W912ES11B0008-Technical_Specs.pdf
PDF 3 MB Posted
- Attached to
- Advance Measures, Tolna Coulee, Nelson County, ND Federal contract opportunity
- Solicitation number
- W912ES-11-B-0008
About this file
Specifications W912ES-11-B-0008
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 11b0008.pdf | ||
| W912ES-11-B-0009 ABSTRACT.pdf | ||
| Amendment 0004.pdf | ||
| Amendment 0003.pdf | ||
| Amend 0002.pdf | ||
| TC_USACE_Testing_110819.pdf | ||
| TLNCL_boring_log_sheets_AmendNo2_HALFSIZE.pdf | ||
| TLNCL_boring_log_sheets_AmendNo2_FULLSIZE.pdf | ||
| Amend 0001.pdf | ||
| W912ES11B0008-Tolna_Coulee_Drawings-11X17_7-29-11.pdf | ||
| SOLICITATION W912ES-11-B-0008.pdf | ||
| W912ES11B0008-Tolna_Coulee_Drawings-22x34_7-29-11.pdf |
Show all 12
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation No. W912ES-11-B-0008
DEVILS LAKE SUB RIVER BASIN
NELSON COUNTY
DEVILS LAKE, NORTH DAKOTA
CONSTRUCTION
DOCUMENTS FOR
TOLNA COULEE
ADVANCE MEASURES
July 2011
US Army CorpsUS Army Corps Of EngineersOf Engineers St. Paul DistrictSt. Paul District
THIS SHEET LEFT INTETIONALLY BLANK FOR PRINTING
TOLNA COULEE ADVANCE MEASURES
PROJECT TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00.00 13 GENERAL
01 14 00.00 13 WORK RESTRICTIONS
01 22 00.00 13 MEASUREMENT AND PAYMENT
01 32 01.00 13 PROJECT SCHEDULE
01 33 00 SUBMITTAL PROCEDURES
01 35 29.00 13 SAFETY AND OCCUPATIONAL HEALTH REQUIREMENTS
01 41 26.00 13 NORTH DAKOTA POLLUTANT DISCHARGE ELIMINATION SYSTEM
01 45 02.00 10 QUALITY CONTROL SYSTEM (QCS)
01 45 04.00 13 CONTRACTOR QUALITY CONTROL
01 50 02.00 13 TEMPORARY CONSTRUCTION FACILITIES
01 57 20.00 13 ENVIRONMENTAL PROTECTION
01 71 23.00 13 CONTRACTOR SURVEYS
01 78 02.00 10 CLOSEOUT SUBMITTALS
DIVISION 03 - CONCRETE
03 11 13.00 10 STRUCTURAL CAST-IN-PLACE CONCRETE FORMING
03 15 13.00 10 EXPANSION JOINTS, CONTRACTION JOINTS, AND WATERSTOPS
03 20 01.00 10 CONCRETE REINFORCEMENT
03 31 00.00 10 CAST-IN-PLACE STRUCTURAL CONCRETE
DIVISION 05 - METALS
05 50 14 STRUCTURAL METAL FABRICATIONS
05 50 15 CIVIL WORKS FABRICATIONS
DIVISION 31 - EARTHWORK
31 00 00.00 13 EARTHWORK
31 11 00 CLEARING AND GRUBBING
31 41 16 METAL SHEET PILING
DIVISION 32 - EXTERIOR IMPROVEMENTS
32 11 16.00 13 AGGREGATE BASE COURSE
32 31 13.53 CHAIN-LINK FENCES AND GATES
32 92 19.00 13 SEEDING
DIVISION 33 - UTILITIES
33 40 00 STORM DRAINAGE UTILITIES
DIVISION 35 - WATERWAY AND MARINE CONSTRUCTION
35 20 14 STOPLOG SYSTEM
35 31 19.00 13 SLOPE PROTECTION
35 60 00 COFFERDAM AND DEWATERING SYSTEM
35 73 13 EMBANKMENT
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 1
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 00 00.00 13
GENERAL
PART 1 GENERAL
1.1 ORGANIZATION OF SPECIFICATIONS
1.2 USE OF REFERENCES
1.3 MEASUREMENT AND PAYMENT
PART 2 PRODUCTS
2.1 RECYCLED/RECOVERED MATERIALS
PART 3 EXECUTION
3.1 DISPOSAL OF DEBRIS AND WASTE
3.1.1 Burning
3.1.2 Disposal offsite for useful purposes
3.1.3 Disposal in a locally operated sanitary landfill
3.1.4 Disposal of Solid Construction Debris and Waste
3.2 SCHEDULING
3.2.1 General
3.2.2 Notification
3.3 OTHER CONTRACTS
-- End of Section Table of Contents --
SECTION 01 00 00.00 13 Page 1 W912ES-11B-0008
SECTION 01 00 00.00 13
GENERAL
PART 1 GENERAL
1.1 ORGANIZATION OF SPECIFICATIONS
The specifications which govern the materials and equipment to be furnished and the work to be performed under this contract are listed in the Table of Contents. No attempt has been made in the specifications to segregate work to be performed by any trade, craft, or subcontractor. Any segregation between the trades or crafts shall be solely a matter for agreement between the Contractor, Contractor's employees, and subcontractors.
1.2 USE OF REFERENCES
Reference to the standards, specifications, or codes of any technical society, organization, or association, or local, State, or Federal authority shall mean the specific edition or revision listed.
Various publications are referenced in other sections of the specifications to establish requirements for the work. Any referenced publication is to be used solely for technical requirements. Measurement and payment and any other matters respecting the administration of this contract shall be governed by the terms of this contract without considering any referenced publication. These references are identified in each section by document number, date and title. The addresses, phone numbers, and Internet addresses (if available) for references cited in these specifications are available on the TECHINFO page of the Corps of Engineers Huntsville District Internet site: http://www.hnd.usace.army.mil/.
1.3 MEASUREMENT AND PAYMENT
The Contractor shall be responsible for the work of this section, without any direct compensation being made other than the payment received for contract line items on the bidding schedule.
PART 2 PRODUCTS
2.1 RECYCLED/RECOVERED MATERIALS
Government procurement policy is to acquire, in a cost effective manner, items containing the highest percentage of recycled and recovered materials practicable consistent with maintaining a satisfactory level of competition without adversely affecting performance requirements or exposing suppliers' employees to undue hazards from the recovered materials. The Environmental Protection Agency (EPA) has designated certain items which must contain a specified percent range of recovered or recycled materials. EPA designated products specified in this contract comply with the stated policy and with the EPA guidelines. The Contractor shall make all reasonable efforts to use recycled and recovered materials in providing the EPA designated products and in otherwise utilizing recycled and recovered materials in the execution of the work.
SECTION 01 00 00.00 13 Page 2 W912ES-11B-0008
PART 3 EXECUTION
3.1 DISPOSAL OF DEBRIS AND WASTE
The Contractor's attention is directed to Section 01 57 20.00 13 ENVIRONMENTAL PROTECTION and to the following CONTRACT CLAUSES: 52.236-7
PERMITS AND RESPONSIBILITIES; 52.236-9 PROTECTION OF EXISTING VEGETATION,
STRUCTURES, EQUIPMENT, UTILITIES, AND IMPROVEMENTS; 52.236-10 OPERATIONS
AND STORAGE AREAS; and 52.236-12 CLEANING UP. Burning will not be permitted at the project site and debris or waste shall not be left on the site. Disposal of clearing and grubbing debris shall be by one of the following methods:
3.1.1 Burning
Burning will not be permitted at the project site.
3.1.2 Disposal offsite for useful purposes
In the interest of conservation, it is required that the Contractor make a reasonable effort to dispose of the material offsite for some useful purpose. Timber may be cut into convenient lengths and utilized for making saw logs, posts, cordwood, wood chips for paper making or other uses, or other similar use.
3.1.3 Disposal in a locally operated sanitary landfill
Contractor shall select the disposal site with the approval of the Contracting Officer. The Contractor shall secure the required permits for disposal and provide copies of the permit to the Contracting Officer.
3.1.4 Disposal of Solid Construction Debris and Waste
Disposal of Solid Construction Debris and Waste shall consist of removal from the construction site and disposal in compliance with Federal, State, and local requirements for solid waste disposal. Contractor shall select the disposal site with the approval of the Contracting Officer.
3.2 SCHEDULING
3.2.1 General
It shall be the responsibility of the Contractor to schedule and execute the work, incorporating the necessary requirements set forth in these specifications. The Contractor shall develop and submit a schedule in accordance with CONTRACT CLAUSE: 52.236-15 SCHEDULES FOR CONSTRUCTION
CONTRACTS.
3.2.2 Notification
The Contractor shall inform the Government in writing within 5 days after receipt of notice to proceed and before work begins as to which hours of the day and days of the week for which work under this contract will be performed. The Contractor shall notify the Government at least 24 hours before work is to be conducted on overtime, in multiple shifts, on weekends, or on Federal government holidays.
SECTION 01 00 00.00 13 Page 3 W912ES-11B-0008
3.3 OTHER CONTRACTS
The Contractor shall coordinate with other contractors in the performance of the work and schedule such work to provide for a minimum of delays and interferences. Coordination shall be through the Contracting Officer.
Work listed below is currently required under separate contract or is scheduled to be awarded as a separate contract prior to completion of work under this contract. These contracts will be considered in the application of CONTRACT CLAUSE: 52.236-8 OTHER CONTRACTS.
The volume of work within the region may create resource shortages. The following projects are not in the immediate area of the current project but are shown to make the contractor aware of other heavy construction projects within the region. The Corps of Engineers is aware of the following other heavy construction projects being planned or undertaken in the vicinity of Devils Lake, North Dakota:
1. Devils Lake City Embankments Phase 1 Creel Bay Reach - Contract W912ES-10-C-0001, construction scheduled for completion November 2011.
2. Devils Lake City Embankments Phase 2A - Contract W912ES-10-C-0021, construction scheduled for completion November 2011.
3. Devils Lake City Embankments Phase 2B/East Ditch Pump Station - Contract W912ES-11-B-0006, construction scheduled for completion November 2012.
4. Devils Lake City Embankments Phase 3 - Contract W912ES-11-B-0005, construction scheduled for completion November 2012.
5. NDDOT Highway 20 Road Improvements - Construction scheduled for completion Fall 2011.
6. NDDOT Highway 19 Road Improvements - Construction scheduled for completion Fall 2011.
The North Dakota State Water Commission is considering constructing a new outlet at the east end of Devils Lake. The current East End Outlet Alignment and Alternatives can be attained via the North Dakota State Water Commission, or at the following website:
http://www.swc.state.nd.us/4dlink9/4dcgi/GetSubCategoryRecord/Devils%20Lake%20Flooding/Ou
-- End of Section --
SECTION 01 00 00.00 13 Page 4 W912ES-11B-0008
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 14 00.00 13
WORK RESTRICTIONS
PART 1 GENERAL
1.1 MEASUREMENT AND PAYMENT
1.2 GROUNDS AND ROADWAYS
1.2.1 Parking
1.2.2 Snow Removal
1.3 BLASTING
PART 2 PRODUCTS
PART 3 EXECUTION
3.1 EXISTING UTILITIES
3.1.1 General
3.1.2 North Dakota One Call Excavation Notice System
3.2 PROTECTION OF TREES
3.2.1 Restoration of Damaged Trees
3.3 PROTECTION OF ADJACENT AREAS
3.4 ORDER OF WORK
3.4.1 Installation of Sheet Pile
3.4.2 Riprap and Geotextile
SECTION 01 14 00.00 13 Page 1 W912ES-11B-0008
SECTION 01 14 00.00 13
WORK RESTRICTIONS
PART 1 GENERAL
1.1 MEASUREMENT AND PAYMENT
The Contractor shall be responsible for the work of this section, without any direct compensation being made other than the payment received for contract items.
1.2 GROUNDS AND ROADWAYS
1.2.1 Parking
Contractor parking, including the Contractor's staging area shall be coordinated with the Government.
1.2.2 Snow Removal
The Contractor shall be responsible for all snow removal and storage in the access road, work area, staging area,and designated parking areas through contract completion.
1.3 BLASTING
Blasting will not be permitted.
PART 2 PRODUCTS (Not used)
PART 3 EXECUTION
3.1 EXISTING UTILITIES
3.1.1 General
No utilities are known to exist within the work limits. The Contractor shall be responsible for ordering utility locates prior to any excavation.
In the event the Contractor does encounter an existing utility line, report thereof shall be made immediately to the Contracting Officer. The Contractor shall be responsible for all costs related to protecting existing utilities and repair of any damaged utilities shall be in accordance with CLAUSE 52.236-9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND IMPROVEMENTS.
3.1.2 North Dakota One Call Excavation Notice System
For contract work performed within the State of North Dakota, the Contractor shall meet the requirements of North Dakota Statutes, Chapter 42-23 "One Call Excavation Notice System." The North Dakota One Call notification center telephone numbers are:
Hotline 800-795-0555 Administration 701-475-2942
SECTION 01 14 00.00 13 Page 2 W912ES-11B-0008
The website for North Dakota One Call is listed below:
Website http://www.ndonecall.com/
3.2 PROTECTION OF TREES
Trees to be protected shall be determined and staked by the Contracting Officer. The following measures shall be implemented for tree protection and shall be addressed in the Environmental Protection Plan required under Section 01 57 20.00 13 ENVIRONMENTAL PROTECTION:
a. The trees shall be protected from wounds to the bark and foliage.
b. The critical root zone shall be protected from compaction and grading.
c. Changes in temporary site drainage and ponding that affect the protected trees shall be minimized to the extent possible.
The critical root zone of trees designated to be protected shall be surrounded by a high visibility fence 4 feet in height, supplied and erected by the Contractor. The critical root zone shall be defined by an area extending 1.5 feet radius from each tree for each inch of Diameter at Breast Height (DBH). The fence shall be securely erected and installed prior to any movement through the project site by construction vehicles or equipment, and remain in place until construction and clean-up are completed. The critical root zone shall remain free of all construction activities including trenching, staging, stockpiling and storage of materials. Vehicles and equipment shall not drive or park within the critical root zone. Variation to the critical root zone size or configuration will only be permitted where it is absolutely necessary for construction of the project, and requires approval of the Contracting Officer. Short duration alterations of the critical root zone involving wood chips and limited equipment travel shall be submitted in writing for approval.
3.2.1 Restoration of Damaged Trees
Any existing tree designated to be protected that is damaged by the Contractor's operations shall be replaced. Trees will be considered damaged if the critical root zone in cohesive soils is compacted, if there are significant wounds that could contribute to rot, or if distress (evident by reduced growth or other observations of distress documented by a forester) is observed prior to closing the contract. Trees shall be replaced in kind on a caliper inch per caliper inch basis (DBH) (e.g. one 6-inch red oak shall be replaced with two 3-inch red oaks, three 2-inch red oaks, or six 1-inch red oaks). The Contractor shall warrant that the replacement trees remain viable and disease free for a period of not less than one year from date of acceptance of the replacement trees.
Replacement tree size and location will be determined and staked by the Contracting Officer. Repair by pruning, aeration, soil conditioning, or other recommendation from a qualified forester will be considered by the Contracting Officer for substitution for replacement.
3.3 PROTECTION OF ADJACENT AREAS
The Contractor shall not operate equipment in vegetated areas outside the work limits.
SECTION 01 14 00.00 13 Page 3 W912ES-11B-0008
3.4 ORDER OF WORK
The Contractor shall plan and perform the work in a manner that takes into account freezing temperatures and inclimate weather expected during the contract period in the project area. In recognition of these conditions, embankment work shall be prosecuted in a manner that results in the embankment being constructed in accordance with Section 35 73 13 EMBANKMENT, specifically with regard to that sections requirements for frozen materials and frozen foundations. Once embankment construction has started, it shall commence uninterrupted 24 hours per day, 7 days per week until it is complete.
3.4.1 Installation of Sheet Pile
Sheet pile for the I-wall/embankment composite system shall not be installed until the embankment work is complete in the area that the sheet pile is to be installed. The sheet pile shall be driven through the completed embankment material, and shall not be driven within 100 feet of concrete less than 7 days old.
3.4.2 Riprap and Geotextile
The Contractor shall not drive pile through the Geotextile material. The Contractor may install the geotextile and riprap before or after the sheet pile is installed.
SECTION 01 14 00.00 13 Page 4 W912ES-11B-0008
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 22 00.00 13
MEASUREMENT AND PAYMENT
PART 1 GENERAL
1.1 REFERENCES
1.2 APPROVAL OF MATERIALS OR ALTERNATES
1.3 COMPENSATION
1.4 QUANTITY SURVEYS
1.5 MEASUREMENT BY WEIGHT
1.5.1 Determination of Excess Bulk Materials
1.5.2 Final Surveys
1.6 MEASUREMENT UNITS
1.7 UNIT PRICE PAYMENT ITEMS
1.7.1 24" CMP Culverts
1.7.1.1 Payment
1.7.1.2 Measurement
1.7.1.3 Unit of Measure
1.7.2 24" CMP End Sections (CMP)
1.7.2.1 Payment
1.7.2.2 Measurement
1.7.2.3 Unit of Measure
1.7.3 Stripping
1.7.3.1 Payment
1.7.3.2 Measurement
1.7.3.3 Unit of Measure
1.7.4 Excavation
1.7.4.1 Payment
1.7.4.2 Measurement
1.7.4.3 Unit of Measure
1.7.5 Fill
1.7.5.1 Payment
1.7.5.2 Measurement
1.7.5.3 Unit of Measure
1.7.6 Sheet Pile
1.7.6.1 Payment
1.7.6.2 Measurement
1.7.6.3 Unit of Measure
1.7.7 Geotextile
1.7.7.1 Payment
1.7.7.2 Measurement
1.7.7.3 Unit of Measure
1.7.8 Bedding
1.7.8.1 Payment
1.7.8.2 Measurement
1.7.8.3 Unit of Measure
1.7.9 Riprap
1.7.9.1 Payment
1.7.9.2 Measurement
1.7.9.3 Unit of Measure
1.7.10 Aggregate Base Course
1.7.10.1 Payment
1.7.10.2 Measurement
SECTION 01 22 00.00 13 Page 1 W912ES-11B-0008
1.7.10.3 Unit of Measure
1.7.11 Topsoil and Seed
1.7.11.1 Payment
1.7.11.2 Measurement
1.7.11.3 Unit of Measure
1.8 LUMP SUM PAYMENT ITEMS
1.8.1 Performance and Payment Bonds
1.8.1.1 Payment
1.8.1.2 Unit of Measure
1.8.2 Existing Fence Modifications
1.8.2.1 Payment
1.8.2.2 Unit of Measure
1.8.3 Cofferdams and Dewatering
1.8.3.1 Payment
1.8.3.2 Unit of Measure
1.8.4 Control Structure
1.8.4.1 Payment
1.8.4.2 Unit of Measure
1.8.5 Stop Log System
1.8.5.1 Payment
1.8.5.2 Unit of Measure
1.8.6 Instrumentation
1.8.6.1 Payment
1.8.6.2 Unit of Measure
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION (Not Applicable)
SECTION 01 22 00.00 13 Page 2 W912ES-11B-0008
SECTION 01 22 00.00 13
MEASUREMENT AND PAYMENT
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by basic designation only.
NATIONAL INSTITUTE OF STANDARDS AND TECHNOLOGY (NIST)
NIST HB 44 (2010) Specifications, Tolerances, and Other Technical Requirements for Weighing and Measuring Devices
1.2 APPROVAL OF MATERIALS OR ALTERNATES
Requests for approval of materials and products, or substitutes thereof, will not be considered prior to award of the contract.
1.3 COMPENSATION
Payment for each contract line item provided for in the contract bid schedule shall constitute full compensation for all costs associated with furnishing all material and constructing the work in place, complete, fully functional and operational, in a complete and acceptable manner, in compliance with all contract requirements, and for all costs associated with but not limited to:
Furnishing all plant, labor, tools, supplies, materials, and equipment, Performing all associated Contractor Quality Control, providing all supervision and administration, complying with all environmental protection rules and regulations and requirements, meeting all safety requirements, providing all tests and reports as required and as necessary to assure that all contract requirements are met, and
Assuming all risk, loss, damage, and expense arising out of the nature of the work or its prosecution, subject to conditions of the contract.
1.4 QUANTITY SURVEYS
The Contractor shall provide quantity surveys for bulk materials measured by volume, unless an alternate method of measurement is specified.
Quantity surveys are specified in Section 01 71 23.00 13 CONTRACTOR SURVEYS.
1.5 MEASUREMENT BY WEIGHT
Bulk materials paid for by weight will be measured for payment by the ton (TN) (2,000 pounds avoirdupois), by weighing each truck loaded with material on an approved scale. Scales shall be of sufficient length to permit simultaneous weighing of all axle loads and shall be accurate to within 0.2 percent throughout the range of the scales. Prior to weighing any bulk materials the scale's accuracy shall conform to the applicable requirements of NIST HB 44 and shall be certified by an acceptable scales
SECTION 01 22 00.00 13 Page 3 W912ES-11B-0008 servicing company representative or by an inspector of the State Inspection Bureau charged with scales inspection within the state in which the project is located. The scales shall be capable of printing a weight ticket including time, date, truck number, and weight. If commercial scales are readily available in close proximity of site of work, documentation shall be submitted certifying that the scales meet the requirements of the specification. The Contracting Officer may elect to accept certified weight certificates furnished by a public weighmaster in lieu of scale weights at the jobsite. Scales will be checked and certified before hauling bulk materials and after each 50,000 tons increment of bulk materials weighed under this contract. As a minimum, each ticket shall contain the following information:
(1) Date and time.
(2) Vehicle number.
(3) Gross weight.
(4) Vehicle tare weight.
(5) Net weight.
(6) Job total for material weighed.
(7) Signature of weighmaster.
(8) Signature of Contractor's receiver.
Bulk materials stockpiled on the worksite will not be required to be re-weighed prior to placement.
1.5.1 Determination of Excess Bulk Materials
All bulk materials outside the limits and tolerances of the cross sections will be deducted from the quantity of new bulk materials for which payment is to be made. Weight of excess bulk materials will be determined from the cross sections obtained by the method provided for in paragraph Final Surveys below, on the basis that the cubic feet of volume (including voids) for each type of bulk materials, as listed in the Table in paragraph FACTORS USED FOR CONVERTING IN PLACE VOLUME TO WEIGHT of Section 35 31 19.00 13 SLOPE PROTECTION, is equal to one ton or 2,000 pounds for the bulk specific gravity and percentage of voids shown. If the bulk specific gravity of the stone furnished or the percentage of voids is other than as listed below, the cubic feet of volume equaling 2,000 pounds shall be recomputed as described in paragraph REVISION OF BID SCHEDULE QUANTITIES of Section 35 31 19.00 13 SLOPE PROTECTION. Should any excess bulk materials be disclosed above the tolerance line as defined in paragraph CONSTRUCTION TOLERANCES of Section 35 31 19.00 13 SLOPE PROTECTION, its volume will be computed by the average end area method, based upon the cross section in the following manner. The average end area of excess bulk materials above the tolerance line for two (2) successive cross sections, multiplied by the distance between the cross sections will be accepted as the volume. The Contractor will not be required to remove such excess bulk materials and deductions for the weights thereof will be made from contract payments for new stone. In addition to the above, bulk materials, which has been delivered to the site and has been lost or wasted or otherwise not properly incorporated into the final required work, shall be deducted from the quantity for which payment is to be made.
1.5.2 Final Surveys
Survey work and measurements required for determination of excess volume computations for bulk materials shall be performed in the presence of the Contracting Officer. Notify the Contracting Officer not less than 3 days in advance of each survey. In the event of unavailability of the
SECTION 01 22 00.00 13 Page 4 W912ES-11B-0008
Contracting Officer, perform the survey and certify to the Contracting Officer that it complies with the specifications. Cross section surveys shall be taken perpendicular to the axis of the structures. Elevations and soundings shall be taken on lines 50 feet apart measuring along the structure reference line, with the readings at 5-foot intervals and at breaks in the grade along the line. Other survey intervals and readings may be used if deemed appropriate or advisable by the Contracting Officer.
Additional cross sections, elevations, and soundings may be taken if determined necessary by the Contracting Officer. Determination of quantities will be made by the Government's on-site representative and having once been made, will not reopen, except on evidence of collusion, fraud or obvious error. Prior to performing any work under this Section, coordinate all operations with the Contracting Officer so that excess volume surveys will be made at the appropriate time. Bulk materials quantity computations shall be based entirely upon weights of new bulk materials as determined from carrier displacement or certified scale weight tickets. Existing bulk materials placed in lieu of new bulk materials from off-site sources is excluded from measurement and payment.
1.6 MEASUREMENT UNITS
When materials are measured in units other than the measurement units specified as the basis of payment, the measured quantities shall be converted to the specified unit of measure. Factors for conversions from one basis or unit of measurement to another shall be approved by the Contracting Officer.
1.7 UNIT PRICE PAYMENT ITEMS
Payment items for the work of this contract are listed in the BIDDING SCHEDULE and described below. The payment items provided for on the bidding schedule embody the majority of the work; but the work descriptions provided below do not specifically discuss all incidental work required to complete the contract work.
The unit price and payment made for each item listed shall constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for each of the unit price items.
1.7.1 24" CMP Culverts
1.7.1.1 Payment
Payment will be made for furnishing all materials, equipment and labor and performing all operations necessary for supplying and installing the corrugated metal pipe as shown and specified. Items of work include, but are not limited to excavation and backfill; control of ground water;
furnishing and installing corrugated metal pipe and jointing materials, and bedding. Include costs for all work in other sections containing associated requirements.
1.7.1.2 Measurement
Corrugated metal pipe shall be measured after acceptable installation. The measured length shall be the distance between the upstream and downstream ends of the corrugated metal pipe, not including the end sections. The actual measured length shall be rounded to the nearest foot for payment
SECTION 01 22 00.00 13 Page 5 W912ES-11B-0008 purposes.
1.7.1.3 Unit of Measure
Unit of measure: linear foot.
1.7.2 24" CMP End Sections (CMP)
1.7.2.1 Payment
Payment will be made for furnishing all materials, equipment and labor and performing all operations necessary for supplying and installing the corrugated metal pipe end sections as shown and specified. Items of work include, but are not limited to excavation and backfill; control of ground water; furnishing and installing all corrugated metal pipe flared end sections and jointing materials, and bedding. Include costs for all work in other sections containing associated requirements.
1.7.2.2 Measurement
Corrugated metal pipe end sections shall be measured for payment by each end section acceptably installed.
1.7.2.3 Unit of Measure
Unit of measure: each.
1.7.3 Stripping
1.7.3.1 Payment
Payment will be made for furnishing all materials, equipment and labor and performing all operations necessary for completing the stripping as shown and specified. Items of work include, but are not limited to removing material designated to be stripped, transporting stripped material to stockpiles or if suitable for use as topsoil to areas already graded and prepared for topsoil, transporting stripped material to off site disposal, clearing and grubbing, and all work in other sections containing associated requirements.
1.7.3.2 Measurement
Stripping shall be measured for payment in the original position, using the average-end-area method based on the original ground lines, as determined by the surveys required in SECTION 01 71 23.00 13, CONTRACTOR SURVEYS, and the lines and grades as shown or directed by the CO.
Materials stripped outside the lines and grades shown, without specific direction or approval from the Contracting Officer will not be measured for payment.
Material stripped outside the lines and grades as shown or directed by the CO, but within the specified tolerance will not be measured for payment.
Material stripped prior to the taking of elevations and measurements of the undisturbed grade will not be measured for payment.
SECTION 01 22 00.00 13 Page 6 W912ES-11B-0008
1.7.3.3 Unit of Measure
Unit of measure: cubic yard
1.7.4 Excavation
1.7.4.1 Payment
Payment will be made for furnishing all materials, equipment and labor and performing all operations necessary for performing excavation as shown and specified. Items of work include, but are not limited to excavation as indicated on the embankment sections and access road sections; transporting excavated material to stockpiles or to areas already prepared for embankment construction; transporting excess or unsatisfactory excavated material to disposal areas; design, construction and maintenance of berms required to contain and control excess excavated material placed in disposal areas; grading and turf establishment in disposal areas; control of water and sediment in disposal areas; dewatering and control of water in excavation areas; and all work in other sections containing associated requirements.
1.7.4.2 Measurement
Excavation shall be measured for payment in the original position, using the average-end-area method based on the original ground lines, surveyed ground lines after stripping, and the excavation lines and grades as shown on the drawings or as directed by the CO, and as determined by the surveys required in SECTION 01 71 23.00 13, CONTRACTOR SURVEYS.
Materials excavated outside the lines and grades shown, without specific direction or approval from the Contracting Officer will not be measured for payment.
Material excavated outside the lines and grades as shown or directed by the CO, but within the specified tolerance will not be measured for payment.
Material excavated or stripped at borrow sites will not be measured for payment.
Material excavated or stripped at disposal areas will not be measured for payment.
Material excavated prior to the taking of elevations and measurements of the undisturbed grade will not be measured for payment.
1.7.4.3 Unit of Measure
Unit of measure: cubic yard.
1.7.5 Fill
1.7.5.1 Payment
Payment will be made for furnishing all materials, equipment and labor and performing all operations necessary for placing fill as shown and as specified. Items of work include, but are not limited to foundation preparation, harrowing, removal of objectionable materials, borrow operations, hauling, placement, moisture control, compaction, disposal of
SECTION 01 22 00.00 13 Page 7 W912ES-11B-0008 encountered unsatisfactory material, dewatering and control of water, and all other incidental work required for the construction, protection, and maintenance of fill material, and all work in other sections containing associated requirements. The requirements for Measurement and Payment for Fill applies to the following bid items:
0008 Fill, Impervious 0008AA Up to 8,000 Cubic Yards 0008AB Over 8,000 Cubic Yards
0009 Fill, Random 0009AA Up to 3,000 Cubic Yards 0009AB Over 3,000 Cubic Yards
0010 Fill, Pervious (Measured)
Pervious Fill (Measured) refers to pervious fill that is placed at the downstream toe of the embankment as shown on the drawings. Pervious fill placed under the control structure will not be measured for payment. The costs for pervious fill placed under the control structure should be included in the price bid for the Control Structure.
1.7.5.2 Measurement
Fill shall be measured for payment in place and compacted as shown and as specified, using the average-end-area method based on the excavated or stripped grade lines as determined by the surveys required in SECTION 01 71 23.00 13, CONTRACTOR SURVEYS, and the lines and grade shown.
Fill materials placed outside the lines and grades shown, without specific direction or approval from the Contracting Officer will not be measured for payment.
Fill materials placed outside the lines and grades shown, or outside the lines and grades as directed by the CO but within the specified tolerance will not be measured for payment.
Fill materials that are scarified or plowed and reused in-place will not be measured for payment.
Fill materials placed prior to the taking of elevations and measurements of the excavated grade will not be measured for payment.
Fill materials placed for cofferdams and dewatering systems will not be measured for payment.
Fill materials placed for the embankment, roads and parking areas will be measured for payment.
1.7.5.3 Unit of Measure
Unit of measure: cubic yard.
1.7.6 Sheet Pile
1.7.6.1 Payment
Payment will be made for furnishing all materials, equipment and labor and performing all operations necessary for furnishing and installing Sheet
SECTION 01 22 00.00 13 Page 8 W912ES-11B-0008
Pile as shown and as specified. Items of work include, but are not limited to furnishing, transporting, stockpiling (if necessary), backfilling voids and satisfactory installation, including handling, driving, splicing, cutting and all work incidental thereto. No separate payment will be made for stockpiling materials. The requirements for Measurement and Payment for Sheet Pile applies to the following bid items:
0011 Sheet Pile, PZC-13
0012 Sheet Pile, PZC-14
1.7.6.2 Measurement
Sheet Pile shall be measured for payment by the square foot of sheet pile acceptably installed. The number of sheet piles measured for payment shall not exceed the number of piles indicated on the drawings. The length of each pile will be measured to the nearest tenth of a linear foot and converted to square feet for payment purposes. The square footage will be determined by multiplying the number of piles times the measured length acceptably installed times the theoretical driving width of each sheet as published by the manufacturer. The portion of any pile driven below the tip elevation shown on the drawings will not be measured for payment unless overdriving is directed by the Contracting Officer.
1.7.6.3 Unit of Measure
Unit of Measure: square foot.
1.7.7 Geotextile
1.7.7.1 Payment
Payment will be made for furnishing all materials, equipment and labor and performing all operations necessary for supplying and installing geotextile fabric as shown and specified. Items of work include, but are not limited to furnishing and placing geotextile fabric, overlaps and seams in geotextile fabric, including extra fabric required for the overlaps and seams, installation of pins or other methods of securing the fabric in place, and material and operations used to prevent damage to the geotextile. No additional payment will be made for geotextile replaced because of waste, contamination, damage, or repair.
1.7.7.2 Measurement
Geotextile fabric shall be measured for payment in place to the nearest square yard of protected area as shown and as directed by the CO. Area shall not be added for laps, seams, or extra length. Material that is replaced because of waste, contamination, damage, or repair shall not be measured for payment.
1.7.7.3 Unit of Measure
Unit of Measure: square yard.
1.7.8 Bedding
1.7.8.1 Payment
Payment will be made for furnishing all materials, equipment and labor and
SECTION 01 22 00.00 13 Page 9 W912ES-11B-0008 performing all operations necessary for placing bedding as shown and as specified. Items of work include, but are not limited to foundation preparation, harrowing, removal of objectionable materials, borrow operations, sorting, mixing, testing, hauling, placement, disposal of encountered unsatisfactory material, dewatering and control of water, and all other incidental work required for the construction, protection, and maintenance of the bedding material, and all work in other sections containing associated requirements. The requirements for Measurement and Payment for Bedding applies to the following bid items:
0016 Bedding, Gradation 1
0017 Bedding, Gradation 3
0018 Bedding, Gradation 4
1.7.8.2 Measurement
Bedding shall be measured for payment in accordance with paragraph Measurement by Weight, above.
1.7.8.3 Unit of Measure
Unit of Measure: ton.
1.7.9 Riprap
1.7.9.1 Payment
Payment will be made for furnishing all materials, equipment and labor and performing all operations necessary for placing riprap as shown and as specified. Items of work include, but are not limited to foundation preparation, harrowing, removal of objectionable materials, borrow operations, sorting, mixing, testing, hauling, placement, disposal of encountered unsatisfactory material, dewatering and control of water, and all other incidental work required for the construction, protection, and maintenance of the riprap material, and all work in other sections containing associated requirements. The requirements for Measurement and Payment for Fill applies to the following bid items:
0019 Riprap, Gradation 1
0020 Riprap, Gradation 3
0021 Riprap, Gradation 4
1.7.9.2 Measurement
Riprap shall be measured for payment in accordance with paragraph Measurement by Weight, above.
1.7.9.3 Unit of Measure
Unit of Measure: ton.
SECTION 01 22 00.00 13 Page 10 W912ES-11B-0008
1.7.10 Aggregate Base Course
1.7.10.1 Payment
Payment will be made for furnishing all materials, equipment and labor and performing all operations necessary for placing aggregate base course as shown and as specified. Items of work include, but are not limited to foundation preparation, harrowing, removal of objectionable materials, chinking of riprap under the aggregate base course, hauling, placement, moisture control, compaction, disposal of encountered unsatisfactory material, dewatering and control of water, and all other incidental work required for the construction, protection, and maintenance of the aggregate base course material, and all work in other sections containing associated requirements.
1.7.10.2 Measurement
Aggregate Base Course shall be measured for payment in place and compacted as shown and as specified, using the average-end-area method as determined by the surveys required in SECTION 01 71 23.00 13, CONTRACTOR SURVEYS, and the lines and grade shown.
1.7.10.3 Unit of Measure
Unit of Measure: cubic yard.
1.7.11 Topsoil and Seed
1.7.11.1 Payment
Payment will be made for furnishing all materials, equipment and labor and performing all operations necessary for placing topsoil and seed as shown and as specified. Items of work include, but are not limited to preparing surfaces to receive topsoil; furnishing, hauling and spreading topsoil;
removal of objectionable materials; disposal of encountered unsatisfactory material; dewatering and control of water; turf establishment, including seeding, fertilizing, mulching and watering; care of the turf during the contract period; and all other incidental work required for the installation, protection, and maintenance of the topsoil and seed material, and establishment of turf, including all work in other sections containing associated requirements.
1.7.11.2 Measurement
Measurement of Topsoil and Seed will be based on survey and measurement, limited to the areas required to receive topsoil and seed as shown on the drawings.
Restoration of disturbed areas not designated for topsoil and seed on the drawings or outside the limits of work will not be measured for payment.
Turf establishment in disposal areas will not be measured for payment. In those cases, costs for topsoil and seed shall be included in the price bid for the item to which the work pertains.
1.7.11.3 Unit of Measure
Unit of Measure: acre.
SECTION 01 22 00.00 13 Page 11 W912ES-11B-0008
1.8 LUMP SUM PAYMENT ITEMS
Payment items for the work of this contract for which contract lump sum payments will be made are listed in the BIDDING SCHEDULE and described below. All costs for items of work, which are not specifically mentioned to be included in a particular lump sum or unit price payment item, shall be included in the listed lump sum item most closely associated with the work involved. The lump sum price and payment made for each item listed shall constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided.
1.8.1 Performance and Payment Bonds
1.8.1.1 Payment
Payment for performance and payment bonds shall be in accordance with Contract Clause 52.2325 PAYMENTS UNDER FIXED PRICE CONSTRUCTION CONTRACTS.
1.8.1.2 Unit of Measure
Unit of measure: lump sum.
1.8.2 Existing Fence Modifications
1.8.2.1 Payment
Payment will be made for furnishing all materials, equipment and labor and performing all operations necessary for modifications to existing fences as shown and as specified. Items of work include, but are not limited to cutting and removal of existing fencing and posts where required, new posts, new fencing, installation of tubular steel gate, tying new fence work into existing fencing, and all work in other sections containing associated requirements.
1.8.2.2 Unit of Measure
Unit of measure: lump sum.
1.8.3 Cofferdams and Dewatering
1.8.3.1 Payment
Payment will be made for furnishing all materials, equipment and labor and performing all operations necessary for design, construction, operation, and removal of cofferdams and dewatering systems as shown and as specified. Items of work include, but are not limited to designing cofferdams and dewatering systems; furnishing, placing, and maintaining all cofferdam and dewatering systems; preparatory and restorative required sitework; initial dewatering; maintenance dewatering; monitoring of the cofferdams and dewatering system during construction; rewatering; and removing cofferdam materials and dewatering equipment as specified. No associated cofferdam work or materials will be measured for separate payment under any other bid item. Include costs for all work in other sections containing associated requirements.
SECTION 01 22 00.00 13 Page 12 W912ES-11B-0008
1.8.3.2 Unit of Measure
Unit of measure: lump sum.
1.8.4 Control Structure
1.8.4.1 Payment
Payment will be made for furnishing all materials, equipment and labor and performing all operations necessary for construction of the control structure as shown and as specified. Items of work include, but are not limited to reinforced concrete work, including reinforcing, dowels, design and installation of formwork, water stops, expansion joints, sealer, and concrete; subdrainage system, including pervious fill, drainage material, and PVC pipe; structural steel, including beams, bracing, bearing plates, and anchors; embedded and bolted on metal items including ladders, gratings, framework, chain link fencing, fencing support posts, gates, grab bars, handrail, and staff gauges; and all fasteners and welding required for installation of the Control Structure and associated features. Include costs for all work in other sections containing associated requirements.
1.8.4.2 Unit of Measure
Unit of measure: lump sum.
1.8.5 Stop Log System
1.8.5.1 Payment
Payment will be made for furnishing all materials, equipment and labor and performing all operations necessary for construction of the stoplog system as shown and as specified. Items of work include, but are not limited to stoplogs, pickup beam, gantry crane and supporting tracks, hoists, rigging, and acceptance trial operation. Include costs for all work in other sections containing associated requirements. No additional payment will be made for repairs or replacement of defective items. No additional payment will be made for additional trial operations required after correction of defects.
1.8.5.2 Unit of Measure
Unit of measure: lump sum.
1.8.6 Instrumentation
1.8.6.1 Payment
Payment will be made for furnishing all materials, equipment and labor and performing all operations necessary for supply and installation of instrumentation as shown and as specified. Items of work include, but are not limited to type 1 alignment monuments on the sheet pile I-wall, type 2 alignment monuments on the concrete structure; staff gages; stainless steel piping for piezometers, including pipe, couplings, elbows, well screen, and end caps; and steel pipe for monitoring well casings. Include costs for all work in other sections containing associated requirements.
Installation of monitoring wells and piezometers will be by others.
SECTION 01 22 00.00 13 Page 13 W912ES-11B-0008
1.8.6.2 Unit of Measure
Unit of measure: lump sum.
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION (Not Applicable)
SECTION 01 22 00.00 13 Page 14 W912ES-11B-0008
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 32 01.00 13
PROJECT SCHEDULE
PART 1 GENERAL
1.1 SUBMITTALS
1.2 QUALIFICATIONS
PART 2 PRODUCTS
2.1 COMPUTER SOFTWARE REQUIREMENTS
PART 3 EXECUTION
3.1 GENERAL
3.2 BASIS FOR PAYMENT
3.3 SOFTWARE
3.3.1 Use of the Critical Path Method
3.3.2 Level of Detail Required
3.3.2.1 Activity Durations
3.3.2.2 Procurement Activities
3.3.2.3 Critical Activities
3.3.2.4 Government Activities
3.3.2.5 Responsibility
3.3.2.6 Feature of Work
3.3.3 Scheduled Project Completion
3.3.3.1 Constraint of Last Activity
3.3.3.2 Early Project Completion
3.3.4 Interim Completion Dates
3.3.5 Default Progress Data Disallowed
3.3.6 Out-of-Sequence Progress
3.3.7 Extended Non-Work Periods
3.3.8 Negative Lags
3.4 PROJECT SCHEDULE SUBMISSIONS
3.4.1 Initial Project Schedule Submission
3.4.2 Periodic Updates
3.4.3 Standard Activity Coding Dictionary
3.5 SUBMISSION REQUIREMENTS
3.5.1 Earnings Report
3.5.2 Network Diagram
3.6 PERIODIC PROGRESS MEETINGS
3.6.1 Meeting Attendance
3.6.2 Update Submission Following Progress Meeting
3.6.3 Progress Meeting Contents
3.7 REQUESTS FOR TIME EXTENSIONS
3.7.1 Justification of Delay
3.7.2 Submission Requirements
3.8 DIRECTED CHANGES
3.9 OWNERSHIP OF FLOAT
SECTION 01 32 01.00 13 Page 1 W912ES-11B-0008
SECTION 01 32 01.00 13 Page 2 W912ES-11B-0008
SECTION 01 32 01.00 13
PROJECT SCHEDULE
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Submittals
Initial Project Schedule; G,CO Periodic Updates; G,CO
Five copies of the initial project schedule shall be submitted, five days prior to the preconstruction meeting. Two copies of periodic project schedule updates shall be submitted.
SD-04 Samples
Software;
The Contractor shall furnish the Government copies of the scheduling software if required under paragraph COMPUTER SOFTWARE
REQUIREMENTS.
1.2 QUALIFICATIONS
The Contractor shall designate an authorized representative who shall be responsible for the preparation of all required project schedule reports.
PART 2 PRODUCTS
2.1 COMPUTER SOFTWARE REQUIREMENTS
The Contractor shall furnish the Government with the software to be used, unless waived by the Contracting Officer. The Contactor shall assist in installing the software in the Government resident office. The Contractor shall provide the software complete, including documentation and updates used in the Contractor's system. The software shall remain the property of the Contractor, but shall be in the possession of and for the exclusive use by the Government during the contract period. The Government shall have rights to install the software on 3 computers (resident office, area office, and district office).
PART 3 EXECUTION
3.1 GENERAL
Pursuant to the Contract Clause, SCHEDULES FOR CONSTRUCTION CONTRACTS (FAR 52.236-15), a project schedule as described below shall be prepared. The scheduling of construction shall be the responsibility of the Contractor.
Contractor management personnel shall actively participate in its
SECTION 01 32 01.00 13 Page 3 W912ES-11B-0008 development. Subcontractors and suppliers working on the project shall contribute in developing and maintaining an accurate project schedule. The approved project schedule shall be used to measure the progress of the work, to aid in evaluating time extensions, and to provide the basis of progress payments.
3.2 BASIS FOR PAYMENT
The project schedule shall be the basis for measuring Contractor progress.
The Contracting Officer will use an approved project schedule to evaluate Contractor progress for payment purposes. In the case where project schedule revisions have been directed by the Contracting Officer and those revisions have not been included in the project schedule, then the Contracting Officer may hold retainage up to the maximum allowed by contract, each payment period, until the project schedule updates have been accepted.
3.3 SOFTWARE
Computer software systems utilized by the Contractor to produce the project schedule shall be capable of providing all requirements of this specification.
3.3.1 Use of the Critical Path Method
The project schedule shall clearly show the critical path. If a network analysis system is used, the Critical Path Method (CPM) of network calculation shall be used to generate the project schedule, provided in either the Precedence Diagram Method (PDM) or the Arrow Diagram Method
(ADM).
3.3.2 Level of Detail Required
The project schedule shall include an appropriate level of detail. The Contracting Officer will use, but is not limited to, the following conditions to determine the appropriate level of detail to be used in the project schedule.
3.3.2.1 Activity Durations
The Contractor shall breakout lump-sum or sum-job contract line items into subcategories, or activities. The number of activities shall be sufficient to allow the progress to be accurately determined between payment periods.
3.3.2.2 Procurement Activities
Tasks related to the procurement of long lead materials or equipment shall be included as separate activities in the project schedule. Long lead materials and equipment are those materials that have a procurement cycle of over 90 calendar days. Examples of procurement process activities include, but are not limited to: submittals, approvals, procurement, fabrication, and delivery.
3.3.2.3 Critical Activities
The following activities…