Attachment A-Placemat for PDB with OTA Process Overview.pdf

PDF 298 KB Posted

Attached to
Market Survey – Industry Capabilities and Experience with Alternate Design and Delivery Methodologies (ADDM) for USACE Europe District
Solicitation number
W912GB27Z1C2F
Issued by

About this file

This document is an infographic describing the end-to-end process for Progressive Design-Build (PDB) projects utilizing Other Transaction (OT) agreements under 10 U.S.C. § 2808a for Military Construction (MILCON) projects.

The PDB with OT approach consists of two agreement phases. Phase 1 (Design & Preconstruction Services) uses MILCON Design Funds and progresses through eight pre-agreement steps: Project Requirements definition, Request for Qualifications (RFQ), Statement of Qualifications (SOQ) submission, down-select, pitch presentations, Qualifications Based Selection (QBS), negotiation of OT Phase 1 services, and award of the OT Phase 1 Agreement. Phase 1 execution includes kickoff and alignment, schematic design, budget lockdown, design development, preconstruction readiness activities, and an off-ramp decision point. Phase 2 (Final Design & Construction) uses MILCON Construction Funds and authorizes construction when cost, scope, schedule, and risk are acceptable. Phase 2 involves overlapping final design/construction documents and construction execution in work packages, followed by red zone commissioning, beneficial occupancy, and turnover/construction completion. The process emphasizes five core benefits: early alignment between government and industry, open book collaboration with transparent estimating, iterative and flexible strategy evolution, off-ramp protection providing government exit points at key milestones, and overlapped execution optimizing design and construction. Governance includes tailored oversight, periodic reporting, and risk management throughout both phases.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PROGRESSIVE DESIGN-BUILD (PDB) WITH OT

End-to-End Process for MILCON Projects

Right Authority.

Right Collaboration.

Right Outcome.

OT STATUTORY

AUTHORITY:

10 U.S.C. § 2808a, Facility Construction or Repair:

Transactions Other Than Contracts and

Grants

AGREEMENT PHASE 1 – DESIGN & PRECONSTRUCTION SERVICES (OT Agreement using MILCON Design Funds)

EARLY ALIGNMENT

Aligns Government & Industry Goals Early

OPEN BOOK COLLABORATION

Transparency in estimating drives informed decisions

ITERATIVE & FLEXIBLE

Evolves Strategy & Solves Challenges Early

OFF RAMP PROTECTION

Exit points protect Government at key milestones

OVERLAPPED EXECUTION

Design and Construction Optimized

BETTER OUTCOMES

Deliver facilities with more cost and schedule confidence

AGREEMENT PHASE 2 – FINAL DESIGN & CONSTRUCTION (OT Agreement using MILCON Construction Funds)

KICKOFF & ALIGNMENT SCHEMATIC DESIGN BUDGET LOCK DESIGN DEVELOPMENT DECISION GATEWAY TO

PHASE 2

PRECONSTRUCTION

READINESS

Outcome: Government Authorizes Phase 2 Construction when Cost, Scope, Schedule and Risk are Acceptable

Risk Informed Project Alignment Meeting

• Goals & Objectives

• Risk Workshop

• Success Metrics

• Communication Plan

Concept Solutions

• Further Alternates

• Innovation Opportunities

• Risk Reduction

Schematic Design Development

• Develop Design

Concepts

• Evaluate Systems

• Confirm Approach

Budget Estimate Submission

• Level 3 Cost Estimate

• Cost Confidence Package

• Scope/Schedule Validation

Advance Design (Technical Development)

• Tailored Design

• Engineer Analysis

• Constructability Reviews

Integrated Schedule Development

• Long Lead Item

Identification

• Resource Planning

Execution-Ready Integrated Solution

• Coordinate Estimate

• Constructability

• Risk Mitigation

Government Decision

• Scope Confirmed

• Cost Validated

• Risk Accepted

• Negotiate Phase 2:

Construction

Pre-Construction Work

• BCOES

• Permitting

• Early Submittals

• Site Readiness

Open Book Estimate / Price Schedule Open Book Estimate / Price Schedule

Switch to Firm-Fixed Price

1. Project Requirements

• Mission Need

• Performance Objectives

• Industry Outreach /

Market Intelligence

• SCO OTA Approval

AUTHORIZE PHASE

2 CONSTRUCTION

FINAL DESIGN / CONSTRUCTION DOCUMENTS

(OVERLAPPING)

CONSTRUCTION (OVERLAPPING w/ DESIGN) REDZONE / BENEFICIAL OCCUPANCY TURNOVER /

CONSTRUCTION

COMPLETE

LONG LEAD / EARLY

WORK

• Early Site

Acquisition

• Site Access

• Site Preparation

• Early Package

• Execute Construction in Work Packages

• Foundations / Structure

• Building / Systems

• Interior / Exterior

• Site Utilities

• Continuous Quality & Safety Reviews

• Punchlist

• Red Zone Commissioning

• Joint Occupancy (if needed)

• Beneficial Occupancy

• Base Certification

• Turnover / Construction Complete

• Close Out

• Mission Complete!

• Complete Construction Documents

• Permitting & Submittals

• Ongoing Design Development

• Submittals & Coordination

• Continued BCOES Reviews

• Receive MILCON Construction Funding

• Issue Modification to Agreement

• Obligate Funding

• Decision Milestones

• Green Light Long Lead Item Procurement Construction Continues

2. Request for Qualifications

(RFQ)

3. Statement of Qualifications

(SOQs)

• Industry Submits SOQs •Government Evaluation

4. Down-Select •Government

Selects Best Qualified Offers

• Invite Firms to Pitch Presentations

5. Pitch Presentations

6. Qualifications Based Selection

(QBS)

• Government Selects

Best Qualified Offeror

7. Negotiate OT (Phase 1) Services

• Scope of Ph 1 Design/ Preconstruction Services

• Performance Metrics

8. Award OT (Phase 1)

Agreement •Award Other

Transaction Agreement

GOVERNANCE

& OVERSIGHT

• Tailored Oversight

• Periodic Reporting

•Cost, Schedule, Performance Reviews

• Risk Management

Why PDB with

OT?

PRE-AGREEMENT: PLANNING, SOLICITATION, & AWARD

OFF RAMP

DECISION POINT

OFF RAMP

DECISION POINT

• Finalize Requirements Package

• Industry Day / Notice

• Publish Solicitation

• Offeror Presentations / Meetings / Interviews

• Q&A

• Site Visit, if applicable