DITCH 19 CHANNEL CLEANOUT Federal contract opportunity
Solicitation number
W912EQ24C0014
Issued by
Department of the Army Corps of Engineers Engineering District Memphis

About this file

This is an official bid abstract from the US Army Corps of Engineers Memphis District for solicitation W912EQ24B0012, "DITCH 19 CHANNEL CLEANOUT" in Dunklin County, MO. The bid opening occurred on September 10, 2024 at 2:00 PM, and the procurement was designated as an SDVOSB competitive small business set-aside.

Seven contractors submitted bids for the base work and Option 1. The base work included mobilization/demobilization, environmental protection, storm water pollution prevention, clearing and snagging, channel cleanout excavation, and seeding/mulching. Option 1 added similar line items plus bedding material and R-200 materials. The total bids (base + Option 1) ranged from $8,886,105.37 (Dynamic Wallcovering LLC dba Ozark Constructors) to $19,657,899.15 (SSD Contracting LLC), compared to the government estimate of $11,974,070.96. The file shows detailed unit pricing for each contractor's bid broken down by line item.

View the file

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

I certify that I have read all offers received in response to this solicitation and all offers have been recorded on this abstract Kimberly E. D. Bass

UNIT EXTENDED UNIT EXTENDED UNIT EXTENDED UNIT EXTENDED UNIT EXTENDED UNIT EXTENDED UNIT EXTENDED

NO. DESCRIPTION QTY U/M PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT

0001 MOBILIZATION AND DEMOBILIZATION 1 JA XXX 318,152.00$ XXX 368,321.00$ XXX 679,400.00$ XXX 199,302.39$ XXX 71,500.00$ XXX 162,255.21$ XXX 388,468.67$

0002 ENVIRONMENTAL PROTECTION 1 JA XXX 9,027.00$ XXX 9,150.00$ XXX 45,920.00$ XXX 108,898.78$ XXX 35,000.00$ XXX 127,202.50$ XXX 9,900.00$

0003 STORM WATER POLLUTION PREVENTION XXX XXX XXX XXX XXX XXX XXX XXX XXX XXX XXX XXX XXX XXX XXX XXX

0003AA WRITE/MAINTAIN SWPP, OBTAIN SW PERMIT & MAINTAIN PERMIT 1 JA

XXX

6,601.00$ XXX 3,640.00$ XXX 33,530.00$ XXX 326,728.76$ XXX 25,000.00$ XXX 8,163.72$ XXX 7,425.00$

0003AB EROSION CONTROL BERM 75,847 LF

1.45$

109,978.15$ 3.20$ 242,710.40$ 3.30$ 250,295.10$ 2.15$ 163,071.05$ 6.60$ 500,590.20$ 1.61$ 122,113.67$ 2.97$ 225,265.59$

0003AC SLIT FENCE 2,180 LF

4.03$

8,785.40$ 3.50$ 7,630.00$ 3.40$ 7,412.00$ 50.00$ 109,000.00$ 7.70$ 16,786.00$ 2.99$ 6,518.20$ 3.47$ 7,553.70$

0003AD TEMPORARY ENVIRONMENTAL SEEDING 117 AC

1,631.76$

190,915.92$ 767.00$ 89,739.00$ 1,845.00$ 215,865.00$ 1,612.50$ 188,662.50$ 1,650.00$ 193,050.00$ 1,247.07$ 145,907.19$ 792.00$ 92,664.00$

0003AE CONSTRUCTION EXIT 23 EA

4,304.27$

98,998.21$ 2,350.00$ 54,050.00$ 3,870.00$ 89,010.00$ 2,150.00$ 49,450.00$ 16,500.00$ 379,500.00$ 3,333.19$ 76,663.37$ 2,970.00$ 68,310.00$

0004 CLEARING AND SNAGGING 805 HL

1,888.29$

1,520,073.45$ 1,228.50$ 988,942.50$ 5,800.00$ 4,669,000.00$ 2,150.00$ 1,730,750.00$ 132.00$ 106,260.00$ 1,846.40$ 1,486,352.00$ 1,039.50$ 836,797.50$

0005 CHANNEL CLEANOUT EXCAVATION 230,438 CY

5.66$

1,304,279.08$ 3.78$ 871,055.64$ 6.10$ 1,405,671.80$ 8.60$ 1,981,766.80$ 22.00$ 5,069,636.00$ 3.42$ 788,097.96$ 3.71$ 854,233.67$

0006 SEEDING AND MULCHING 468 AC

2,070.20$

968,853.60$ 1,861.50$ 871,182.00$ 2,200.00$ 1,029,600.00$ 1,881.25$ 880,425.00$ 4,950.00$ 2,316,600.00$ 1,815.93$ 849,855.24$ 1,782.00$ 833,976.00$

4,535,663.81$ 3,506,420.54$ 8,425,703.90$ 5,738,055.28$ 8,713,922.20$ 3,773,129.06$ 3,324,594.13$

OPTION 1

0007 MOBILIZATION AND DEMOBILIZATION 1 JA XXX 271,030.00$ XXX 145,137.00$ XXX 584,920.00$ XXX 288,930.76$ XXX 71,500.00$ XXX 96,453.68$ XXX 148,500.00$

0008 ENVIRONMENTAL PROTECTION 1 JA XXX 9,004.00$ XXX 9,100.00$ XXX 48,690.00$ XXX 398,174.99$ XXX 35,000.00$ XXX 149,649.99$ XXX 9,900.00$

0009 STORM WATER POLLUTION PREVENTION XXX XXX XXX XXX XXX XXX XXX XXX XXX XXX XXX XXX XXX XXX XXX XXX

0009AA WRITE/MAINTAIN SWPPP, OBTAIN SW PERMIT & MAINTAIN PERMIT 1 JA XXX 6,601.00$ XXX 3,640.00$ XXX 33,530.00$ XXX 117,746.03$ XXX 25,000.00$ XXX 5,831.23$ XXX 7,425.00$

0009AB EROSION CONTROL BERM 92810 LF 1.45$ 134,574.50$ 3.20$ 296,992.00$ 4.10$ 380,521.00$ 2.14$ 198,613.40$ 6.60$ 612,546.00$ 1.61$ 149,424.10$ 3.50$ 321,586.65$

0009AC SLIT FENCE 1884 LF 4.02$ 7,573.68$ 3.50$ 6,594.00$ 4.00$ 7,536.00$ 50.00$ 94,200.00$ 7.70$ 14,506.80$ 2.99$ 5,633.16$ 3.71$ 6,983.99$

0009AD TEMPORARY ENCIRONMENTAL SEEDING 73 AC 1,356.07$ 98,993.11$ 767.00$ 55,991.00$ 2,017.00$ 147,241.00$ 1,612.96$ 117,746.08$ 1,650.00$ 120,450.00$ 1,247.08$ 91,036.84$ 891.00$ 65,043.00$

0009AE CONSTRUCTION EXIT 16 EA 4,293.53$ 68,696.48$ 2,350.00$ 37,600.00$ 4,300.00$ 68,800.00$ 12,413.34$ 198,613.40$ 16,500.00$ 264,000.00$ 3,333.19$ 53,331.04$ 3,465.00$ 55,440.00$

0010 CLEARING AND SNAGGING 1005 HL 1,884.05$ 1,893,470.25$ 758.00$ 761,790.00$ 4,640.00$ 4,663,200.00$ 2,140.00$ 2,150,700.00$ 132.00$ 132,660.00$ 1,408.70$ 1,415,743.50$ 618.75$ 621,843.75$

0011 CHANNEL CLEANOUT EXCAVATION 237621 CY 6.97$ 1,656,218.37$ 3.78$ 898,207.38$ 6.25$ 1,485,131.25$ 8.56$ 2,034,035.76$ 22.00$ 5,227,662.00$ 4.68$ 1,112,066.28$ 3.96$ 940,979.16$

0012 SEEDING AND MLUCHING 292 AC 2,070.94$ 604,714.48$ 1,861.50$ 543,558.00$ 2,300.00$ 671,600.00$ 1,872.50$ 546,770.00$ 4,950.00$ 1,445,400.00$ 1,815.93$ 530,251.56$ 1,782.00$ 520,344.00$

0013 BEDDING MATERIAL 18676 TN 45.18$ 843,781.68$ 46.50$ 868,434.00$ 56.00$ 1,045,856.00$ 39.59$ 739,382.84$ 38.50$ 719,026.00$ 37.58$ 701,844.08$ 57.42$ 1,072,375.92$

0014 R-200 31745 TN 58.08$ 1,843,749.60$ 55.21$ 1,752,641.45$ 66.00$ 2,095,170.00$ 42.80$ 1,358,686.00$ 38.50$ 1,222,182.50$ 44.11$ 1,400,271.95$ 64.35$ 2,042,790.75$

OPTION 1 SUB-TOTAL ITEMS 0007-0014 7,438,407.15$ 5,379,684.83$ 11,232,195.25$ 8,243,599.26$ 9,889,933.30$ 5,711,537.41$ 5,813,212.22$

GRAND TOTAL BASE + OPTION 1 11,974,070.96$ 8,886,105.37$ 19,657,899.15$ 13,981,654.54$ 18,603,855.50$ 9,484,666.47$ 9,137,806.34$

VETERANS ELITE DEVELOPMENT AND CONSTRUCTION LLC

1300 St. Denis Street

Florissant, MO 63033

RANDY KINDER EXCAVATING INC

12965 Carrier Lane

Dexter, MO 63841

MEMPHIS

DISTRICT

DYNAMIC WALLCOVERING, LLC

DBA Ozark Constructors

ENGINEERING

SSD CONTRACTING, LLC

Fort Pierce, FL 34951

OFFICIAL ABSTRACT

US ARMY, CORPS OF ENGINEERS - MEMPHIS DISTRICT ABSTRACT OF BIDS

NUMBER OF AMENDMENTS: 1

SMALL BUSINESS DETERMINATION:SDVOSB Competitive Small Business Set-Aside

3067 S. Westwood Blvd

Poplar Bluff, MO 63901

TITLE: DITCH 19 CHANNEL CLEANOUT at Dunklin County, MO

VENERGY GROUP LLC

INVITATION NO.: W912EQ24B0012

GOVT. ESTIMATE

5591 Peachtree Road

BID OPENING DATE AND TIME: September 10, 2024 at 2:00PM COST

Base Sub-Total Items 0001-0006

GENESIS 360 LLC

8352 Bluebonnet Blvd.

East Baton Rough Parish

Baton Rouge, LA 70810

Chamblee, GA 30341

3130 Seminole Road

CEMVM 967 (REV. JAN 00)

ABSTRACT OF BIDS

File details come from the government source that posted it. Updated .