01 45 10.pdf
PDF 18 KB Posted
- Solicitation number
- W912GB20R0016
- Issued by
-
Department of the Army European Command
About this file
This document outlines requirements for a Multiple Award Task Order Contract to provide design-build and design-bid-build construction services in Estonia. The US Army Corps of Engineers Europe District intends to award IDIQ contracts to at least two offerors totalling $49,950,000 to support defense operations. A pre-proposal conference will be held on February 10, 2020 in Riga, Latvia. Offerors will be given fair opportunity to compete for individual task orders not to exceed the total contract value. The scope includes new facilities and real property repair and maintenance.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amend 02 Riga Event List.XLSX | XLSX spreadsheet | |
| Amend 02_W912GB20R0016.pdf | ||
| Amend 02 Baltics Slide Deck.pdf | ||
| Amend 01_Attachment 1 USACE Specifications.pdf | ||
| Amend 01_W912GB20R0016.pdf | ||
| 00 74 01.pdf | ||
| 01 45 00.pdf | ||
| 00 74 70.pdf | ||
| Attachment 1 Specifications Binder.pdf | ||
| 01 32 01.pdf | ||
| Attachment 7 Letter of Commitment.docx | DOCX document | |
| 01 45 01.pdf | ||
| 01 35 26.pdf | ||
| 01 78 00.pdf | ||
| Attachment 3 ExpInfoSheet.pdf | ||
| 01 45 05.pdf | ||
| W912GB20R0016_FINAL.pdf | ||
| 01 33 16.pdf | ||
| 01 30 01.pdf | ||
| Attachment 4 PPQ.pdf | ||
| Attachment 8 Baltics Pre-proposal Conf Industry Pre-Registration Form.xlsx | XLSX spreadsheet | |
| 00 74 02.pdf | ||
| Attachment 2 ExpOverviewSheet.docx | DOCX document | |
| Attachment 5 BankLetterAssuranceSample_final.pdf | ||
| Attachment 6 BankLetterGuaranteeSample_final.pdf | ||
| 01 33 00.pdf |
Show all 26
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 45 10
DESIGN QUALITY CONTROL (NAU)
10/19
PART 1 GENERAL
1.1 PURPOSE
1.2 REFERENCES
1.3 SUBMITTALS
1.4 DESIGN QUALITY CONTROL (QC) PERSONNEL
PART 2 PRODUCTS
PART 3 EXECUTION
3.1 GENERAL REQUIREMENTS
3.2 DESIGN QUALITY CONTROL (DQC) PLAN
3.2.1 Design Quality Control (DQC) Plan
3.2.2 Acceptance of DQC Plan
3.2.3 Notification of Changes
3.3 INDEPENDENT TECHNICAL REVIEW
3.4 SUBMITTALS AND DELIVERABLES
3.4.1 Submittal Requirements
3.4.2 ProjNet/DrChecks
3.4.3 Government Review Comments
3.4.4 Contractor Required Response
-- End of Section Table of Contents --
SECTION 01 45 10 Page 1
SECTION 01 45 10
DESIGN QUALITY CONTROL (NAU)
10/19
PART 1 GENERAL
1.1 PURPOSE
This section establishes additional Quality Control requirements for the design activities associated with a Design-Build contract. It supplements and does not replace any of the requirements of Section
01 45 00 CONSTRUCTION QUALITY CONTROL.
1.2 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
ER 1110-1-12 (2006; Change 1) Engineering and Design -- Quality Management
1.3 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for Contractor Quality Control approval. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00
SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Design Quality Control (DQC) Plan; G, DO
SD-05 Design Data
Discipline-Specific Checklists
1.4 DESIGN QUALITY CONTROL (QC) PERSONNEL
Refer to Section 01 45 10CONTRACTOR PERSONNEL REQUIREMENTS.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
3.1 GENERAL REQUIREMENTS
In addition to the requirements of paragraph GENERAL REQUIREMENTS of Section 01 45 00 CONSTRUCTION QUALITY CONTROL, the QC system shall include all design operations, both onsite and offsite, and be keyed to the proposed design and construction sequence.
SECTION 01 45 10 Page 2
3.2 DESIGN QUALITY CONTROL (DQC) PLAN
Design will be permitted to begin only after acceptance of the Design QC Plan.
3.2.1 Design Quality Control (DQC) Plan
At least 30 days prior to the planned start of design, submit a Design Quality Control (DQC) Plan. The DQC Plan must include:
a. The procedures to be followed to ensure all services required by this contract are performed and provided in a manner that meets professional architectural and engineering quality standards. As a minimum, all documents must be technically reviewed by competent, independent reviewers identified in the DQC Plan. The same element that produced the product may not perform the independent technical review (ITR). Correct errors and deficiencies in the design documents prior to submitting them to the Government.
b. Discipline-specific checklists to be used during the quality control review of each design submittal. Submit at each design phase as part of the project documentation these completed discipline-specific checklists. The checklists must identify in adequate detail the information reviewed and validated to be in compliance with the requirements of the contract.
c. A copy of the letter to the DQC SM signed by an authorized official of the firm which describes the responsibilities and delegates sufficient authorities to adequately perform the functions of the DQC SM, including authority to stop work which is not in compliance with the Contract.
The Contracting Officer will notify the Contractor in writing of the acceptance of the DQC Plan. After acceptance, any changes proposed by the Contractor are subject to the acceptance of the Contracting Officer.
3.2.2 Acceptance of DQC Plan
Acceptance of the DQC Plan is required prior to the start of design.
Acceptance is conditional and will be predicated on satisfactory performance.
The Government reserves the right to require the Contractor to make changes in the DQC Plan and operations including removal of personnel, as necessary, to obtain the quality specified.
3.2.3 Notification of Changes
After acceptance of the DQC Plan, notify the Contracting Officer in writing of any proposed change and provide a revised submittal of the applicable plan. Proposed changes are subject to acceptance by the Contracting Officer.
3.3 INDEPENDENT TECHNICAL REVIEW
Prior to submission of any design submittal, the contractor shall ensure an Independent Technical Review (ITR) is performed and documented. ITR requirements are explained in Chapter 4 of ER 1110-1-12. This is considered an integral part of the design quality control requirements and the procedures shall be included in the DQC Plan. The Government will not perform an ITR of the contractors designs.
SECTION 01 45 10 Page 3
3.4 SUBMITTALS AND DELIVERABLES
3.4.1 Submittal Requirements
Design Submittals shall comply with the requirements in Section 01 33 00 SUBMITTAL PROCEDURES. The CQC organization is responsible for certifying that all submittals and deliverables are in compliance with the contract requirements.
Organize the design documents in a manner that will assure ensure thorough coordination between various details on drawings, between the various sections of the specifications, and between the drawings and specifications. Designers of Record must thoroughly cross-check and coordinate all work until they are professionally satisfied that no conflicts exist, vital information has not been omitted, and that indefinite language open to interpretation has been resolved.
3.4.2 ProjNet/DrChecks
The contractor shall provide design submittals through the ProjNet/DrChecks system (https://www.projnet.org) in addition to RMS-CM to allow for identification and tracking of review comments.
If an alternate means of tracking comments is authorized, it shall be documented in writing and the procedures included in the DQC Plan.
3.4.3 Government Review Comments
As part of the Government's review of the contractor prepared design, comments will be made by Government reviewers. These comments may include "recommendations" or "suggestions".
Any comment regarding "recommendations" or "suggestions" shall not be considered a change to the contract. The comment is intended to improve the design and/or construction, but is not required to be incorporated. The contractor shall clearly respond to each comment containing a "recommendation" or "suggestion" indicating whether they will comply with the comment or not.
Acceptance or incorporation of any such comment by the contractor in their design shall not be the basis for an adjustment in the contract performance period or amount.
3.4.4 Contractor Required Response
The Contractor must respond to all comments in no later than the next scheduled submittal. Responses must identify the specific action taken with citation of location (drawing number or specification paragraph) within the relevant document. Generalized statements of intention such as "will comply" or "will revise the specification" are not acceptable.
If the Contractor disagrees technically with any comment and does not intend to comply with the comment, the Contractor must clearly outline, with ample justification, the reasons for non-compliance within five (5) days after close of the review period in order that the comment can be resolved in a timely manner.
-- End of Section --
SECTION 01 45 10 Page 4