W81G6752179651
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this Amendment is to respond to Contractor questions and revise paragraph 3c.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 2
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 20-Aug-2015
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912ES-15-T-0138
X 9B. DATED (SEE ITEM 11)
11-Aug-2015
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
20-Aug-2015
CODE
CONTRACTING DIVISION
USACE - ST. PAUL
180 5TH STREET E SUITE 700
ST. PAUL MN 55101-1678
W912ES 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912ES-15-T-0138
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE
The following have been added by full text:
CONTRACTOR QUESTION
Question: The contract calls for the Contractor to reposition rootballs, but if not feasible, "the root-ball should be removed from the site." Does this mean to haul off the intact rootball, or can we grind it before removing it?
ANS: IF THE ROOTBALLS CANNOT BE REPOSITIONED, THEY MUST BE REMOVED.
FOLLOWING REMOVAL, THEY CAN BE HAULED OFF-SITE INTACT, OR GROUND AND
THEN THE CHIPS, DETRIS AND DEBRIS MUST BE HAULED OFF SITE AND DISPOSED OF
OFF SITE.
Question: What is meant by "filter fabric" when a rootball is removed? ("Sediments should be covered with filter fabric and then covered with fill...") Do you have a product in mind?
ANS: EITHER FILTER FABRIC OR LANDSCAPING FABRIC IS ACCEPTABLE.
REVISE PARAGRAPH 3C
c. Repositioning of Root-balls: All dislodged root-balls shall be returned to their original position with minimal disturbance of soil.
If it is not feasible to return the root-ball to its original position, the root-ball shall be removed from the site. The rootball may be hauled off site intact, or may be ground before removal from the site. Prior to removal, sediments adhering to exposed roots should be removed. Techniques such as manual vibration or machine assisted shaking shall be utilized to remove these sediments. Sediments should be covered with filter fabric and then covered with fill from a borrow source outside of the campground. Fill may not be excavated within the boundaries of the Corps property. The COR shall be notified and must give his or her concurrence before removal of rootballs.
Add sentence in red to SOW
(End of Summary of Changes)