Amendment 00002 22 Sep 09.doc
DOC document 39 KB Posted
- Attached to
- RECOVERY--99--RECOVERY- Repair of existing asphalt roads at Eau Galle Recreation Area, Spring Valley, WI.
- Solicitation number
- W912ES-09-T-0061
About this file
Amendment 0002- changing the set aside from small business to full and open and extending the completion date to 15 June 2010.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Final Solicitation Eau Galle Sealcoating 29 July 09.doc | DOC document | |
| Amendment 00001.doc | DOC document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION 00010 - SOLICITATION CONTRACT FORM
The required response date/time has changed from 18-Sep-2009 02:00 PM to 07-Oct-2009 02:00 PM.
SECTION 00700 - CONTRACT CLAUSES
The following have been modified:
52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)
The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 15 June, 2010. The time stated for completion shall include final cleanup of the premises.
*The Contracting Officer shall specify either a number of days after the date the contractor receives the notice to proceed, or a calendar date.
(End of clause)
The following have been deleted:
| 52.219-6 |
| Notice Of Total Small Business Set-Aside |
| JUN 2003 |
(End of Summary of Changes)