This is a presentation document from the Jacksonville District of the U.S. Army Corps of Engineers detailing the Coastal & Navigation Program quarterly industry briefing held on July 13, 2026. The presentation provides a comprehensive overview of upcoming contract advertisements for dredging and coastal projects managed by the Water Resources Branch across Florida and Georgia.
The document outlines 2026 remaining advertisements and 2027 scheduled advertisements for navigation and coastal projects. For 2026, navigation projects include Kings Bay Entrance Channel (Unrestricted IFB, 1.1M CY, advertised July 2026, award September 2026), Banana River NASA O&M (Small Business MATOC, 500K CY, advertised July 2026, award September 2026), Palm Beach Harbor O&M (Unrestricted IFB, 100K CY, advertised July 2026), Everglades Harbor (Small Business MATOC, 89K CY, advertised July 2026), Port Everglades O&M (Unrestricted IFB, 400K CY, advertised July 2026), Fort Pierce Harbor (Unrestricted IFB, 150K CY, advertised September 2026), Jacksonville Harbor (Unrestricted IFB, 750K CY, advertised October 2026), Pass A Grille Pass (Small Business MATOC, 100K CY, advertised October 2026), and GIWW Caloosahatchee to Anclote River (advertised November 2026). Coastal projects include Manatee County SPP (Unrestricted IFB, 1M CY, advertised July 2026) and Broward County Segment II (Unrestricted IFB, 360K CY, advertised September 2026). For 2027, major projects include Naval Station Mayport (Unrestricted IFB, 1M CY, advertised February 2027), Kings Bay Subbase (Small Business MATOC, 1.5M CY, advertised February 2027), Kennedy Space Center SPP (Unrestricted IFB, 2.5M CY, advertised June 2027), and multiple additional harbor and waterway dredging projects. Most solicitations are advertised as Invitations for Bid (IFB) or Multiple Award Task Orders Contracts (MATOC) with varying small business set-asides. Work windows and environmental restrictions, such as turtle protection windows, are noted for applicable projects.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
JACKSONVILLE DISTRICT
COASTAL & NAVIGATION PROGRAM
QUARTERLY INDUSTRY DAY
Presented by: Jason Harrah, Acting Chief
Water Resources Branch
July 13, 2026
Georgia
Florida
Gulf of America
Atlantic Ocean
St. Lucie County, HSDR
Duval County SPP ‘2024’
Nassau County SPP** ‘2025’
Ft. Pierce SPP ‘2026
Broward County – Seg II ‘2022’
Dade County – Sunny Isles ‘2021’
Manatee County SPP ’2020’
Lee County Gasparilla ‘2019’ Lee County Captiva 2025 (NF) Lee County Estero Island 2025(NF)
Sarasota Lido Key ‘2026’ Sarasota Venice ‘2026’
Pinellas Sand Key 2025(NF) Pinellas Treasure Isl. 2025(NF) Pinellas Long Key 2025(NF)
Martin County SPP** ‘2026’
Flagler County CSRM ‘2024’
Miami – Dade County Back Bay
‘Date of Last Renourishment’ (NF) = Non-Fed Renourishment
COASTAL PROJECTS
FLOOD RISK MANAGEMENT (FRM) / COASTAL
STORM RISK MANAGEMENT (CSRM)
28 Constructed CSRM Segments 5 Authorized Unconstructed Projects (2 x IIS) 6 Feasibility Studies
Daytona Beach FRM (Termination Underway)
Collier County CSRM (Terminated)
Charlotte Co (Termination Underway)
Key Biscayne Study (Termination Underway)
Kennedy Space Center (IIS)
Ponte Vedra Beach CSRM ‘N/A’ Vilano Beach CSRM ‘2024’ St. Augustine Back Bay CSRM Study (Termination Underway)
St. Johns County SPP (St. Aug Beach)** ‘2024’
Monroe County – Florida Keys
Naval Station Mayport (IIS)
4 Rivers Basins Project
4 - Rivers Basin Project (SWFWMD)
St. Lucie County Hutchinson CSRM ‘2026
Brevard County North Reach** ‘2025’ Brevard County Mid Reach ‘2025’ Brevard County South Reach** ‘2021’
PBC – Jupiter Carlin** ‘2020’ PBC – Ocean Ridge** ‘2026’ PBC – Delray ‘2026’
PBC – North Boca ‘2020’ PBC – Mid-Town ‘2026’
Dade County – Main Seg ‘2025’
Broward County – Seg III ‘2024’
Atlantic Ocean
Georgia
St. Augustine Inlet (10’-16’)
Palm Beach Harbor (33’)
Key West (8-34’) & N.S. Key West (34’)
NSB Kings Bay Subbase & Entrance Channel (44’-49’)
Ponce de Leon Inlet (7’-15’)
Johns Pass(6-10’)
Port Everglades (31’-42’) Bakers Haulover Inlet (8’-11’)
Miami Harbor (34’ - 50’)
IWW – Jax to Miami (10’)
Everglades Harbor (8’)
Naples to Big Marco Pass (6’-12’)
Steinhatchee River (6’) Horseshoe Cove (6’)
Ft. Harbor (28’)
St. Lucie Inlet (7 - 16’)
IWW – Jacksonville to Miami (10 - 12’)
14 Deep Draft Harbors 4 Designated as a South Atlantic Division Top Ten Deep Draft Harbor
42 Shallow Draft Projects
1 Ongoing Feasibility Study (Miami Harbor) 2 New Harbor Improvements Authorized
(Port Everglades and Tampa Harbor) 900 miles of Inland Waterways 6 Navigation Locks Intracoastal Waterway (IWW) from
Jacksonville to Miami Okeechobee Waterway (OWW) connecting the
Atlantic Ocean to the Gulf of America Parts of the Gulf Intracoastal Waterway (GIWW) from the Caloosahatchee River to Anclote River
(Authorized Depths)
Okeechobee Water Way (8’-10’)
Florida
AIWW – Norfolk to St. Johns River (12’) Jacksonville Harbor (30’-47’); MCSF Blount Island (38’); NS Mayport (50’)
Tampa Harbor (32’-43’)
(Authorized Depths)
Fernandina Harbor (36’)
Port Canaveral/NOTU (35’-46’) Canaveral Barge Canal (12’) Banana River NASA Channel (12’)
Cedar Island/Keaton Beach (4’)
Anclote River (9’) Clearwater Pass (8’-10’)
Pass A Grille (8’)St. Pete Harbor (24’)
Port Manatee (40’) Longboat Pass (10’-12’)
New Pass (8’-10’)
Charlotte Harbor (10’-32’) GIWW – CR to AR (9’)
Fort Myers (11’-12’)
Casey’s Pass (Venice Inlet) (9’)
Suwannee River (6’)
Gulf of America
NAVIGATION PROJECTS
Florida
Atlantic Ocean
Georgia
Melbourne Harbor (8’)
New River (8’)
Hillsboro Inlet(8’)
(authorized but not currently active)
Rice Creek (12’)
Largo Sound Channel(6’)
Eau Gallie Harbor (8’)
Miami River (15’)
Oklawaha River (6’)
Lake Crescent to Dunns Creek(8’)
Taylor Creek (6’)
Orange River (4’)
Cedar Keys Harbor(6’)
Crystal River (6’) Homosassa River (5’)
Pithalachascotee River (6’)
Withlacoochee River (10’)
St Johns River Jacksonville to Lake Harney (5’-13’)
Courtenay Channel(8’)
Boot Key Harbor (12’)
Gulf of America
NAVIGATION PROJECTS
Jason Harrah, Acting Chief jason.s.harrah@usace.army.mil Water Resources Branch Senior Project Manager Duval, St. Johns, Flagler, Jacksonville Harbor, St. Augustine Inlet
Ashleigh Fountain, Acting Chief Florida Gulf Coastal & Navigation Projects Section
JACKSONVILLE DISTRICT
WATER RESOURCES BRANCH – PROJECT MANAGERS
Beau Corbett, Acting Chief
Florida Atlantic Coastal & Navigation
Projects Section
Eduardo Marin, P.E.
AIWW
IWW
GIWW
OWW
Ponce Inlet
Chris Ren, PMP Brevard
Canaveral Kennedy
Banana River
Manny Vianzon
Tampa Harbor St. Pete Harbor
Jim LaGrone St. Lucie Volusia Martin
Stephen Meyer, P.E.
Broward Port Everglades
Chris McNees
Palm Beach Miami-Dade Key Biscayne
Palm Beach Harbor Miami Harbor
Brooke Schuchart, EI
Pinellas Lee
Charlotte SW Gulf
Channels
William Aley, PG Monroe Sarasota Manatee
Collier Port Manatee
Key West Harbor
Lindsay Brantley
4-Rivers Basin Cedar Island/ Keaton Beach
Steinhatchee River Horseshoe Cove
Geoff Klug, PE Nassau
Fernandina Harbor Kings Bay
2026 – REMAINING ADVERTISEMENTS
Navigation Projects Kings Bay Entrance Channel 10 Jul 26 Banana River 21 Jul 26 Palm Beach Harbor O&M 21 Jul 26 Everglades Harbor 21 Jul 26 Port Everglades O&M 31 Jul 26 Ft. Pierce Harbor 10 Sep 26 Palm Beach Harbor Jetty 16 Sep 26 Jacksonville Harbor 13 Oct 26 Pass A Grille Pass 30 Oct 26 GIWW CR to AR 20 Nov 26
Coastal Projects Manatee County SPP 13 Jul 26 Broward County Segment II 25 Sep 26
Dates Subject to Change
NAVY: KINGS BAY ENTRANCE CHANNEL
LOCATION: Camden County, GA / Nassau County, FL
DREDGE TYPE: Unrestricted PLACEMENT:
Beach, Nearshore, ODMDS QUANTITY: 1.1M CY
DEPTH: 46’
BUSINESS TYPE: IFB- Unrestricted ADVERTISE:
JUL 2026
BID OPENING: AUG 2026
AWARD: SEP 2026
COMMENCE DREDGING: DEC 2026 DREDGE
COMPLETE: MAR 2027 WORK RESTRICTIONS/
WINDOW: Turtle window – 15 Dec - 31 Mar*
CMMC LEVEL 1 REVIEW: CMMC, CUI, FCI not present in solicitation.
* Navy has chosen to voluntarily abide by "old" endangered species environmental window. Working Today to Build a Better Tomorrow
BANANA RIVER (NASA) O&M
LOCATION: Brevard County, Florida
DREDGE TYPE: Cutter-Suction
PLACEMENT: Upland DMMA(s)
QUANTITY: ~500k CY (TBD)
BUSINESS TYPE: Small Business MATOC
ADVERTISE: JUL 2026
BID OPENING: AUG 2026
AWARD: SEP 2026
COMMENCE DREDGING: NOV 2026
DREDGE COMPLETE: JUN 2027 WORK
RESTRICTIONS/WINDOW: N/A
CMMC LEVEL 1 REVIEW: CMMC, CUI,
FCI not present in solicitation.
Working Today to Build a Better Tomorrow
PALM BEACH HARBOR
LOCATION: Palm Beach County
DREDGE TYPE: Hopper/Cutter-suction
PLACEMENT: Nearshore Placement
QUANTITY: 100K CY
DEPTH: 25’ - 39’
BUSINESS TYPE: IFB - Unrestricted
ADVERTISE: JUL 2026
BID OPENING: AUG 2026
AWARD: SEP 2026
COMMENCE DREDGING: JAN 2027
DREDGE COMPLETE: MAR 2027
WORK RESTRICTIONS/WINDOW: N/A
EVERGLADES HARBOR, FL O&M
LOCATION: Collier County, Florida DREDGE TYPE: Cutter-suction PLACEMENT: In water Beneficial Use
QUANTITY: 89K CY
DEPTH: 8’
BUSINESS TYPE: MATOC – Small Business
ADVERTISE: JUL 2026
BID OPENING: AUG 2026
AWARD: SEP 2026
COMMENCE DREDGING: NOV 2026
DREDGE COMPLETE: FEB 2027
PORT EVERGLADES HARBOR O&M
LOCATION: Broward County, Florida DREDGE TYPE: Hopper/Bucket
PLACEMENT: ODMDS
QUANTITY: 400k CY
DEPTH: 45’
BUSINESS TYPE: IFB
ADVERTISE: JUL 2026
BID OPENING: AUG 2026
AWARD: SEP 2026
COMMENCE DREDGING: DEC 2026
DREDGE COMPLETE: APR 2027
FORT PIERCE HARBOR O&M
LOCATION: St Lucie County, FL
DREDGE TYPE: Hopper/Cutter-Suction
PLACEMENT: Beach
QUANTITY: 150 KCY
DEPTH: 28’ - 30’
BUSINESS TYPE: IFB - Unrestricted
ADVERTISE: SEP 2026
BID OPENING: OCT 2026
AWARD: NOV 2026
COMMENCE DREDGING: FEB 2027
DREDGE COMPLETE: MAY 2027
LOCATION: Duval County, FL
DREDGE TYPE: Hopper/Mechanical
PLACEMENT: ODMDS / Upland
QUANTITY: 750k CY
DEPTH: 47’ to Blount Island Terminal
40’ Blount Island to Talleyrand Terminal
BUSINESS TYPE: IFB - Unrestricted
ADVERTISE: OCT 2026
BID OPENING: NOV 2026
AWARD: DEC 2026
COMMENCE DREDGING: FEB 2027
DREDGE COMPLETE: AUG 2028
WORK RESTRICTIONS/WINDOW: N/A
JACKSONVILLE HARBOR O&M
PASS-A-GRILLE PASS O&M
LOCATION: Pinellas County, Florida DREDGE TYPE: Cutter-suction PLACEMENT: Beach QUANTITY: 100k CY
BUSINESS TYPE: MATOC – Small Business
ADVERTISE: OCT 2026
BID OPENING: DEC 2026
AWARD: JAN 2027
COMMENCE DREDGING: MAR 2027
DREDGE COMPLETE: MAY 2027
Pass-A-Grille Pass
GIWW MANATEE COUNTY O&M
LOCATION: Manatee County, FL
DREDGE TYPE: Cutter-suction
PLACEMENT: Nearshore
QUANTITY: 80K CY
DEPTH: 9’
BUSINESS TYPE: MATOC – Small Business
ADVERTISE: NOV 2026
BID OPENING: JAN 2027
AWARD: FEB 2027
COMMENCE DREDGING: ~MAY 2027
DREDGE COMPLETE: ~MAR 2028
MANATEE CO SPP – ANNA MARIA ISLAND
LOCATION: Manatee County, FL
DREDGE TYPE: Hopper/Cutter-Suction
PLACEMENT: Beach
QUANTITY: 1M CY
BUSINESS TYPE: IFB - Unrestricted
ADVERTISE: JUL 2026
BID OPENING: AUG 2026
AWARD: SEP 2026
COMMENCE DREDGING: NOV 2026
DREDGE COMPLETE: APR 2027
BROWARD COUNTY – SEGMENT II
LOCATION: Broward County
DREDGE TYPE: Truck Haul
PLACEMENT: Beach
QUANTITY: 360K CY
BUSINESS TYPE: IFB - Unrestricted
ADVERTISE: SEP 2026
BID OPENING: OCT 2026
AWARD: NOV 2026
COMMENCE PLACEMENT: ~FEB - MAR 2027
PLACEMENT COMPLETE: ~APR 2028
WORK RESTRICTIONS/WINDOW:
Turtle Window: 1 NOV – 30 APR
2027 – SCHEDULED ADVERTISEMENTS
Navigation Projects Naval Station Mayport 9 Feb 27 Kings Bay Subbase 12 Feb 27 St. Lucie Inlet 26 Mar 27 USMC Blount Island 4 May 27 Tampa Harbor Alafia 31 May 27 IWW Jax to Miami (Matanzas) 7 Jul 27 Naples to Big Marco Pass 12 Jul 27
Coastal Projects Kennedy Space Center 21 Jun 27 Naval Station Mayport 10 Aug 27
Dates Subject to Change
NAVAL STATION MAYPORT
LOCATION: Duval County, FL
DREDGE TYPE:
Unrestricted/Bucket/Hopper
PLACEMENT: ODMDS
QUANTITY: 1 M CY
DEPTH: Varies 27’, 35’, 42’, 50’
BUSINESS TYPE: IFB - Unrestricted
ADVERTISE: FEB 2027
BID OPENING: MAR 2027
AWARD: APR 2027
COMMENCE DREDGING: JUN 2027
DREDGE COMPLETE: DEC 2027 WORK
RESTRICTIONS/WINDOW: N/A
CMMC LEVEL 1 REVIEW: CMMC, CUI,
KINGS BAY SUBBASE
LOCATION: Camden County, GA
DREDGE TYPE: Cutter-suction PLACEMENT: Upland
QUANTITY: 1.5M CY
DEPTH: 44’-46’/38’
BUSINESS TYPE: MATOC – Small Business
ADVERTISE: FEB 2027
BID OPENING: MAR 2027
AWARD: MAY 2027
COMMENCE DREDGING: AUG 2027
DREDGE COMPLETE: JUN 2028 WORK
RESTRICTIONS/WINDOW: N/A
CMMC LEVEL 1 REVIEW: CMMC, CUI, FCI
not present in solicitation.
21MARINE CORPS SUPPORT FACILITY
BLOUNT ISLAND
LOCATION: Duval County, FL DREDGE
TYPE: Unrestricted PLACEMENT:
ODMDS
QUANTITY: 135 KCY
DEPTH: 38’
BUSINESS TYPE: TBD
ADVERTISE: MAY 2027
BID OPENING: JUN 2027
AWARD: JUL 2027
COMMENCE DREDGING: SEP 2027
DREDGE COMPLETE: FEB 2028 WORK
RESTRICTIONS/WINDOW: N/A
CMMC LEVEL 1 REVIEW: CMMC, CUI,
TAMPA HARBOR: MAINTENANCE
ALAFIA RIVER
LOCATION: Hillsborough County, FL
DREDGE TYPE: Cutter-Suction/Bucket
PLACEMENT: DMMA 3-D
QUANTITY: 250k CY
BUSINESS TYPE: Small Business MATOC
ADVERTISE: JUN 2027
BID OPENING: JUL 2027
AWARD: AUG 2027
COMMENCE DREDGING: DEC 2027
DREDGE COMPLETE: MAY 2028
IWW JAX TO MIAMI:
VICINITY OF MATANZAS INLET
LOCATION: St. Johns County, Florida DREDGE TYPE: Cutter-suction PLACEMENT: Summer Haven Beach
QUANTITY: 300K CY
DEPTH: 12’
BUSINESS TYPE: MATOC – Small Business
ADVERTISE: JUL 2027
BID OPENING: AUG 2027
AWARD: SEP 2027
COMMENCE DREDGING: ~NOV 2027
DREDGE COMPLETE: ~MAR 2028
NAPLES TO BIG MARCO PASS
LOCATION: Collier County, Florida DREDGE TYPE: Cuttersuction PLACEMENT: Beach
QUANTITY: 90K CY
DEPTH: 12’, 10’, and 6’
BUSINESS TYPE: MATOC – Small Business
ADVERTISE: JUL 2027
BID OPENING: AUG 2027
AWARD: SEP 2027
COMMENCE DREDGING: NOV 2027
DREDGE COMPLETE: MAR 2028
KENNEDY SPACE CENTER SPP
LOCATION: Brevard County, Florida DREDGE TYPE: Hopper/Cutter-suction PLACEMENT: Beach
QUANTITY: 2.5M CY
BUSINESS TYPE: IFB – Unrestricted
ADVERTISE: JUN 2027
BID OPENING: JUL 2027
AWARD: AUG 2027
COMMENCE DREDGING: NOV 2027
DREDGE COMPLETE: APR 2029
WORK RESTRICTIONS/WINDOW: Turtle Window (Nov – Apr) and Rocket Launch restrictions
CMMC LEVEL 1 REVIEW: CMMC, CUI,
Potential Borrow Areas Working Today to Build a Better Tomorrow
QUESTIONS?
NEXT MEETING 19 OCT AT 2:00
Microsoft Teams meeting Join:
https://dod.teams.microsoft.us/meet/993621128230?p=BArhXfcRF1NK O9oG37 Meeting ID: 993 621 128 230 Passcode: w2TR3k3T
Need help? | System reference Dial in by phone +1 503-207-9433,,820187976# United States, Beaverton Find a local number Phone conference ID: 820 187 976# For organizers: Meeting options | Reset dial-in PIN
| jacksonville district�coastal & navigation program�quarterly industry day |
| Slide Number 2 |
| Slide Number 3 |
| Slide Number 4 |
| Slide Number 5 |
| 2026 – remaining advertisements |
| Navy: Kings Bay Entrance Channel |
| BANANA RIVER (NASA) O&M |
| PALM BEACH HARBOR |
| EVERGLADES HARBOR, FL o&m |
| Port everglades harbor o&m |
| Fort Pierce HARBOR O&M |
| JACKSONVILLE HARBOR O&M |
| PASS-A-GRILLE PASS o&M |
| GIWW Manatee county o&m |
| Manatee co SPP – Anna Maria island |
| Broward COUNTY – segment ii |
| 2027 – scheduled advertisements |
| Naval Station Mayport |
| Kings Bay SubBase |
| MARINE CORPS SUPPORT FACILITY �BLOUNT ISLAND |
| Tampa harbor: Maintenance �Alafia river |
| IWW Jax to Miami:�Vicinity of Matanzas inlet |
| NAPLES TO BIG MARCO PASS |
| KENNEDY Space Center SPP |
| �Questions?���Next Meeting 19 Oct at 2:00���� |
File details come from the government source that posted it. Updated .