Lock & Dam 5 Entrance Road W912ES-09-B-0005 US Army Corps of Engineers, 190 East 5th Street, Suite 401, Saint Paul, Minnesota 55101-1638 B13 July, 2009 2:00PM

Bidder 1 Frontier Construction Bidder 2 Aspen Construction Co Bidder 3 Fuel Tank Maintenance Unit Unit Unit Unit

Item Description Quantity Unit Price Amount Price Amount %+-IGE Price Amount %+-IGE Price Amount %+- IGE

0001 REMOVALS 1 LS $21,500.00 $21,500.00 $126,457.37 $126,457.37 588.17% $79,513.50 $79,513.50 369.83% $82,036.00 $82,036.00 381.56% 0002 EXCAVATION 2,838.00 CY $16.60 $47,110.80 $8.78 $24,917.64 52.89% $50.97 $144,652.86 307.05% $41.00 $116,358.00 246.99% 0003 STEEL SHEET PILING 4,216 LF $51.00 $215,016.00 $73.90 $311,562.40 144.90% $62.15 $262,024.40 121.86% $105.00 $442,680.00 205.88% 0004 STRUCTURAL STEEL CHANNEL 488 LF $47.50 $23,180.00 $50.32 $24,556.16 105.94% $22.55 $11,004.40 47.47% $42.00 $20,496.00 88.42% 0005 8-INCH DRAINAGE PIPE 510 LF $31.40 $16,014.00 $62.03 $31,635.30 197.55% $11.00 $5,610.00 35.03% $27.00 $13,770.00 85.99% 0006 FILTER FABRIC 1,471 SF $1.00 $1,471.00 $1.17 $1,721.07 117.00% $1.54 $2,265.34 154.00% $4.00 $5,884.00 400.00% 0007 GEOSYNTHETIC CLAY LINER 285 SY $14.55 $4,146.75 $5.85 $1,667.25 40.21% $33.00 $9,405.00 226.80% $137.00 $39,045.00 941.58% 0008 SEPARATION GEOTEXTILE 466 SY $5.40 $2,516.40 $2.93 $1,365.38 54.26% $24.20 $11,277.20 448.15% $41.00 $19,106.00 759.26% 0009 4 - INCH DRAINAGE PIPE 489 LF $13.20 $6,454.80 $10.53 $5,149.17 79.77% $8.80 $4,303.20 66.67% $13.00 $6,357.00 98.48%

0010 FLOWABLE FILL $0.00 #DIV/0!

0010AA FIRST 70 CUBIC YARDS 70 CY $151.00 $10,570.00 $175.53 $12,287.10 116.25% $368.50 $25,795.00 244.04% $205.00 $14,350.00 135.76% 0010AB OVER 70 CUBIC YARDS 20 CY $151.00 $3,020.00 $157.98 $3,159.60 104.62% $308.00 $6,160.00 203.97% $205.00 $4,100.00 135.76%

0011 AGGREGATE BASE COURSE 518 CY $72.00 $37,296.00 $29.26 $15,156.68 40.64% $26.95 $13,960.10 37.43% $30.00 $15,540.00 41.67% 0012 ASPHALT PAVEMENT, 4-1/2 -INCH THICK 1,786.00 SY $23.60 $42,149.60 $26.24 $46,864.64 111.19% $24.20 $43,221.20 102.54% $30.00 $53,580.00 127.12% 0013 CONCRETE CURB AND GUTTER 559 LF $20.00 $11,180.00 $33.65 $18,810.35 168.25% $49.50 $27,670.50 247.50% $47.00 $26,273.00 235.00% 0014 CONCRETE SIDEWALK, 4 INCH THICKNESS 580 SF $5.15 $2,987.00 $5.97 $3,462.60 115.92% $7.70 $4,466.00 149.51% $14.00 $8,120.00 271.84% 0015 12-INCH REINFORCED CONCRETE PIPE CL 1V 27 LF $123.25 $3,327.75 $468.09 $12,638.43 379.79% $93.50 $2,524.50 75.86% $685.00 $18,495.00 555.78% 0016 REINSTALL SALVAGED DRAINAGE & MANHOLE CASTINGS 3 EA $3,950.00 $11,850.00 $662.48 $1,987.44 16.77% $550.00 $1,650.00 13.92% $4,790.00 $14,370.00 121.27% 0017 SELECT GRANULAR BACKFILL 1,680 CY $36.50 $61,320.00 $17.55 $29,484.00 48.08% $26.95 $45,276.00 73.84% $30.00 $50,400.00 82.19% 0018 COARSE GRANULAR BACKFILL 668 CY $60.25 $40,247.00 $37.45 $25,016.60 62.16% $26.95 $18,002.60 44.73% $30.00 $20,040.00 49.79% 0019 TEMPORARY TRAFFIC CONTROL 1 LS $13,125.00 $13,125.00 $4,680.89 $4,680.89 35.66% $5,500.00 $5,500.00 41.90% $27,300.00 $27,300.00 208.00%

TOTAL $574,482.10 $702,580.07 122.30% $724,281.80 126.08% $998,300.00 173.77%

Government Estimate Contract Specialist: Dick HallContracting Officer: Lee Wright