US Army Corps of Engineers Europe District
APO AE 09049
sr16
Statement of Work Project Number:
RB-HA-2018-00034859
Renovation of Housing Unit at Special Hospital for Psychiatric Disorders
Gornja Toponica, Serbia
Prepared by:
Design Section
Engineering Branch
21MAY2019
01 10 10 Statement of Work Special Hospital for Psychiatric Disorders Housing Unit Renovation, 21-May-19 Page 2 of 52
SECTION 01 10 10
STATEMENT OF WORK
SECTION TABLE OF CONTENTS:
1 GENERAL
2 CIVIL AND GEOTECHNICAL
3 ARCHITECTURAL
4 STRUCTURAL
5 ELECTRICAL & COMMUNICATIONS
6 MECHANICAL
7 FIRE PROTECTION (NO CONTENT - LIFE SAFETY COVERED IN OTHER SECTIONS)
ATTACHMENTS
Att. # 1 Location Map & Conceptual Site Plan Att. # 2 Dedication Plaque Att. # 3 Functional Layout Att. # 4 Structural Calculations Guideline
1.0 GENERAL
1.1 PROJECT DESCRIPTION
The Request for Proposal (RFP) provides parameters for a design-build project for renovation of Housing Unit at Special Hospital for Psychiatric Disorders in Gornja Toponica, Serbia. This building that serves as a Housing Unit for Alcohol Addicts must be renovated. After the renovation the building must accommodate 20 employees and 70 patients. Out of 70 patients there will be 64 males and 6 females. Male / female ratio for the employees is 50/50. The facility is occupied 24/7.
The building is a two-story solid structure with pitched roofs without basement.
It was constructed in 1927 and did not have any major renovation since 40 years.
The structure is made of masonry walls and concrete slabs / beams. Roof structure is made of wood with clay tile roofing. Exterior and interior walls are plastered.
The project includes the following general items of work, detailed requirements are contained elsewhere in this Statement of Work:
a. Repair existing building
b. Provide site improvements
1.2 GENERAL REQUIREMENTS
The Contractor must deliver fully functional, turnkey type facilities (without furniture) as described in this document. The work includes - but is not limited to - design, demolition, fabrication, delivery, installation, construction, and site work. The facility and the installed equipment must be permanent construction.
The facility in this project must be complete and usable to meet codes and technical and functional requirements per this Statement of Work (SOW). The proposal price must include all design, calculations, approvals, certificates, fees, labor, material, equipment, direct overhead, indirect overhead, general and administrative expenses (G&A) and general conditions to complete this project as described in the SOW.
These design and product requirements are minimum requisites. Compliance with the provisions of this section by subcontractors is the responsibility of the Contractor.
21-May-19 Page 3 of 52
1.2.1 BASE BID ITEMS AND OPTIONAL BID ITEMS
This Statement of Work addresses the technical requirements necessary to complete all work associated with this project. For information and requirements regarding the allocation of pricing between elements of the work, refer to the Bid Schedule included as a separate document. The Bid Schedule identifies the breakdown between the individual base bid and optional items for all work identified in this Statement of Work, associated drawings, and attachments. All work as described in these documents is included in either the Base Bid or Optional Items: consider all items not specifically identified in the Optional Items as part of the Base Bid Items.
1.3 FUNCTIONAL AREAS
Provide the following functional areas within the facility:
1.3.1 First Floor
- Office 20 m2
- Main Entry / Stairwell 22 m2
- Utility Connection Room 6 m2
- Storage / Janitor 12 m2
- Corridor 12 m2
- Office 19 m2
- Office 19 m2
- Hall 42 m2
- Nurse RM 67 m2
- Intensive Care 62 m2
- Treatment 14 m2
- Female Employee Toilet 5 m2
- Male Employee Toilet 5 m2
- Corridor 45 m2
- Female Patients 6 Bedroom (BR) 32 m2
- Female Patients Bathroom 7 m2
- Male Patients Lavatory RM 25 m2
- Male Patients Shower RM 25 m2
- Male Patients Toilets 19 m2
- Male Patients 4 BR 26 m2
- Male Patients 6 BR 38 m2
- Dining RM 122 m2
- Kitchen 18 m2
- Storage 15 m2
First floor net area to be provided must be approximately 677 m2.
1.3.2 Second Floor
- Office 20 m2
- Main Stairwell 22 m2
- Roof Access 12 m2
- Male Patients 8 BR 50 m2
- Male Patients 12 BR 67 m2
- Living RM 86 m2
- Hall 42 m2
- Corridor 8 m2
- Office 14 m2
- Office 17 m2
- Corridor 45 m2
- Male Patients 4 BR 25 m2
- Male Patients 4 BR 25 m2
21-May-19 Page 4 of 52
- Male Patients Toilets 19 m2
- Male Patients 4 BR 26 m2
- Male Patients 6 BR 38 m2
- Corridor 27 m2
- Male Patients 3 BR 19 m2
- Male Patients 3 BR 19 m2
- Male Patients 3 BR 19 m2
- Male Patients 3 BR 19 m2
- Male Patients 3 BR 19 m2
Second floor net area to be provided must be approximately 638 m2.
Total first and second floors net area to be renovated must be approximately 1315 m2.
1.4 SUBMITTALS
Government approval is required for submittals with “G” designation; submittals not having a “G” are for Contractor Quality Control approval. When used, a designation following the “G” designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section
01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Demolition Plan; G
Inspection Plan; G
Preconstruction Survey of Furniture, Fixtures, and Equipment; G
SD-05 Design Data
65% Pre-Final Design; G, DO
95% Final Design; G, DO
100% Corrected Final Design; G, DO
SD-06 Test Reports
Test Results and Reports; FIO
1.4.1 DESIGN SUBMITTALS
Provide a complete design package at each milestone, as described in Specification Section 01 33 16 DESIGN AFTER AWARD. The milestones for this project are indicated above in Section 1.4 SUBMITTALS. The specific requirements of each milestone are described in each discipline-specific section of this Specification.
Submit all documents in electronic format (.pdf for text and calculations, .pdf and .dwg (AutoCAD, latest version) for drawings). See Specification 01 33 00 SUBMITTAL PROCEDURES for additional information.
1.4.2 TEST REPORTS
Provide all test results and reports identified in this SOW to the Government as a submittal in accordance with Specification Section 01 33 00 SUBMITTAL PROCEDURES.
Submittals will be considered for information only (FIO) submittals unless specifically identified as a submittal requiring government approval. Coordinate
21-May-19 Page 5 of 52 with the COR after award for the specific items to be included in the submittal register.
1.5 MATERIALS AND EQUIPMENT
Materials and products used must be durable, heavy duty, industry standard. The equipment must be the manufacturer’s standard quality and must be compatible with all other equipment and materials within the system or assembly. Equipment and materials must include all connections and accessories necessary to ensure operability and correct installation according to manufacturer’s requirements.
Provide a nameplate secured to each major piece of equipment. Each nameplate must have the manufacturer’s name, address, contact information, type or style, model or serial number, and catalog number. The definition of a “major piece of equipment” is at the discretion of the COR.
1.5.1 LIFE-SPAN
Construction must have an expected life span of 25 years.
1.5.2 MAINTAINABILITY
Provide low maintenance materials and systems appropriate for the project climate and location.
1.5.3 OPERABILITY
Systems (including but not limited to architectural, electrical, communications, and mechanical systems) must be simple to operate and easy to maintain.
1.5.4 STANDARDIZATION
Provide standardized materials, products, equipment, and systems to minimize the requirements for replacement parts, storage facilities, and service requirements.
1.6 DESIGN DIMENSIONS
Develop the design using the metric system.
1.7 DESIGN CRITERIA
Project design, site facilities, utility systems and material standards must be in accordance with the latest editions of the Host Nation building codes. In the absence of Host Nation building codes, use the International Building Code (IBC) and codes, technical standards, and regulations referenced in this RFP.
While this RFP references various source standards and specifications, all design documents must meet Host Nation codes and requirements. It is the designer's responsibility to demonstrate that the Host Nation standard is equal to the cited standard or specifications being supplanted. Apply the more restrictive standards when conflicts arise between the requirements of this RFP and any referenced or other applicable codes, standards or regulations. If equivalency cannot be met, use the more stringent requirement and quote both codes verbatim in correspondence to the COR. The designer is responsible to determine the required material and execution standards where specific standards are not indicated.
Provide an electronic copy of the local Host Nation standards and building codes in their original language as related to facility design and construction.
1.8 DESIGN CONFERENCES AND MEETINGS
The Contractor and the entire design team are required to participate in a design review conference for each design submittal. The Contractor may request a review conference, but the Government is under no obligation to conduct or participate in a review conference unless specifically identified in the contract documents. The
21-May-19 Page 6 of 52
Contractor must bring the personnel that developed the design submittal to any review conference.
All design review conferences must be held via teleconference or be reviewed and comments resolved via email.
The Contractor is responsible for taking meeting minutes during each design review conference and submitting to the COR for information and approval.
The Contractor is responsible for evaluating all Government comments prior to each design review conference. The Contractor is responsible for resolving all Government comments from each design phase. The Contractor must provide annotated responses to each design review comment with the subsequent design submittal packages. Construction may not begin until all Government comments from all design phases have been resolved.
1.9 SPECIAL CONSTRUCTION REQUIREMENTS
1.9.1 PROTECTION OF WORK AREA
1.9.1.1 DUST AND DEBRIS CONTAINMNET
Seal the project area with construction barriers and dust partitions in order to contain construction dust and debris and maintain a clean environment outside of the work area. In addition to protections within the work area, provide temporary protection for all finishes from the entrance of the facility to each area of work. Patch and repairing any damage caused during construction. Coordinate the locations of barriers with the COR prior to the start of work.
1.9.1.2 PROTECTION OF FURNITURE, FIXTURES, AND EQUIPMENT
Protect all existing furniture, fixtures, and equipment that remain within the work area. Coordinate with the COR and the User for any special protection measures required for sensitive equipment. The Contractor is responsible for repairing or replacing any damage caused during construction. Either the Contractor and the COR must conduct a preconstruction survey of furniture, fixtures, and equipment with both the Contractor and Government representative present.
1.9.1.3 NOISE AND VIBRATION CONTROL
Employ demolition and construction methods that minimize the production of sound and vibration. The acceptable average noise level during the work hours from 07:00-19:00 h is 60 dB(A). Coordinate the schedule of loud or disruptive activities with the COR prior to the start of work.
END OF SECTION
21-May-19 Page 7 of 52
2.0 CIVIL AND GEOTECHNICAL
Provide and perform civil engineering design and construction services as required to provide a complete, accessible, functional and usable project. The Contractor is required to extensively coordinate civil design and construction work with the scope of the other disciplines described in this SOW.
2.1 SCOPE SUMMARY
Civil works for this project include, but are not limited to, site survey, geotechnical investigation, site layout, demolition, earthwork, storm drainage, sanitary system, pavement, and landscaping. Refer to the bid SECTION 01 22 00, PRICE AND PAYMENT PROCEDURES for which of these are base bid or optional.
2.2 EXISTING CONDITIONS
The proposed project is located Hospital Compound south west of Gornja Toponica, Serbia (Latitude 43.398236°N, Longitude 21.805264°E). See Location Map on Attachment#1.
2.2.1 TOPOGRAPHY
There is no known topographic survey for the project site. The existing site contains the existing housing unit building, pavement, utilities, fences, and vegetation as shown in the Conceptual Site Plan on Attachment#1. The site is nearly flat including the terrain around the housing unit causing poor site drainage away from the building.
Existing fencing is dilapidated and remains of already torn down/ abandoned building attachments (sheds) are still in place. The existing information shown in the Conceptual Site Plan on Att#1 was compiled from google earth, and site photos.
2.2.2 UTILITIES
The existing housing unit building ties into municipal utility systems including water supply, sewage and power. Capacity of the systems will suffice the needs of the renovated housing unit building.
The site is not connected to an existing storm drainage sewer system. Site drainage is managed by infiltration and sheet flow towards the close by pavements. Closest available legal point of discharges is not known but storm water from project and neighbored sites will generally be conveyed towards the stream running in approx.
380 m distance North West of the project site. Rainfall discharges from the existing building downspouts to the ground.
2.2.3 GEOTECHNICAL
There is no geotechnical information provided for the project site.
2.2.4 ENVIRONMENTAL
There are no known environmental protection areas or archeological preservation areas on the project site. There is no prior knowledge of any hazardous or contaminated materials in the site’s soil or pavement.
2.2.5 EXISTING CONDITIONS INVESTIGATION
Prior to bid, investigate the general and local conditions which can affect the work and/or its cost, including but not limited to:
a. Weather, river stages, or similar physical conditions at the site.
b. Surface and subsurface materials or obstacles to be encountered insofar as this information is reasonably ascertainable from an inspection of the site and due diligence research of as-built drawings, geotechnical reports, environmental reports, and publicly available information on the site.
c. Mobilization and staging constraints.
2.3 DESIGN SUBMITTALS
21-May-19 Page 8 of 52
Provide civil design submittals in accordance with RFP Section 01 33 16, DESIGN AFTER AWARD and in compliance with SOW Section 1.0 – GENERAL.
65% Design Submittal:
a. Pre-Final Design Analysis of civil features.
b. Final Site Survey (include in the Design Analysis).
c. Final Geotechnical Report (include in the Design Analysis).
d. Final Existing Conditions Plan.
e. Pre-Final Demolition Plan
f. Pre-Final Site Layout Plans - Indicate existing and proposed civil features.
Include other disciplines’ features (faded back) that affect the Civil Design (buildings, mechanical structures, electrical utilities, etc.).
g. Pre-Final Grading Plans, including contours, spot elevations, spot grades of curbs, slopes, and finish floor elevations. Include erosion control design.
h. Pre Final Pavement Plans, including Profiles, Cross Sections, Jointing Plans and Details.
i. Pre-Final Utility (Sanitary, and Water) Profiles, Cross Sections, and Details.
j. Preliminary Landscape Plan and Details, including seed mix and seed coverage rate
k. Preliminary Civil Specifications.
95% Design Submittal:
a. Update all items from the 65% Design Submittal to 95% (Final) Design.
Incorporate all 65% design comments.
100% Submittal:
The 100% Submittal provides a complete and final set of contract documents ready for construction. Update all Final submittals from 95% to a corrected Final submittal.
Address all previous government review comments before submitting.
2.3.1 DESIGN ANALYSIS
Provide a Design Analysis for all Civil features that documents significant design choices and substantiates design compliance with contract requirements, applicable codes and standards. Documentation includes narrative, calculations, photographs, sketches, and catalog cut sheets. Reference all applicable regulations, standards, and criteria for the design. Reference sources are subject to Government approval.
Provide design assumptions. For design choices, discuss alternative systems considered, and provide rationale for the selected alternative.
The Design Analysis includes but is not limited to:
a. Discussion of Site Layout constraints and design decisions, including but not limited to, land use, pedestrian access, orientation of features on-site, setbacks from site features, minimizing earthwork and tree removal, and future expansion.
b. Discussion of Demolition constraints and design decisions. Include discussion on how access will be provided during construction, and how each utility will be maintained and operated during construction.
c. Discussion of Earthwork and Site Grading constraints and design decisions.
Provide cut and fill calculations. Include pertinent geotechnical information that affects earthwork.
d. Discussion of site drainage constraints and design decisions. Provide a hydrologic and hydraulic analysis of the site drainage, including legal point of discharge or recipient, and offsite areas that contribute to and influence the project’s site drainage. Provide drainage basin map(s), rainfall data, and coefficients used. Provide hydraulic analysis for planned conveyance systems including discharge capacity verification of the existing systems they contribute to. Indicate cross section dimensions, friction factor, length, 21-May-19 Page 9 of 52 elevations, slope, design flow (Q), maximum flow capacity, design depth of flow, design percentage full, and design flow velocity for each section of pipe or open channel. Provide calculations for sizing of detention, infiltration, and sustainable storm water management features needed. Provide Pre and Post Development comparisons for detention/retention facilities. Use the Rational Method or TR-55 for analysis and design. In the absence of Host Nation requirements, use a minimum 10-year storm frequency for analysis and design.
Provide calculations on the pipe’s structural capacity if the pipe is shallower than required in section 2.10-Utilities. Include pertinent geotechnical information that affects the drainage systems. Demonstrate that adverse impact on downstream and on-site facilities is precluded and provide accordant documentation.
e. Discussion of Sanitary system constraints and design decisions. For each section of pipe, include analyses indicating pipe size, friction factor, length, elevations at each end of pipe, slope, design flow (Q), maximum flow capacity, design depth of flow, design percentage full, and design flow velocity. Provide calculations on the pipe’s structural capacity if the pipe is shallower than required in section 2.10-Utilities.
f. Discussion of Water system constraints, and design decisions. Provide calculations to demonstrate water system meets project requirements, including demand, water pipe sizing, design water pressure and flow rates. Provide calculations on the pipe’s structural capacity if the pipe is shallower than required in section 2.10-Utilities.
g. Discussion of Pavement constraints and design decisions. Provide calculations for the pavement section. Include pertinent geotechnical information that affects the pavement design.
h. Discussion of Landscaping constraints and design decisions.
i. Site Survey as an appendix.
j. Geotechnical Investigation and Report as an appendix.
2.3.2 DESIGN DRAWINGS
Provide Civil design drawings of sufficient detail to address the requirements of each design submittal. Civil drawings include plans, profiles, cross sections, and details of Civil features for the project. Civil drawings also include temporary construction plans/methods that affect the design and construction of the project.
These temporary plans include mobilization, traffic control, erosion control, dewatering, shoring, construction sequence, etc. Design drawings include all necessary information (labeling, dimensioning, legend, details, notes, etc.) to allow for complete understanding and constructability of all proposed features.
Provide comprehensible differentiation between features that are proposed, existing, future, or proposed to be demolished by use of appropriate choice of line styles, line weights, and/or colors. Reference USACE A/E/C Graphics Standard for graphic requirements.
2.3.3 SPECIFICATIONS
Provide Civil specifications of sufficient detail to address the requirements of each design submittal. Specifications, when combined with the design drawings, allow for complete understanding and constructability of all proposed Civil features.
2.4 DESIGN CRITERIA
Provide civil design in accordance with Host Nation codes. In the absence of Host Nation codes, use the latest release of the International Building Code (IBC) and the following codes and technical standards:
a. Uniform Facility Criteria (UFC) 3-201-01, Civil Engineering
b. Wastewater Committee of the Great Lakes-Upper Mississippi River, Recommended
Standards for Wastewater Facilities
21-May-19 Page 10 of 52
c. Water Supply Committee of the Great Lakes-Upper Mississippi River, Recommended Standards for Water Works
d. UFC 3-220-01, Geotechnical Engineering
e. Architectural Barriers Act (ABA) Guidelines
f. USACE A/E/C Graphics Standard (ERDC/ITL TR-12-1
2.5 GEOTECHNICAL INVESTIGATION AND REPORT
Perform a geotechnical investigation and assessment of the project site to determine the subsurface conditions and geotechnical parameters for foundation, grading, and utility design. Perform the necessary amount of testing, borings and test pits at depths suitable for the project improvements. Include geotechnical investigation in areas where borrow material will be used. The Geotechnical work must be performed under the supervision of a professional geotechnical engineer registered with the jurisdiction having authority, and the report must be signed by the Geotechnical Engineer. In the absence of Host Nation codes, perform the geotechnical investigation and report per UFC 3-220-01, Geotechnical Engineering and IBC.
Coordinate testing locations with the COR to avoid impact to existing utilities and facility operations. Utility locates, permits, pavement removal and vegetation clearing is the Contractor’s responsibility. Repair disturbed areas with a concrete patch in paved areas, and compacted soil in non-paved areas. The repaired area must be flush with the adjacent surface. Following restoration, stake and flag each of the hole locations with boring identification numbers. In paved areas, use white paint on the paved surface to mark hole locations. Provide a map indicating the borehole and test pit locations.
2.5.1 REPORT
Include, as a minimum, the following information:
a. Description of field work completed and equipment used; names, signatures and stamps of licensed professionals involved; name of drilling company.
b. A description of site subsurface conditions, regional geology, and seismic conditions at the site.
c. Site map of borehole and test pit locations.
d. High resolution color digital photographs of each borehole and test pit location.
e. Test pit logs with classification of all subsurface materials. The logs must distinguish fill materials from native materials, include all in‐situ test results, and include groundwater depth information, if groundwater is encountered. Distinguish between bedrock and rock boulders.
f. Reports of all the field and laboratory testing.
g. Recommendations for allowable bearing capacity, expected settlement, type of foundation, minimum footing and grade beam dimensions, lateral earth pressure parameters, and minimum depth of foundation for footing and grade beams.
h. Recommendations for preparation, placement, and compaction of onsite soils, borrow material, soil replacement, soil amendment/treatment, structural fill, topsoil, and trench backfill. Include dewatering and temporary retaining structure needs.
i. Soil Resistivity.
j. Frost Depth.
k. Recommendations for pavement design and construction.
l. Recommendations for the drainage systems involving infiltration.
m. Calculations to support conclusions and recommendations
2.5.2 DESIGN DRAWINGS AND SPECIFICATIONS
On the design drawings and/or specifications, include geotechnical information that affect the design of the project, including but is not limited to, boring locations, boring logs, groundwater and frost depths, and any details that convey requirements for site preparation.
21-May-19 Page 11 of 52
2.6 SITE SURVEY
Provide a topographic survey from a licensed surveyor that includes all existing site information needed to design and construct the project. Include x, y, and z coordinates to the nearest 0.005 meters, dimensions, material, and basic characteristics of all features within the project site limits, as well as all features outside of the project site limits that will affect the design and construction of the project. Research record drawings to obtain utility and pavement information that is not visible from the surface. Provide notes indicating the sources and any limitations or assumptions of the data. Provide a copy of the survey in CAD, in addition to the paper/electronic requirements of the Design Analysis.
Locate and show on the topographic survey the following information:
a. Property boundary, public right of way, and easements. Include the address numbers, street names, and easement records.
b. Survey monuments. Include description.
c. Spot elevations covering the entire survey limits showing high points, low points, grade changes, and at sufficient intervals to represent the general character of the terrain.
d. Buildings and other miscellaneous structures. Provide finish floor elevation.
e. Pavements. Include pavement type, thicknesses, joint patterns, and pavement markings. Include top of curb and gutter elevations.
f. Surface Drainage Features.
g. Utility lines and structures. Include rim elevations and invert elevations for utility structures; identification of lines as underground or aboveground;
pipe sizes and materials.
h. Fences. Include height, material, gate locations and types.
i. Signs. Include sign text.
j. Trees/Woods: In wooded areas that trees are to be protected, locate outside drip line of wooded area, include general density and type of trees. For wooded areas with proposed tree removal, identify trees per Host Nation permitting requirements. Where selective clearing will be proposed, locate trees over 150 millimeter diameter at a height of 1.3 m above existing ground, and include tree species, diameter at chest height, and dripline diameter.
k. Geotechnical boring locations.
l. Locate environmentally sensitive areas (determined and marked by others).
m. North arrow and scale of drawing.
n. Legend depicting the symbols and abbreviations used on the drawing.
o. Horizontal and vertical coordinate systems, date of survey, licensed surveyor name and license number.
Site information provided to the Contractor by the Government is not to be considered accurate Site Survey information. Utility field locates and as-built research are the responsibility of the Contractor.
Upon completion of construction, update the original survey with an As-built survey of the site as constructed, including underground utility locations and depths.
Submit the As-built survey to the COR for approval.
Reference UFC 3-201-01, Civil Engineering, Section 2-2.2-SURVEYING for survey requirements. In the absence of Host Nation’s coordinate system, use the Universal Transverse Mercator (UTM) coordinate system. The vertical coordinate system must be based on sea level.
2.7 SITE LAYOUT
Locate the proposed improvements as indicated in the Conceptual Site Plan on Attachment #2. Amend the site layout as determined by the site-specific constraints, 21-May-19 Page 12 of 52 the owner’s preferences, accessibility, future expansion, and opportunities that are identified and evaluated as part of the Contractor’s scope of work.
The Contractor is responsible for all aspects of the project whether they are shown on the conceptual plan or not.
2.8 DEMOLITION
Remove existing structures, utilities, pavement, vegetation, and any other features to construct the proposed improvements. Provide straight, neat saw cuts at limits of pavement removal.
Remove the existing fence including foundations, unneeded pavements, as well as all remains of torn down/ abandoned structures on the project site to obtain clear site around the building and the planned improvements in order to provide open green space consisting of new and existing lawn area and other existing vegetation.
Demoed material shall be tested per host nation standards. If hazardous materials are discovered, cease demolition, secure the area, and notify the COR for further guidance.
2.8.1 CONSTRUCTION LIMITS
Do not disturb the project site beyond necessary for installation of proposed construction. Do not disturb any areas past the site’s property line. Show demolition work and limits of disturbance in the drawings. Stake-out the limits of disturbance on-site with temporary fencing before beginning construction.
2.8.2 ITEMS TO REMAIN IN PLACE WITHIN CONSTRUCTION LIMITS
Take necessary precautions to avoid damage to existing items to remain in place, to be reused, or to remain the property of the Government. Repair or replace damaged items as approved by the COR. Construct and maintain shoring, bracing, and supports as required. Ensure that structural elements are not overloaded. Provide new supports and reinforcement for existing construction weakened by demolition, deconstruction, or removal work. Repairs, reinforcement, or structural replacement require approval by the COR prior to performing said work.
2.8.3 TREES
Remove trees with driplines within the footprint of the new stairwell. Protect trees larger than 150 mm diameter at 1.3 m above existing grade within the project site which might be damaged during construction, with a 1.8 m high fence around the dripline of the tree(s), which is assumed to be the extent of the tree’s roots.
Mitigate for tree removal per Host Nation Requirements.
2.8.4 UTILITIES
Any existing utilities encountered that are impacted by this project must be protected, or relocated if protection is not feasible. Remove any existing utilities found under or within 3.0 m of new foundations planned for proposed facilities, structures, or buildings. Reroute existing utilities to be displaced in accordance with SOW Section 2.10-UTILITIES.
Remove or abandon the remains of relocated utilities between the connection points of the rerouted utility run. Manholes or underground structures planned to be abandoned must be removed to a minimum depth of 50 centimeters below finish grade.
Fill abandoned manhole or structure per Section 2.9-EARTHWORK requirements.
2.8.5 DUST, DEBRIS, AND EROSION CONTROL
Prevent the spread of dust, debris, and erosion from the project site. Install erosion control measures before beginning construction. Sweep pavements as often
21-May-19 Page 13 of 52 as necessary to control the spread of debris. Do not use water if it results in hazardous or objectionable conditions such as, but not limited to, ice, flooding, erosion, or pollution. Remove snow, dust, dirt, and debris from work areas daily.
Remove and transport the debris in a manner that prevents spillage on streets or adjacent areas. Apply local regulations regarding hauling and disposal.
2.9 EARTHWORK
Perform all earth work necessary for the installation of the proposed improvements.
2.9.1 PLANS AND SPECIFICATIONS
Define earthwork requirements in the plans and specifications. Include requirements for satisfactory material, borrow material, structural fill, topsoil, utility trenches, replacement and improvement of on-site soils, soil compaction (for subgrades of structures, paving, and landscaped areas), compaction for utility trenches, maximum lift depths, density testing frequency, maximum temporary and permanent slopes, and engineered support systems. The earthwork requirements must not conflict with the recommendations in the Contractor-provided Geotechnical Report.
2.9.2 CONTAMINATED SOIL
Inspect and test all soil according to Host Nation requirements. If hazardous materials are discovered, cease excavation, secure the area, and notify the COR for further guidance.
2.9.3 CULTURAL RESOURCES
Cultural resources, such as archaeological remains, may be uncovered during excavation operations. If suspected cultural remains are found, cease excavation, secure the area, and notify the COR for further guidance.
2.9.4 TOPSOIL
Remove and save topsoil (first 20 centimeters of excavation). Separate out subsoil, brush, litter, weeds, roots, stones larger than 25 mm in diameter, and other materials that would interfere with planting and maintenance operations. When restoring the site to finish grade, place topsoil back in excavated areas that do not include proposed paving or structures.
2.9.5 SATISFACTORY MATERIAL
Excavated material (below topsoil), if satisfactory for reuse per the Contractor’s Geotechnical Engineer, may be used on the project site where fill is required.
Unsatisfactory material, and surplus excavated material not required for fill, must be disposed of offsite, and is the responsibility of the Contractor. Borrow material may be required for construction from sources off site. Borrow materials are to be free of hazardous materials and contaminants. Any soil brought in from off-site sources must be certified for the intended use by accredited authority based on HN regulations.
2.9.6 BACKFILL COMPACTION
In the absence of Host Nation requirements and geotechnical recommendations, fill and backfill must be placed in layers of 20 centimeters loose thickness and compacted to a minimum 95% of the maximum dry density as determined by Host Nation test method equivalent to ASTM D-1557 (Modified Proctor test). Provide density tests on all lifts at a frequency of 1 test per 40 square meters for foundations and parking, and 1 test per 30 meters of road and utility trench. Round up to nearest whole number (i.e. a 25 square meter foundation requires one test). The location of all tests must be selected by the Contractor’s geotechnical engineer, and copies of all test results must be furnished to the COR. All structure foundation excavations must be inspected and approved by the Contractor’s Geotechnical Engineer prior to placing
21-May-19 Page 14 of 52 concrete. Repair earthwork areas as recommended by the Contractor’s Geotechnical Engineer, and approved by the COR.
2.9.7 ENGINEERED SOIL SUPPORT SYSTEMS
Provide engineered soil support systems (i.e. shoring) as required for the construction of the proposed improvements. The Contractor is responsible for all dewatering necessary for earthwork.
2.9.8 SITE GRADING
Set finished floor elevation of the stairwell addition a minimum of 15 centimeters above finished grade at the perimeter of the building.
Perform site grading around the building to meet Host Nation accessibility guidelines.
2.10 UTILITIES
This section applies to all project underground utilities located outside the building, including but not limited to, sanitary sewer, water supply, storm drainage, electrical, communications, and heat. See Sections 5.0-ELECTRICAL, and Section 6.0- MECHANICAL for additional utility requirements.
Install newly required utility main alignments at least 3.0 meters from facility or building foundations, except for building connections. Provide horizontal and vertical separation between relocated and existing utilities for rehabilitation, maintenance, repair or replacement. Provide utility line depths, bedding, and backfill as required by applicable requirements and geotechnical recommendations.
Minimum cover over pipes is 0.6 meters; greater than frost penetration; or sufficient to support imposed dead and live loads for the pipe materials used; whichever is more stringent. Place plastic warning tape along the route of the buried pipe after installation at a height of 0.3 meters above the pipe.
Coordinate all required relocation, improvement and protection of utilities held by third party (e.g. public or private utility). This includes coordination of any work to be performed by the utility owner. Choice of materials and products for utility installation must be coordinated with the utility owner (customer or third party) to ensure proper integration and compliance with existing systems and allow for easy maintenance and repair of the utilities in the future.
Provide utility materials per IBC requirements. Provide corrosion protection for utilities that provides the minimum life expectancy specified in GENERAL Section
1.0. Any piping or equipment exposed to sunlight must be coated with protective coatings suitable for UV exposure with a minimum expected coating life of 10 years before recoating.
2.10.1 STORM SYSTEM
Provide positive site drainage to direct runoff away from the existing Housing Unit and the planned improvements, eliminate ponding, and prevent erosion. Take maximum advantage of existing drainage patterns and systems. Include gravity collecting and conveyance systems like open channels, and pipe systems, as needed to preclude adverse impact on planned and existing facilities on site and on adjacent properties.
Direct run-off to the closest applicable legal point of discharge, or convey storm water into adjacent terrain provided that adverse impact on downstream facilities is precluded and HN regulations allow for this. Provide detention or infiltration systems as required to control flow and keep run-off on site. Employ sustainable storm water management practices like infiltration facilities as far as geotechnical conditions allow.
21-May-19 Page 15 of 52
If using an infiltration or detention system, locate infiltration/detention facilities a minimum of 3 meters away from structures. Provide an overflow to the infiltration/detention system that will not damage improvements or cause erosion.
Provide a French drain system around the Housing Unit and the new stairwell to keep run-off and seepage water away from the foundations since the flat site will not allow for sufficient grading needed for effective site drainage. Provide a pump system if the French drain system cannot be connected to the next point of discharge using gravity flow. Connect the French drain system to an effective infiltration system instead of using a pump system if geotechnical constraints allow.
Connect building downspouts to infiltration features or to splash blocks that drain away from foundations a minimum of 1 m.
Storm structures must be concrete, with traffic rated cast iron or ductile iron frames and covers. In the absence of Host Nation standards, design the storm drainage system per the IBC.
After installation, test storm lines and structures for leakage and deflection per local codes. Provide test results to the COR. Locate and repair any sections failing to pass the required tests. Repeat the specified tests and inspections on the repaired sections.
2.10.2 SANITARY SYSTEM
Connect the new sanitary systems of the Housing Unit to the existing municipal sewer system running in close vicinity to the building. In the absence of Host Nation standards, design the sanitary system per the IBC.
After installation, test sanitary lines and structures for leakage and deflection per local codes. Provide test results to the COR. Locate and repair any sections failing to pass the required tests. Repeat the specified tests and inspections on the repaired sections.
See SOW Section 6.0 – MECHANICAL for further details.
2.10.3 WATER SYSTEM
Provide a water system to connect the new utility room of the Housing Unit to the existing municipal water system running in close vicinity to the building. Design the system to meet all flow requirements of the facility, including potable water and fire flows. In the absence of Host Nation standards, design the water system per the IBC.
After installation, test water supply lines according to local codes for leakage.
Before the water supply line is put into final operation, disinfect the line, and then flush the line to remove traces of the sterilization agent. Test treated line for coliform bacteria. Provide test results to the COR. Locate and repair any sections failing to pass the required tests. Repeat the specified tests and inspections on the repaired sections.
See SOW Section 6.0 – MECHANICAL for further details.
2.11 PAVEMENT
Provide site access for pedestrians to all building entries to allow for operational and maintenance access to the facility. This is to include accessible routes to the three (3) building entries that need to be handicapped accessible as per architectural requirements (see Conceptual site layout on Attachment#1 and
21-May-19 Page 16 of 52
Attachment#3 – Functional Building Layout). Provide the handicapped accessible routes to consist of Portland cement concrete (PCC) walkway connections to the existing roads with a width of minimum 1.8 m, wheelchair ramps of minimum 1.2 m width as well as exterior stairs and stoops made of PCC.
In the absence of Host Nation standards, design pavements per UFC 3-201-01, Civil Engineering and pedestrian access, accessible stairs and wheelchair ramps per ABA Guidelines.
Install a perimeter apron around the Housing Unit and the Stairwell with minimum 1 m width and minimum 2% cross slope directing run-off away from the exterior building walls. The perimeter apron shall be either made of tiles or PCC pavement.
For PCC, reference SOW Section 4.0 - STRUCTURAL for concrete requirements. Perform subgrade tests for all pavements as described in Section 2.9 - EARTHWORK. The location of all tests must be selected by the Contractor’s Geotechnical Engineer, and copies of all test results must be furnished to the COR.
2.12 LANDSCAPING
Provide grass seed and 20 centimeters of topsoil on the site in areas that do not have pavement or a building within the limits of disturbance. Seeds must be locally sourced and native to the area. Provide seed coverage density per manufacturer/supplier’s recommendations. Provide watering, weeding, and any other necessary care to establish growth. Limit planting to times of the year per local codes and/or manufacturer/supplier’s recommendations. Replace topsoil and seeds, at Contractor’s expense, in areas which do not have new growth coverage of 75% before the warranty period ends.
Before using chemicals during landscaping work, including for use on plants and on site features, the Contractor must submit to the COR, in the form of brochures, certificates and other technical material, information about the chemicals proposed, including about their environmental compatibility. Their use is only permitted with approval of the COR.
21-May-19 Page 17 of 52
3.0 ARCHITECTURAL
3.1 PROJECT DESCRIPTION
Design and renovation work of housing unit at special hospital for psychiatric disorders in Gornja Toponica, Serbia.
Design and then perform the renovation work of two-story, solid masonry / concrete building that will serve as housing unit at special hospital for psychiatric disorders.
Extensive coordination is required between the architectural work and the civil, geotechnical, structural, fire protection, mechanical, and electrical requirements of this project.
3.1.1 DESIGN
Provide a design and construction package that uses the space allocations, functional adjacencies, design details, and features given or referenced in this RFP. The design must incorporate all referenced codes and regulations. The Contractor is responsible for creating additional details as required to complete a full design. All details must conform to the requirements of this RFP and are subject to the approval of the COR. A schematic design has been attached for reference. The schematic plans are provided for diagrammatic purposes only and do not necessarily represent an approved floor plan or design. The Contractor is responsible for providing a design that meets all requirements of the User and the codes and criteria referenced in this Statement or Work.
3.1.2 DESIGN SUBMITTALS
Provide all architectural submittals after contract award in accordance with Section 01 33 16 DESIGN AFTER AWARD and Section 01 33 00 SUBMITTAL PROCEDURES.
Prepare and submit the documents listed below at the submittals indicated.
3.1.2.2 65% DESIGN SUBMISSION
Include the following drawings and reports as applicable to the project:
a. Code Summary – Provide a tabular code compliance summary.
b. Life Safety Plans – Provide plans depicting smoke/fire resistance ratings, egress routes, dead-end corridors, exits, and other aspects of life safety pertaining to the design.
c. Demolition Plans – Provide existing floor plans, indicating all demolition required.
d. Floor Plans – Provide all floor plans, indicating room names, areas, and basic dimensions, scale 1:50.
e. Ceiling Plans – Provide reflected ceiling plans for all rooms, indicating ceiling materials and fixtures, scale 1:50.
f. Building Elevations – Provide all building elevations indicating all exterior materials.
g. Roof Plan – Provide a plan of all roof areas, indicating direction of slope and method of drainage.
h. Building Section – Indicate heights of critical building elements.
i. Wall Section - Provide a typical interior and exterior wall section for each building – describe wall materials.
j. Interior Elevations – Provide interior elevations of all bathrooms and built-in casework and kitchenettes, indicate critical heights of surfaces and plumbing fixtures and describe all materials and finishes.
k. Pre-Final Design Analysis – Provide a narrative explaining the design and indicating how the design and materials meet the requirements of this SOW.
l. Pre-Final Specifications – Provide detailed explanations of requirements for all performed work or provide product specific manufacturer information (brochures, technical information, cut sheets) for all materials and products
21-May-19 Page 18 of 52 to be provided/installed.
3.1.2.3 95% DESIGN SUBMISSION
The 95% Submittal provides a complete and final set of contract documents essentially ready for construction by the D/B Contractor. All previous government review comments must have been addressed. Include the following drawings and reports as applicable to the project:
a. All documents from the 65% submittal updated to incorporate 65% review comments.
b. Floor Plans – Provide all floor plans, indicating room names, areas, and dimensions, scale 1:50.
c. Building Elevations – Provide all building elevations indicating all exterior materials.
d. Roof Plan – Provide a plan of all roof areas, indicating direction of slope and method of drainage.
e. Building Section – Indicate heights.
f. Wall Sections – Provide sufficient wall section(s) to indicate all materials and different conditions.
g. Section and Plan Details – Provide details of critical building intersections.
h. Window and Door Schedule – Provide a schedule of all windows and doors, indicating sizes, hardware, and operation.
i. Stair Section and Details.
j. Finish Schedule – Indicate all proposed finishes.
k. Final Design Analysis – Provide a finalized narrative describing all work to be performed on the project and how it meets the functional and code requirements of the project. Provide product specific manufacturer information (brochures, technical information, cut sheets) for all materials and products to be provided/installed.
l. Final Specifications – Provide line items and detailed descriptions of all work to be performed.
3.1.2.4 100% DESIGN SUBMISSION
The 100% Submittal provides a complete and final set of contract documents ready for construction by the D/B Contractor. All previous government review comments must have been addressed. Include all drawings, specifications and calculations from the 95% Submittal updated to incorporate all previous review comments.
3.2 TECHNICAL CRITERIA AND STANDARDS
Design and construct the project in accordance with the requirements outlined in Section 1.7 DESIGN CRITERIA.
3.2.1 LIFE SAFETY REQUIREMENTS
The Design must meet all Host Nation and local Fire Suppression System codes and requirements.
All structures to be provided must have exits and means of egress that comply with current Host Nation codes and standards, or in accordance with US codes and standards.
In the absence of Host Nation codes and standards, for individual concerns of Life Safety the Contractor must follow appropriate US codes and standards, including the International Building Code (IBC) and NFPA 101 Life Safety Code.
3.2.2 HANDICAPPED ACCESSIBILITY REQUIREMENTS
The first floor of this building must meet applicable Host Nation handicapped accessibility requirements.
21-May-19 Page 19 of 52
3.3 GENERAL SCOPE OF WORK
Design the architectural elements of this facility to withstand all site-specific environmental conditions such as wide seasonal temperature swings, local wind, rain, snow and earthquake conditions. All architectural features must be appropriately braced for anticipated seismic activity. The Contractor may propose alternate building materials to meet the facility’s requirements, but final selection of materials is subject to the approval of the COR. Consider economics not only in the initial acquisition, but also in the future maintenance of the materials, when selecting materials and building systems to be incorporated into the project. When requested, the Contractor must provide documentation demonstrating that a chosen alternative material is life cycle cost effective.
3.4 DETAILED SCOPE OF WORK
The Contractor is responsible for the following specific tasks required for the construction of this facility.
3.4.1 DEMOLITION
The Contractor is responsible for all required demolition as indicated in…