W912ES21B0012 Bidding Abstract - Drain 27.pdf
PDF 227 KB Posted
- Attached to
- Fargo Moorhead Metropolitan (FMM) Area Flood Risk Management Project, Drain 27 Wetland Restoration
- Solicitation number
- W912ES21B0012
About this file
This bid abstract documents bids received for the Fargo Moorhead Metropolitan (FMM) Area Flood Risk Management Project, Drain 27 Wetland Restoration project. The solicitation was issued by the US Army Corps of Engineers Engineering District St Paul with bid opening on March 1st, 2022. It includes bids from six contractors for a base scope of work and optional additional work. The base work involves wetland restoration including demolition, clearing, excavation, installation of geotextiles, riprap, bedding and other materials. Optional work includes additional demolition, excavation and installation of temporary cover crops. Pricing is provided on a line item basis for the various work elements. The low bidder for the total base bid and optional work was Itapela Infrastructure, LLC at $4,650,720.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FMM Drain 27 Wetland Restoration Solicitation Number: W912ES21B0012 US Army Corps of Engineers. 180 East 5th Street, Suite 700. Saint Paul, Minnesota 55101 BID OPENING: 03/01/2022 2:00pm
Contracting Officer: Kevin P. Henricks Contract Specialist: Scott E. Hendrix
Unit Unit Unit Unit Unit Unit Unit Item Description Quantity Unit Price Amount Price Amount Price Amount Price Amount Price Amount Price Amount Price Amount
BASE BID
0001 Performance and Payment Bonds 1 JOB $48,000.00 $48,000.00 $36,359.60 $36,359.60 $29,500.00 $29,500.00 $60,000.00 $60,000.00 $302,864.61 $302,864.61 $30,000.00 $30,000.00 $50,000.00 $50,000.00 0002 Demolition 1 JOB $33,464.36 $33,464.36 $67,742.11 $67,742.11 $185,200.00 $185,200.00 $75,000.00 $75,000.00 $7,116.59 $7,116.59 $165,462.00 $165,462.00 $50,000.00 $50,000.00 0003 Signs 1 JOB $39,909.99 $39,909.99 $2,189.57 $2,189.57 $273,000.00 $273,000.00 $45,000.00 $45,000.00 $14,719.51 $14,719.51 $75,271.00 $75,271.00 $45,000.00 $45,000.00 0004 Clearing and Grubbing 1 JOB $20,000.00 $20,000.00 $136,000.00 $136,000.00 $144,300.00 $144,300.00 $125,000.00 $125,000.00 $15,470.84 $15,470.84 $137,682.00 $137,682.00 $48,500.00 $48,500.00 0005 Road Removal 1,600 CY $16.33 $26,128.00 $7.76 $12,416.00 $8.50 $13,600.00 $10.00 $16,000.00 $8.66 $13,856.00 $45.50 $72,800.00 $35.00 $56,000.00 0006 Stripping
0006AA First 170,000 CY 170,000 CY $6.18 $1,050,600.00 $5.00 $850,000.00 $1.57 $266,900.00 $4.00 $680,000.00 $10.15 $1,725,500.00 $4.65 $790,500.00 $3.75 $637,500.00 0006AB Over 170,000 CY 31,000 CY $6.18 $191,580.00 $4.81 $149,110.00 $1.35 $41,850.00 $2.00 $62,000.00 $9.28 $287,680.00 $2.50 $77,500.00 $3.75 $116,250.00
0007 Excavation 0007AA First 170,000 CY 170,000 CY $8.06 $1,370,200.00 $7.12 $1,210,400.00 $8.75 $1,487,500.00 $14.75 $2,507,500.00 $16.32 $2,774,400.00 $11.80 $2,006,000.00 $6.80 $1,156,000.00 0007AB Over 170,000 CY 43,000 CY $8.63 $371,090.00 $6.73 $289,390.00 $6.75 $290,250.00 $7.00 $301,000.00 $11.22 $482,460.00 $11.80 $507,400.00 $6.80 $292,400.00
0008 Geotextile - Type 2 15,000 SY $2.26 $33,900.00 $2.27 $34,050.00 $2.40 $36,000.00 $4.00 $60,000.00 $3.09 $46,350.00 $18.20 $273,000.00 $5.00 $75,000.00 0009 Aggregate Surface 5,000 TON $34.64 $173,200.00 $46.56 $232,800.00 $29.20 $146,000.00 $50.00 $250,000.00 $35.04 $175,200.00 $76.00 $380,000.00 $38.00 $190,000.00 0010 Topsoil Respread
0010AA First 170,000 CY 170,000 CY $3.98 $676,600.00 $7.30 $1,241,000.00 $1.92 $326,400.00 $6.00 $1,020,000.00 $2.78 $472,600.00 $2.85 $484,500.00 $3.75 $637,500.00 0010AB Over 170,000 CY 31,000 CY $3.98 $123,380.00 $7.11 $220,410.00 $1.75 $54,250.00 $2.00 $62,000.00 $1.55 $48,050.00 $2.85 $88,350.00 $3.75 $116,250.00
0011 Low Flow Pipe 148 LF $91.91 $13,602.68 $167.26 $24,754.48 $96.10 $14,222.80 $200.00 $29,600.00 $272.29 $40,298.92 $210.00 $31,080.00 $350.00 $51,800.00 0012 Geotextile - Type 1 1,650 SY $2.64 $4,356.00 $3.87 $6,385.50 $2.50 $4,125.00 $4.00 $6,600.00 $3.09 $5,098.50 $11.75 $19,387.50 $8.50 $14,025.00 0013 R270 Riprap 1,100 CY $123.73 $136,103.00 $96.96 $106,656.00 $91.40 $100,540.00 $110.00 $121,000.00 $167.09 $183,799.00 $225.00 $247,500.00 $180.00 $198,000.00 0014 B3 Bedding 450 CY $105.90 $47,655.00 $42.04 $18,918.00 $113.00 $50,850.00 $150.00 $67,500.00 $106.75 $48,037.50 $185.00 $83,250.00 $165.00 $74,250.00 0015 Sheet Pile 1,700 SF $71.88 $122,196.00 $162.86 $276,862.00 $48.40 $82,280.00 $55.00 $93,500.00 $103.65 $176,205.00 $99.50 $169,150.00 $92.00 $156,400.00 0016 King Pile 800 LF $128.50 $102,800.00 $647.13 $517,704.00 $332.00 $265,600.00 $400.00 $320,000.00 $634.30 $507,440.00 $925.00 $740,000.00 $489.00 $391,200.00 0017 Temporary Cover Crop 75 ACE $1,039.60 $77,970.00 $400.23 $30,017.25 $554.00 $41,550.00 $700.00 $52,500.00 $1,137.11 $85,283.25 $930.00 $69,750.00 $1,200.00 $90,000.00
TOTAL BASE $4,662,735.03 $5,463,164.51 $3,853,917.80 $5,954,200.00 $7,412,429.72 $6,448,582.50 $4,446,075.00
OPTION 1
1001 Performance and Payment Bonds 1 JOB $5,000.00 $5,000.00 $1,543.20 $1,543.20 $16,000.00 $16,000.00 $5,000.00 $5,000.00 $15,984.49 $15,984.49 $5,000.00 $5,000.00 $3,200.00 $3,200.00 1002 Demolition 1 JOB $116,664.00 $116,664.00 $8,951.83 $8,951.83 $32,400.00 $32,400.00 $65,000.00 $65,000.00 $82,248.96 $82,248.96 $88,449.00 $88,449.00 $20,000.00 $20,000.00 1003 Clearing and Grubbing 1 JOB $10,000.00 $10,000.00 $6,800.00 $6,800.00 $104,800.00 $104,800.00 $45,000.00 $45,000.00 $4,008.75 $4,008.75 $13,491.00 $13,491.00 $30,500.00 $30,500.00 1004 Road Removal 1,200 CY $16.33 $19,596.00 $7.76 $9,312.00 $13.50 $16,200.00 $10.00 $12,000.00 $17.45 $20,940.00 $39.30 $47,160.00 $9.40 $11,280.00 1005 Stripping
1005AA First 7,000 CY 7,000 CY $6.18 $43,260.00 $4.12 $28,840.00 $2.05 $14,350.00 $6.00 $42,000.00 $4.67 $32,690.00 $2.65 $18,550.00 $2.75 $19,250.00 1005AB Over 7,000 CY 1,200 CY $6.18 $7,416.00 $4.12 $4,944.00 $2.00 $2,400.00 $2.00 $2,400.00 $2.06 $2,472.00 $2.65 $3,180.00 $2.75 $3,300.00
1006 Excavation 1006AA First 12,000 CY 12,000 CY $8.66 $103,920.00 $6.24 $74,880.00 $7.55 $90,600.00 $12.00 $144,000.00 $15.52 $186,240.00 $11.80 $141,600.00 $5.00 $60,000.00 1006AB Over 12,000 CY 2,200 CY $8.73 $19,206.00 $6.24 $13,728.00 $9.55 $21,010.00 $6.00 $13,200.00 $8.85 $19,470.00 $11.80 $25,960.00 $5.00 $11,000.00
1007 Geotextile - Type 2 200 SY $2.26 $452.00 $2.27 $454.00 $2.55 $510.00 $10.00 $2,000.00 $4.85 $970.00 $17.50 $3,500.00 $6.00 $1,200.00 1008 Aggregate Surface 70 TON $34.64 $2,424.80 $46.56 $3,259.20 $38.30 $2,681.00 $75.00 $5,250.00 $36.36 $2,545.20 $76.00 $5,320.00 $112.00 $7,840.00 1009 Topsoil Respread
1009AA First 10,000 CY 10,000 CY $3.98 $39,800.00 $6.43 $64,300.00 $2.15 $21,500.00 $3.00 $30,000.00 $3.33 $33,300.00 $2.80 $28,000.00 $2.75 $27,500.00 1009AB Over 10,000 CY 2,000 CY $3.98 $7,960.00 $6.43 $12,860.00 $2.15 $4,300.00 $2.00 $4,000.00 $1.94 $3,880.00 $2.80 $5,600.00 $2.75 $5,500.00
1010 Temporary Cover Crop 5 ACRE $1,039.60 $5,198.00 $400.23 $2,001.15 $575.00 $2,875.00 $700.00 $3,500.00 $666.68 $3,333.40 $925.00 $4,625.00 $815.00 $4,075.00 TOTAL OPTION 1 $380,896.80 $231,873.38 $329,626.00 $373,350.00 $408,082.80 $390,435.00 $204,645.00 TOTAL BASE AND OPTION 1 $5,043,631.83 $5,695,037.89 $4,183,543.80 $6,327,550.00 $7,820,512.52 $6,839,017.50 $4,650,720.00
Note: Upon reviewing the bids, mathamatical errors were discovered for the highlighted items. The highlighted amount and subsequent totals are correct.
I certify that I have opened, read, and recorded on this abstract all bids received in response to this solicitation.
Kevin P. Henricks Contracting Officer
Post Office Box 128 817 West Main Street
Brownsville, WI 53006
Montana Civil Contractors, Inc.
62 Skyway Blvd Belgrade, MT 59714
Government Estimate HSG Park Joint Venture, LLC NW Construction, Inc., Neil
W. Construction MG Facility Services, LLC Itapela Infrastructure, LLC
Hamburg, IA 51640 Harvey, ND 58341 Bozeman, MT 59718 Minneapolis, MN 55416
Hendrickson Transportation, LLC
2762 310th St. P.O. Box 213 7585 Shedhorn Drive 1600 Utica Avenue South, Suite 900
Sheet1
| 2022-03-01T15:53:01-0600 | |
| HENRICKS.KEVIN.PHILIP.1249726873 |