Official Abstract Signed.pdf

PDF 282 KB Posted

Attached to
Island 8, Parcel 2 Seepage Remediation
Solicitation number
W912EQ21B0009
Issued by

About this file

This abstract of bids is for the Island 8, Parcel 2 Seepage Remediation project solicited by the Department of the Army Corps of Engineers Engineering District Memphis. The solicitation number is W912EQ21B0009 and the project consists of 79 relief wells, 12,000 linear feet of subsurface drain pipe, 1,900 linear feet of new drainage ditches, modification of existing drainage ditches, culvert replacement at five locations with associated adjacent rip-rap placement, and removal of snags and debris from Running Slough. This procurement was set aside for service-disabled veteran owned small businesses and utilized sealed bid procedures. Six bids were received by the August 31, 2021 bid opening date. Bid prices ranged from $7,774,232.59 to $10,304,738.07. The government estimate was $9,964,190.00.

View the file

Other files

File Type Posted
Site Visit Attendance forms- W912EQ21B0009.pdf PDF
Pilot Hole Sieve Data_08-I8P2G-19.xls XLS spreadsheet
Pilot Hole Sieve Data_13-I8P2G-19.xls XLS spreadsheet
Pilot Hole Sieve Data_16-I8P2G-19.xls XLS spreadsheet
Pilot Hole Sieve Data_11-I8P2G-19.xls XLS spreadsheet
Pilot Hole Sieve Data_79-I8P2G-19.xls XLS spreadsheet
Pilot Hole Sieve Data_41-I8P2G-19.xls XLS spreadsheet
Pilot Hole Sieve Data_71-I8P2G-19.xls XLS spreadsheet
Pilot Hole Sieve Data_65-I8P2G-19.xls XLS spreadsheet
Pilot Hole Sieve Data_25-I8P2G-19.xls XLS spreadsheet
Pilot Hole Sieve Data_75-I8P2G-19.xls XLS spreadsheet
Pilot Hole Sieve Data_49-I8P2G-19.xls XLS spreadsheet
Pilot Hole Sieve Data_63-I8P2G-19.xls XLS spreadsheet
Pilot Hole Sieve Data_73-I8P2G-19.xls XLS spreadsheet
Pilot Hole Sieve Data_42-I8P2G-19.xls XLS spreadsheet
Pilot Hole Sieve Data_78-I8P2G-19.xls XLS spreadsheet
Pilot Hole Sieve Data_44-I8P2G-19.xls XLS spreadsheet
Pilot Hole Sieve Data_09-I8P2G-19.xls XLS spreadsheet
Pilot Hole Sieve Data_59-I8P2G-19.xls XLS spreadsheet
Pilot Hole Sieve Data_15-I8P2G-19.xls XLS spreadsheet
Pilot Hole Sieve Data_28-I8P2G-19.xls XLS spreadsheet
Pilot Hole Sieve Data_39-I8P2G-19.xls XLS spreadsheet
Pilot Hole Sieve Data_30-I8P2G-19.xls XLS spreadsheet
Pilot Hole Sieve Data_38-I8P2G-19.xls XLS spreadsheet
Pilot Hole Sieve Data_24-I8P2G-19.xls XLS spreadsheet
Pilot Hole Sieve Data_32-I8P2G-19.xls XLS spreadsheet
Pilot Hole Sieve Data_18-I8P2G-19.xls XLS spreadsheet
Pilot Hole Sieve Data_45-I8P2G-19.xls XLS spreadsheet
Pilot Hole Sieve Data_02-I8P2G-19.xls XLS spreadsheet
Pilot Hole Sieve Data_34-I8P2G-19.xls XLS spreadsheet
Pilot Hole Sieve Data_54-I8P2G-19.xls XLS spreadsheet
Pilot Hole Sieve Data_57-I8P2G-19.xls XLS spreadsheet
Pilot Hole Sieve Data_77-I8P2G-19.xls XLS spreadsheet
Pilot Hole Sieve Data_76-I8P2G-19.xls XLS spreadsheet
Pilot Hole Sieve Data_37-I8P2G-19.xls XLS spreadsheet
Pilot Hole Sieve Data_67-I8P2G-19.xls XLS spreadsheet
Island 8 Parcel 2 Pilot Hole Field Logs with coversheet.pdf PDF
Pilot Hole Sieve Data_29-I8P2G-19.xls XLS spreadsheet
Pilot Hole Sieve Data_50-I8P2G-19.xls XLS spreadsheet
Pilot Hole Sieve Data_19-I8P2G-19.xls XLS spreadsheet
Pilot Hole Sieve Data_48-I8P2G-19.xls XLS spreadsheet
Pilot Hole Sieve Data_01-I8P2G-19.xls XLS spreadsheet
Pilot Hole Sieve Data_17-I8P2G-19.xls XLS spreadsheet
Pilot Hole Sieve Data_62-I8P2G-19.xls XLS spreadsheet
Pilot Hole Sieve Data_35-I8P2G-19.xls XLS spreadsheet
Pilot Hole Sieve Data_22-I8P2G-19.xls XLS spreadsheet
Pilot Hole Sieve Data_52-I8P2G-19.xls XLS spreadsheet
Pilot Hole Sieve Data_40-I8P2G-19.xls XLS spreadsheet
Pilot Hole Sieve Data_36-I8P2G-19.xls XLS spreadsheet
Pilot Hole Sieve Data_21-I8P2G-19.xls XLS spreadsheet
Show 40 more

Latest 50 of 87 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

UNOFFICIAL ABSTRACT

I certify that I have read all offers received in response to this solicitation and all offers have been recorded on this abstract Latashia Muse, Bid Opening Officer Priscilla G. Sweeney, Contracting Officer

UNIT EXTENDED UNIT EXTENDED UNIT EXTENDED UNIT EXTENDED UNIT EXTENDED UNIT EXTENDED

NO. DESCRIPTION QTY U/M PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT

0001 MOBILIZATION AND DEMOBILIZATION 1 JA XXX $193,735.00 XXX 449,000.00$ XXX 140,454.00$ XXX 340,000.00$ XXX 850,000.00$ XXX 547,316.00$

0002 ENVIRONMENTAL PROTECTION 1 JA XXX $14,560.00 XXX 428,000.00$ XXX 6,242.40$ XXX 1,800.00$ XXX 115,000.00$ XXX 10,262.00$

0003 TRAFFIC CONTROL AND SIGNAGE 1 JA XXX $19,205.00 XXX 12,400.00$ XXX 5,722.20$ XXX 10,000.00$ XXX 25,000.00$ XXX 8,894.00$

0004 STORM WATER POLLUTION PREVENTION

0004AA WRITE AND MODIFY SWPPP 1 JA XXX 4,344.00$ XXX 6,200.00$ XXX 4,681.80$ XXX 2,600.00$ XXX 8,500.00$ XXX 35,576.00$

0004AB SILT FENCE 400 LF 2.70$ 1,080.00$ 7.70$ 3,080.00$ 3.12$ 1,248.00$ 4.70$ 1,880.00$ 5.50$ 2,200.00$ 4.10$ 1,640.00$

0004AC EROSION CONTROL BERM 17,000 LF 2.24$ $38,080.00 2.40$ 40,800.00$ 1.24$ 21,080.00$ 3.95$ 67,150.00$ 4.50$ 76,500.00$ 2.05$ 34,850.00$

0004AD CONSTRUCTION EXIT 2 EA 8,002.39$ 16,004.78$ 5,500.00$ 11,000.00$ 2,913.12$ 5,826.24$ 2,500.00$ 5,000.00$ 7,000.00$ 14,000.00$ 4,104.87$ 8,209.74$

0004AE CHECK DAM 7 EA 668.91$ 4,682.37$ 1,700.00$ 11,900.00$ 499.39$ 3,495.73$ 980.00$ 6,860.00$ 2,800.00$ 19,600.00$ 684.14$ 4,788.98$

0005 RELIEF WELL CONSTRUCTION

0005AA Relief Well, 10-inch (79 total) 8,194 LF 823.50$ 6,747,759.00$ 536.75$ 4,398,129.50$ 503.55$ 4,126,088.70$ 571.50$ 4,682,871.00$ 465.00$ 3,810,210.00$ 599.40$ 4,911,483.60$

0005AB Relief Well Testing (First 158 hours) 158 HR 287.74$ 45,462.92$ 380.00$ 60,040.00$ 350.61$ 55,396.38$ 210.00$ 33,180.00$ 300.00$ 47,400.00$ 410.49$ 64,857.42$

0005AC Relief Well Testing (Additional hours) 40 HR 287.74$ 11,509.60$ 380.00$ 15,200.00$ 350.61$ 14,024.40$ 210.00$ 8,400.00$ 300.00$ 12,000.00$ 410.49$ 16,419.60$

0005AD Piezometer Installation (8 total) 216 LF 105.89$ 22,872.24$ 388.00$ 83,808.00$ 353.74$ 76,407.84$ 132.00$ 28,512.00$ 450.00$ 97,200.00$ 418.70$ 90,439.20$

0006 EXCAVATION 4,700 CY 10.92$ 51,324.00$ 10.70$ 50,290.00$ 5.07$ 23,829.00$ 3.70$ 17,390.00$ 19.00$ 89,300.00$ 8.21$ 38,587.00$

0007 SEMI-COMPACTED EMBANKMENT 2,700 CY 9.36$ 25,272.00$ 12.80$ 34,560.00$ 4.68$ 12,636.00$ 4.20$ 11,340.00$ 8.00$ 21,600.00$ 6.84$ 18,468.00$

0008 Corrugated Metal Pipe (CMP) Culvert

0008AA 30 In. Dia. CMP Culvert 80 LF 208.10$ 16,648.00$ 256.00$ 20,480.00$ 153.98$ 12,318.40$ 420.00$ 33,600.00$ 180.00$ 14,400.00$ 273.66$ 21,892.80$

0008AB 60 In. Dia. CMP Culvert 350 LF 430.75$ 150,762.50$ 520.00$ 182,000.00$ 478.58$ 167,503.00$ 683.00$ 239,050.00$ 710.00$ 248,500.00$ 684.14$ 239,449.00$

0008AC 72 In. Dia. CMP Culvert 296 LF 617.66$ 182,827.36$ 680.00$ 201,280.00$ 660.65$ 195,552.40$ 788.00$ 233,248.00$ 900.00$ 266,400.00$ 684.14$ 202,505.44$

0009 Corrugated Polyethylene (PE) Pipe

0009AA 24 In. Dia. Cor. PE Pipe 1,524 LF 115.61$ 176,189.64$ 175.00$ 266,700.00$ 118.61$ 180,761.64$ 105.00$ 160,020.00$ 155.00$ 236,220.00$ 171.04$ 260,664.96$

0009AB 30 In. Dia. Cor. PE Pipe 2,000 LF 109.94$ 219,880.00$ 211.50$ 423,000.00$ 139.41$ 278,820.00$ 131.00$ 262,000.00$ 190.00$ 380,000.00$ 205.24$ 410,480.00$

0009AC 36 In. Dia. Cor. PE Pipe 3,411 LF 140.82$ 480,337.02$ 243.75$ 831,431.25$ 158.14$ 539,415.54$ 158.00$ 538,938.00$ 220.00$ 750,420.00$ 218.93$ 746,770.23$

0009AD 48 In. Dia. Cor. PE Pipe 5,000 LF 153.03$ 765,150.00$ 257.25$ 1,286,250.00$ 232.89$ 1,164,450.00$ 210.00$ 1,050,000.00$ 260.00$ 1,300,000.00$ 314.71$ 1,573,550.00$

0010 10 In. Dia. PVC Service Pipe 820 SY 17.52$ 14,366.40$ 192.00$ 157,440.00$ 206.00$ 168,920.00$ 300.00$ 246,000.00$ 500.00$ 410,000.00$ 275.03$ 225,524.60$

0011 Precast Concrete Manhole

0011AA 48 In. Dia. Precast Concrete Manhole 5 EA 5,587.72$ 27,938.60$ 11,200.00$ 56,000.00$ 6,242.40$ 31,212.00$ 8,900.00$ 44,500.00$ 13,000.00$ 65,000.00$ 8,893.88$ 44,469.40$

0011AB 60 In. Dia. Precast Concrete Manhole 14 EA 6,528.88$ 91,404.32$ 13,500.00$ 189,000.00$ 8,323.20$ 116,524.80$ 10,500.00$ 147,000.00$ 15,000.00$ 210,000.00$ 12,040.95$ 168,573.30$

0011AC 72 In. Dia. Precast Concrete Manhole 14 EA 11,760.72$ 164,650.08$ 16,900.00$ 236,600.00$ 10,924.20$ 152,938.80$ 15,750.00$ 220,500.00$ 16,000.00$ 224,000.00$ 15,359.05$ 215,026.70$

0011AD 96 In. Dia. Precast Concrete Manhole 2 EA 14,076.98$ 28,153.96$ 28,200.00$ 56,400.00$ 22,368.60$ 44,737.20$ 27,000.00$ 54,000.00$ 30,000.00$ 60,000.00$ 29,623.47$ 59,246.94$

0012 Precast Concrete Headwall, 48" Dia. Pipe 2 EA 8,781.75$ 17,563.50$ 11,400.00$ 22,800.00$ 6,762.80$ 13,525.60$ 6,300.00$ 12,600.00$ 7,000.00$ 14,000.00$ 9,304.37$ 18,608.74$

0013 FLAP GATES

0013AA 48 In. Dia. Aluminum Flap Gate 2 EA 11,679.11$ 23,358.22$ 17,200.00$ 34,400.00$ 6,034.32$ 12,068.64$ 19,000.00$ 38,000.00$ 20,000.00$ 40,000.00$ 8,893.88$ 17,787.76$

0013AB 60 In. Dia. Aluminum Flap Gate 2 EA 18,108.05$ 36,216.10$ 21,300.00$ 42,600.00$ 7,907.04$ 15,814.08$ 23,000.00$ 46,000.00$ 28,000.00$ 56,000.00$ 11,630.46$ 23,260.92$

0014 STONE PRODUCTS

0014AA Bedding Material 200 TN 24.11$ 4,822.00$ 72.30$ 14,460.00$ 39.54$ 7,908.00$ 32.00$ 6,400.00$ 65.00$ 13,000.00$ 54.73$ 10,946.00$

0014AB RIPRAP, R90 540 TN 55.70$ 30,078.00$ 52.70$ 28,458.00$ 43.70$ 23,598.00$ 115.00$ 62,100.00$ 85.00$ 45,900.00$ 61.57$ 33,247.80$

0014AC Aggregate Base Course 42 TN 46.91$ 1,970.22$ 86.00$ 3,612.00$ 43.70$ 1,835.40$ 105.00$ 4,410.00$ 70.00$ 2,940.00$ 61.57$ 2,585.94$

0014AD Aggregate Surface Course 60 TN 39.87$ 2,392.20$ 71.00$ 4,260.00$ 43.70$ 2,622.00$ 105.00$ 6,300.00$ 65.00$ 3,900.00$ 61.57$ 3,694.20$

0015 Asphalt Paving 40 TN 185.61$ 7,424.40$ 435.00$ 17,400.00$ 296.51$ 11,860.40$ 249.00$ 9,960.00$ 215.00$ 8,600.00$ 410.49$ 16,419.60$

0016 DEBRIS REMOVAL 92 HL 1,621.90$ 149,214.80$ 330.00$ 30,360.00$ 582.62$ 53,601.04$ 1,050.00$ 96,600.00$ 1,400.00$ 128,800.00$ 992.01$ 91,264.92$

0017 CLEARING AND GRUBBING 32 AC 2,140.99$ 68,511.68$ 1,350.00$ 43,200.00$ 567.02$ 18,144.64$ 2,200.00$ 70,400.00$ 6,400.00$ 204,800.00$ 1,094.63$ 35,028.16$

0018 ESTABLISHMENT OF TURF 32 AC 3,127.07$ 100,066.24$ 1,990.00$ 63,680.00$ 1,967.76$ 62,968.32$ 1,900.00$ 60,800.00$ 2,900.00$ 92,800.00$ 2,873.41$ 91,949.12$

10,304,738.07$

33%

BIDDER #5

Jett's Specialty Contracting

913 Park Avenue

Paducah, KY 42001

Jerry B. Young Construction

Lebanon, TN 37090 Arkansas City, KS 67005BID OPENING DATE AND TIME: 08/31/2021 AT 1:30 PM COST

MEMPHIS

DISTRICT

ENGINEERING

NUMBER OF AMENDMENTS: 1

BASE CONTRACT: (STA 2+13 TO 341+71)

VARIATION FROM GOVT. EST.----------------------------------------------------------------->> -1% -22% -11%

GRAND TOTAL ITEMS 0001 THRU 0018 $9,955,816.15 7,774,232.59$ 8,859,409.00$ 9,816,218.75$

OFFICIAL ABSTRACT

US ARMY, CORPS OF ENGINEERS - MEMPHIS DISTRICT ABSTRACT OF BIDS

SMALL BUSINESS DETERMINATION: SDVOSB SET-ASIDE

BIDDER #3

INVITATION NO.: W912EQ-21-B-0009

GOVT. ESTIMATE BIDDER #1 BIDDER #2

33819 21st Road115 Stumpy Lane

Babcock SDV, LLC

Dexter, MO 63841

RKE Contractors

12965 Carrier Lane

TITLE: ISLAND 8 PARCEL 2 SEEPAGE REMEDIATION

BIDDER #4

HamHed, LLC

410 Wall Street

Jeffersonville, IN 47130

9,964,190.00$

2%

CEMVM 967 (REV. JAN 00)

ABSTRACT OF BIDS

2021-09-01T11:35:12-0500
MUSE.LATASHIA.A.1557281963
2021-09-01T12:32:31-0500
Priscilla G. Sweeney