This document is an Industry Day presentation for Tampa Harbor Navigation Improvements - Contract 1 (The Upper Channels), held on November 18, 2026, by the U.S. Army Corps of Engineers Jacksonville District in partnership with the Port of Tampa Bay and Moffatt & Nichol.

Contract 1 encompasses dredging and deepening of upper channels in Hillsborough County, Florida, with a total estimated volume of approximately 4.7 million cubic yards. Specific work areas include Cut-C (HB) North (470,000 CY), Cut-D (HB) South (620,000 CY), Port Sutton Channel and Turning Basin (1,280,000 CY), Port Sutton Terminal Channel (230,200 CY), East Bay Channel (910,000 CY), East Bay Channel Extensions 1 & 2 (580,000 CY), and non-federal berths (600,000 CY). Construction depths range from 41 to 49 feet with one foot of allowable overdepth. All dredged material will be disposed of in the East Bay Placement Area, DMMA 2-D, and DMMA 3-D. The acquisition approach is an unrestricted competitive procurement using the Best Value - Tradeoff process under FAA Part 15. The contract type is firm-fixed-price. Anticipated milestones include advertisement in May 2028, proposal receipt in July 2028, and award in September 2028. The estimated contract value ranges from $100,000,000 to $500,000,000 with an estimated period of performance of approximately 500 calendar days. The applicable NAICS code is 237990 (Dredging and Surface Cleanup Activities) with a small business size standard of $37.0 million. Environmental compliance requirements include manatee protection measures, turbidity monitoring, biological monitoring, and adherence to NMFS and USFWS biological opinions. No blasting is permitted. Contact information: Ruth C. Rodriguez (Contracting Officer) at Ruth.C.Rodriguez@usace.army.mil and Nicole M. Batista-Cruz (Contract Specialist) at Nicole.M.Batista-Cruz@usace.army.mil.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

TAMPA HARBOR

NAVIGATION IMPROVEMENTS - CONTRACT 1

THE UPPER CHANNELS

HILLSBOROUGH COUNTY, FLORIDA

INDUSTRY DAY

November 18, 2026

Presented by:

U.S. Army Corps of Engineers - Jacksonville District Port of Tampa Bay Moffatt & Nichol

AGENDA

Wednesday, 18 November 2026

9:00 a.m. – 10:00 a.m. Registration and Social 10:00 a.m. – 10:10 a.m. Opening Remarks 10:10 a.m. – 11:15 a.m. Presentations 11:15 a.m. – 11:45 p.m. Open Discussion and Questions 11:45 p.m. – 12:00 p.m. Closing Remarks 12:00 p.m. – 1:15 p.m. Lunch 1:15 p.m. – 4:40 p.m. Break-Out Sessions

*No site visit to the East Bay Placement Area is scheduled. Anyone interested will need to coordinate with the Port for access (POC is Nick Depin).

Opening Remarks Port of Tampa Bay and USACE

• Project Overview and Schedule – Manny Vianzon, Project Manager

• Engineering and Design – Katie Barry, P.E., Engineering Team Lead

• Geotechnical Data – Barbara Nist, P.G., Project Geologist

• East Bay Placement Area – Moffatt & Nichol

• Environmental – Aaron Lassiter, Environmental Team Lead

• Procurement Strategy – Ruth Rodriguez, Contracting Officer

• Discussion and Questions

TOPICS OF DISCUSSION

Project Overview and Schedule

Manny Vianzon – Project Manager

TAMPA HARBOR IMPROVEMENTS - OVERVIEW

Project Authority

• 43' to 47' Project: Chief of Engineers Report signed 14 AUG 2024

• Water Resources Development Act (WRDA): Authorized by Congress in 2024.

Primary Objectives

• Reduce marine transportation costs and improve efficiencies for deep-draft vessels.

• Enhance maneuverability and transit safety in the federal channel.

Recommended Plan/Scope

• Deepening: Deepen the main channel from 43 ft to 47 ft, with Egmont Cuts deepened to 49

ft. Deepen upper channels (Port Sutton, Sparkman, Ybor) to previously authorized depths.

• Widening & Extensions: Implement several turn wideners and extend the entrance channel to access natural deep water.

• Beneficial Use: Maximize the beneficial use of dredged material for habitat creation (Egmont

Key, hardbottom creation), and port expansion.

Project History:

• Real Estate Acquisition

• Relocations (if needed)

• Plans & Specifications Final

• Construction

PROJECT SCHEDULE

ABM MEETING

10 MAR 2022

CHIEF’S REPORT

SIGNED

22 AUG 2024

PUBLIC COMMENT ON

DRAFT REPORT

JUL 2023

DEVELOPMENT OF

BUDM OPTIONS

APR-OCT 2022

FEASIBILITY STUDY (2021-2024)

31 2 4

PRECONSTRUCTION

ENGINEERING DESIGN (2025-2027)

CONGRESSIONAL

AUTHORIZATION

WRDA 2024

CONSTRUCTION PHASE (2028+)

Chief’s Report signed 22 AUG 2024 Congressional Authorization received WRDA 2024 Design Agreement signed 16 SEP 2025 Appropriations for PED received 2025 PED Phase initiated DEC 2025 New Start Selection required subject to the FY28 approval of Construction Appropriations Scheduled Contract 1 Award – SEP 2028

Design Data Collection Begin Plans &

Specifications WQC Permitting Detailed Design

Non-Federal Sponsor: Port Tampa Bay

NEW START

SELECTION

SUBJECT TO FY28

Construction

Appropriations

PROJECT SCHEDULE - KEY MILESTONES

Key Milestone Dates for Contract 1

• Geotech Data Collection Complete & Lab Results Received – November 2026

• Final DEP WQC Permit for Federal Channel Issued – July 2027

• Draft P&S Complete – July 2027

• BCOES Certification – February 2028

• Advertisement – May 2028

• Award – September 2028

PLAN COMPONENTS:

Incremental Deepening to 43’ to 47’ (Main Stem + Big Bend Channel) Egmont Cuts 1 and 2 deepened to 45’ to 49’ to account for increased wind/waves present in the Gulf of Mexico

Upper Channel Deepening 34’ to 42’:

Port Sutton Sparkman (Upper & Lower) Ybor Channel East Bay Extension Cuts

Entrance Extension 9,900’ to access natural depths consistent with channel deepening Extension of Federal Channel 34’ to 47’:

Big Bend East Channel East Bay Channel

Turn Widener Improvements 32’ TO 47’:

Cut F (TB) to Gadsden Point Cut Cut C (HB) to Big Bend Channel Cut C (HB) at Alafia River Channel Hooker’s Point to Port Sutton

East Bay Turning Basin Improvements Project to be Deepened under 6

Contracts

RECOMMENDED PLAN (LOCALLY PREFERRED PLAN)

TAMPA HARBOR DEEPENING CONTRACTS & SCHEDULE

Engineering Overview

Katie Barry, P.E. – Engineering Team Lead

FEDERAL CHANNEL DREDGING OVERVIEW

Contract 1 – Upper Channels

• Cut-C (HB) North

• Cut-D (HB) South

• Port Sutton Channel

• Port Sutton Turning Basin

• Port Sutton Terminal Channel

• East Bay Channel

• East Bay Channel Extension 1

• East Bay Channel Extension 2

Designated Placement Areas

• East Bay Placement Area (primary)

• DMMA 2-D and 3-D

The project includes construction dredging to deepen and widen specified areas within the federal navigation channel of Tampa Harbor. All areas of deepening and widening will incorporate +1 foot of allowable overdepth. All dredged material from the project will be disposed of in the East Bay Placement Area, DMMA 2-D, and DMMA 3-D. Total estimated quantity to be dredged is approximately 4.7 million cubic yards, which includes ~4.1 million cubic yards from the federal channel and ~0.6 million cubic yards from the non-federal berths.

PROJECT SCOPE OF WORK

Channel Name Current Authorized Maintained Depth

(FT, MLLW)

Construction Depth (FT, MLLW)

Post-Construction Authorized Depth

(FT, MLLW)

Port Sutton Channel 43+2 49+1 47+2 Port Sutton Turning Basin 43+2 49+1 47+2

Port Sutton Terminal Channel 42+2 *Currently constructed to 34+2

44+1 42+2

East Bay Channel 43+2 49+1 47+2 East Bay Channel Ext. 1 34+2 41+1 39+2 East Bay Channel Ext. 2 34+2 41+1 39+2 Cut-C (HB) (North) 43+2 49+1 47+2 Cut-D (HB) (South) 41+2 49+1 47+2

HILLSBOROUGH BAY (HB) CUT-C NORTH

Station 313+00 to Station 341+77.21

Construction Dredging Depth:

49’ Req. + 1’ AO

Estimated O&M* Volume to be Dredged:

240,000 CY (43’ Req. + 2’ AO)

Estimated Construction Volume to be Dredged: 230,000 CY

Total Estimated Volume to be Dredged:

470,000 CY

*O&M dredging may be performed under a separate contract prior to Contract 1

HILLSBOROUGH BAY (HB) CUT-D SOUTH

Station 2+62.20 to Station 59+00 Utility crossing located at Station 64+00 s (red line)

Construction Dredging Depth:

49’ Req. + 1’ AO

Estimated O&M* Volume to be Dredged:

40,000 CY (41’ Req. + 2’ AO)

Estimated Construction Volume to be Dredged: 580,000 CY

620,000 CY

PORT SUTTON CHANNEL & TURNING BASIN

Station 0+00 to Station 21+55 Existing utility crossing not impacted (red line)

Construction Dredging Depth:

49’ Req. + 1’ AO

Estimated O&M* Volume to be Dredged:

190,000 CY (43’ Req. + 2’ AO)

Estimated Construction Volume to be Dredged: 1,090,000 CY

Total Estimated Volume to be Dredged:

1,280,000 CY

PORT SUTTON TERMINAL CHANNEL

Station 21+55.01 to Station 71+00 (through Berth 23)

Construction Dredging Depth:

44’ Req. + 1’ AO

Estimated O&M* Volume to be Dredged:

200 CY (34’ Req. + 2’ AO)

Estimated Construction Volume to be Dredged: 230,000 CY

230,200 CY

EAST BAY CHANNEL

Station 0+00 to Station 57+62

Construction Dredging Depth:

49’ Req. + 1’ AO

Estimated O&M* Volume to be Dredged:

190,000 CY (43’ Req. + 2’ AO)

Estimated Construction Volume to be Dredged: 720,000 CY

Total Estimated Volume to be Dredged:

910,000 CY

EAST BAY CHANNEL EXTENSION 1 & 2

Station 0+00 EBC Ext. (1) to Station 29+88.87 EBC Ext. (2)

Construction Dredging Depth:

41’ Req. + 1’ AO

Estimated O&M* Volume to be Dredged:

50,000 CY (34’ Req. + 2’ AO)

Estimated Construction Volume to be Dredged: 530,000 CY

Total Estimated Volume to be Dredged:

580,000 CY

NON-FEDERAL BERTHS

Includes 25 berths, and potentially 4 additional:

1, 2, 3, 30, 31, 139, 150, 151, 201, 202, 204, 205, 208, 209, 210, 211, 212, 213, 214, 218, 219, 220, 222, 223, 227, and potentially 23, 142, 143, & 145

Initial assumption includes a 50-foot dredging offset from the bulkheads, but it could be closer based on structural analysis of each berth.

Volume of material to be dredged from the berths is approximately 600,000 CY.

CONTRACT 1 TOTAL VOLUME SUMMARY

TOTAL Estimated O&M* Volume to be Dredged: 710,200 CY

TOTAL Estimated Construction Volume to be Dredged: 3,380,000 CY

TOTAL Estimated Berth Volume to be Dredged: 600,000 CY

TOTAL Estimated Volume to be Dredged: 4,690,200 CY (~4.7M CY)

Geotechnical Data Barbara Nist, P.G. – Project Geologist

GEOTECHNICAL DATA – MATERIAL TYPES

Marine Muck

Competent Rock

De-composed

Rock

• 60-100% Silt

• >200% Water Content

• 0 N-Value - WOR

• Highly Weathered

• Clayey non-plastic matrix

• Rock Fragments - Layers

• 5-20 N-Values

• Limestone or Sandstone

• 0.2 - 3 ft Bedding

• Pitted, Vuggy

• Strength < 2000 psi

3”

7”

2”

28 SPT/Core Borings

GEOTECHNICAL DATA – MATERIAL DISTRIBUTION

East Bay Extensions 1&2

2-3 ft Muck

4-5 ft Decomp.

Rock

East Bay

2 ft Muck

2-3 ft Decomp.

Rock

2-3 ft Competent Rock

Port Sutton & Turning Basin

3-5 ft Muck

2-4 ft Decomp.

Rock

Port Sutton Terminal Channel

1-5 ft Muck

3-6 ft Decomp.

Rock

1-3 ft Competent Rock

HB Cut-D

1-2 ft Muck

4-5 ft Competent Rock

HB Cut-C

1-2 ft Muck

2-3 ft Decomp.

Rock

3-5 ft Competent Rock

1-3 ft Decomp.

Rock

O&M 240,000 CY

Deep. 230,000 CY

O&M 40,000 CY

Deep. 580,000 CY

O&M 50,000 CY

Deep. 580,000 CY

O&M 190,000 CY

Deep. 1,090,000 CY

O&M 190,000 CY

Deep. 720,000 CY

O&M 200 CY

Deep. 230,000 CY

GEOTECHNICAL DATA – MATERIAL IN WIDENERS

Widener SouthWidener North

5-15 ft Muck

2-10 ft Decomp.

Rock , or Clay

4-5 ft Competent Rock

Widener North

Widener South

0-15 ft Sand

SP,SM, SC

10-15 ft Muck

0-15 ft Decomp.

Rock

0-15 ft Sand

SP,SM, SC

Materials to be Removed are 10-40 ft Thick

East Bay Placement Area

11/18/2026

USACE Harbor Deepening Contract 1 – Industry Day Brian Shaw, PE, SE Geotech Discipline Lead Moffatt & Nichol

Full Buildout – Site Plan

Full Buildout – Typical Section

Geotechnical Data

Muck Probes

Sequence of Construction

Partially Completed Dike

Sequence of Construction

Environmental Overview

Aaron Lassiter – Environmental Team Lead

ENVIRONMENTAL COMPLIANCE

• Sea turtle take is a low concern for Contract 1

• Harbor Improvements have Biological Opinions under NMFS and USFWS

• No blasting of any type shall occur within the project area

• NMFS 2021 Protected Species Construction Conditions and NMFS’ Southeast Region Vessel Strike Avoidance Measures and Reporting for Mariners

• Special conditions for hopper dredging

• NMFS BO requires project to follow SARBO

• Programmatic USFWS SPBO, & P3BO

ENVIRONMENTAL COMPLIANCE

• Two (2) dedicated, qualified manatee observers will be present for ALL dredging work conducted between November 1 and March 31

WWAA /IMA and additional area restrictions

– Dredging restriction: November 15 – March 31: No dredging

(Includes additional closure area)

– No clamshell dredging activities between sunset and sunrise.

– Qualified observers are required during any clamshell dredging.

– Pipelines: placement outside of the manatee wintering period to the maximum extent possible (outside of November 15 - March 31).**

MANATEES - WWAA & IMA – CONTRACT 1

Port Sutton

IMA

Port Sutton

WWAA

Additional seasonal closure area west of Port Sutton IMA and

WWAA

• Turbidity Barriers: May be required prior to initiation of any work authorized by the water quality permit. Curtains with weighted skirts, extending six feet downward from the water surface may need to surround all work areas in, or adjacent to, surface waters.

• Turbidity Monitoring: Independent third party with formal training in water quality monitoring required.

• Biological Monitoring Qualifications: Must be submitted to USACE and FDEP for review and approval at least 30-days prior to a monitoring event.

• Submerged Aquatic Vegetation (SAV): Contractor(s) shall avoid impacts to SAV in or around the project area.

ENVIRONMENTAL MONITORING

Contracting Overview Ruth C. Rodriguez – Contracting Officer

• Unrestricted Procurement • RFO 52.219-4 o Notice of Price Evaluation Preference for HUBZone Small Business Concerns o RFO 52.219-9 Small Business Subcontracting Plan

• RFO Part 15 - Contracting by Negotiation - Request for Proposal (RFP) o Best Value - Tradeoff Process (RFO 15.103-1) o Other procedures established in the RFO or supplements pertinent to the requirement

• Type of contract: Firm-fixed-price o A firm-fixed-price contract provides for a price that is not subject to any adjustment on the basis of the contractor’s experience in performing the contract. (RFO 16.202-1)

ACQUISITION APPROACH

Ruth C. Rodriguez, Contracting Officer Email: Ruth.C.Rodriguez@usace.army.mil Nicole M. Batista-Cruz, Contract Specialist Email: Nicole.M.Batista-Cruz@usace.army.mil

• Anticipated Milestones o Advertisement - May 2028 o Receive Proposals - July 2028 o Award - September 2028

• Estimated Target Range: $100,000,000 - $500,000,000

• Estimated Period of Performance: 500 calendar days (approximately).

• Applicable North American Industry Classification System (NAICS) code is 237990 (Exception), Dredging and Surface Cleanup Activities. The Small Business Size Standard for dredging is $37.0 million.

ACQUISITION APPROACH

mailto:Ruth.C.Rodriguez@usace.army.mil mailto:Nicole.M.Batista-Cruz@usace.army.mil mailto:Nicole.M.Batista-Cruz@usace.army.mil mailto:Nicole.M.Batista-Cruz@usace.army.mil

• Systems for Award Management o www.sam.gov

• Procurement Integrated Enterprise Environment o https://piee.eb.mil/

• USACE Jacksonville District o https://www.saj.usace.army.mil/

• Small Business Search o https://search.certifications.sba.gov/

RESOURCES

http://www.sam.gov/ http://www.sam.gov/ https://piee.eb.mil/ https://piee.eb.mil/ https://www.saj.usace.army.mil/ https://www.saj.usace.army.mil/ https://search.certifications.sba.gov/ https://search.certifications.sba.gov/

• RFO 19.201 - Government Policy

(a) It is the policy of the Government to provide maximum practicable opportunities in its acquisitions to small business, veteran-owned small business, service-disabled veteran-owned small business, HUBZone small business, small disadvantaged business, and women-owned small business concerns. Such concerns must also have the maximum practicable opportunity to participate as subcontractors in the contracts awarded by any executive agency, consistent with efficient contract performance.

SMALL BUSINESS OPPORTUNITIES

• Setting aside requirements for Small Business

• Conducting market research to identify qualified Small Business firms

• Utilizing Mentor-protégé programs

• Utilizing subnet to solicit subcontracting opportunities

• Utilizing the Small Business Administration and local Procurement Technical Assistance Centers (PTACs) for assistance

• Small Business Subcontracting Plan – not applicable to small business concerns.

o The offeror shall submit a subcontracting plan to the Contracting Officer for review and approval as part of their proposal. The subcontracting plan must be based on the specific RFO Clause 52.219-9 Alternate used.

o Acceptability of the plan will be one of the elements considered by the Contracting Officer when determining contractor responsibility prior to award of a contract.

o Contractors should propose small business subcontracting goals that are meaningful and realistic with positive percentage goals for the specific procurement.

• Potential Sub-Contracting Opportunities Exist for:

o Services: surveyor, material testing, environmental monitoring, species monitoring, partnering, etc.

o Suppliers: Equipment

Note: This list is not all inclusive of potential sub-contracting opportunities.

SMALL BUSINESS/SUB-CONTRACTING

• Kimberly Daniel-Ray, Deputy for Small Business Programs o Kimberly.S.Danielray@usace.army.mil

• Alexandria (Alex) Lavey, Small Business Professional o Alexandria.Lavey@usace.army.mil

JACKSONVILLE DISTRICT OFFICE OF SMALL

BUSINESS PROGRAMS

mailto:Kimberly.S.Danielray@usace.army.mil mailto:Kimberly.S.Danielray@usace.army.mil mailto:Alexandria.Lavey@usace.army.mil mailto:Alexandria.Lavey@usace.army.mil

Discussion and Questions

���Tampa HARBOR �navigation improvements - contract 1��The Upper Channels �Hillsborough County, Florida
Agenda
Slide Number 3
TOPICS OF DISCUSSION
Slide Number 5
�
�
PROJECT Schedule - Key Milestones
Slide Number 9
Slide Number 10
Slide Number 11
Federal Channel Dredging Overview
Project Scope of Work
Hillsborough Bay (HB) Cut-c north
Hillsborough Bay (HB) Cut-D SOUTH
Port Sutton channel & turning basin
Port Sutton Terminal channel
East bay channel
East bay channel extension 1 & 2
Non-Federal Berths
Contract 1 TOTAL volume summary
Slide Number 22
Geotechnical data – Material Types
Geotechnical data – Material Distribution
Geotechnical data – Material in Wideners
East Bay Placement Area
Slide Number 27
Slide Number 28
Slide Number 29
Slide Number 30
Slide Number 31
Slide Number 32
Slide Number 34
Environmental compliance
Environmental compliance
Environmental monitoring
Slide Number 38
ACQUISITION APPROACH
ACQUISITION APPROACH
RESOURCES
SMALL BUSINESS OPPORTUNITIES
SMALL BUSINESS OPPORTUNITIES
SMALL BUSINESS OPPORTUNITIES
SMALL BUSINESS/SUB-CONTRACTING