W81G6700987813

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this amendment is to extend the solicitation closing date and extend the delivery date.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 3

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 14-May-2020

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912ES20T0054

X 9B. DATED (SEE ITEM 11)

21-Apr-2020

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

14-May-2020

CODE

CONTRACTING DIVISION

USACE - ST. PAUL

180 5TH STREET E SUITE 700

ST. PAUL MN 55101-1678

W912ES 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912ES20T0054

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 1449 - CONTINUATION SHEET

SOLICITATION/CONTRACT FORM

The required response date/time has changed from 11-May-2020 05:00 PM to 20-May-2020 05:00 PM.

DELIVERIES AND PERFORMANCE

The following Delivery Schedule item for CLIN 0001 has been changed from:

DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /

CAGE

02-JUL-2020 52 FOUNTAIN CITY SERVICE

FOUNTAIN CITY

431 NORTH SHORE DRIVE

PO BOX 397

FOUNTAIN CITY WI 54629-0397

608-687-3011 FOB: Destination

B6M0LD2

To:

DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /

CAGE

31-AUG-2020 52 FOUNTAIN CITY SERVICE

FOUNTAIN CITY

431 NORTH SHORE DRIVE

PO BOX 397

FOUNTAIN CITY WI 54629-0397

608-687-3011 FOB: Destination

B6M0LD2

The following have been modified:

DESCRIPTION

SCOPE OF WORK

Cam Limit Switches for Miter Gates and Tainter Valves U.S. Army Corps of Engineers, St. Paul District

The Contractor shall provide a total of fifty two (52) replacement Rotating Cam Limit Switch Rebuild Kits for Locks and Dams 2 through 10 and deliver all of them to the Fountain City Service Base. These kits shall be right-handed (if applicable for printed numbers, stickers, and information). U.S. Army Corps of Engineers Operations will then transport the required number for each site to their respective locations.

W912ES20T0054

1. General Description.

Each lock chamber within the district has four (4) tainter valves and four (4) miter gates that utilize rotating “cam-style” limit switch assemblies to control motor speed, timing and proximity.

1.1 Submittals

The Contractor shall submit the below for review and approval. The following submittals are required:

a. Product Data The Contractor shall submit shop drawings, catalog cuts, and material certifications WITH THEIR QUOTE to the Government for the furnished rotating switch cam limit switch assembly. This data shall clearly indicate compliance with the requirements of the specifications below. The cam limit switch kit shall meet or exceed the listed specifications. The Contractor shall also provide the name of the manufacturer.

1.2 Delivery and Shipment

The Contractor shall provide the cam limit switch assemblies no later than 31 August 2020 to the below address:

U.S. Army Corps of Engineers 431 North Shore Fountain City, WI 54629

The Contractor is responsible for all shipping / delivery costs. Delivery shall be between the hours of 8:00 A.M. and 3:00 P.M., Monday thru Friday, except on Federal holidays.

2. Equipment Specifications

2.1. Rotating Cam Limit Switch Kit

The cam limit switch rebuild kit consists of a camshaft, six (6) 6” aluminum cams, two (2) brackets, two (2) bearings, six (6) industrial-duty snap switches, six (6) roller follower adapter assemblies, and all necessary installation hardware for the kit. SPDT (single pole double throw) snap switches shall have a sealed plunger and all parts shall be corrosion resistant. The switch adjustment shall have a control ranging from 6 to 354 degrees. The assembly shall be designed to withstand outdoor temperatures from -30oF to +110oF at a minimum.

2.2 Equipment Warranty

The Contractor shall submit the manufacturer’s standard warranty or guarantee for equipment no later than 5 business days after delivery.

(End of Summary of Changes)