This document is an Amendment to Solicitation W912ES24Q0118 for Upright Spud Winches. The purpose of this amendment is to update the scope of work and extend the closing date to September 3, 2024. The key details are:
The requirement for a 230/460 Volt, 3 Phase, 60Hz electric motor has been changed to a 230 Volt, 3 Phase, 60Hz electric motor. The winches must meet the following specifications: Four (4) 65-ton right-hand model winches, rated line-pull of at least 12,000 lbs. on the first layer, no-load line speed of at least 23 FPM, electromagnetic brake release with spring-applied brake, brake holding capacity of at least 60,000 lbs., dog latch system, hand wheel for manual operation, and NEMA 4 rated momentary control box. The winches must be fully assembled and delivered by December 31, 2024. They will be delivered to the Fountain City Service Base in Fountain City, WI. The response date has been extended from August 30, 2024 to September 3, 2024.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment 1_Upright Spud Winches_W912ES24Q0118.pdf | ||
| Solicitation_Upright Spud Winches_W912ES24Q0118.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this amendment is to update the scope of w ork and extend the closing date to 3 September 2024. The requirement for a 230/460 Volt, 3 Phase, 60Hz electric motor is changed to a 230 Volt, 3 Phase, 60Hz electric motor.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 3
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 28-Aug-2024
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912ES24Q0118
X 9B. DATED (SEE ITEM 11)
13-Aug-2024
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
29-Aug-2024
CODE
CONTRACTING DIVISION
USACE, ST PAUL
332 MINNESOTA STREET
SUITE E1500
SAINT PAUL MN 55101-1323
W912ES 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912ES24Q0118
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 1449 - CONTINUATION SHEET
SOLICITATION/CONTRACT FORM
The required response date/time has changed from 30-Aug-2024 03:00 PM to 03-Sep-2024 10:00 AM.
The following have been modified:
SCOPE OF WORK
Scope of Work - Upright Spud Winches
Project Description:
The equipment barges in the dredge Goetz fleet requires four (4) new upright winches to raise and lower anchor spuds.
Specifications:
All four (4) new upright winches shall meet the following specifications:
Four (4) 65ton right-hand model winches.
Winches must be electric, 230 Volts, 3 Phase, 60 Hz, with totally enclosed weatherproof A/C motors.
Rated line-pull of not less than 12,000 Lbs. on the first layer.
No-load line speed of no less than 23 FPM.
Electromagnetic brake release with a spring applied brake.
Brake holding capacity shall be rated at no less than 60,000 lbs.
Dog latch system for securing the winch drum once the spuds have been hoisted in the upright position.
Hand wheel to operate the winch in the event there is a power loss on the barge.
NEMA 4 rated momentary control box for each winch for operating the winch in either direction.
When the switch is released, it shall go to the neutral position and apply the spring brake on the winch.
Winch drum able to accommodate 7/8 cable with a minimum drum capacity of 200’.
Dimensions:
Overall Length: 30-48” Overall Width: 20-30” Overall Height: 40-55”
** Specification sheet shall be included with quote.
Delivery Information:
Winches shall be delivered fully assembled and ready for installation NLT 31 December 2024. All industry standard safety devices shall be installed. Hours for delivery must be between 7:00 AM and 3:30 PM. No deliveries will be received on holidays or weekends.
The winches shall be delivered to:
W912ES24Q0118
Fountain City Service Base 431 North Shore Drive Fountain City, WI 54629-0397
All invoices shall be sent to:
POC for invoicing will be provided after award.
(End of Summary of Changes)