This document provides notice of a planned solicitation for environmental consulting and erosion control services in Germany. The U.S. Army Corps of Engineers, Europe District intends to issue a request for proposals for multiple award task order contracts with a total capacity of $30 million to be awarded on a full and open competitive basis. Services will include surveying, erosion control work, dust control, vegetation maintenance, aerial seeding, construction and repair of check dams and access trails, and unexploded ordnance removal. Task orders will be performed in Germany in support of the Integrated Training Area Management program. The base period of the contracts will be one year with four one-year options. Proposals are due no less than 30 days after issuance of the planned solicitation notice on or after May 17, 2019.

B.08.02 W912GB19R0046 Environmental Consulting Services

View the file

Other files

File Type Posted
FBO_MATOC_AWARD_SYNOPSIS__03.5.19.doc DOC document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SEE ADDENDUM

(No Collect Calls)

W912GB19R0046 04-Jun-2019

b. TELEPHONE NUMBER 8. OFFER DUE DATE/LOCAL TIME

10:00 AM 08 Jul 2019

5. SOLICITATION NUMBER 6. SOLICITATION ISSUE DATE

AUTHORIZED FOR LOCAL REPRODUCTION

PREVIOUS EDITION IS NOT USABLE

STANDARD FORM 1449 (REV. 2/2012)

Prescribed by GSA – FAR (48 CFR) 53.212

(TYPE OR PRINT)

(SIGNATURE OF CONTRACTING OFFICER)

ADDENDA ARE

26. TOTAL AWARD AMOUNT (For Gov t. Use Only )

23.

CODE 10. THIS ACQUISITION IS

SUCH ADDRESS IN OFFER

17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT

BELOW IS CHECKED

TELEPHONE NO.

W912GB9. ISSUED BY

18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a. UNLESS BLOCK

7. FOR SOLICITATION

INFORMATION CALL:

a. NAME

NATASHA S MCKELLUM

2. CONTRACT NO. 3. AWARD/EFFECTIVE DATE 4. ORDER NUMBER

(TYPE OR PRINT)

30b. NAME AND TITLE OF SIGNER 30c. DATE SIGNED 31b. NAME OF CONTRACTING OFFICER

30a. SIGNATURE OF OFFEROR/CONTRACTOR 31a.UNITED STATES OF AMERICA

0 27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1. 52.212-4. FAR 52.212-3. 52.212-5 ARE ATTACHED.

25. ACCOUNTING AND APPROPRIATION DATA

1. REQUISITION NUMBER

20.

ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED.

OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, AND 30

SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS

ARE NOT ATTACHED

27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA ARE ARE NOT ATTACHED

(BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE

SET FORTH HEREIN, IS ACCEPTED AS TO ITEMS:

. YOUR OFFER ON SOLICITATION

28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN

% FOR:SET ASIDE:UNRESTRICTED ORX

SMALL BUSINESS

17a.CONTRACTOR/ CODE FACILITY

OFFEROR CODE

CONTRACTING DIVISION

US ARMY CORPS OF ENGINEERS

KONRAD ADENAUER RING 39

D-65187 WIESBADEN GERMANY

WIESBADEN 65187

18a. PAYMENT WILL BE MADE BY CODE

RATED ORDER UNDER

DPAS (15 CFR 700)

13a. THIS CONTRACT IS A

13b. RATING

CODE15. DELIVER TO CODE 16. ADMINISTERED BY

SEE SCHEDULE

12. DISCOUNT TERMS11. DELIVERY FOR FOB DESTINA-

TION UNLESS BLOCK IS

MARKED

SEE SCHEDULE

14. METHOD OF SOLICITATION

RFQ IFB RFPX

FAX:

TEL: SERVICE-DISABLED

VETERAN-OWNED

SMALL BUSINESS

8(A)

HUBZONE SMALL

BUSINESS

SIZE STANDARD:

$15,000,000

NAICS:

541620

X

OFFER DATED

29. AWARD OF CONTRACT: REF.

DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY

COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND

EMAIL:

TEL:

31c. DATE SIGNED

SEE SCHEDULE

SCHEDULE OF SUPPLIES/ SERVICESITEM NO. QUANTITY UNIT UNIT PRICE AMOUNT

24.22.21.19.

WOMEN-OWNED SMALL BUSINESS (WOSB)

ELIGIBLE UNDER THE WOMEN-OWNED

SMALL BUSINESS PROGRAM

EDWOSB

32g. E-MAIL OF AUTHORIZED GOVERNMENT REPRESENTATIVE

SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS

(CONTINUED)

PAGE 2 OF130

ACCEPTED, AND CONFORMS TO THE CONTRACT, EXCEPT AS NOTED: ______________________________________________________

32a. QUANTITY IN COLUMN 21 HAS BEEN

RECEIVED INSPECTED

32b. SIGNATURE OF AUTHORIZED GOVERNMENT

REPRESENTATIVE

32c. DATE 32d. PRINTED NAME AND TITLE OF AUTHORIZED GOVERNMENT

REPRESENTATIVE

32e. MAILING ADDRESS OF AUTHORIZED GOVERNMENT REPRESENTATIVE 32f . TELEPHONE NUMBER OF AUTHORIZED GOVERNMENT REPRESENTATIVE

37. CHECK NUMBER

FINALPARTIALCOMPLETE

36. PAYMENT35. AMOUNT VERIFIED

CORRECT FOR

34. VOUCHER NUMBER

FINAL

33. SHIP NUMBER

PARTIAL

38. S/R ACCOUNT NUMBER 39. S/R VOUCHER NUMBER 40. PAID BY

41a. I CERTIFY THIS ACCOUNT IS CORRECT AND PROPER FOR PAYMENT

41b. SIGNATURE AND TITLE OF CERTIFYING OFFICER 41c. DATE

42a. RECEIVED BY (Print)

42b. RECEIVED AT (Location)

42c. DATE REC'D (YY/MM/DD) 42d. TOTAL CONTAINERS

STANDARD FORM 1449 (REV. 2/2012) BACK

Prescribed by GSA – FAR (48 CFR) 53.212

AUTHORIZED FOR LOCAL REPRODUCTION

PREVIOUS EDITION IS NOT USABLE

SEE SCHEDULE

20.

SCHEDULE OF SUPPLIES/ SERVICES

21.

QUANTITY UNIT

22. 23.

UNIT PRICE

24.

AMOUNT

19.

ITEM NO.

Section C – Description/Specifications/Work Statement

Section B - Supplies or Services and Prices

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0001 1 Job ITAM Environmental Svcs Base Year

FFP

The contractor shall provide all labor, supervision, administration, transportation, supplies, vehicles, tools, materials, facilities, equipment, and incidentals necessary to survey and consult work erosion control work as required in areas; dust control, vegetation maintenance and removal, aerial seeding, construction and repair of check dams, construction and repair of access trails and removal of unexploded ordnance (UXO) that impedes access to necessary work areas or any combination thereof.

These services will be requested through individual task orders (TOs) issued under this contract in accordance with the specifications for Environmental Services attached in Section C at the time of contract award.

FOB: Destination

NET AMT

0002 Job Contractor Manpower Reporting Base YR

FFP

The contractor shall report ALL contractor labor hours (including subcontractor labor hours) required for performance of services provided under this contract for the US ARMY CORPS OF ENGINEERS via a secure data collection site. The contractor is required to completely fill in all required data fields using the following web address: https://www.ecmra.mil/Login.aspx. Reporting inputs will be for the labor executed during the period of performance during each Government fiscal year (FY), which runs October 1 through September 30. While inputs may be reported any time during the FY, all data shall be reported no later than October 31 of each calendar year of contract/task order performance.

Contractors may direct questions to the help desk at: http://www.ecmra.mil to review user manuals and gain an understanding about the data fields that will be included in the reporting structure that is hosted at http://www.ecmra.mil/.

1001 1 Job OPTION ITAM Environmental Svcs Option YR 1

FFP

The contractor shall provide all labor, supervision, administration, transportation, supplies, vehicles, tools, materials, facilities, equipment, and incidentals necessary to survey and consult work erosion control work as required in areas; dust control, vegetation maintenance and removal, aerial seeding, construction and repair of check dams, construction and repair of access trails and removal of unexploded ordnance (UXO) that impedes access to necessary work areas or any combination thereof.

These services will be requested through individual task orders (TOs) issued under this contract in accordance with the specifications for Environmental Services

1002 Job OPTION Contractor Manpower Reporting Option 1

FFP

The contractor shall report ALL contractor labor hours (including subcontractor labor hours) required for performance of services provided under this contract for the US ARMY CORPS OF ENGINEERS via a secure data collection site. The contractor is required to completely fill in all required data fields using the following web address: https://www.ecmra.mil/Login.aspx. Reporting inputs will be for the labor executed during the period of performance during each Government fiscal year (FY), which runs October 1 through September 30. While inputs may be reported any time during the FY, all data shall be reported no later than October 31 of each calendar year of contract/task order performance.

Contractors may direct questions to the help desk at: http://www.ecmra.mil to review user manuals and gain an understanding about the data fields that will be

2001 1 Job OPTION ITAM Environmental Svcs Option YR 2

FFP

The contractor shall provide all labor, supervision, administration, transportation, supplies, vehicles, tools, materials, facilities, equipment, and incidentals necessary to survey and consult work erosion control work as required in areas; dust control, vegetation maintenance and removal, aerial seeding, construction and repair of check dams, construction and repair of access trails and removal of unexploded ordnance (UXO) that impedes access to necessary work areas or any combination thereof.

These services will be requested through individual task orders (TOs) issued under this contract in accordance with the specifications for Environmental Services

2002 Job OPTION Contractor Manpower Reporting Option 2

FFP

The contractor shall report ALL contractor labor hours (including subcontractor labor hours) required for performance of services provided under this contract for the US ARMY CORPS OF ENGINEERS via a secure data collection site. The contractor is required to completely fill in all required data fields using the following web address: https://www.ecmra.mil/Login.aspx. Reporting inputs will be for the labor executed during the period of performance during each Government fiscal year (FY), which runs October 1 through September 30. While inputs may be reported any time during the FY, all data shall be reported no later than October 31 of each calendar year of contract/task order performance.

Contractors may direct questions to the help desk at: http://www.ecmra.mil to review user manuals and gain an understanding about the data fields that will be

3001 1 Job OPTION ITAM Environmental Svcs Option YR 3

FFP

The contractor shall provide all labor, supervision, administration, transportation, supplies, vehicles, tools, materials, facilities, equipment, and incidentals necessary to survey and consult work erosion control work as required in areas; dust control, vegetation maintenance and removal, aerial seeding, construction and repair of check dams, construction and repair of access trails and removal of unexploded ordnance (UXO) that impedes access to necessary work areas or any combination thereof.

These services will be requested through individual task orders (TOs) issued under this contract in accordance with the specifications for Environmental Services

3002 Job OPTION Contractor Manpower Reporting Option 3

FFP

The contractor shall report ALL contractor labor hours (including subcontractor labor hours) required for performance of services provided under this contract for the US ARMY CORPS OF ENGINEERS via a secure data collection site. The contractor is required to completely fill in all required data fields using the following web address: https://www.ecmra.mil/Login.aspx. Reporting inputs will be for the labor executed during the period of performance during each Government fiscal year (FY), which runs October 1 through September 30. While inputs may be reported any time during the FY, all data shall be reported no later than October 31 of each calendar year of contract/task order performance.

Contractors may direct questions to the help desk at: http://www.ecmra.mil to review user manuals and gain an understanding about the data fields that will be

4001 1 Job OPTION ITAM Environmental Svcs Option YR 4

FFP

The contractor shall provide all labor, supervision, administration, transportation, supplies, vehicles, tools, materials, facilities, equipment, and incidentals necessary to survey and consult work erosion control work as required in areas; dust control, vegetation maintenance and removal, aerial seeding, construction and repair of check dams, construction and repair of access trails and removal of unexploded ordnance (UXO) that impedes access to necessary work areas or any combination thereof.

These services will be requested through individual task orders (TOs) issued under this contract in accordance with the specifications for Environmental Services

4002 1 Job OPTION Contractor Manpower Reporting Option 4

FFP

The contractor shall report ALL contractor labor hours (including subcontractor labor hours) required for performance of services provided under this contract for the US ARMY CORPS OF ENGINEERS via a secure data collection site. The contractor is required to completely fill in all required data fields using the following web address: https://www.ecmra.mil/Login.aspx. Reporting inputs will be for the labor executed during the period of performance during each Government fiscal year (FY), which runs October 1 through September 30. While inputs may be reported any time during the FY, all data shall be reported no later than October 31 of each calendar year of contract/task order performance.

Contractors may direct questions to the help desk at: http://www.ecmra.mil to review user manuals and gain an understanding about the data fields that will be

Section C - Descriptions and Specifications

PERFORMANCE WORK STATEMENT

PERFORMANCE WORK STATEMENT

SECTION C

DESCRIPTION/SPECIFICATIONS/WORK STATEMENT

EROSION PREVENTION/DUST CONTROL AND NATURAL RESOURCE PROTECTION SERVICES

CONTRACT

TABLE OF CONTENTS

C-1.0 GENERAL

C-1.1Contract Definition C-1.2 Total Amount of Contract C-1.3Guarantee C-1.4 Introduction C-2.0 TASK ORDERS (TOs) C-2.1 Preparation of Work Plans for Erosion Control Work C-2.2 Protecting/Preveting/Repairing Eroded (or Potentially Eroded) Areas C-2.3 Repairing/Constructing Check Dams, Retention Basins, and Dams C-2.4 Install Simple Wooden Structures C-2.5 Cleaning Watercourses C-2.6 Repair/Placement of Pipelines C-2.7 Aerial and Ground Seeding C-2.8 Construction of Trafficable Crossings C-2.9 Dust Control Measures C-2.10 Repair of Maneuver Trails, Access and Maitenance Roads and Tank Roads C-2.11 Repair of Sinkholes

C-2.12 Brush Clearing/Tree Pruning for Threatened and Endangered Species Maintenance and to Meet Training Requirements

C-2.13 Survey Work C-2.14 UXO Survey and Identification Using Magnetrometer Sweep and Removal of Located UXO C-2.15 Develop Land Rehabilitation and Maintennace (LRAM) Plans C-2.16 GIS Mapping and Database Development C-2.17 Natural Resources Management Actions

C-3.0 TASK ORDER EXECUTION

C-3.1 Request for Proposal (RFP) C-3.2 Task Order Scopes of Work C-3.3 Task Order Requirements C-3.4 Performance Standards

C-4.0 GENERAL REQUIREMENTS

C-4.1 Point of Contact C-4.2 Public Disclosures C-4.3 Laws, Regulations and Standards C-4.4 US Government Furnished Equipment, Materials, and Personnel C-4.5 Passes/Identification C-4.6 Exercising of Options C-4.7 Management Plan C-4.8 Cooperation with Other Contractors C-4.9 Ammunition C-4.10 Special Conditions C-4.11 Submittals C-4.12 Certificates of Compliance C-4.13 Quality Control

C-4.14 Soil for Earthen Check Dams C-5.0 Specific Work Tasks under Anticipated Task Orders

SECTION C

DESCRIPTION/SPECIFICATIONS/WORK STATEMENT

EROSION PREVENTION/DUST CONTROL AND NATURAL RESOURCE PROTECTION SERVICES

JULY 2018

C.1 GENERAL

This Section C sets forth the general requirements for the performance of the various services required under this contract.

C.1.1 Contract Definition:

The objective of the contract is to provide Firm Fixed Priced (FPP), Indefinite Delivery, Indefinite Quantity (IDIQ), Multiple Award Task Order Contracts (MATOCs) to provide support for reducing/preventing erosion and controlling dust and the protection of natural resources at US Army Europe (USAREUR) military training areas in Germany, but could include work in other European military sites used by USAREUR forces. This solicitation will cover multiple contract awards with a total capacity of up to $30.0M total. The $30.0M capacity shall be evenly divided between the successful awardees.These FFP, IDIQ, MATOCs for services will be awarded on a full and open competitive basis.

C.1.2 Total Amount of Contract: This solicitation will cover multiple contract awards with a total shared capacity of US $30,000,000.00. There is no limit in the number of Task Order(s) that may be executed. The contracts end upon reaching the total term of five (5) years or upon reaching the total capacity or when the options are not exercised.

C.1.3 Guarantee: The awarded contracts shall have a total guarantee minimum amount of US $2,500.00 for the base period. There are no minimum guarantees for option years that are exercised by the Government. The guaranteed minimum may be met with the obligation of a Task Order meeting or exceeding the guarantee amount and shall be de-obligated when the obligation occurs.

C.1.4 Introduction.

This contract provides support for reducing/preventing erosion, controlling dust, and protecting natural resources within USAREUR military training areas in Germany, but also to include work in European military sites used by USAREUR forces. Work includes the servicing of existing and construction of new check dams and other erosion control structures and any additional erosion protection measures required. The ongoing erosion control work is required in areas (1) in or immediately adjacent to watercourses; (2) of overland flow from rainfall or snowmelt; and

(3) where maneuver actions have exacerbated erosion problems. Dust control, vegetation maintenance and removal, and aerial seeding are also required within the training areas and can be performed under this contract.

Landscape Preservation - The Contractor shall give attention to the effect of contract operations upon the landscape, shall take care to maintain natural surroundings, and shall conduct the work in compliance with the following requirements: a. The Contractor shall take sufficient precautions to prevent pollution with fuels, oils or other harmful materials; and b. The Contractor shall clean up all garbage left at the worksite. Subcontractor Approval - The contractor may use rental equipment and/or subcontractors. The Government shall approve the use of any subcontractors. The contractor shall provide the Government with the make, model, manufacturer, date and operator's qualifications for substitute equipment and operators.

C.1.5 Scope of Work In order to control erosion within U.S. military facilities and/or to reduce the adverse effects of these erosive actions the military continuously performs erosion control measures throughout the training areas. In addition to general ongoing repair work, the military constructs features such as trafficable crossings, check dams, roadways and/or other erosion control measures along water courses. Check dams can be found in training areas and other military facilities that support training. Each year, ongoing maintenance is performed on these structures in order to assure their continued proper functioning. Beyond the upkeep of the existing erosion control structures, erosion problems along watercourses and other areas that erode as a result of adverse weather conditions and/or troop movement need to be re-stabilized on a periodic basis. Additionally, structures such as culverts and maneuver trails may need to be repaired when there are associated erosion problems.

These actions assist with carrying out a program of planning for, and the development of, maintenance, and coordination of natural resources related services. This includes fauna habitat improvements or modification, range (or training area) rehabilitation where necessary for support of protected species, and generally supporting the execution of the Integrated Natural Resources Management Plan (INRMP). This also includes prevention and control of invasive species in accordance with the INRMP and EO 13112, Invasive Species/ DoDI 4715.03 and

4150.07. Specific actions include the detection and response to eradicate or control populations of invasive species along with monitoring the results. More specifically, natural resources management actions include, but are not limited to, mapping of the occurrence of invasive species, repairing infrastructure that provides access to buildings housing threatened or endangered species, improving access to bat roosts, camera/monitoring systems , maintenance and installation of bird and bat nesting boxes, maintenance of historic orchards, collection of scions from historic fruit trees, and documentation of management actions. Any plan or project not directly connected with or necessary for the management of Host Nation designated areas of the European net “Natura 2000,” but likely to have a significant effect thereon, either individually or in combination with other plans or projects, shall be subject to appropriate assessment of its implication for the site in view of the site’s conservation objectives.

The Contractor shall furnish all personnel, materials, and services required to reduce erosion through the repair, maintenance, improvement or construction of control structures or protection of deteriorating terrain within areas used by the U.S. military in Host Nations. These services will be requested through individual Task Orders (TOs) issued under this contract. To accomplish these goals the Contractor shall provide a wide range of services including, but not limited to:

a. Preparation of work plans for erosion control work

b. Protecting/preventing/repairing eroded (or potentially eroding) areas

c. Repairing/constructing check dams, retention basins, and dams

d. Installing simple wooden control structures

e. Cleaning watercourses

f. Repair/placement of pipelines

g. Aerial and ground seeding

h. Construction of trafficable crossings

i. Dust control measures

j. Repair of maneuver trails, access and maintenance roads, and tank roads

k. Repair of sinkholes

l. Brush clearing/tree pruning for Threatened and Endangered Species (TES) maintenance and to meet training requirements

m. Survey work

n. UXO survey and identification using magnetometer sweep and removal of located UXO

o. Develop Land Rehabilitation and Maintenance (LRAM) plans

p. GIS mapping and database development

q. Natural resource management actions

C.2 TASK ORDERS (TOs) The Contractor shall receive notice that the Government intends to award a Task Order through a Request for Proposal. The Contractor will have, at a minimum two (2) weeks notification prior to any equipment mobilization.

C.2.1 General Work Tasks under Anticipated Task Orders The following types of TOs have been identified for possible execution under this contract:

C.2.1.1 Preparation of Work Plans for Erosion Control Work Under an individual TO, the Contractor may be asked to develop a work plan. This work may include, but is not limited to, performance of a check dam and/or retention basin survey (determining the need for check dams/retention basins), design of check dams and/or retention basins, torrent structures, placement of pipelines, or any other erosion control measures deemed appropriate. The TO will specify work plan requirements, including the identification of sites to be evaluated, distribution of the document, format, etc.

C.2.1.2 Protecting/Preventing/Repairing Eroded (or Potentially Eroding) Areas Under an individual TO the Contractor may be required to correct or improve problem areas in the training areas where erosion has occurred or where there is danger that this could occur in the future. Actions that could be requested include re-contouring terrain through the movement of soil in or adjacent to the site or the addition of material supplied from off-site; compacting these areas; placing topsoil; and/or seeding. In areas where it has been determined that protection measures are required or where the existing measures have failed, the Contractor may also be required to install and secure erosion control mats, place quarry rock, or perform other erosion control measures deemed appropriate. Some repair of maneuver trails, service roads, and/or tank roads may be required in order to redirect vehicular traffic away from areas that are subject to erosion.

C.2.1.3 Repairing/Constructing Check Dams/Retention Basins/Dams Based on information obtained from the check dams, retention basins and/or dams survey (or from dam inspections) the Contractor may be requested to correct the identified deficiencies. This work could include erosion repair; re-contouring and strengthening areas where settlement has occurred; replacement of broken end culverts at check dam, retention basin, and/or dam structures; clearing clogged drainage pipes; removal of vegetation (small trees etc.); refilling holes created by small animals, training exercises, or any other repair work deemed appropriate. Shall the need be identified, new check dams, retention basin, and/or dams could be constructed under this contract. In this instance, soils investigations, physical testing and any design analysis required for this structure would typically be performed under a separate contract. Line items from this contract would then be used to construct the check dam, retention basin, and/or dams. Examples of typical check dams are included as Figures 1A and 1B.

C.2.1.4 Installing Simple Wooden Structures To restrict the flow of water the Contractor may be requested to install wooden control structures such as torrent structures. Example diagrams of torrent structures are attached as Figures 2A and 2B.

C.2.1.5 Cleaning Watercourses Work required of a Contractor under an individual TO could include the removal of sediment, debris, small trees, etc., along water courses (typically within 10-year high water limits) in order to assure the unimpeded flow of water.

C.2.1.6 Repair/Placement of Pipelines Short stretches of pipeline may need to be replaced or installed in order to direct water in a manner that will reduce erosive forces. This could include installation of pipelines under roadways. Typically, feasibility studies would not be included in this contract. This contract will only be used to install the desired structures.

C.2.1.7 Aerial and Ground Seeding In instances where large areas need to be seeded this may be accomplished through ground seeding or aerial seeding with an aircraft. Specific details regarding aerial seeding are included in Appendix A. Work required of an individual contractor would include the use of a plane to perform aerial seeding, to be priced on a per hour basis (flight time only), with a minimum of 3 hours usage per task to include flight time to and from a local airport.

C.2.1.8 Construction of Trafficable Crossings Trafficable crossings are constructed to provide accessible vehicular crossings of low areas, typically valleys.

C.-2.1.9 Dust Control Measures The Contractor shall apply dust control in areas specified under an individual T.O. The application of dust control chemicals is performed to reduce the raising of dust along roads, thereby reducing potential for decreased visibility of military vehicles.

C.2.1.10 Repair of Maneuver Trails, Access and Maintenance Roads, and Tanks Trails This contract may be used to construct maneuver trails. Maneuver trails are typically 3-6m in width, topped with limestone gravel and considered, if not temporary, certainly ephemeral in that when no longer required, they are no longer maintained. Maneuver trails are constructed to control the movement of traffic to reduce erosion within the training area.

C.2.1.11 Repair of Sinkholes This contract may be used to repair sinkholes. Repair of sinkholes is performed to eliminate safety hazards.

Sinkholes may develop during heavy rain events or for other reasons. Repair work may include, but is not limited to:

Replacement of failing standpipe(s) of a check dam Repair of eroded ditch(s) Removing vegetation Creating slopes Creating Berms Repair of gullies Removal of soil Backfilling Placement of rock dams Construction of a ditch Sludge removal

C.2.1.12 Brush Clearing/Tree Pruning for Threatened and Endangered Species (TES) Maintenance and to Meet Training Requirements This contract may be used to provide selective management of certain plant species to aid in erosion control and soldier safety. Certain invasive plants either out-compete or inhibit the growth of native herbaceous plants that are beneficial in helping to control soil erosion. Other invasive plants may pose severe safety threats to those using the training area and must be removed in a timely basis.

C.2.1.13 Survey Work This contract may be used to perform vertical control surveying work and topographical surveys. Vertical control surveys are performed to ensure that construction or repair work on culverts and torrent control structures are at the correct height and that water flow upstream and downstream of these structures is satisfactory. Topographic surveys may be performed at existing check dams to evaluate the retention capacity of those structures for further analysis.

C.2.1.14 UXO Survey and Identification Using Magnetometer Sweep and Removal of Located UXO. In support of the other types of work listed, this contract may be used to perform unexploded ordinances (UXO) survey and identification using a magnetometer sweep. This includes labor for the equipment operator, all mobilization and demobilization. costs, and use of UXO survey equipment. The equipment shall have a minimum depth sensitivity of 3 meters for all soil types. Additionally, the contract may be used to remove identified UXO and general scrap metal up to 200 cm in depth. This includes all labor, job site equipment (detection devices, cutting devices, small wheel loader, truck, all-terrain vehicles, and other auxiliary and operating resources), storage (if needed), disposal and/or destruction of UXO materials (including with explosives if necessary). Also, required is the opening of the cleared area with a final clearance report and a quality inspection by a US Explosives Safety personnel.

C.2.1.15 Develop Land Rehabilitation and Maintenance (LRAM) Plans. LRAM is a preventive and corrective land rehabilitation and maintenance program that reduces the long-term impacts of training and testing on installation lands. LRAM primary function is to maintain land to ensure its accessibility, capacity and capability to support the training mission. It mitigates mission and training and testing effects by combining preventive and corrective land rehabilitation, repair, and/or maintenance Best Management Practices to reduce the impacts of training and testing on an installation. It includes training area redesign and/or reconfiguration to meet training requirements and must always be completed in coordination with the local Integrated Training Area Management (ITAM) program.

C.2.1.16 GIS Mapping and Database Development. Prepare and develop GIS resources that are related to the specific task order requirements such as recording locations and results of resource surveys, repair actions and vegetation clearing.

C.2.1.17 Natural Resources Management Actions. These actions assist with carrying out a program of planning for, and the development of, maintenance, and coordination of natural resources related services. This includes fauna habitat improvements or modification, range (or training area) rehabilitation where necessary for support of protected species, and generally supporting the execution of the Integrated Natural Resources Management Plan (INRMP). This also includes prevention and control of invasive species in accordance with the INRMP and EO 13112, Invasive Species/ DoDI 4715.03 and 4150.07. Specific actions include the detection and response to eradicate or control populations of invasive species along with monitoring the results. More specifically, natural resources management actions include, but are not limited to:

Using a global positioning system (GPS) with sub-meter accuracy, conduct mapping of the occurrence of invasive species. This effort shall also provide geographical representations of invasive species control efforts that may be tracked over time as part of an overall invasive species monitoring program. The Contractor shall follow the most current Spatial Data Standards for Facilities, Infrastructure and Environment (SDSFIE). The latest data management requirements within the Department of Defense dictate that geospatial data included in projects deliverables is standardized to insure compatibility with GIS and CADD systems. This includes data used for both military operations and public works. All geospatial data submitted as part of a U.S. government contract must be compatible with the SDSFIE, formerly known as the Tri-Service Spatial Data Standards, as well as all applicable Federal Geographic Data Committee (FGDC) standards.

SDSFIE terminology shall correspond to ESRI terminology using the following format:

Entity Set = geodatabase --- eg.<buildings.gdb> Feature Data Set = ‘feature data set’ (ESRI)-----------------eg.<buildings> Feature Class Name = ‘feature class’ (ESRI)------------eg.<structure_existing_site>

There may be circumstances in which SDSFIE and/or FGDC compliance cannot be maintained. In such circumstances, proposed deviations from the standard must be communicated by the contractor and reviewed by the government.

Several protected bat species inhabit buildings in historic villages in training areas. In order to maintain the buildings as suitable habitat for bats minor improvements or repairs to the buildings are required. This effort includes providing improved or maintaining access for personnel by installing or repairing infrastructure that provides access to the building. This may include such items as a removable ladder and platform, steps into the building, or doors. Also, gaps in wooden window frames shall be sealed and owl ingress prevention devices shall be maintained or installed.

Access to and from a cellar locations is required to maintain bat roost habitat. Efforts include, but are not limited to: stone-in-concrete repairs of existing walls and loose stones at entrance areas to the bat roosts, using a mini excavator that is able to access the cellars (e.g., able to move over rough terrain) along with the use of a conveyor belt to transport debris out of the target cellar, after access is acquired, the existing cellar location will be repaired, if required, by repairing masonry work with existing original stone material (“Bruchsteine”) and removing loose material and fixing/renewing failing or missing joints.

Improving access to bat roosts for bats by cleaning existing trenches using equipment or cleaning by hand.

This effort also includes profiling the existing ditch/depression so that water is directed from the cellar sites to ensure dry conditions of cellar floor.

Various types of camera/monitoring systems are used to monitor TES species and their habitats. As described within an individual Task Order, specified monitoring equipment will be procured by the Contractor and installed at designated location(s). Examples include, but are not limited to; remotely controlled video cameras, scouting/trail/game cameras, and associated power supplies and data storage devices. Additionally, this equipment shall be maintained as described within an individual Task Order.

This effort may include maintaining the camera devices, the solar panels, the battery banks, the wiring associated with the system and any other electronic equipment and associated mounting or housing for the system. Downloading and providing data to the appropriate point of contact designated within the individual Task Order may also be required.

As described within an individual Task Order, bird and bat nesting boxes will be inspected for appropriate maintenance actions. Appropriate maintenance actions includes cleaning out and, if required, repairing the boxes. Some boxes will not be repairable and will require replacement. Separate CLINs will be utilized to replace and install boxes. At each box site, the number of and species of animal using that box will be recorded.

Maintenance of historic orchards is required to maintain specific varieties of fruit trees. Within individual

Task Order, specified orchards will require the following efforts: mowing of open areas within the orchards to reduce grasses and weeds; pruning of individual trees (may be designated within the Task Order to prune in manner to obtain viable tree scions) and watering stressed or newly planted trees.

Collection of scions from historic fruit trees is required to maintain certain historic fruit tree varieties. Older aged trees are pruned in manner to encourage viable scions for future collections. The scions from these trees will be removed by a senior biologist (botanist preferred). Before scions are collected, the senior biologist shall coordinate the selection of which trees will have scions removed with the appropriate personnel at the garrison environmental office. After the scions are collected they will prepare the scions for transport and storage and then provided to the tree nursery.

Documentation of management actions taken using a GPS and providing digital maps and a report of all work completed along with recommendations of work to be completed in the future as a result of the present management actions (employing adaptive management). The Contractor shall follow the most current Spatial Data Standards for Facilities, Infrastructure and Environment (SDSFIE). The latest data management requirements within the Department of Defense dictate that geospatial data included in projects deliverables is standardized to insure compatibility with GIS and CADD systems. This includes data used for both military operations and public works. All geospatial data submitted as part of a U.S.

government contract must be compatible with the SDSFIE, formerly known as the Tri-Service Spatial Data Standards, as well as all applicable Federal Geographic Data Committee (FGDC) standards.

SDSFIE terminology shall correspond to ESRI terminology using the following format:

Entity Set = geodatabase --- eg.<buildings.gdb> Feature Data Set = ‘feature data set’ (ESRI)-----------------eg.<buildings> Feature Class Name = ‘feature class’ (ESRI)------------eg.<structure_existing_site>

There may be circumstances in which SDSFIE and/or FGDC compliance cannot be maintained. In such circumstances, proposed deviations from the standard must be communicated by the contractor and reviewed by the government.

C.3 TASK ORDER EXECUTION

C.3.1 Request for Proposal (RFP) As each project is identified for execution under this contract, the Contractor will be notified by an RFP letter. Each RFP letter will contain the project title, project location, scope of work, and schedule for submittal of Contractor’s proposal for that TO.

C.3.2 Task Order Scopes of Work An RFP under this contract will include a site or project specific scope of work. Scopes will vary in detail but will provide an adequate description of the actual services required to allow suitable negotiations. Typically the individual TO will provide the Contractor with the location, description of work, and schedule of execution. When applicable, the quantities of a particular item that is required will be stated. As attachments to the scope, the Government will provide, as necessary, a map showing the location of the required work, access route to that work, any drawing details which further clarify the work effort and any additional applicable project background information.

C.3.3 Task Order Requirements Additional specific requirements will be identified with the RFP and the related site-specific scope of work. Some of the more common requirements are discussed below:

Time Schedule: The Contractor shall be required to commence work required by a TO within the time specified on that TO. The Contractor shall perform the work and complete the entire project not later than the completion time specified in the TO. Any order issued during the effective period of this contract and not completed within that time period (i.e., prior to expiration of the base or option year of the contract) shall be completed by the Contractor within the time specified in the order. The contract shall govern the Contractor’s and Government’s rights and obligations with respect to that order to the same extent as if the order were completed during the effective period of the contract.

Approvals: As required under the TO, the Contractor shall receive approval from the Contracting Officer or Contracting Officer’s Representative (COR) on all site specific plans (such as work plans) prior to initiating any on-site activity and prior to any new/next phase of planned or scheduled work.

Price Proposals: The Contractor shall be required to propose a price for each TO. Instructions pertaining to the required level of detail will be stipulated in each TO RFP. The Contractor is reminded that, in accordance with FAR 52.215-20, the Contracting Officer may require additional Other than Cost and Pricing Data to support analysis as required to determine a price fair and reasonable in accordance with

FAR 15.403-1..

Notifications: The Contractor is reminded that neither it nor any of its sub-contractors are to accept direction or to proceed with any activity that is outside the scope of any particular TO without the written authority of the Contracting Officer. Upon completion of a TO, the Contractor shall notify the Contracting Officer or COR.

Limitations: Frequency and magnitude of TOs are limited in accordance with FAR 52.216-19, although the Government may exceed the stated minimum/maximum task order limitation upon mutual agreement of all parties. Other than this, there is no limit to the number and size of orders that may be issued. The Government may issue orders requiring delivery to multiple destinations or performance at multiple locations. If, due to the scheduling needs, the Contractor has multiple TOs underway simultaneously; the Contractor shall complete all orders within the schedule allowed. The Government reserves the right to divert the Contractor to work on TOs of higher priority. In such cases, time extensions will be granted for completion of TOs that have been delayed because of Government actions.

C.3.4 Performance Standards Performance standards will be identified for each TO and shall be specific to the type of work being executed under that TO.

C.4 GENERAL REQUIREMENTS

C.4.1 Point of Contact The Government will name a point of contact (POC) at the award of a TO. The Contractor shall supply a single point of contact for this contract upon award of the base contract.

C.4.2 Public Disclosures The Contractor shall make no public announcements or disclosures to a third party, relative to information contained or developed under this contract. This applies also to US Government-owned information made available to the Contractor. The Contractor shall not release or allow access to this information outside of US Government officials designated under the TO and its own officers, employees and lesser agents who require access to the information in order to perform the work. All requests for the release of any of this information shall be referred to the Contracting

Officer for reply. The obligation to maintain the confidentiality of this information shall extend beyond the completion of a TO until release by a United States or German court of competent jurisdiction.

C.4.3 Laws, Regulations and Standards The Contractor shall perform all efforts in full compliance with applicable Host Nation environmental laws. The Contractor shall also comply with EM 385-1-1 (U.S. Army Corps of Engineers SAFETY AND HEALTH REQUIREMENTS MANUAL) and all Host Nation, Federal and local safety requirements. In case of conflict between these regulations, the most protective standard will prevail. The Contractor shall be responsible for insuring that his agents, employees and subcontractors perform the work in a safe manner. The Contractor, subcontractors, employees and his agents shall all have the required certifications and licenses for performance of the work. Regardless of the lack or omission of information within a specific TO, while working in Germany the Contractor is still responsible for meeting the requirements of all applicable German regulations, including all applicable D(eutsche) I(ndustrie) N(orm) German Industry Standard] DIN standards and all work directions and safety regulations of German Trade Union and Civil Engineer Trade Unions. The requirements related to German Construction Code, Vergabe- und Vertragsordnung für Bauleistungen (VOB), Part C, latest addition and technical requirements of the following include, but are not limited to the following:

DIN 4032 Concrete pipes and fittings DIN 4033 Sewage channels and pipe lines; code of practice for construction DIN 18299 General Regulations for Construction Work DIN 18300 Earth Work DIN 18305 Dewatering Work DIN 18306 Sewer Work DIN 18318 Road Construction Work DIN 18310 Stabilization Work at Waters, Dikes and Coastal Dunes DIN 18320 Landscape Construction Work DIN 18331 Concrete and Reinforced Concrete Work DIN 18917 Landscaping turf; seed, sod, turf establishment part (2.2.3 landscaping turf)

The above listing asserts no claim for completeness.

While working in Host Nation countries outside of Germany, the contractor, subcontractors, employees and his agents shall all have the required certifications and licenses for performance of the work and shall meet the applicable Host Nation regulations, requirements and standards comparable to what is identified above.

C.4.4 US Government Furnished Equipment, Materials, and Personnel The amount of Government assistance will vary from location to location and will be negotiated as part of the individual TO. Limited storage space will be available to the Contractor at each project site. The location of this storage area will be determined with each TO.

All other aspects of the contract are the Contractor’s responsibility. The Contractor understands that all offers of assistance or work directives (verbal or written) by US Government personnel other than the Contracting Officer or COR are unauthorized and that the Contractor shall not accept any such offers, other than those which are directed by the Contracting Officer or the COR.

C.4.5 Passes/Identification Installation passes are required for Contractor personnel before the Contractor may be able to proceed with any fieldwork. The Contractor shall be responsible for furnishing identification for each employee and for each employee on the work site to display such identification as directed by the Contracting Officer or COR. The Contractor shall submit a personnel list and vehicle lists to the Government POC prior to the commencement of work. Installation passes shall be obtained by each of the Contractor’s personnel in accordance with AE Regulation 190-16, Installation Access Control (5 Dec 2002).

C.4.6 Exercising of Options The base period shall be for 3 years and each subsequent option year shall run for a period of 365 days. The Government reserves the right to exercise Option 1 during the performance period of the base contract and Option 2 during the performance period of Option 1, and so on throughout the two optional periods.

C.4.7 Management Plan After award of the base contract, the successful Contractor shall submit an overall management plan for execution of work under this contract. The preparation of this plan (draft and any subsequent required revision needed to obtain approval of this document from the COR) shall be requested, if required, under a separate Task Order. The Management Plan shall contain, at a minimum, an Organization Plan, a Work Plan, a Health and Safety Plan (HASP), and a QA/QC Plan. Approval of the Management Plan by the COR is required prior to the commencement of any fieldwork.

Organizational Plan: The Organizational Plan shall describe staff organization, responsibilities, and qualifications of personnel assigned to accomplish the various facets of this contract. The plan will also contain the names of all subcontractors and off-site disposal facilities. Deviations from the Organizational Plan are subject to approval by the Contracting Officer or the COR. The plan shall include the telephone number, facsimile number, e-mail address, and point of contact by which the Government can contact the Contractor. Of particular importance is the identification of competent supervisor(s) who will act for the Contractor at work.

Work Plan: The Work Plan shall identify the types of equipment and potential number and type of staff that will be used for the following major work efforts:

- Sludge/Soil work (including grading, moving, excavation, installation)

- Check Dam Repair/Construction

- Aerial Seeding

- Maneuver Trail and Tank Road Repairs

- Repair sinkholes

- Dust Control

- Natural Resource Protection

Health and Safety Plan (HASP): The HASP shall comply with all applicable requirements of the US Army Corps of Engineers’ Safety and Health Manual (EM 385-1) and with all applicable German laws and regulations. Health and Safety standards for working at the site as identified in the Health and Safety Plan, shall be observed during all activities performed by the Contractor. At a minimum, the HASP shall address the following:

- Potential hazards to the Contractor’s personnel as well as to the surrounding area and other third parties (i.e., site visitors).

- General UXO safety awareness and procedures to be followed when UXO is encountered.

- Site control measures.

- On-site first aid and emergency equipment.

- Emergency response plan shall an accident occur.

Quality Assurance/Quality Control Plan (QA/QC): The Contractor is responsible for quality control and shall establish and maintain an effective quality control plan and system. The quality control plan shall detail the quality control system, consisting of plans, procedures, and organization necessary to produce an end product that complies with the contract requirements. The system shall cover all construction operations, both on-site and off-site, and shall be keyed to the proposed construction sequence. The QA/QC Plan shall include as a minimum the name and qualifications of the quality control representative(s) as well as an outline of the Contractor's procedure for performing the inspection on the major job features discussed under the potential Task Orders (to include replacement of a pipeline in a check dam, aerial seeding, and dust control, at a minimum). It will be determined at the first meeting with the contractor if additional QA/QC features shall be addressed. For individual TOs, as part of the work effort the Contractor may be required to submit specific QA/QC plans for that site. This additional work requirement will be paid for as part of that individual TO. Specific QA/QC requirements are discussed under section C.4.15.

C.4.8 Cooperation with Other Contractors The Government may have other Contractors in the same area in which work is being performed.