- Full Hookup Campsites at Leech Lake Dam
- Solicitation number
- W912ES21Q0027
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment 4 W912ES21Q0027.pdf | ||
| Amendment 3 W912ES21Q0027.pdf | ||
| Amendment 2 W912ES21Q0027.pdf | ||
| Amendment 1 W912ES21Q0027.pdf | ||
| W912ES21Q0027 RFQ.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Full Hookup Campsite Construction Specifications for Leech Lake Dam
General: The contractor shall supply and provide all equipment, labor, supervision, and materials necessary to construct, according to codes, three seasonal full hookup campsites within the park at the existing Leech Lake Dam, US Army Corps of Engineers (USACE) Civil Works Project.
Location: The construction site is located adjacent to the town of Federal Dam in Cass County, Minnesota:
U.S. Army Corps of Engineers, Leech Lake Dam
01217 Federal Dam Drive NE Federal Dam, MN 56641
Measurement and Payment: Payment will be made upon completion and acceptance of all contracted work.
Completion Date: The completion date for this contract/all work is June 30, 2021. All trees must be cut prior to May 01, 2021. The contractor may request in writing a completion date extension if weather conditions prevented completion by June 30, 2021. Work extension requests will require the contractor to provide a new detailed work schedule. The request must document ground conditions that are too wet, deep snow cover, or frost as valid reasons for the extension. Cold air temperatures by themselves are not considered valid for an extension request. The extension must be approved by the Contracting Officer.
Codes: All work shall conform to local, county, and state laws and codes.
Utility Locates: The contractor is responsible for locating all utilities prior to initiating the work. The following utilities are potentially within the scope of the area: telephone/internet, electrical, water lines, and sewer lines.
Licenses/Certifications: Installers must be licensed applicable to the State of Minnesota and provide copies of licenses during the on-site initial pre-work conference that will be held prior to initiating work that includes the following:
a. MN State Licensed Septic Installer. Sewer and potable water lines must be installed to meet MN Dept. of Health (MDH) and Minnesota Pollution Control Agency (MPCA) laws/codes.
b. Master Plumber, Pipe Fitter. Sewer and potable water lines must be installed to meet MDH and MPCA laws/codes.
c. Master Electrician. All electrical work shall conform to the National Electric Code (NEC) and National Electric Safety Code (NESC).
d. Qualified contractor for horizontal directional boring.
e. Qualified contractor with experience for earth work, excavation, trucking, and landscaping.
Safety: The Contractor shall complete all work according to the Corps of Engineers’ Safety Manual, USACE EM 385-1-1-http://www.publications.usace.army.mil/Portals/76/Publications/EngineerManuals/EM_385-1- 1.pdf
Insurance: The Contractor shall submit proof of insurance for Workman Compensation and Liability at the initial pre construction meeting (detailed below). All insurance shall be adequate to indemnify the Government from liability for injury to the Contractor’s employees and damage to Government property.
Cleanup: The contractor is responsible for all cleanup and disposal pursuant to all codes.
Contracting Officer Representative: The USACE Contracting Officer’s Representative (COR) is Jason Hauser. His contact information is telephone 651-290-5791 or email jason.a.hauser@usace.army.mil
Initial Pre-Construction Meeting: An initial pre-work meeting shall be held at the Leech Lake Dam office at least 14-days prior to start of contract work. The contractor must contact the USACE (COR) within 10-days after award of this contract to coordinate administration and schedules.
Work Plan: Contractor shall submit a work plan that details the sequence and scheduling of the proposed work at the initial meeting. The work plan also shall include shop drawings and a list of subcontractors and their licenses, sewer design, potable water design, and electrical design. The work plan shall also include spec sheets of all products being proposed by the contractor to be used under this contract. The Work Plan shall be approved by the USACE Contracting Officer prior to start of work.
Specifications: Care will be taken not to damage existing trees that will be marked or otherwise identified “Do Not Remove” within and near the work area. An overview of the work consists of the following: but all specifications shall be met that are detailed later within attached drawings and photos:
1) Site Prep:
a. Measuring and staking out location of new campsites and locations of new utilities to be constructed and then approved by the USACE. The layout will strive to preserve significant trees already existing within the work area, but it’s known that many trees will need to be removed that are impacted by this work.
b. Locating existing utilities.
c. Tree and brush clearing within work area and removing from site for disposal.
d. Excavating topsoil, roots, stumps, etc. from within work area and removing from site for proper disposal.
e. Reshaping ground surface to achieve proper elevations of campsites and drainage within new campsite surrounding areas.
2) Utilities: Installation of new utilities from existing locations to new campsites for Sewer, Potable Water, and Electric. Standard configuration for utilities shall be as such: Potable water spigot located off rear right corner of campsite. Electric pedestal about 12’ from potable water spigot. Sewer about
25’ from potable water spigot. Water and sewer lines shall not cross each other and remain far enough apart and installed to meet MDH laws, codes, and guidelines. MDH laws, codes, and guidelines shall supersede the distances specified above and on attached drawings. See attached drawings for additional details.
The contractor may use the following existing utilities while completing the work at no cost: Contractors may use restrooms located within the USACE, Leech Lake Dam Recreation Area that are available to the public. The contractor can utilize USACE potable water and/or electricity. Use of such utilities must not impede traffic on roadways. All impacts to traffic must be coordinated with USACE staff in advance.
A. Sewer. The existing concrete sewer manhole (which is the starting point) is about 10’ deep and consists of approximately 24” diameter cover on top of a concrete conical riser. There is a seam between the concrete manhole and the conical riser. The depth of this seam is about 4’ from the ground surface. Care must be taken not to damage this seam. Sewage flowing through this manhole runs at the bottom of the manhole. Trench in new 4” SDR Sewer Line starting from and tapping into the existing concrete sewer manhole (see attached drawing for location of this manhole) in-series to the specified locations adjacent to the new campsites. Cleanout riser pipes must be installed at all angles and every 100 feet of distance as applicable to the contractor’s design. Holes cut through the manhole must be a clean cut and shall utilize a modular mechanical sealing system that creates a permanent seal for cylindrical objects that pass through a barrier. A sealer designed for septic/sewer/manholes shall be used to seal any gaps. Sewer lines shall be installed with tracer line attached for future locating needs.
Sewer Design. Contractor shall submit a design that details the sewer installation. The sewer design shall be submitted at the on-site initial meeting. The Sewer Design shall be approved by the Contracting Officer prior to start of work and shall contain the following information:
a. Layout drawing of new sewer plumbing and depth.
b. A list of components with spec sheets.
B. Potable Water. Photos of existing manholes are attached for reference below. Waterlines will be constructed to allow for winterization each fall and restarted each spring by USACE staff. Potable water lines shall be installed with tracer line attached for future locating needs.
All water standpipes specified shall be installed in concrete pads at ground level appropriately sized to support the standpipes. All shut off and drain valves specified shall consist of ball valves. Utilize underground horizontal directional boring to install a new seasonal 200 lbs. poly 2” potable water line with shut off valve starting from and tapping into the existing approximately 24” diameter x 4’ deep, concrete manhole located near campsite #57 that contains approximately 2-1/2” copper piping that exists approximately 12” below the ground surface inside the manhole. The existing concrete manhole located near campsite #57 (which is the starting point) contains an existing gate valve that shall be replaced with a ball valve at the same time the contractor “T’s” into the existing water line inside of the manhole. The contractor shall “T” into the existing copper waterline “upstream” of the new ball valve being installed. Directional boring and new waterline shall be installed to the specified location near the new campsites and install a new approximately 24” diameter PVC manhole with a fiberglass reinforced plastic cover that shall contain a ball shut off and drain valve. Then extend waterline and install a 36” high, 2” galvanized standpipe adjacent to the manhole that includes a shut off ball valve near the top and a hose bib on top. Then “T” underground adjacent to the standpipe and then trench in-series to each of the three new campsites with new ¾” poly waterline including 18” galvanized standpipes, with shutoff valves, and hose bibs on top for each. Place about 12” of approximately 1” rock at the base of the new manhole. Holes cut through the manhole must be a clean cut and shall utilize a modular mechanical sealing system that creates a permanent seal for cylindrical objects that pass through a barrier. A sealer designed for septic/sewer/manholes shall be used to seal any gaps or holes where that system is not applicable.
Potable Water Design. Contractor shall submit a design that details the plumbing installation. The potable water design shall be submitted at the on-site initial meeting. The Potable Water Design shall be approved by the Contracting Officer prior to start of work and shall contain the following information:
a. Layout drawing of new potable water plumbing and depth.
b. A list of components with spec sheets.
C. Electric. Utilize underground horizontal directional boring to install 20amp, 30amp, and 50amp electric starting from and tapping into an existing single phase EATON main electric panel. This existing panel is 400amps, 240vac; see attached photos for more information on the EATON panel. It is the contractor’s responsibility to verify that the meter base, transformer, and primary feed from Lake Country Power is sufficient to supply the new circuit being installed. Bore to the specified location adjacent to the new campsites and then install one new Outdoor Rated 20 amp/30amp/50amp Grey Campground RV Pedestals with Breakers and Receptacles in-series for each of the three new campsites at the specified locations.
New Loop Conductors: All loop conductors shall be, one set of three (3) 250 MCM AL conductors with a #3/0 AL Ground minimum, unless otherwise required by the NEC or to reduce the voltage drop.
Contractor shall calculate voltage drops. Voltage drop shall not exceed 5% from any campground pedestal to service transformer.
Electrical Design. Contractor shall submit a design that details the electrical installation. The electrical design shall be submitted at the on-site initial meeting. The Electrical Design shall be approved by the Contracting Officer prior to start of work and shall contain the following information:
a. Layout drawing of new electrical service including proposed depths of installation.
b. New components for existing EATON main electrical cabinet and electrical service equipment.
c. New Outdoor rated 20 amp/30amp/50amp Grey Campground RV Pedestals with Breakers and Receptacles designed for such use.
d. New underground service conduit and wiring.
e. New distribution wiring and conduit.
f. Circuit runs and cable lengths.
g. Circuit voltage drop calculations.
3) Campsite Construction:
a. Supplying, hauling, and constructing with class v and top soil. Campsites must be constructed with a minimum of 15” of compacted Class V. Compacted class v for the new campsites will be constructed approximately 12” above surrounding grade.
b. New campsites must be constructed level and sized approximately as stated on attached drawings with sloping edges extending away from the sides of the campsites consisting of topsoil with about 1” drop for every 12” of distance. The side slopes will add about 12’ all around to the actual size of the campsite dimensions shown on below drawings. Drainage will be landscaped outside of the sloped areas. Side slopes and drainage areas will be seeded with a significant amount of Kentucky Blue Grass or sodded.
4) Landscaping:
a. All measurements, depths, heights, etc. for materials specified for this contract is defined as after proper compaction.
b. Reshape and slope ground surface for drainage of area surrounding new campsites and side slopes.
c. All surrounding areas will be constructed with at least 4” of clean top soil and grass/sod all around.
d. Provide and plant six, at least 4’ tall (above ground level), Colorado blue spruce trees in approved locations. Trees will include root balls and will not be bare root.
e. Seed or sod all impacted grounds with grass seed containing a significant amount of Kentucky Blue Grass.
f. Contractor shall sufficiently water seed/sod immediately after completion.
g. Finished product will be equivalent to “residential yard” quality that will appropriately shed rainfall and ready for intense mowing and activity once the grass has taken root.
h. The contractor shall warranty growth of seeding/sod and trees for 1-year from the date of final completion for all work. During that time, the contractor will re-seed/sod and/or replace trees that did not survive.
5) Horizontal Directional Boring: The contractor shall excavate holes no larger than 12’ x 12’ at the starting points for potable water and electrical directional boring. The utility lines will be used for seasonal use and waterlines will be winterized each fall by park staff. Depths must meet codes but no less than approximately 24” and will be designed to “fit current conditions”. Waterlines will be constructed to allow for winterization each fall and de-winterization each spring by park staff.
6) Warranty: The contractor shall provide in writing a warranty that will ensure that the contractor will repair/replace any defective components of this contract, including landscaping, that does not function/grow/work as designed/intended by this USACE SOW/Specification for up to 12-months. This warranty will not cover any damages that happen after USACE acceptance of work that are not the fault of the contractor. An amount will be withheld by the USACE until the warranty has been met and then will be paid to the contractor after proper invoicing, submittals, administration, etc. has been met.
See Attachments:
a. USACE, Leech Lake Dam, Site Map/Work Location.
b. Campsite Construction Drawing 1.
c. Campsite Construction Drawing 2.
d. Photo of existing concrete manhole of potable water.
e. Photo of an example of new approximately 24” diameter PVC manhole with a fiberglass reinforced plastic cover.
f. Photos of existing EATON main electrical panel.
Work Area
Affected Area (Water & Electric)
Continued on next page.
Existing Water Hookup
Existing Electrical Panel
Existing Sewer Hookup Existing Walking Trail
Existing Campsites
New Campsites
* All measurements are approximate
Campsite Construction Drawing 1
Directional Boring/ Electrical Install
Directional Boring/ Water Line
Existing Sewer Manhole
Existing Walking Trail
New Campsites
50 feet
Existing Campsites
* All measurements are approximate
Campsite Construction Drawing 2
Water Manhole
Water Spigot
Water Line
Electrical Pedestal
Electrical Line
Sewer Hookup
Sewer Line
Continued on next page
End of attachments.