifications, and tabulated data. Extreme care must be used when excavating near direct burial electric underground cables.

3.4.4 Trenching Machinery

Operate trenching machines with digging chain drives only when the spotters/laborers are in plain view of the operator. Provide operator and spotters/laborers training on the hazards of the digging chain drives with emphasis on the distance that needs to be maintained when the digging chain is operating. Keep documentation of the training on file at the project site.

3.5 UTILITIES WITHIN CONCRETE SLABS

Utilities located within concrete slabs or pier structures, bridges, and the like, are extremely difficult to identify due to the reinforcing steel used in the construction of these structures. Whenever contract work involves concrete chipping, saw cutting, or core drilling, the existing utility location must be coordinated with station utility departments in addition to a private locating service. Outages to isolate utility systems must be used in circumstances where utilities are unable to be positively identified. The use of historical drawings does not alleviate the contractor from meeting this requirement.

3.6 ELECTRICAL

3.6.1 Portable Extension Cords

Size portable extension cords in accordance with manufacturer ratings for the tool to be powered and protected from damage. Iimmediately removed from service all damaged extension cords. Portable extension cords shall meet the requirements of NFPA 70.

-- End of Section --

SECTION 01 35 26 Page 9

Attachment 3

Work Sheet for Preliminary Accident Notification

SECTION TABLE OF CONTENTS

DIVISION 32 - EXTERIOR IMPROVEMENTS

32 12 10.00 38

BITUMINOUS PRIME COAT

PART 1 GENERAL

1.1 REFERENCES

PART 2 PRODUCTS

2.1 REVISIONS TO VDOT ROAD AND BRIDGE SPECIFICATIONS SECTION 311 PRIME

COAT

2.1.1 Article 311.02 Materials

PART 3 EXECUTION

3.1 REVISIONS TO VDOT ROAD AND BRIDGE SPECIFICATIONS SECTION 311 PRIME

COAT

3.1.1 Article 311.03 Procedures

3.1.2 Article 311.04 Measurement and Payment

3.2 NEW ARTICLE 311.05 QUALITY CONTROL

-- End of Section Table of Contents --

SECTION TABLE OF CONTENTS 32 12 10.00 38 Page 1

32 12 10.00 38

BITUMINOUS PRIME COAT

PART 1 GENERAL

1.1 REFERENCES

The publication listed below forms a part of this specification to the extent referenced. The publication is referred to within the text by the basic designation only.

AMERICAN ASSOCIATION OF STATE HIGHWAY AND TRANSPORTATION OFFICIALS

(AASHTO)

AASHTO M 81 (1992; R 2004) Cut-Back Asphalt (Rapid-Curing Type)

VIRGINIA DEPARTMENT OF TRANSPORTATION (VDOT)

VDOT STD SPECS (2007) Road and Bridge Specifications

PART 2 PRODUCTS

2.1 REVISIONS TO VDOT ROAD AND BRIDGE SPECIFICATIONS SECTION 311 PRIME COAT

2.1.1 Article 311.02 Materials

In paragraph (a), delete second sentence and substitute the following:

"Asphalt shall be cut back asphalt RC250, meeting requirements of

AASHTO M 81."

PART 3 EXECUTION

3.1 REVISIONS TO VDOT ROAD AND BRIDGE SPECIFICATIONS SECTION 311 PRIME COAT

3.1.1 Article 311.03 Procedures

In the first sentence of the first paragraph delete the phrase "The rates of application of materials" and substitute the following: "The rate of application for the asphalt shall be 0.4 gallon per square yard. The rate of application of the cover material..."

3.1.2 Article 311.04 Measurement and Payment

Delete Article 311.04 Measurement and Payment and substitute the following: "There will be no measurement made of the number of gallons of prime coat which has been incorporated into the completed and accepted work. Payment for furnishing the prime coat in accordance with this section shall be included in the following items of the BIDDING SCHEDULE:

PAVING ARRA FUNDED NORTH BEND PARK

PAVING ARRA FUNDED RUDD'S CREEK RECREATION AREA BOAT RAMP PARKING

PAVING ARRA FUNDED LONGWOOD PARK CAMPGROUND ENTRANCE

PAVING ARRA FUNDED LONGWOOD PARK BOAT RAMP PARKING

PAVING ARRA FUNDED IVEY HILL DAY USE AREA

SECTION 32 12 10.00 38 Page 1

3.2 NEW ARTICLE 311.05 QUALITY CONTROL

Add the following new Article after Article 311.04

"311.05 QUALITY CONTROL

The Contractor shall establish and maintain quality control for prime coat operations to insure compliance with contract requirements and maintain records of his quality control for all operations including but not limited to the following:

Prime coat material meets specified requirements.

Base preparation in accordance with specifications.

Application equipment, rates and temperature meets specified requirements.

Maintenance and protection is in accordance with specifications.

The Contractor shall provide labor, material, transportation, and equipment for sampling and testing. The Contractor shall follow AASHTO, VDOT AND Corps of Engineers methods of sampling, testing, and the Contracting Officer shall approve these samples before testing."

-- End of Section --

SECTION 32 12 10.00 38 Page 2

32 12 10.01 38

BITUMINOUS TACK COAT

PART 1 GENERAL

1.1 REFERENCES

The publication listed below forms a part of this specification to the extent referenced. The publication is referred to within the text by the basic designation only.

VIRGINIA DEPARTMENT OF TRANSPORTATION (VDOT)

VDOT STD SPECS (2007) Road and Bridge Specifications

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

3.1 REVISIONS TO VDOT ROAD AND BRIDGE SPECIFICATIONS SECTION 310 TACK COAT

3.1.1 Article 310.04 Measurement and Payment

Delete Article 310.04 Measurement and Payment and substitute the following: "There will be no measurement made of the number of gallons of tack coat which has been incorporated into the completed and accepted work. Payment for furnishing the tack coat in accordance with this section shall be included in the following items of the BIDDING SCHEDULE:

PAVING ARRA FUNDED NORTH BEND PARK

PAVING ARRA FUNDED RUDD'S CREEK RECREATION AREA BOAT RAMP PARKING

PAVING ARRA FUNDED LONGWOOD PARK CAMPGROUND ENTRANCE

PAVING ARRA FUNDED LONGWOOD PARK BOAT RAMP PARKING

PAVING ARRA FUNDED IVEY HILL DAY USE AREA

3.2 NEW ARTICLE 310.05 QUALITY CONTROL

Add the following new Article after Article 310.04

"310-05 QUALITY CONTROL

The Contractor shall establish and maintain quality control for prime coat operations to insure compliance with contract requirements and maintain records of his quality control for all operations including but not limited to the following:

Tack coat material meets specified requirements.

Base preparation in accordance with specifications.

Application equipment, rates and temperature meets specified requirements.

Maintenance and protection is in accordance with specifications.

SECTION 32 12 10.01 38 Page 1

The Contractor shall provide labor, material, transportation, and equipment for sampling and testing. The Contractor shall follow AASHTO, VDOT AND Corps of Engineers methods of sampling, testing, and the Contracting Officer shall approve these samples before testing."

-- End of Section --