Questions and Answers.docx

DOCX document 18 KB Posted

Attached to
Forced Air Gas Furnace
Solicitation number
W912GY-24-Q-0024
Issued by

About this file

This document is a set of Questions and Answers related to a federal contract opportunity for Forced Air Gas Furnaces.

The key details are as follows: The government has a requirement for 4 forced air gas furnaces under the base CLIN 0001, with additional option CLINs for up to 26 more furnaces of various sizes. The delivery date for the base CLIN is December 1, 2024, while the option CLINs have a delivery date of December 1, 2025 or December 1, 2026. The government is a tax-exempt entity, and payment terms will be in accordance with FAR 52.212-4. There is no incumbent contractor, and this is a new requirement. Funds are currently available for the base CLIN. The furnaces will be delivered to a single location, and government personnel will be available to unload them using forklifts. The furnaces must meet or exceed the specifications provided, and include a minimum 2-year warranty on parts and a 10-year warranty on the heat exchanger.

View the file

Other files

File Type Posted
W912GY24Q0024_Forced Air Gas Furnace Replacement.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions and Answers 03 SEP 2024

1. A question about the delivery schedule for the equipment. Most of the equipment has a single delivery date schedule of 12/1/2025. Can some equipment be delivered sooner than that? If so, what would be the acceptable timeframe prior to that date when equipment could be delivered?

A. To clarify, delivery date for the base line item (CLIN 0001) is Dec 1, 2024. “OPTION CLINs” 1001-1006 have a delivery of 12/1/2025 and “OPTION CLINs 2001 and 2002 have a delivery of 12/1/2026.

B. To further clarify, “OPTION” line items are not guaranteed. From FAR clause 52.217-7, the Government **may** require the delivery of the numbered line items identified in the schedule as an option item,”

1. If the Government has a need for additional heaters and determines the “OPTION” line item is the most advantageous method to buy additional heaters, it will send the contractor a notice of intent to exercise and then send a modification to fund the desired option line items.

2. The delivery dates for option line items will be determined if/when the option CLIN is exercised.

C. Dec 1, 202X, is given for each option line item, for the purpose of providing timeframe and contract expiration point of reference.

1. The timeframe informs potential offerors when to potentially expect the option to be exercised so they can price accordingly. Pricing for option line items 1001-1006 will need to remain valid until Dec 1, 2025, and pricing for option line items 2001 and 2002 will need to remain valid until Dec 1, 2026.

2. Expiration point of reference, if the Government decides to exercise the option, notice must be given within 60 days of contract expiration (12/1/202X).

2. Is there a current incumbent? If so, what is the award number?

A. No

3. Is this a new requirement?

A. Yes

4. Are funds currently available for this solicitation?

A. Yes, there is funding for the base line item 0001.

5. Will the government be tax exempt.

A. Yes

6. What are the specific lead times for each batch of furnaces, and are there any penalties for late delivery?

A. See details above regarding exercising option line items.

B. If deliveries are not timely and not due to an excusable delay (iaw paragraph (f) of FAR 52.212-4), contractor will be in default and subject to contract remedies in accordance with FAR 12.

7. Can you clarify the total amount of furnaces my calculations add up to 32 in total ?

A. Total is 30:

1. The initial/base CLIN 0001 is for the delivery of 4 Each, forced air gas furnaces (Thermocycler GTR-486 or equal).

2. The remaining/option line items equate to 26 various sized forced air gas furnaces (see schedule) 1001 (4), 1002 (4), 1003 (4), 1004 (4), 1005 (4), 1006 (2), 2001 (2) and 2002 (2).

8. Will the furnaces be going to the same location or multiple locations?

A. All furnaces will be delivered to the receiving building.

9. Will the furnaces only need to be delivered? If so, will someone be available to pick the furnaces up? How would delivery take place? Will personnel be available with a forklift to unload the equipment?

A. Yes, furnaces only need to be delivered to receiving building. Yes, Government personnel will be able to unload with forklifts and move to the intended building after inspection and acceptance.

10. Will old equipment need to be removed?

A. Not as part of this contract.

11. Can you provide more details on the warranty coverage and any included maintenance services?

A. Reference warranty bullet in the specifications:

1. Both sized heaters must include at a minimum, 2-year manufacturer warranty for all parts, the heat exchanger portion must include a 10-year (non-prorated) warranty.

2. No maintenance is required as part of this contract action.

12. Are there any specific compliance standards or certifications required for the furnaces?

A. Heaters must meet or exceed the specifications listed in the solicitation.

13. What are the payment terms and conditions, including any milestones or progress payments?

A. Payment terms are in accordance with FAR Clause 52.212-4 paragraph (i).