W912HN-22-B-4005_SPECS_VOL2.pdf
PDF 21 MB Posted
- Solicitation number
- W912HN22B4005
About this file
This solicitation notice provides details for Federal Contract Opportunity W912HN22B4005 to repair Building 973 at Fort Benning, Georgia. The U.S. Army Corps of Engineers Savannah District will issue an Invitation for Bid seeking a firm-fixed-price contract for project number FD-00105-0J, with a magnitude anticipated between $1-5 million. This acquisition is set aside as a competitive small disadvantaged business contract under NAICS code 236220. The solicitation closing date is September 16, 2022 at 1:00 PM EST. The period of performance is 540 calendar days from the notice to proceed. The scope of work involves repairs to building systems including HVAC, fire suppression and alarm, lighting, electrical, ceilings, interior and exterior finishes, plumbing, and site utilities. A site visit is scheduled for August 23 at 1:30 PM EST. Offerors must register in the System for Award Management and submit bids electronically through the Procurement Integrated Enterprise Environment.
View the file
Other files
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Fort Benning, Georgia
Solicitation Number
W912HN-22-B-4005
Repair Bldg. 973 Barracks Volume 2 of 2: Specification Divisions 12 - 32 and Appendices
PN FD-00105-0J
August 2022
U.S. ARMY ENGINEER DISTRICT, SAVANNAH
CORPS OF ENGINEERS
100 WEST OGLETHORPE AVENUE
SAVANNAH, GEORGIA 31401-3640
US Army Corps Of Engineers Savannah District
Page intentionally left blank for duplex printing.
CUI
Ready to Advertise (RTA)
Repair of Building 973 Fort Benning, GA
Specifications Volume 2 of 2 (Divisions 12 – 32 and Appendices)
PN: FD-00105-0J
Solicitation Number: W912HN-22-B-4005
August 2022
Prepared by
Stantec Consulting Services Inc.
Raleigh, North Carolina
With consultants
Engineered Designs Inc.
Cary, North Carolina
The Fire Consultants Inc.
Apex, North Carolina
Mabbett and Associates, Inc.
Alexandria, Virginia
Crawford Consulting Services, Inc.
East Pittsburgh, Pennsylvania
Prepared for
U.S. Army Corps of Engineers Savannah District
8/10/22
CIVIL
ELECTRICAL MECHANICAL
STRUCTURAL ARCHITECTURAL
PLUMBING
TELECOMMUNICATIONS
Repair Bldg. 973 Barracks
Fort Benning, Georgia
22B4005
PROJECT TABLE OF CONTENTS Page 1
PROJECT TABLE OF CONTENTS
VOLUME 2 OF 2
DIVISION 12 - FURNISHINGS
12 21 00 WINDOW BLINDS
ATTACHMENT A – ALUMINUM BLINDS DATA SHEET
12 24 13 ROLLER WINDOW SHADES
DIVISION 21 - FIRE SUPPRESSION
21 13 13 WET PIPE SPRINKLER SYSTEMS, FIRE PROTECTION
21 13 16 DRY PIPE SPRINKLER SYSTEMS, FIRE PROTECTION
DIVISION 22 - PLUMBING
22 00 00 PLUMBING, GENERAL PURPOSE
DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)
23 05 15 COMMON PIPING FOR HVAC
23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC
23 07 00 THERMAL INSULATION FOR MECHANICAL SYSTEMS
23 30 00 HVAC AIR DISTRIBUTION
23 81 00 DECENTRALIZED UNITARY HVAC EQUIPMENT
DIVISION 25 - INTEGRATED AUTOMATION
25 05 11.02 CYBERSECURITY FOR FACILITY-RELATED CONTROL SYSTEMS
ATTACHMENT A – L-L-L CCI CHECKLIST FAMNS
DIVISION 26 - ELECTRICAL
26 20 00 INTERIOR DISTRIBUTION SYSTEM
26 28 01.00 10 COORDINATED POWER SYSTEM PROTECTION
26 51 00 INTERIOR LIGHTING
DIVISION 27 - COMMUNICATIONS
27 10 00 BUILDING TELECOMMUNICATIONS CABLING SYSTEM
DIVISION 28 - ELECTRONIC SAFETY AND SECURITY
28 31 76 INTERIOR FIRE ALARM AND MASS NOTIFICATION SYSTEM,
ADDRESSABLE
DIVISION 31 - EARTHWORK
31 00 00 EARTHWORK
DIVISION 32 - EXTERIOR IMPROVEMENTS
32 11 23 AGGREGATE BASE COURSES
32 16 19 CONCRETE CURBS, GUTTERS AND SIDEWALKS
32 17 23 32 92 23
PAVEMENT MARKINGS
SODDING
Repair Bldg. 973 Barracks
22B4005
PROJECT TABLE OF CONTENTS Page 2
APPENDICES
APPENDIX A HAZMAT REPORT
APPENDIX B SAS EQUIVALENCY WAIVER AND EXEMPTION REQUEST
APPENDIX C USACE EVALUATION REPORT FOR BUILDING 976
APPENDIX D NEC TELECOMMUNICATIONS AND NETWORK INSTALLATION
SPECIFICATIONS
APPENDIX E NEC ISP-OSP TTP FEBRUARY 2022 v1.4
APPENDIX F FORT BENNING BLDG 973 INTERPRETATION REQUEST – USE
OF DOAS
APPENDIX G HYDRANT FLOW TEST AND WATER SUPPLY GRAPH
APPENDIX H STANDARD FORMS
-- End of Project Table of Contents – Volume 2 OF 2 --
Repair Bldg. 973 Barracks 22B4005
SECTION 12 21 00
WINDOW BLINDS
PART 1 GENERAL
1.1 SUMMARY
Provide window treatment, conforming to NFPA 701 , complete with necessary brackets, fittings, and hardware. Provide each window treatment type as a complete unit in accordance with paragraph WINDOW TREATMENT PLACEMENT SCHEDULE. Mount and operate equipment in accordance with manufacturer's instructions. Completely cover windows to receive a treatment.
1.2 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by basic designation only.
NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)
NFPA 701 (2019) Standard Methods of Fire Tests for Flame Propagation of Textiles and Films
SCIENTIFIC CERTIFICATION SYSTEMS (SCS)
SCS SCS Global Services (SCS) Indoor Advantage
UNDERWRITERS LABORATORIES (UL)
UL 2818 (2013) GREENGUARD Certification Program For Chemical Emissions For Building Materials, Finishes And Furnishings
1.3 SUBMITTALS
Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for information only. When used, a code following the "G" classification identifies the office that will review the submittal for the Government.
Submit the following in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES
SD-02 Shop Drawings
Installation
SD-03 Product Data
Window Blinds; G
SD-04 Samples
Window Blinds; G
SECTION 12 21 00 Page 1
SD-06 Test Reports
Window Blinds
SD-07 Certificates
Indoor Air Quality for window blinds; S
SD-08 Manufacturer's Instructions
Window Blinds; G
SD-10 Operation and Maintenance Data
Window Blinds; G
1.4 CERTIFICATIONS
1.4.1 Window Blinds
Provide products certified to meet indoor air quality requirements by UL 2818 Greenguard, SCS Global Services Indoor Advantage Gold or provide certification or validation by other third-party program that products meet the requirements of this Section. Provide current product certification documentation from certification body. When product does not have certification, provide validation that product meets the indoor air quality product requirements cited herein.
1.5 DELIVERY, STORAGE, AND HANDLING
Deliver components to the jobsite in the manufacturer's original packaging with the brand or company name, item identification, and project reference clearly marked. Store components in a dry location that is adequately ventilated and free from dust, water, or other contaminants and has easy access for inspection and handling. Store materials flat in a clean dry area with temperature maintained above 50 degrees F. Do not open containers until needed for installation unless verification inspection is required.
1.6 WARRANTY
Provide manufacturer's standard performance guarantees or warranties that extend beyond a 1 year period.
PART 2 PRODUCTS
2.1 WINDOW BLINDS
Provide each blind, including hardware, accessory items, mounting brackets and fastenings, as a complete unit produced by one manufacturer. Unless otherwise indicated, all parts will be the same color and will match the color of the blind slat. Treat steel features for corrosion resistance.
Submit product data and samples of each type and color of window treatment. Provide slat samples 6 inch in length for each color.
Provide certification of indoor air quality for window blinds.
SECTION 12 21 00 Page 2
2.1.1 Horizontal Blinds
Provide horizontal blinds with 1 inch slats. Blind units must be capable of nominally 180 degree partial tilting operation and full-height raising. Blinds must be inside mount. Provide tapes for 2 inch slats with longitudinal reinforced vinyl plastic in 1-piece turn ladder construction. Tapes for 1 inch slats must be braided polyester or nylon.
2.1.1.1 Head Channel and Slats
Provide head channel made of steel or aluminum with corrosion-resistant finish nominal 0.024 inch for 1 inch slats. Provide slats of aluminum, not less than 0.008 inch thick, and of sufficient strength to prevent sag or bow in the finished blind. Provide a sufficient amount of slats to assure proper control, uniform spacing, and adequate overlap. Enclose all hardware in the headrail.
2.1.1.2 Controls
A transparent tilting wand will be provided to tilt the slats, it will hang vertically by its own weight, and will swivel for easy operation.
Provide a tilter control of enclosed construction. Provide moving parts and mechanical drive made of compatible materials which do not require lubrication during normal expected life. The tilter will tilt the slats to any desired angle and hold them at that angle so that any vibration or movement of ladders and slats will not drive the tilter and change the angle of slats. Include a mechanism to prevent over tightening. Provide a wand of sufficient length to reach to within 5 feet of the floor.
Provide cordless blinds or blinds with cords that are out of reach of children and strangle proof.
2.1.1.3 Bottom Rail
Provide bottom rail made of corrosion-resistant steel with factory applied finish. Provide closed oval shaped bottom rail with double-lock seam for maximum strength. Bottom rail and end caps to match slats in color.
2.1.1.4 Braided Ladders
Provide braided ladders of 100 percent polyester yarn, color to match the slat color. Space ladders 15.2 slats per foot of drop in order to provide a uniform overlap of the slats in a closed position.
2.2 COLOR
Provide color, pattern and texture as indicated. Color listed is not intended to limit the selection of equal colors from other manufacturers.
PART 3 EXECUTION
3.1 EXAMINATION
After becoming familiar with details of the work, verify all dimensions in the field, and advise the Contracting Officer of any discrepancy before performing the work.
3.2 INSTALLATION
Do not install building construction materials that show visual evidence
SECTION 12 21 00 Page 3 of biological growth.
Submit drawings showing fabrication and Installation details. Show layout and locations of track, direction of draw, mounting heights, and details.
Provide Manufacturer's Instructions and Operation and Maintenance Data.
Perform installation of window blinds in accordance with the approved detail drawings and manufacturer's installation instructions. Install units level, plumb, secure, and at proper height and location relative to window units. Provide and install supplementary or miscellaneous items in total, including clips, brackets, or anchorages incidental to or necessary for a sound, secure, and complete installation. Do not start installation until completion of room painting and finishing operations.
3.3 CLEAN-UP
Upon completion of the installation, inspect window treatments for soiling, damage or blemishes; and adjust them for form and appearance and proper operating condition. Repair or replace damaged units as directed by the Contracting Officer. Isolate metal parts from direct contact with concrete, mortar, or dissimilar metals. Ensure blinds installed in recessed pockets can be removable without disturbing the pocket. The entire blind, when retracted, must be contained behind the pocket. For blinds installed outside the jambs and mullions, overlap each jamb and mullion 0.75 inch or more when the jamb and mullion sizes permit. Include all hardware, brackets, anchors, fasteners, and accessories necessary for a complete, finished installation.
-- End of Section --
SECTION 12 21 00 Page 4
SECTION 12 24 13
ROLLER WINDOW SHADES
PART 1 GENERAL
1.1 GENERAL REQUIREMENTS
Provide roller window shades, complete with necessary brackets, fittings, and hardware as indicated. Mount and operate equipment in accordance with manufacturer's instructions. Windows to receive a shade must be completely covered.
a. Submit drawings showing plans, elevations, sections, product details, installation details, operational clearances, wiring diagrams and relationship to adjacent work. Include the use of same room designations as indicated on the drawings.
b. Provide manufacturer's data composed of catalog cuts, brochures, product information, and operating and maintenance instructions on each product to be used. Include styles, profiles and features.
c. Furnish samples of each type and color of roller shade fabric and roller shade channel. Shade material shall be minimum 6 by 6 inch in size. Mark face of material to indicate interior faces.
d. Mock up: Install shade in area designated by Contracting Officer. Do not proceed with remaining work until the Contracting Officer approves workmanship and operation. Re-work mock-up as required to produce acceptable work. The approved shade can be used in installation.
e. Submit fire resistance data, flame spread and smoke contribution data.
1.2 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by basic designation only.
AMERICAN NATIONAL STANDARDS INSTITUTE (ANSI)
ANSI/WCMA A100.1 (2018) American National Standard for Safety of Window Covering Products
ASTM INTERNATIONAL (ASTM)
ASTM G21 (2015) Standard Practice for Determining Resistance of Synthetic Polymeric Materials to Fungi
NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)
NFPA 701 (2019) Standard Methods of Fire Tests for Flame Propagation of Textiles and Films
SECTION 12 24 13 Page 1
SCIENTIFIC CERTIFICATION SYSTEMS (SCS)
SCS SCS Global Services (SCS) Indoor Advantage
UNDERWRITERS LABORATORIES (UL)
UL 2818 (2013) GREENGUARD Certification Program For Chemical Emissions For Building Materials, Finishes And Furnishings
1.3 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submittals with an "S" are for inclusion in the Sustainability eNotebook, in conformance to Section 01 33 29 SUSTAINABILITY REPORTING. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES
SD-02 Shop Drawings
Detailed Drawings; G, RO
Location Schedule; G, RO
SD-03 Product Data
Window Shades; G, RO
Recycled Content for various fiber components; S
SD-04 Samples
Window Shades; G, RO
SD-06 Test Reports
Flammability Requirements; G, RO
SD-07 Certificates
Indoor Air Quality for roller window shades; S
SD-10 Operation and Maintenance Data
Window Shades, Data Package 1; G, RO
SD-11 Closeout Submittals
Submit Data Package for roller window shades, in accordance with Section 01 78 23 OPERATIONS AND MAINTENANCE DATA.
SECTION 12 24 13 Page 2
1.4 CERTIFICATES
1.4.1 Indoor Air Quality Certifications
1.4.1.1 Roller Window Shades
Provide products certified to meet indoor air quality requirements by UL 2818 (Greenguard) Gold, SCS Global Services Indoor Advantage Gold or provide validation by other third-party program that products meet the requirements of this paragraph. Provide current product certification documentation from certification body.
1.5 QUALITY ASSURANCE
1.5.1 Qualifications
1.5.1.1 Installer's Qualifications
Installer trained and certified by the manufacturer with a minimum of ten years experience in installing products comparable to those specified in this section.
1.5.2 Flammability Requirements
Passes in accordance with NFPA 701 small and large-scale vertical burn.
Materials tested are identical to products proposed for use.
1.5.3 Anti-Microbial Requirements
'No Growth' per ASTM G21 results for fungi ATCC9642, ATCC 9644, ATCC9645.
1.6 DELIVERY, STORAGE, AND HANDLING
Deliver components to the jobsite in the manufacturer's original packaging with the brand or company name, item identification, and project reference clearly marked. Store components in a dry location that is adequately ventilated and free from dust, water, or other contaminants and has easy access for inspection and handling. Store materials flat in a clean dry area with temperature maintained above 50 degrees F. Do not open containers until needed for installation unless verification inspection is required. Handle and store shades in accordance with manufacturer's recommendations.
1.7 WARRANTY
Provide manufacturer's warranty to repair or replace defective materials and workmanship for a period of 10 years from date of final acceptance of the work.
PART 2 PRODUCTS
2.1 WINDOW SHADES
Submit drawings showing plans, elevations, sections, product details, installation details, operational clearances, and relationship to work.
Submit a location schedule showing location, size and quantity of shades.
Include the use of same room designations as indicated on the drawings.
Provide product data composed of catalog cuts, brochures, and operating
SECTION 12 24 13 Page 3 and maintenance instructions on each product to be used. Include styles, profiles and features.
Furnish samples of each type and color of roller shade fabric and roller shade channel. Provide shade material minimum 6 by 6 inches in size.
Mark face of material to indicate interior faces.
Mock up: Install shade in area designated by Contracting Officer. Do not proceed with remaining work until the Contracting Officer approves workmanship and operation. Rework mock up as required to produce acceptable work. The approved shade can be used in the installation.
Submit fire resistance data, flame spread and smoke contribution data.
Provide roller tube that operates smoothly and of sufficient diameter and thickness to prevent excessive deflection. Provide brackets that are appropriate for inside mount. Provide shade cloth meeting the performance described in NFPA 701 , small scale test. Treat steel features for corrosion resistance.
Provide Various Fiber Components with a minimum of 60 percent recycled content. Provide data identifying percentage of recycled content for various fiber components. Provide certification of indoor air quality for roller window shades.
2.1.1 Manufacturer's Qualifications
Obtain roller shades through one source from a single manufacturer with a minimum of twenty years of experience and minimum of three projects of similar scope and size in manufacturing products comparable to those specified in this section. Furnish manualshades produced by the same manufacturer to provide matching appearance.
2.1.2 Manually Operated Shades with Single Rollers
2.1.2.1 Chain-and-Clutch Operating Mechanisms
Provide continuous-loop bead chain and clutch that stops shade movement when bead chain is released; shade to be permanently adjusted and lubricated.
2.1.2.2 Bead Chains
Provide bead chain from #10 stainless steel rated to 90 lb. minimum breaking strength with pull chain tensioning device complying with
ANSI/WCMA A100.1
a. Loop Length: Full length of roller shade.
b. Limit Stops: Allows shade to stop when chain is released. Provide limit stops to prevent shade from being raised or lowered too far.
c. Chain-Retainer Type: Clip, jamb mount.
2.1.2.3 Rollers
Provide corrosion-resistant steel or extruded-aluminum tubes of diameters and wall thicknesses required to accommodate operating mechanisms and weights and widths of shade bands indicated without deflection. Provide
SECTION 12 24 13 Page 4 with permanently lubricated drive-end assemblies and idle-end assemblies designed to facilitate removal of shade cloth for service.
a. Roller Drive-End Location: As directed by Architect/Interior Designer.
b. Direction of Shade cloth Roll: Regular, from back (exterior face) of roller.
c. Shade cloth-to-Roller Attachment: Manufacturer's standard method.
Adhesive attachment is not acceptable.
2.1.2.4 Mounting Hardware
Provide corrosion resistant brackets or endcaps compatible with roller assembly, operating mechanism, installation accessories, and mounting location and conditions indicated. Provide hardware that allows for field adjustment or removal of shade roller tube and other operable hardware component without removal of brackets and end or center supports.
2.1.2.5 Shade Cloth
a. Shade Material: Light-blocking fabric.
b. Shade Cloth Bottom (Hem) Bar: Extruded aluminum. Provide shade bar enclosed in sealed pocket of shade band material.
2.1.2.6 Installation Accessories
a. Front Fascia: L-shaped aluminum extrusion to conceal shade roller and hardware that snaps onto end caps without requiring exposed fasteners of any kind. Fascia can be mounted continuously across two or more shade bands. Provide manufacturers standard height fascia as required to conceal roller and shade band assembly when shade is fully open.
2.1.2.7 Room Darkening Shades
Provide room darkening (black-out) window shades designed to eliminate all visible light gaps when shades are fully closed and conform with the following:
a. Provide roller tube made of aluminum. Provide shop fabricated light traps consisting of a head box to house the roller shade, and U-shaped channels to serve as guides for the shade along the sides and to receive the bottom edge of the shade along the sill.
b. Provide light trap made of sheet steel having a minimum thickness of 22 gauge or anodized, extruded, aluminum. Provide legs of the channels not less than 1-3/4 inches long and separated by the minimum distance that permits free operation of the shade. Edges of light trap coming into contact with the shade cloth are smooth pile light seal. The exposed face of the head box is hinged or removable for access to the shade roller. The interior or unexposed surfaces of the light trap have a finish coat of flat black enamel. The exposed portions of the light trap have a factory-applied priming coat of gray paint.
c. Provide type of cloth for blackout purposes. Provide shade from a single piece of PVC fiberglass.
SECTION 12 24 13 Page 5
d. Fit the bottom edge of the shade with a steel operating bar. Shades to engage positively with bottom rail through operating bar or chain pull. Paint bars with flat black enamel. Make pull cords of No. 4 braided nylon or beaded chain having not less than 175 pounds breaking strength.
2.2 COLOR
Provide color, pattern and texture for metal trim and shade fabric as indicated; colors listed are not intended to limit the selection of equal colors from other manufacturers.
PART 3 EXECUTION
3.1 FIELD MEASUREMENTS
After becoming familiar with details of the work, verify all dimensions in the field, and advise the Contracting Officer of any discrepancy before performing the work.
3.2 INSTALLATION
Do not install building construction materials that show visual evidence of biological growth.
Provide roller window shades, complete with necessary brackets, fittings, and hardware as indicated.
Perform installation in accordance with the approved detailed drawings and manufacturer's installation instructions. Install units level, plumb, secure, and at proper height and location relative to window units.
Provide and install supplementary or miscellaneous items in total, including clips, brackets, or anchorages incidental to or necessary for a sound, secure, and complete installation. Do not start installation until completion of room painting and finishing operations.
3.3 CLEAN-UP
Upon completion of the installation, clean window treatments and exposed components as recommended by manufacturer. Adjust window treatment for form and appearance and proper operating condition. Repair or replace damaged units as directed by the Contracting Officer. Isolate metal parts from direct contact with concrete, mortar, or dissimilar metals. Ensure shades installed in recessed pockets can be removed without disturbing the pocket. The entire shade, when retracted, is contained inside the pocket. For shades installed outside the jambs and mullions, overlap each jamb and mullion 0.75 inch or more when the jamb and mullion sizes permit. Include all hardware, brackets, anchors, fasteners, and accessories necessary for a complete, finished installation.
SECTION 12 24 13 Page 6
SECTION 21 13 13
WET PIPE SPRINKLER SYSTEMS, FIRE PROTECTION
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AMERICAN SOCIETY OF MECHANICAL ENGINEERS (ASME)
ASME B16.1 (2020) Gray Iron Pipe Flanges and Flanged Fittings Classes 25, 125, and 250
ASME B16.3 (2016) Malleable Iron Threaded Fittings, Classes 150 and 300
ASME B16.4 (2016) Standard for Gray Iron Threaded Fittings; Classes 125 and 250
ASME B16.21 (2016) Nonmetallic Flat Gaskets for Pipe Flanges
AMERICAN SOCIETY OF SANITARY ENGINEERING (ASSE)
ASSE 1013 (2021) Performance Requirements for Reduced Pressure Principle Backflow Prevention Assemblies
ASSE 1015 (2021) Performance Requirements for Double Check Backflow Prevention Assemblies
AMERICAN WATER WORKS ASSOCIATION (AWWA)
AWWA C104/A21.4 (2016) Cement-Mortar Lining for Ductile-Iron Pipe and Fittings for Water
AWWA C110/A21.10 (2012) Ductile-Iron and Gray-Iron Fittings for Water
AWWA C111/A21.11 (2017) Rubber-Gasket Joints for Ductile-Iron Pressure Pipe and Fittings
AWWA C203 (2020) Coal-Tar Protective Coatings and Linings for Steel Water Pipelines - Enamel and Tape - Hot-Applied
AWWA M14 (2015) Manual: Recommended Practice for Backflow Prevention and Cross-Connection Control
SECTION 21 13 13 Page 1
ASTM INTERNATIONAL (ASTM)
ASTM A47/A47M (1999; R 2018; E 2018) Standard Specification for Ferritic Malleable Iron Castings
ASTM A53/A53M (2020) Standard Specification for Pipe, Steel, Black and Hot-Dipped, Zinc-Coated, Welded and Seamless
ASTM A135/A135M (2021) Standard Specification for Electric-Resistance-Welded Steel Pipe
ASTM A153/A153M (2016a) Standard Specification for Zinc Coating (Hot-Dip) on Iron and Steel Hardware
ASTM A183 (2014; R 2020) Standard Specification for Carbon Steel Track Bolts and Nuts
ASTM A536 (1984; R 2019; E 2019) Standard Specification for Ductile Iron Castings
FM GLOBAL (FM)
FM 1637 (2010) Flexible Sprinkler Hose with Threaded End Fittings
FM APP GUIDE (updated on-line) Approval Guide http://www.approvalguide.com/
INTELLIGENCE COMMUNITY STANDARD (ICS)
ICS 705-1 (2010) Physical and Technical Security Standard for Sensitive Compartmented Information Facilities
MANUFACTURERS STANDARDIZATION SOCIETY OF THE VALVE AND FITTINGS
INDUSTRY (MSS)
MSS SP-71 (2018) Gray Iron Swing Check Valves, Flanged and Threaded Ends
NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)
NFPA 13 (2019; Errata 19-1; Errata 19-2; TIA 19-1;
TIA 19-2; TIA 19-3; TIA 19-4; Errata 19-3;
Errata 20-4; TIA 19-5; TIA 19-6) Standard for the Installation of Sprinkler Systems
NFPA 13R (2022) Standard for the Installation of Sprinkler Systems in Low-Rise Residential Occupancies
NFPA 24 (2022) Standard for the Installation of Private Fire Service Mains and Their Appurtenances
NFPA 101 (2021) Life Safety Code
SECTION 21 13 13 Page 2
NFPA 291 (2016) Recommended Practice for Fire Flow Testing and Marking of Hydrants
NATIONAL INSTITUTE FOR CERTIFICATION IN ENGINEERING TECHNOLOGIES
(NICET)
NICET 1014-7 (2012) Program Detail Manual for Certification in the Field of Fire Protection Engineering Technology (Field Code 003) Subfield of Automatic Sprinkler System Layout
UNDERWRITERS LABORATORIES (UL)
UL 193 (2016) UL Standard for Safety Alarm Valves for Fire-Protection Service
UL 199 (2020) UL Standard for Safety Automatic Sprinklers for Fire-Protection Service
UL 262 (2004; Reprint Oct 2011) Gate Valves for Fire-Protection Service
UL 312 (2010; Reprint Mar 2018) UL Standard for Safety Check Valves for Fire-Protection Service
UL 405 (2013; Bul. 2020) UL Standard for Safety Fire Department Connection Devices
UL 668 (2004; Reprint Jul 2016) UL Standard for Safety Hose Valves for Fire-Protection Service
UL 789 (2004; Reprint May 2017) UL Standard for Safety Indicator Posts for Fire-Protection Service
UL 1626 (2008; Bul. 2018) UL Standard for Safety Residential Sprinklers for Fire-Protection Service
UL 2443 (2015; Reprint May 2020) UL Standard for Safety Flexible Sprinkler Hose with Fitings for Fire Protection Service
UL Fire Prot Dir (2012) Fire Protection Equipment Directory
1.2 SYSTEM DESCRIPTION
Provide wet pipe sprinkler system(s) in all areas of the building .
Except as modified herein, the system must meet the requirements of NFPA 13 .
Pipe sizes which are not indicated on the Contract drawings must be determined by hydraulic calculations.
SECTION 21 13 13 Page 3
1.2.1 Hydraulic Design
1.2.1.1 Basis for Calculations
A waterflow test was performed on 10 October 2021 at FWLL-B2601 and resulted in a static pressure of 62 psi with a residual pressure of 58 psi while flowing 1,120 gpm. Perform a fire hydrant flow test prior to shop drawing submittal in accordance with NFPA 291 . Results must include hydrant elevations relative to the building and hydrant number/identifiers for the tested hydrants, including which were flowed, which had a gauge.
This information must be presented in a tabular form if multiple hydrants were flowed. The results must be included with the hydraulic calculations. Hydraulic calculations must be based on flow test noted in this paragraph, unless verified by the Fire Protection Engineer and approved by Contracting Officer. Hydraulic calculations must be based upon the Hazen-Williams formula with a "C" value noted in NFPA 13 for piping, ..
1.2.1.2 Hydraulic Calculations
a. Water supply curves and system requirements must be plotted on semi-logarithmic graph (N^1.85) paper so as to present a summary of the complete hydraulic calculation.
b. Provide a summary sheet listing sprinklers in the design area and their respective hydraulic reference points, elevations, minimum discharge pressures and minimum flows. Elevations of hydraulic reference points (nodes) must be indicated.
c. Documentation must identify each pipe individually and the nodes connected thereto. Indicate the diameter, length, flow, velocity, friction loss, number and type fittings, total friction loss in the pipe, equivalent pipe length and Hazen-Williams coefficient for each pipe.
d. Where the sprinkler system is supplied by interconnected risers, the sprinkler system must be hydraulically calculated using the hydraulically most demanding single riser. The calculations must not assume the simultaneous use of more than one riser.
e. All calculations must include the backflow preventer manufacturer's stated friction loss at the design flow or 12 psi for reduced pressure backflow preventer, whichever is greater.
f. All calculations must be performed back to the actual location of the flow test, taking into account the direction of flow in the service main at the test location.
g. For gridded systems, calculations must show peaking of demand area friction loss to verify that the hydraulically most demanding area is being used. A flow diagram indicating the quantity and direction of flows must be included.
1.2.1.3 Design Criteria
Hydraulically design the system to discharge a minimum density as indicated on the drawings. Hydraulic calculations must be in accordance with the Area/Density Method of NFPA 13 . Add an allowance for exterior hose streams of 150 gpm to the sprinkler system demand at the fire hydrant
SECTION 21 13 13 Page 4 shown on the drawings closest to the point where the water service enters the building .
1.2.2 Sprinkler Coverage
Sprinklers must be uniformly spaced on branch lines. Provide coverage throughout 100 percent of the building. This includes, but is not limited to, telephone rooms, electrical equipment rooms (regardless of the fire resistance rating of the enclosure), boiler rooms, switchgear rooms, transformer rooms, attached electrical vaults and other electrical and mechanical spaces. Coverage per sprinkler must be in accordance with NFPA 13 . Provide sprinklers below all obstructions in accordance with NFPA 13 . Exceptions are as follows:
a. Sprinklers may be omitted from small rooms which are exempted for specific occupancies in accordance with NFPA 101 .
b. Facilities that are designed in accordance with NFPA 13R.
1.2.3 Qualified Fire Protection Engineer (QFPE)
An individual who is a licensed professional engineer (P.E.) who has passed the fire protection engineering written examination administered by the National Council of Examiners for Engineering and Surveying (NCEES) and has relevant fire protection engineering experience. Services of the QFPE must include:
a. Reviewing SD-02, SD-03, and SD-05 submittal packages for completeness and compliance with the provisions of this specification. Working (shop) drawings and calculations must be prepared by, or prepared under the immediate supervision of, the QFPE. The QFPE must affix their professional engineering stamp with signature to the shop drawings, calculations, and material data sheets, indicating approval prior to submitting the shop drawings to the DFPE.
b. Provide a letter documenting that the SD-02, SD-03, and SD-05 submittal package has been reviewed and noting all outstanding comments.
c. Performing in-progress construction surveillance prior to installation of ceilings (rough-in inspection).
d. Witnessing pre-Government and final Government functional performance testing and performing a final installation review.
e. Signing applicable certificates under SD-07.
1.3 SUBMITTALS
Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for information only. When used, a code following the "G" classification identifies the office that will review the submittal for the Government.
Partial submittals and submittals not fully complying with NFPA 13 and this specification section must be returned disapproved without review.
SD-02, SD-03 and SD-05 must be submitted simultaneously.
Shop drawings (SD-02), product data (SD-03) and calculations (SD-05) must be prepared by the designer and combined and submitted as one complete
SECTION 21 13 13 Page 5 package. The QFPE must review the SD-02/SD-03/SD-05 submittal package for completeness and compliance with the Contract provisions prior to submission to the Government. The QFPE must provide a Letter of Confirmation that they have reviewed the submittal package for compliance with the contract provisions. This letter must include their professional engineer stamp and signature. Partial submittals and submittals not reviewed by the QFPE must be returned disapproved without review.
Submit the following in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
SD-01 Preconstruction Submittals
Qualified Fire Protection Engineer (QFPE); G , RO
Sprinkler System Designer; G , RO
Sprinkler System Installer; G , RO
SD-02 Shop Drawings
Shop Drawing; G , RO
SD-03 Product Data
Pipe; G , RO
Fittings; G , RO
Valves, including gate, check, butterfly, and globe; G , RO
Alarm Valves; G , RO
Relief Valves; G , RO
Sprinklers; G , RO
Pipe Hangers and Supports; G , RO
Sprinkler Alarm Switch; G , RO
Valve Supervisory (Tamper) Switch; G , RO
Fire Department Connection; G , RO
Backflow Prevention Assembly; G , RO
Air Vent; G , RO
Hose Valve; G
Seismic Bracing; G , RO
Nameplates; G , RO
SD-05 Design Data
Seismic Bracing; G , RO
SECTION 21 13 13 Page 6
Load calculations for sizing of seismic bracing
Hydraulic Calculations; G , RO
SD-06 Test Reports
Test Procedures; G , RO
SD-07 Certificates
Verification of Compliant Installation; G , RO
Request for Government Final Test; G , RO
SD-10 Operation and Maintenance Data
Operating and Maintenance (O&M) Instructions; G , RO
Spare Parts Data; G , RO
SD-11 Closeout Submittals
As-built drawings
1.4 QUALITY ASSURANCE
1.4.1 Preconstruction Submittals
Within 36 days of contract award but no less than 14 days prior to commencing work on site, the prime Contractor must submit the following for review and approval. SD-02, SD-03 and SD-05 submittals received prior to the review and approval of the qualifications will be returned Disapproved Without Review.
1.4.1.1 Shop Drawing
Three copies of the shop drawings, no later than 28 days prior to the start of system installation. Working drawings conforming to the requirements prescribed in NFPA 13 and must be no smaller than the Contract Drawings. Each set of drawings must include the following:
a. A descriptive index with drawings listed in sequence by number. A legend sheet identifying device symbols, nomenclature, and conventions used in the package.
b. Floor plans drawn to a scale not less than 1/8-inch equals 1-foot clearly showing locations of devices, equipment, risers, and other details required to clearly describe the proposed arrangement.
c. Actual center-to-center dimensions between sprinklers on branch lines and between branch lines; from end sprinklers to adjacent walls; from walls to branch lines; from sprinkler feed mains, cross mains and branch lines to finished floor and roof or ceiling. A detail must show the dimension from the sprinkler and sprinkler deflector to the ceiling in finished areas.
d. Longitudinal and transverse building sections showing typical branch line and cross main pipe routing, elevation of each typical sprinkler above finished floor and elevation of "cloud" or false ceilings in
SECTION 21 13 13 Page 7 relation to the building ceilings.
e. Plan and elevation views which establish that the equipment will fit the allotted spaces with clearance for installation and maintenance.
f. Riser layout drawings drawn to a scale of not less than 1/2-inch equals 1-foot to show details of each system component, clearances between each other and from other equipment and construction in the room.
g. Details of each type of riser assembly, pipe hanger, sway bracing for earthquake protection, and restraint of underground water main at point-of-entry into the building, and electrical devices and interconnecting wiring. The dimension from the edge of vertical piping to the nearest adjacent wall(s) must be indicated on the drawings when vertical piping is located in stairs or other portions of the means of egress.
h. Details of each type of pipe hanger, seismic bracing/restraint and related components.
1.4.1.2 Product Data
Three copies of annotated catalog data to show the specific model, type, and size of each item. Catalog cuts must also indicate the NRTL listing.
The data must be highlighted to show model, size, options, and other pertinent information, that are intended for consideration. Data must be adequate to demonstrate compliance with all contract requirements.
Product data for all equipment must be combined into a single submittal.
1.4.1.3 Hydraulic Calculations
Calculations must be as outlined in NFPA 13 except that calculations must be performed by computer using software intended specifically for fire protection system design using the design data shown on the drawings.
Calculations must include isometric diagram indicating hydraulic nodes and pipe segments.
1.4.1.4 Operating and Maintenance (O&M) Instructions
Submit in accordance with Section 01 78 23 OPERATION AND MAINTENANCE DATA as supplemented and modified by this specification section.
Provide six manuals and one pdf version on electronic media. The manuals must include the manufacturer's name, model number, parts list, list of parts and tools that should be kept in stock by the owner for routine maintenance, troubleshooting guide, and recommended service organization (including address and telephone number) for each item of equipment. Each service organization submitted must be capable of providing 4-hour on-site response to a service call on an emergency basis.
Submit spare parts data for each different item of material and equipment specified. The data must include a complete list of parts and supplies, and a list of parts recommended by the manufacturer to be replaced after 1-year and 3 years of service. Include a list of special tools and test equipment required for maintenance and testing of the products supplied.
SECTION 21 13 13 Page 8
1.4.2 Qualifications
1.4.2.1 Sprinkler System Designer
The sprinkler system designer must be certified as a Level IV Technician by National Institute for Certification in Engineering Technologies (NICET) in the Water-Based Systems Layout subfield of Fire Protection Engineering Technology in accordance with NICET 1014-7 .
1.4.2.2 Sprinkler System Installer
The sprinkler system installer must be regularly engaged in the installation of the type and complexity of system specified in the contract documents, and must have served in a similar capacity for at least three systems that have performed in the manner intended for a period of not less than 6 months.
1.4.3 Regulatory Requirements
Equipment and material must be listed or approved. Listed or approved, as used in this Section, means listed, labeled or approved by a Nationally Recognized Testing Laboratory (NRTL) such as UL Fire Prot Dir or FM APP GUIDE. The omission of these terms under the description of an item or equipment described must not be construed as waiving this requirement. All listings or approvals by testing laboratories must be from an existing ANSI or UL published standard. The recommended practices stated in the manufacturer's literature or documentation are mandatory requirements.
1.5 DELIVERY, STORAGE, AND HANDLING
Protect all equipment delivered and placed in storage from the weather, excessive humidity and temperature variations, dirt and dust, or other contaminants. All pipes must be either capped or plugged until installed.
1.6 EXTRA MATERIALS
Spare sprinklers and wrench(es) must be provided as spare parts in accordance with NFPA 13 .
PART 2 PRODUCTS
2.1 MATERIALS AND EQUIPMENT
2.1.1 Standard Products
Provide materials, equipment, and devices listed for fire protection service when so required by NFPA 13 or this specification. Select material from one manufacturer, where possible, and not a combination of manufacturers, for a classification of material. Material and equipment must be standard products of a manufacturer regularly engaged in the manufacture of the products for at least 2 years prior to bid.
2.1.2 Nameplates
Major components of equipment must have the manufacturer's name, address, type or style, model or serial number, catalog number, date of installation, installing Contractor's name and address, and the contract number provided on a new name plate permanently affixed to the item or
SECTION 21 13 13 Page 9 equipment. Nameplates must be etched metal or plastic, permanently attached by screws to control units, panels or adjacent walls.
2.1.3 Identification and Marking
Pipe and fitting markings must include name or identifying symbol of manufacturer and nominal size. Pipe must be marked with ASTM designation. Valves and equipment markings must have name or identifying symbol of manufacturer, specific model number, nominal size, name of device, arrow indicating direction of flow, and position of installation (horizontal or vertical), except if valve can be installed in either position. Markings must be included on the body casting or on an etched or stamped metal nameplate permanently on the valve or cover plate.
2.1.4 Pressure Ratings
Valves, fittings, couplings, alarm switches, and similar devices must be rated for the maximum working pressures that can be experienced in the system, but in no case less than 175 psi.
2.2 UNDERGROUND PIPING COMPONENTS
2.2.1 Pipe
Pipe must comply with NFPA 24 . Minimum pipe size is 4 inches. Piping more than 5 feet outside the building walls must comply with Section 33 11 00 WATER UTILITY DISTRIBUTION PIPING. A continuous section of welded stainless steel fire water service piping from a point outside the building perimeter to a flanged fitting at least 1-foot above the finished floor within the building is acceptable.
2.2.2 Fittings and Gaskets
Fittings must be ductile-iron conforming to AWWA C110/A21.10 with cement mortar lining conforming to AWWA C104/A21.4 . Gaskets must be suitable in design and size for the pipe with which such gaskets are to be used.
Gaskets for ductile-iron pipe joints must conform to AWWA C111/A21.11 .
2.2.3 Gate Valve and Indicator Posts
Installation must comply with NFPA 24 . Gate valves for use with indicator post must conform to UL 262 . Indicator posts must conform to UL 789 .
Provide each indicator post with one coat of primer and two coats of red enamel paint.
2.2.4 Buried Utility Warning and Identification Tape
Provide detectable aluminum foil plastic backed tape or detectable magnetic plastic tape manufactured specifically for warning and identification of buried piping. Tape must be detectable by an electronic detection instrument. Provide tape, 3 inches minimum width, color coded for the utility involved with warning and identification imprinted in bold block letters continuously and repeatedly over the entire tape length.
Warning and identification must read "CAUTION BURIED WATER PIPING BELOW" or similar wording. Use permanent code and letter coloring unaffected by moisture and other substances contained in trench backfill material.
SECTION 21 13 13 Page 10
2.3 ABOVEGROUND PIPING COMPONENTS
2.3.1 Steel Piping Components
2.3.1.1 Steel Pipe
Except as modified herein, steel pipe must be black as permitted by NFPA 13 and conform to the applicable provisions of ASTM A53/A53M, ASTM A135/A135M or ASTM A153/A153M .
Steel pipe must be minimum Schedule 40 for sizes 2 inches and less; and minimum Schedule 10 for sizes larger than 2 inches. Steel piping with wall thickness less than Schedule 40 must not be threaded. Grooved pipe must be cut-grooved.
2.3.1.2 Fittings
Fittings must be welded, threaded, or grooved-end type. Threaded fittings must be cast-iron conforming to ASME B16.4 , malleable-iron conforming to ASME B16.3 or ductile-iron conforming to ASTM A536. Plain-end fittings with mechanical couplings, fittings that use steel gripping devices to bite into the pipe, steel press fittings and field welded fittings are not permitted. Fittings, mechanical couplings, and rubber gaskets must be supplied by the same manufacturer. Threaded fittings must use Teflon tape or manufacturer's approved joint compound. Reducing couplings are not permitted except as allowed by NFPA 13 .
2.3.1.3 Grooved Mechanical Joints and Fittings
Joints and fittings must be designed for not less than 175 psi service and the product of the same manufacturer. Field welded fittings must not be used. Fitting and coupling housing must be malleable-iron conforming to ASTM A47/A47M, Grade 32510; ductile-iron conforming to ASTM A536, Grade 65-45-12. Rubber gasketed grooved-end pipe and fittings with mechanical couplings are permitted in pipe sizes 2 inches and larger. Gasket must be the flush type that fills the entire cavity between the fitting and the pipe. Nuts and bolts must be heat-treated steel conforming to ASTM A183 and must be cadmium-plated or zinc-electroplated.
2.3.1.4 Flanges
Flanges must conform to NFPA 13 and ASME B16.1 . Gaskets must be non-asbestos compressed material in accordance with ASME B16.21 , 1/16-inch thick, and full face or self-centering flat ring type.
2.3.2 Flexible Sprinkler Hose
Flexible sprinkler hose must comply with UL 2443 and FM 1637 .
2.3.3 Pipe Hangers and Supports
Provide galvanized pipe hangers, supports and seismic bracing in accordance with NFPA 13 . Design and install seismic protection in accordance with the requirements of NFPA 13 section titled "Protection of Piping Against Damage Where Subject to Earthquakes for Seismic Design Category "D".
SECTION 21 13 13 Page 11
2.3.4 Valves
Provide valves of types approved for fire service. Valves must open by counterclockwise rotation.
2.3.4.1 Control Valve
Manually operated sprinkler control/gate valve must be as indicated on the drawings and must be listed.
2.3.4.2 Check Valves
Check valves must comply with UL 312 . Check valves 4 inches and larger must be of the swing type, have a clear waterway and meet the requirements of MSS SP-71 , for Type 3 or 4. Inspection plate must be provided on valves larger than 6 inches.
2.3.4.3 Hose Valve
Valve must comply with UL 668 .
2.3.5 Alarm Valves
Provide variable pressure type alarm check valve, standard trim piping, pressure gauges, bypass, retarding chamber, testing valves, and main drain, and other components as required for a fully operational system.
Alarm valves must comply with UL 193 .
2.4 ALARM INITIATING AND SUPERVISORY DEVICES
2.4.1 Sprinkler Alarm Switch
Vane or pressure-type flow switch(es). Connection of switch must be by the fire alarm installer. Vane type alarm actuating devices must have mechanical diaphragm controlled retard device adjustable from 10 to 60 seconds and must instantly recycle.
2.4.2 Valve Supervisory (Tamper) Switch
Switch must be integral to the control valve or suitable for mounting to the type of control valve to be supervised open. The switch must be tamper resistant and contain SPDT (Form C) contacts arranged to transfer upon removal of the housing cover or closure of the valve of more than two rotations of the valve stem.
2.5 BACKFLOW PREVENTION ASSEMBLY
Reduced-pressure principle valve assembly backflow preventer complying with ASSE 1013 , ASSE 1015 and AWWA M14. Each check valve must have a drain. Backflow prevention assemblies must have current "Certificate of Approval from the Foundation for Cross-Connection Control and Hydraulic Research, FCCCHR List" and be listed for fire protection use. Listing of the specific make, model, design, and size in the FCCCHR List is acceptable as the required documentation.
2.5.1 Backflow Preventer Test Connection
Test connection must consist of a series of listed hose valves with 2 1/2-inch National Standard male hose threads with cap and chain.
SECTION 21 13 13 Page 12
2.6 FIRE DEPARTMENT CONNECTION
Fire department connection must be projecting type with cast-brass body, matching wall escutcheon lettered "Auto Spkr" with a chromium-plated finish. The connection must have individual self-closing clappers, caps with drip drains and chains. Female inlets must have 5-inch diameter Storz.
Comply with UL 405 .
2.7 SPRINKLERS
Sprinklers must comply with UL 199 and NFPA 13 . Sprinklers with internal O-rings are not acceptable. Sprinklers in high heat areas including attic spaces or in close proximity to unit heaters must have temperature classification in accordance with NFPA 13 . Extended coverage sprinklers are permitted for loading docks, residential occupancies and high-piled storage applications only.
2.7.1 Pendent Sprinkler
Pendent sprinkler must be recessed quick-response type with nominal K-factor of 5.6. Pendent sprinklers must have a polished chrome finish.
Assembly must include an integral escutcheon.
2.7.2 Upright Sprinkler
Upright sprinkler must be chrome-plated quick-response type and have a nominal K-factor of 5.6.
2.7.3 Sidewall Sprinkler
Sidewall sprinkler must be the quick-response type. Sidewall sprinkler must have a nominal K-factor of 5.6. Sidewall sprinkler must have a polished-chrome finish.
2.7.4 Concealed Sprinkler
Concealed sprinkler must be chrome-plated quick-response type and have a nominal K-factor of 5.6. Coverplate must be white.
2.7.5 Residential Sprinkler
Residential sprinkler must be recessed pendent type with nominal K-factor of 5.6. Residential sprinkler must have a polished-chrome finish.
Sprinkler must comply with UL 1626 .
2.8 ACCESSORIES
2.8.1 Sprinkler Cabinet
Provide spare sprinklers in accordance with NFPA 13 and must be placed in a suitable metal or plastic cabinet of sufficient size to accommodate all the spare sprinklers and wrenches in designated locations.
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .