AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
1. The purpose of this amendment is to add the Tensile Strength to the Statement of Work.
2. Add the questions and answ ers to this solicitation.
3. To extend this solicitation until 16 May 2022.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 3
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912EQ22Q0034
X 9B. DATED (SEE ITEM 11)
27-Apr-2022
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT
THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO.
5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE
DATE
6 MAY 2022
CODE
US ARMY ENGINEER DISTRICT, MEMPHIS
KENDELL RILEY
167 N. MAIN STREET
KENDELL.M.RILEY@USACE.ARMY.MIL
MEMPHIS TN 38103-1894
W912EQ 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912EQ22Q0034
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION C - DESCRIPTIONS AND SPECIFICATIONS
The following have been modified:
STATEMENT OF WORK
Statement of Work
Scope: The Contractor shall supply and deliver, by truck, 1786 TN of 3" rock, 2042 TN of 610 gravel, and 50 rolls (~59000 SF) of Geotech fabric to Ensley Engineering Yard (EEY). (Tensile Strength-ASTM D-4632 205lbs.).
Stone Sources:
Stone meeting the requirements of this statement of work has been produced from the sources listed. THE APPROVED STONE SOURCES CAN BE FOUND AT:
http://www.mvm.usace.army.mil/Portals/51/docs/construction/MVDStoneLST.pdf
Service Required, Location: The Contractor will be responsible for the supply and delivery of material to the project location at 2915 Riverport .Road, Memphis, TN 38109. Any load fees shall be included in the unit price of material. Any additional fees or surcharges for longer haul distances, truck fees, fuel surcharge and/or standby fees shall be included in the unit price of material.
All contractor and all associated sub-contractors employees shall comply with applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative). The contractor shall also provide all information required for background checks to meet installation/facility access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office. Contractor workforce must comply with all personal identity verification requirements (FAR clause 52.204-9, Personal Identity Verification of Contractor Personnel) as directed by DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any installation or facility change, the Government may require changes in contractor security matters or processes.
All contract employees, including subcontractor employees who are not in possession of the appropriate security clearance or access privileges, will be escorted in areas where they may be exposed to classified and/or sensitive materials and/or sensitive or restricted areas.
The Contractor must pre-screen Candidates using the E-verify Program (http://www.uscis.gov/e-
W912EQ22Q0034
verify) website to meet the established employment eligibility requirements. The Vendor must ensure that the Candidate has two valid forms of Government issued identification prior to enrollment to ensure the correct information is entered into the E-verify system. An initial list of verified/eligible Candidates must be provided to the COR no later than 3 business days after the initial contract award.
Coordination of Work: The Contractor shall coordinate delivery with the following personnel:
The Point of Contact for this effort is Kenneth Burden or Sean Fegette.
Mr. Burden can be reached at (901) 634-9857 or by email: Kenneth.L.Burden@usace.army.mil Mr. Fegette can be reached at (901) 728-7330 or by e-mail: Sean.E.Fegette@usace.army.mil
SECTION I - CONTRACT CLAUSES
The following have been added by full text:
QUESTIONS AND ANSWERS
EEY LAYDOWN AREA MATERIALS: Questions and Answers
1. The 50 rolls of Geotech fabric is it woven or nonwoven? - 8oz Nonwoven Geotech fabric
2. What is the tensile? - Tensile-the strength of the fabric material, which must be to able hold the material being loaded on to it without tearing or unraveling.
3. Is this used for erosion or separation? - Separation
4. I would like to know if the following substitutions can be made:
a. SB2 granite instead of 610 gravel - SB2 granite is going to be a little harder than 610 gravel but will serve the same purpose. At EEY around the yard they have always mostly use 610 gravel to keep the same texture.
b. 2 1/2" D Ballast instead of 3" Rock - The 2 ½ D Ballast will be somewhat the same as the 3” rock.
(End of Summary of Changes)