W912ES21B0001 I-29 Grade Raise Abstract.pdf
PDF 301 KB Posted
- Attached to
- I-29 Grade Raise and Borrow Ditch Crossing
- Solicitation number
- W912ES21B0001
About this file
This document provides an abstract of bids received for the I-29 Grade Raise and Borrow Ditch Crossing project solicitation issued by the U.S. Army Corps of Engineers, St. Paul District. The solicitation requests bids to complete highway and bridge construction work including clearing, excavation, paving, drainage, signs, guardrails and other items. Four contractors submitted bids ranging from $47 million to $56 million. The government estimate was $54.8 million. The solicitation also includes optional items for concrete or asphalt shoulders on the mainline and temporary bypass work priced from $1 to $19.5 million. The contracting officer will award to the responsible bidder with the lowest priced, technically acceptable offer. All questions must be submitted through one of the prequalified contractors by the March 11, 2021 bid opening date.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| W912ES21B0001 Prequalified Sources List (Rev 1).pdf | ||
| W912ES21B0001 Prequalified Sources List.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
I-29 Grade Raise & Borrow Ditch Crossing Solicitation W912ES21B0001
US Army Corps of Engineers. 180 5th Street East, Suite 700, St. Paul, MN 55101-1678 Bid Opening: 11 March 2021 @ 2:00 p.m. Central
Contracting Officer: Kenneth J. Eshom Contract Specialist: Toni W. Wasgatt
BASE
Item Description Quantity Unit Unit Price Amount Unit Price Amount Unit Price Amount Unit Price Amount 0001 Performance and Payment Bonds 1 JOB $670,000.00 $670,000.00 $475,000.00 $475,000.00 $150,000.00 $150,000.00 $300,000.00 $300,000.00 0002 Clearing & Grubbing 1 JOB $15,862.00 $15,862.00 $250,000.00 $250,000.00 $150,000.00 $150,000.00 $300,000.00 $300,000.00 0003 Demolition 1 JOB $431,871.00 $431,871.00 $751,000.00 $751,000.00 $2,116,000.00 $2,116,000.00 $500,000.00 $500,000.00 0004 Milling Pavement Surface 2-inch 6,607 SY $2.14 $14,138.98 $3.00 $19,821.00 $3.00 $19,821.00 $5.00 $33,035.00 0005 Pavement Removal 213,774 TN $12.00 $2,565,288.00 $12.00 $2,565,288.00 $13.00 $2,779,062.00 $11.00 $2,351,514.00 0006 Temporary Traffic Control 1 JOB $369,338.00 $369,338.00 $570,000.00 $570,000.00 $3,250,000.00 $3,250,000.00 $1,500,000.00 $1,500,000.00 0007 Common Excavation
0007AA First 250,000 CY 250,000 CY $6.79 $1,697,500.00 $15.00 $3,750,000.00 $4.10 $1,025,000.00 $6.50 $1,625,000.00 0007AB Over 250,000 CY 71,142 CY $6.79 $483,054.18 $15.00 $1,067,130.00 $4.10 $291,682.20 $5.65 $401,952.30
0008 Borrow Excavation 0008AA First 630,000 CY 630,000 CY $7.00 $4,410,000.00 $14.00 $8,820,000.00 $9.25 $5,827,500.00 $11.00 $6,930,000.00 0008AB Over 630,000 CY 219,701 CY $7.00 $1,537,907.00 $14.00 $3,075,814.00 $9.25 $2,032,234.25 $6.40 $1,406,086.40
0009 Pipe Conduit 12-inch 454 LF $43.89 $19,926.06 $90.00 $40,860.00 $50.00 $22,700.00 $75.00 $34,050.00 0010 Pipe Conduit 15-inch 155 LF $77.25 $11,973.75 $100.00 $15,500.00 $55.00 $8,525.00 $52.50 $8,137.50 0011 Pipe Conduit 18-inch 604 LF $45.44 $27,445.76 $125.00 $75,500.00 $45.00 $27,180.00 $70.25 $42,431.00 0012 Pipe Conduit 24-inch 3,044 LF $159.78 $486,370.32 $140.00 $426,160.00 $105.00 $319,620.00 $100.00 $304,400.00 0013 Pipe Conduit 27-inch 44 LF $140.00 $6,160.00 $180.00 $7,920.00 $95.00 $4,180.00 $116.50 $5,126.00 0014 Pipe Conduit 30-inch 3,286 LF $156.00 $512,616.00 $200.00 $657,200.00 $150.00 $492,900.00 $130.00 $427,180.00 0015 Pipe Conduit 36-inch 596 LF $308.00 $183,568.00 $220.00 $131,120.00 $160.00 $95,360.00 $189.00 $112,644.00 0016 Pipe Conduit 36-inch Temproary Levee 254 LF $759.25 $192,849.50 $350.00 $88,900.00 $450.00 $114,300.00 $442.00 $112,268.00 0017 Pipe Conduit 42-inch 654 LF $341.00 $223,014.00 $240.00 $156,960.00 $200.00 $130,800.00 $226.00 $147,804.00 0018 Pipe Conduit 54-inch 1,084 LF $375.00 $406,500.00 $265.00 $287,260.00 $225.00 $243,900.00 $266.00 $288,344.00 0019 Pipe Conduit 66-inch 72 LF $443.00 $31,896.00 $425.00 $30,600.00 $175.00 $12,600.00 $347.00 $24,984.00 0020 Alignment and Right-of-Way Monumenting 1 JOB $10,395.00 $10,395.00 $35,000.00 $35,000.00 $75,000.00 $75,000.00 $25,000.00 $25,000.00 0021 Drainage Structures 44 EA $2,831.00 $124,564.00 $5,000.00 $220,000.00 $3,000.00 $132,000.00 $2,720.00 $119,680.00 0022 Salvaged Base Course 110,020 TN $27.01 $2,971,640.20 $8.00 $880,160.00 $12.00 $1,320,240.00 $10.00 $1,100,200.00 0023 Aggregate Base Course CL 5 17,863 TN $17.31 $309,208.53 $18.00 $321,534.00 $23.00 $410,849.00 $18.00 $321,534.00 0024 Aggregate Base Course CL 13 643 TN $22.90 $14,724.70 $20.00 $12,860.00 $33.00 $21,219.00 $20.00 $12,860.00 0025 I-29 SB Borrow Ditch Bridge 1 JOB $2,408,488.00 $2,408,488.00 $3,000,000.00 $3,000,000.00 $3,000,000.00 $3,000,000.00 $3,224,500.00 $3,224,500.00 0026 I-29 NB Borrow Ditch Bridge 1 JOB $2,408,488.00 $2,408,488.00 $3,000,000.00 $3,000,000.00 $3,000,000.00 $3,000,000.00 $3,224,500.00 $3,224,500.00 0027 County Road 18 Overpass Bridge 1 JOB $1,745,903.00 $1,745,903.00 $2,024,000.00 $2,024,000.00 $2,825,000.00 $2,825,000.00 $2,750,000.00 $2,750,000.00 0028 Steel Piling HP 10 x 42 3,150 LF $39.70 $125,055.00 $50.00 $157,500.00 $40.00 $126,000.00 $43.00 $135,450.00 0029 Steel Piling HP 14 x 73 3,900 LF $52.50 $204,750.00 $60.00 $234,000.00 $55.00 $214,500.00 $65.00 $253,500.00 0030 Steel Piling HP 14 x 102 5,940 LF $74.00 $439,560.00 $80.00 $475,200.00 $72.00 $427,680.00 $87.00 $516,780.00 0031 Concrete Bridge Approach Slab 913 SY $420.00 $383,460.00 $300.00 $273,900.00 $320.00 $292,160.00 $550.00 $502,150.00 0032 Asphalt Pavement 22,499 TN $94.72 $2,131,105.28 $97.00 $2,182,403.00 $85.00 $1,912,415.00 $101.00 $2,272,399.00 0033 Permanent I-29 Mainline Roadway Concrete Pavement 153,100 SY $50.16 $7,679,496.00 $50.00 $7,655,000.00 $49.36 $7,557,016.00 $60.00 $9,186,000.00 0034 Signs 1 JOB $132,105.00 $132,105.00 $130,000.00 $130,000.00 $2,000,000.00 $2,000,000.00 $175,000.00 $175,000.00 0035 Permanent Pavement Markings 1 JOB $63,030.00 $63,030.00 $150,000.00 $150,000.00 $2,000,000.00 $2,000,000.00 $300,000.00 $300,000.00 0036 Temporary Pavement Markings 1 JOB $526,152.00 $526,152.00 $89,500.00 $89,500.00 $750,000.00 $750,000.00 $550,000.00 $550,000.00 0037 Fence Woven Wire 75,221 LF $4.95 $372,343.95 $2.80 $210,618.80 $2.80 $210,618.80 $5.00 $376,105.00 0038 OHB Gate 2 EA $900.00 $1,800.00 $3,100.00 $6,200.00 $3,000.00 $6,000.00 $10,000.00 $20,000.00 0039 W-Beam Guardrail 1,765 LF $59.59 $105,176.35 $53.00 $93,545.00 $55.00 $97,075.00 $75.00 $132,375.00 0040 Topsoil 527,237 CY $4.11 $2,166,944.07 $9.00 $4,745,133.00 $4.00 $2,108,948.00 $8.00 $4,217,896.00 0041 Silt Fence 16,103 LF $2.35 $37,842.05 $4.00 $64,412.00 $2.99 $48,147.97 $3.50 $56,360.50 0042 Fiber Rolls 193,094 LF $2.35 $453,770.90 $2.55 $492,389.70 $2.45 $473,080.30 $3.50 $675,829.00 0043 Temporary Seeding & Stabilization 1 JOB $276,020.00 $276,020.00 $600,000.00 $600,000.00 $755,000.00 $755,000.00 $250,000.00 $250,000.00 0044 Permanent Seeding 300.4 ACRE $1,506.46 $452,540.58 $1,140.00 $342,456.00 $856.95 $257,427.78 $1,000.00 $300,400.00 0045 Prefabricated Vertical Wick Drains 800,000 LF $0.58 $464,000.00 $0.46 $368,000.00 $0.43 $344,000.00 $0.43 $344,000.00 0046 Granular Blanket Drain 24,630 CY $36.35 $895,300.50 $24.00 $591,120.00 $40.50 $997,515.00 $37.50 $923,625.00 0047 Preload Embankment 296,000 CY $9.85 $2,915,600.00 $6.00 $1,776,000.00 $6.00 $1,776,000.00 $7.50 $2,220,000.00 0048 Embankment Monitoring 1 JOB $182,450.00 $182,450.00 $50,000.00 $50,000.00 $50,000.00 $50,000.00 $100,000.00 $100,000.00 0049 Preload Removal 320,630 CY $4.56 $1,462,072.80 $6.00 $1,923,780.00 $6.25 $2,003,937.50 $6.00 $1,923,780.00 0050 Dam and Levee Embankment 34,615 CY $9.85 $340,957.75 $10.00 $346,150.00 $5.50 $190,382.50 $15.00 $519,225.00 0051 Riprap 11,670 CY $92.61 $1,080,758.70 $100.00 $1,167,000.00 $95.00 $1,108,650.00 $100.00 $1,167,000.00 0052 Inspection Trench 1,386 LF $14.40 $19,958.40 $30.00 $41,580.00 $14.00 $19,404.00 $40.00 $55,440.00
TOTAL BASE BID (Items 0001 through 0052 Included) $47,202,939.31 $56,921,474.50 $55,623,630.30 $54,806,544.70
Industrial Builders Inc.
1307 County Rd 17 N.
West Fargo, ND 58078
Ames Construction 2500 County Road 42 W
Burnsville, MN 55337
Central Specialties, Inc.
6325 Co. Rd. 87 SW
Alexandria, MN 56308 Government Estimate
OPTION A MAINLINE - CONCRETE SHOULDER
1001 Salvaged Base Course 27,518 TN $27.01 $743,261.18 $10.00 $275,180.00 $12.00 $330,216.00 $7.50 $206,385.00 1002 Permanent Concrete Shoulder Pavement 38,624 SY $52.00 $2,008,448.00 $62.00 $2,394,688.00 $49.00 $1,892,576.00 $60.00 $2,317,440.00
Total Option A $2,751,709.18 $2,669,868.00 $2,222,792.00 $2,523,825.00
OPTION B MAINLINE - ASPHALT SHOULDER
1003 Salvaged Base Course 38,624 TN $27.00 $1,042,848.00 $9.50 $366,928.00 $12.00 $463,488.00 $8.00 $308,992.00 1004 Permanent Roadway Asphalt Shoulder Pavement 8,882 TN $96.06 $853,204.92 $108.70 $965,473.40 $78.52 $697,414.64 $82.50 $732,765.00
Total Option B $1,896,052.92 $1,332,401.40 $1,160,902.64 $1,041,757.00
OPTION C TEMPORARY BYPASS - CONCRETE
1005 Pavement Removal 172,868 TN $12.00 $2,074,416.00 $9.50 $1,642,246.00 $12.60 $2,178,136.80 $15.00 $2,593,020.00 1006 Common Excavation 507,628 CY $3.72 $1,888,376.16 $7.00 $3,553,396.00 $3.60 $1,827,460.80 $3.00 $1,522,884.00 1007 Borrow Excavation 233,848 CY $7.00 $1,636,936.00 $14.00 $3,273,872.00 $10.25 $2,396,942.00 $9.00 $2,104,632.00 1008 Aggregate Base Course CL 5 85,079 TN $18.07 $1,537,377.53 $15.50 $1,318,724.50 $21.10 $1,795,166.90 $19.00 $1,616,501.00 1009 Temporary Shoulder Concrete Pavement 31,934 SY $52.00 $1,660,568.00 $62.00 $1,979,908.00 $54.00 $1,724,436.00 $49.50 $1,580,733.00 1010 Temporary Roadway Concrete Pavement 129,408 SY $78.28 $10,130,058.24 $60.00 $7,764,480.00 $58.79 $7,607,896.32 $54.30 $7,026,854.40
Total Option C $18,927,731.93 $19,532,626.50 $17,530,038.82 $16,444,624.40
OPTION D TEMPORARY BYPASS - ASPHALT
1011 Pavement Removal 250,645 TN $12.00 $3,007,740.00 $7.50 $1,879,837.50 $9.05 $2,268,337.25 $5.30 $1,328,418.50 1012 Common Excavation 461,392 CY $3.77 $1,739,447.84 $6.00 $2,768,352.00 $3.60 $1,661,011.20 $3.10 $1,430,315.20 1013 Borrow Excavation 176,894 CY $7.00 $1,238,258.00 $14.00 $2,476,516.00 $9.25 $1,636,269.50 $9.55 $1,689,337.70 1014 Aggregate Base Course CL 5 190,679 TN $17.14 $3,268,238.06 $15.50 $2,955,524.50 $15.10 $2,879,252.90 $15.50 $2,955,524.50 1015 Temporary Asphalt Pavement 59,966 TN $95.28 $5,713,560.48 $66.00 $3,957,756.00 $58.56 $3,511,608.96 $62.00 $3,717,892.00
Total Option D $14,967,244.38 $14,037,986.00 $11,956,479.81 $11,121,487.90
Total Base Plus Options A and C $68,882,380.42 $79,123,969.00 $75,376,461.12 $73,774,994.10
Total Base Plus Options A and D $64,921,892.87 $73,629,328.50 $69,802,902.11 $68,451,857.60
Total Base Plus Options B and C $68,026,724.16 $77,786,502.40 $74,314,571.76 $72,292,926.10
Total Base Plus Options B and D $64,066,236.61 $72,291,861.90 $68,741,012.75 $66,969,789.60
I certify that I have opened, read, and recorded on this abstract all offers received in response to this solicitation.
Kevin P. Henricks Contracting Officer
| 2021-03-11T22:04:38-0600 | |
| HENRICKS.KEVIN.PHILIP.1249726873 |