USACE_industry_day_Projectsjune_19_Final___.ppt
PPT presentation 545 KB Posted
- Solicitation number
- W912GB20X0001
About this file
Industry Day Israel FMS - Projections June 2019
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Israel_FMS_Industry_Day_Legal_2019_.ppt | PPT presentation | |
| Industry_Day_Participants.xlsx | XLSX spreadsheet | |
| Contracting_Slide_Deck_Israel_Industry_Day_NYC_19_June19_Rev3.ppt | PPT presentation |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Date: June 2019
FMS Project Projections
Europe District
.59
PROCUREMENT METHODS
Best Value (C-Contract)
MATOC – Multiple Award Task Order Contract
IDIQ A-E contracts
.59
IDF
Israel Defense Force (Army)
.59
ARMORED VEHICLE WORKSHOP (SOUTH)
Project Description: New construction of an armored-vehicle-workshop
Fully Designed or Design/Build: Design bid Build
Magnitude of Construction: $5.0M - $10.0M
Anticipated Issue Date: July 2019
Anticipated Contracting Method: MATOC
.59
NEW INFANTRY FACILITIES- SITE 84
| Project Description: New construction (58,000 SQM ) |
| of a number of buildings to include, offices, barracks, DFAC and infrastructure. |
| Fully Designed or Design/Build: Design Bid Build |
Magnitude of Construction: $100.0M - $250.0M
Anticipated Issue Date: 2021
Anticipated Contracting Method: Best Value
.59
WESTERN ELEVATOR SHAFT
| Project Description:. |
| Construction of a 1 level, upper structure that will serve as an entrance for an existing Elevator shaft. This shaft was done and is existing (concrete only).installing 2 elevators |
| Fully Designed or Design/Build: Design bid Build |
Magnitude of Construction: $1.0M - $5.0M
Anticipated Issue Date: August 2019
Anticipated Contracting Method: MATOC
.59
IAF
Israel Air Force
.59
NEW HAS 416
Project Description: New construction of Hardened Shelters and Support facilities.
Fully Designed or Design/Build: Design Bid Build
Magnitude of Construction: $25.0M - $100.0M
Anticipated Issue Date: August 2019
Anticipated Contracting Method: Best Value
.59
13851&13850
| Project Description: |
| Construction of approx. 2,600 m2, two (2) story building, for maintenance of composite materials equipment |
| Construction of approx. 1,100m² Office building and approx. 1,900 m² of Aircraft Hangar for maintenance works |
Fully Designed or Design/Build: Fully Designed
Magnitude of Construction: $10.0M - $25.0M
Anticipated Issue Date: September 2019
Anticipated Contracting Method: Best Value
.59
13748
| Project Description: |
| New construction of a two (2) story building containing offices and operational areas. |
Approx. area: 2,100 m²
Fully Designed or Design/Build: Fully Designed
Magnitude of Construction: $10.0M - $25.0M
Anticipated Issue Date: September 2019
Anticipated Contracting Method: Best value
.59
POWER STATION
Project Description: New power station, electricity and generators facilities
Fully Designed or Design/Build: Fully Designed
Magnitude of Construction: $5.0M - $10.0M
Anticipated Issue Date: November 2019
Anticipated Contracting Method: MATOC
.59
JET FUEL STATION
Project Description: Renovation of a jet fuel station
Fully Designed or Design/Build: Fully Designed
Magnitude of Construction: $1.0M - $5.0M
Anticipated Issue Date: April 2020
Anticipated Contracting Method: MATOC
.59
ACU FACILITIES
Project Description: New construction of a DFAC complex 1000m
Fully Designed or Design/Build: Fully Designed
Magnitude of Construction: $5.0M - $10.0M
Anticipated Issue Date: March 2020
Anticipated Contracting Method: MATOC
.59
TACTICAL COMM
Project Description: : New construction of office building complex approximately 3000m2 , Hangars approximately 2000m
Fully Designed or Design/Build: Fully Designed
Magnitude of Construction: $10.0M - $25.0M
Anticipated Issue Date: August 2020
Anticipated Contracting Method: Best Value
.59
UAV FACILITIES
Project Description: New construction for maintenance facility which contains UAV hangar and support buildings
Fully Designed or Design/Build: Fully Designed
Magnitude of Construction: $5.0M - $10.0M
Anticipated Issue Date: June 2020
Anticipated Contracting Method: MATOC
.59
STAR REAPER HANGER
| Project Description: |
| Construction of a new maintenance hangar 500 m² for UAV’s |
Fully Designed or Design/Build: Fully Designed
Magnitude of Construction: $1.0M - $5.0M
Anticipated Issue Date: July 2020
Anticipated Contracting Method: MATOC
.59
INFERMERY
Project Description: New construction of an infirmary 1200 m²
Fully Designed or Design/Build: Design Build
Magnitude of Construction: $5.0M - $10.0M
Anticipated Issue Date: August 2020
Anticipated Contracting Method: MATOC
.59
BOING REFUELING SURFACE
Project Description:
Jet fuel infrastructures on existing taxiways
Fully Designed or Design/Build: Fully Designed
Magnitude of Construction: $1.0M - $5.0M
Anticipated Issue Date: April 2020
Anticipated Contracting Method: MATOC
.59
FUEL INFRASTRUCTURE OVD
Project Description: New jet fuel line 2500m
Fully Designed or Design/Build: fully designed
Magnitude of Construction: $5.0M - $10.0M
Anticipated Issue Date: April 2020
Anticipated Contracting Method: MATOC
.59
AIR DEFENSE BASE
Project Description: New construction of the base admin section to include ; Barracks , HQ, office building and infrastructures
Fully Designed or Design/Build: Fully Designed
Magnitude of Construction: $25.0M - $100.0M
Anticipated Issue Date: June 2020
Anticipated Contracting Method: Best Value
.59
POWER STATION
Project Description: construction of a new Co Gen power station 5MV
Fully Designed or Design/Build: Design build
Magnitude of Construction: $5.0M - $10.0M
Anticipated Issue Date: August 2020
Anticipated Contracting Method: MATOC
.59
INF
Israel Naval Force
.59
TIRA-IN CENTRAL DFAC COMPLEX (NORTH )
Project Description: New construction of a DFAC complex 1000 m²
Fully Designed or Design/Build: Design Build
Magnitude of Construction: $5.0M - $10.0M
Anticipated Issue Date: September 2019
Anticipated Contracting Method: MATOC
.59
ATLIT HQ
Project Description: New construction of a 2-story HQ building.
Fully Designed or Design/Build: Fully Designed
Magnitude of Construction: $10.0M - $25.0M
Anticipated Issue Date: June 2020
Anticipated Contracting Method: MATOC
.59
IN ASHDOD BASE PIERS
Project Description: New construction of two piers
Fully Designed or Design/Build: Design Build
Magnitude of Construction: $10.0M - $25.0M
Anticipated Issue Date: July 2020
Anticipated Contracting Method: Best Value
.59
EILAT BARRACKS
| Project Description: New construction of a 5 story barrack building |
| Fully Designed or Design/Build: Design Build |
Magnitude of Construction: $5.0M - $10.0M
Anticipated Issue Date: July 2020
Anticipated Contracting Method: MATOC
.59
Questions?
File details come from the government source that posted it.