This file is a pre-bid site visit PowerPoint presentation for the Flamingo Marina Bulkhead Rehabilitation project at Everglades National Park in Monroe County, Florida. The U.S. Army Corps of Engineers Jacksonville District is seeking a contractor to rehabilitate the marina's bulkhead walls across four marina basins, involving 3,864 linear feet of sheet pile wall installation, new precast concrete wall panels, site grading, and mechanical/electrical equipment replacements. The project includes critical environmental considerations for protected species like West Indian Manatees, Smalltooth Sawfish, and American Crocodiles, with strict contractor requirements for habitat protection.

The solicitation (W912EP25RA006) is an unrestricted, full and open competitive procurement for a Firm-Fixed-Price contract with an anticipated construction magnitude between $25-100 million. Key procurement details include a best value tradeoff process with evaluation factors for technical merit, past performance, small business participation, project labor agreement, and price. The project is scheduled for solicitation on September 24, 2025, with proposals due December 11, 2025, estimated contract award on March 31, 2026, and a 1,350-calendar day performance period. Small business subcontracting opportunities exist in areas like trucking, earthwork, electrical work, and equipment operations, with potential for various small business participation.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

NPS: Everglades National park flamingo marina bulkhead rehabilitation Monroe county, Florida U.S. Army Corps of Engineers Jacksonville District agenda Welcome

Presentations Project Overview Project Environmental and Park Concerns Engineering Procurement Strategy Small Business Opportunities Construction

Questions (Submit via ProjNet)

Flamingo Marina Bulkhead Rehabilitation project overview Project Goals:

Flamingo Marina is a bulkhead rehabilitation project with new wall system constructed water side of existing wall system.

Replacement of existing mechanical/electrical features within project footprint.

Flamingo Marina consists of four (4) marina bays:

Visitor Center Bay (Basin 3) Florida Bay (Basin 2) Whitewater Bay (Basin 1) Maintenance Marina Bay (Basin 4) Visitor Center Bay and Florida Bay are located on the brackish water side.

Whitewater Bay and Maintenance Marine Bay are located on the freshwater side.

Both sides are separated by a plug (not included in project).

The marina is open year-round to visitors, including during construction.

The marina is also home crocodiles that regularly nest near the bulkhead walls.

Site originally constructed in the 1950s.

Flamingo Marina Bulkhead Rehabilitation project overview Project Features 3,864 linear feet of sheet pile wall installation 587 – Visitor Center Bay 1037 – Florida Bay 1284 – Whitewater Bay 964 – Maintenance Marina Bay Precast concrete overhanging wall panel “façade” wall with cast-in-place cap tie-in.

Flowable fill placement between the wall systems. Also placed between sheet pile and precast “façade” wall.

All construction must be done landside, aside from the removal/replacement of the floating docks, guide piles, and timber piles.

3 Stormwater Outfall Pipes to be continued through new wall system.

Replacement of mechanical/electrical features:

Utility pedestals Dock panels Boat off-loading sewage pumps Fuel dispensers Electrical (circuit breaker) panels Plumbing and wiring/conduits for the equipment Sewage shore ties Equipment housekeeping pads Additional mechanical/electrical features:

Separate meters between NPS and concessionaire Transformer (to be installed by FPL and coordinated by NPS) Packaged utility wastewater pumping station (grinder pump)

Flamingo Marina Bulkhead Rehabilitation project Location

Everglades National Park

Flamingo Marina

Flamingo Marina Bulkhead Rehabilitation Project Environmental and Park Concerns Presented by: Kristina Witter, NPS Biologist

Federally Protected Species and Habitat

Legal protection under Endangered Species Act

Violations subject to civil and criminal penalties

NPS Mission: Preserve natural resources for future generations Flamingo Marina Bulkhead Rehabilitation Project Environmental and Park Concerns

Credit: National Park Service

West Indian Manatee (Threatened)

Concerns Year-round activity in Flamingo Marinas Attracted to freshwater outflows – drink from pipes in marina Often present with calves Very slow moving

Risks Accustomed to humans = vulnerable to injury from equipment

Contractor Requirements If a manatee comes within 50 ft, shut down all in-water work Idle vessel engines when manatees are nearby Report any collision/injury immediately Florida Fish & Wildlife Conservation Commission Everglades National Park Law Enforcement

Credit: Keith Ramos, USFWS

West Indian Manatee (Threatened)

Credit: Kristina Witter, NPS

Credit: Pablo Ruiz, NPS Credit: Kristina Witter, NPS

Credit: Holiday Point, National Marine Sanctuary Foundation Smalltooth Sawfish (Endangered)

Information Year-round activity in Flamingo Marinas Dorsal fins often mistaken for sharks or dolphins Juveniles use mangrove prop roots for shelter Eggs/juveniles found in seagrass Highly sensitive to water quality Entire Flamingo Marina = designated critical habitat

Risks Turbidity breaches can injure or kill eggs and juveniles Adults and juveniles are vulnerable to injury or death from equipment

Contractor Requirements Use turbidity curtains during all sediment-producing activities Prevent spills, discharge, and sediment plumes If observed within 50 ft, shut down all in-water work Report all sightings (alive or dead) to Biological Resources Chief (or delegate)

Flamingo Marina Bulkhead Rehabilitation Project Environmental and Park Concerns

Smalltooth Sawfish (Endangered)

Credit: FWC

Credit: Marine Conservation Institute

Credit: Marine Conservation Institute

Flamingo Marina Bulkhead Rehabilitation Project Environmental and Park Concerns

American Crocodile (Threatened)

Information Year-round activity in Flamingo Marinas Return to same area annually to breed Courtship: March Nesting: April–August Hatchlings in vicinity: June–September Entire Flamingo Marina = designated critical habitat

Risks (expect presence and territorial behavior) History of nesting along bulkhead walls Nests are not easily identifiable Adults + hatchlings may be near equipment, walking or basking on pavement or grass, exploring excavations Accustomed to human activity but still dangerous Readily utilize disturbed sandy soils for nesting

Contractor Requirements Cover all excavations nightly Inspect pits/equipment each morning for entrapped animals Stay clear of all crocodiles — do not push, corner, or haze Follow NPS nest flagging and avoidance buffers Construction schedules may be adjusted to avoid nests

Credit: National Park Service

Flamingo Marina Bulkhead Rehabilitation Project Environmental and Park Concerns

American Crocodile (Threatened)

Credit: Pablo Ruiz, NPS

Credit: Alison Joslyn, NPS American crocodile basking on bulkhead within Maintenance Marina American crocodile basking on boat launch at Flamingo Marina

Credit: Pablo Ruiz, NPS

Flamingo Marina Bulkhead Rehabilitation Engineering Presented by: Kayte Lubyonne, P.E., Lead / Structural Engineer

Flamingo Marina Bulkhead Rehabilitation Overall Site Plan

Visitor Center Bay (Basin 3) Site Plan

Visitor Center Bay (Basin 3) Section View

Florida Bay (Basin 2) Site Plan

Florida Bay (Basin 2) Section View

Whitewater Bay (Basin 1) Site Plan

Whitewater Bay (Basin 1) Section View

Maintenance Marina Bay (Basin 4) Site Plan

Maintenance Marina Bay (Basin 4) Section View

Construction Considerations Limited Access and Staging Public access must be maintained during construction Contractor trailer location separate from staging areas Phased Construction Base contract followed by additional optional work Each optional phase is to be constructed consecutively; except for the floating dock replacement and portable generator for final commissioning, which can be concurrently.

Significant Environmental and Ecological Concerns Water quality and clarity must be maintained Limited waterside activities due endangered fish and crocodiles Existing Bulkhead Condition The existing structure could be at risk of failure due to age, design, and possible scour.

Standby Time Paid by hour and utilized ONLY in the presence of endangered species in the immediate area of the work operations, differing site conditions, security operations, or other conditions determined by KO

Flamingo Marina Bulkhead Rehabilitation Procurement Presented by: Ireishal Adams, Contract Specialist William Wallace, Contracting Officer

Contracting Team William Wallace, Contracting Officer Email: William.J.Wallace@usace.army.mil

Ireishal Adams, Contract Specialist Email: Ireishal.C.Adams@usace.army.mil

Acquisition Method FAR Part 15 - Contracting by Negotiation

FAR 15.002(b) - Competitive Acquisitions Best Value Continuum

Tradeoff Process (FAR 15.101-1) Factor 1 – Technical Merit Factor 2 – Past Performance Factor 3 – Small Business Participation Factor 4 – Project Labor Agreement (PLA) Factor 5 – Price

FACTORS TO BE EVALUATED

FACTOR 1 - TECHNICAL MERIT

Factor 1 will consist of two elements:

Technical Approach Plan Management Plan

Factors to be Evaluated

FACTOR 2 - PAST PERFORMANCE

There are two submission requirements for Factor 2:

Company Specialized Experience Form

NAVFAC/USACE Past Performance Questionnaire (PPQ) or Contractor Performance Assessment Reporting System (CPARS) evaluation.

Factors to be Evaluated

FACTOR 3 - SMALL BUSINESS PARTICIPATION

It is expected that this factor will consist of:

Proposed Small Business Participation Plan Past Utilization of Small Business Concerns

All offerors, both other than small business and small business shall complete a Proposed Small Business Participation Plan.

Offerors shall identify the extent to which Small Businesses (SBs) will be utilized in the performance of this contract, by proposing goals for the Small Business Participation Plan. These goals shall demonstrate their best effort for small business participation.

Factors to be Evaluated

FACTOR 4 - PROJECT LABOR AGREEMENT (PLA)

In accordance with FAR 52.222-33, Notice of Project Labor Agreement, which is incorporated into this solicitation, all offerors are required to:

Negotiate or become party to a project labor agreement with one or more labor organizations for the term of the resulting construction contract.

Require its subcontractors to become a party to the resulting project labor agreement.

Submit said project labor agreement with their offer.

Factors to be Evaluated

FACTOR 5 - PRICE

The Price Factor is not rated. It is evaluated for reasonableness.

Offerors are advised that their business decision to submit a low-priced proposal can be considered in assessing their understanding or the risk associated with their proposal.

In accordance with FAR 19.1307, if applicable, the price evaluation preference for HUBZone small business concerns will be used for this acquisition.

Milestones MILESTONES (Dates are estimates):

Issue Solicitation24 September 2025
Proposals Due Date11 December 2025
Estimated Contract Award31 March 2026
Estimated Issue Notice to Proceed20 April 2026

Flamingo Marina Bulkhead Rehabilitation Small Business Presented by: Alexandria Lavey, Small Business

Small Business Opportunities FAR 19.201(a) - Government policy It is the policy of the Government to provide maximum practicable opportunities in its acquisitions to small business, veteran-owned small business, service-disabled veteran-owned small business, HUBZone small business, small disadvantaged business, and women-owned small business concerns. Such concerns must also have the maximum practicable opportunity to participate as subcontractors in the contracts awarded by any executive agency, consistent with efficient contract performance.

Small Business Participation Subcontracting Plan (Large Business concerns only)

DFARS 215.304(c)(i) - Evaluation factors and significant subfactors In acquisitions that require use of the clause at FAR 52.219-9, Small Business Subcontracting Plan, other than those based on the lowest price technically acceptable source selection process (see FAR 15.101-2), the extent of participation of small businesses to include service-disabled veteran-owned small business concerns, HUBZone small business concerns, small disadvantaged business concerns, and women-owned small business concerns in performance of the contract shall be addressed in source selection. The contracting officer shall evaluate the extent to which offerors identify and commit to small business performance of the contract, whether as a joint venture, teaming arrangement, or subcontractor.

Small Business Participation plan vs. subcontracting plan NOTE: Both are contractually binding.

Small Business / subcontracting

POTENTIAL OPPORTUNITIES EXIST:

Trucking (hauling) Earthwork (GPS based Excavation) Earthwork (Processing & Screening) Clearing & Grubbing (Tractors & Bushhogs, etc.)

Concrete & Rebar Welding

Metal Fabrication Electrical work (Electricians) General Laborers (Skilled & Unskilled) Heavy equipment operators (crane, dozers, excavators, etc.)

Site Security Environmental Monitoring Material Testing

Doing business with the corps of engineers Ensure registered in SAM.gov Ensure registration is updated. Expire each year Ensure the NAICS associated with the solicitation is in your SAM.gov profile Ensure proposals are uploaded in the Procurement Integrated Enterprise Environment (PIEE) system Ensure you read the entire solicitation Ensure you review the responses from the Q&As If there are any questions, regarding SAM.gov, reach out to SAM.

If there are any questions, submit in ProjNet.

Instructions for submitting questions in ProjNet is outlined in the solicitation.

Procurement Assistance

USACE Resources

Main Website: https://www.usace.army.mil/ Infrastructure Work Plans: https://www.usace.army.mil/Missions/Civil-Works/Budget/ Contracting: https://www.usace.army.mil/Business-With-Us/ Contracting Questions? Email DoingBusinessWithUs@usace.army.mil Small Business: https://www.usace.army.mil/Business-With-Us/Small-Business/ Small Business Questions? Email Small-Business-HQ@usace.army.mil Government-wide Resources www.sam.gov: Official government system for contracting opportunities, registering to do business, wage determinations, and contract data.

www.FPDS.gov: Search any unclassified contract award (DoD data has 90-day delay).

www.USASpending.gov: Official open data source of federal spending information.

www.sba.gov: Small Business Administration website has information regarding small business size standards, small business types, and more.

https://www.aptac-us.org/: Free resource dedicated to help local businesses compete successfully in the government marketplace. (Can also help you register with sam.gov).

Kimberly (Kim) Daniel-Ray, Chief of Small Business Programs USACE, Jacksonville District Mobile: (904) 318-6436 Small Business Email: SAJ-SB@usace.army.mil

Alexandria Lavey, Small Business Professional USACE, Jacksonville District Office (904) 232-1005 Small Business Email: SAJ-SB@usace.army.mil

Flamingo Marina Bulkhead Rehabilitation Construction Presented by: Glenn Gannon, P.E., Miami Coastal Resident Engineer

Safety Requirements Contract will require compliance with the EM 385-1-1 (2024) Safety and Health Requirements Manual and contract section 01 35 26 Governmental Safety Requirements Qualified Site Safety Health Officers with demonstrated safety experience Accident Prevention Plan Work is not allowed to start until plans are approved and the 3-phase system for associated definable feature of work (DFOW) has been conducted Activity Hazards Analysis for each DFOW and other major activities must be submitted and approved prior to start work Traffic Control and Hauling Plans Project site has shared roads for project access Mandatory weekly toolboxes and Monthly Supervisors Safety meetings Safety to be documented daily Mandatory use of Deficiency tracking system for Safety

Quality Requirements Contract will include section 01 45 04 Quality Control and 01 45 00 Resident Management System Contractor Mode (RMS CM).

Contractor Quality Control Plan Accident Prevention Plan Work is not allowed to start until plans are approved and the 3-phase system for associated definable feature of work (DFOW) has been conducted Qualified Quality Control Manager with CQM-C certification and demonstrated experience.

Three Phase Control System USACE Validated laboratory for QC Testing QC documentation and daily reports

Schedule Requirements Contract duration is established in Contract clause 52.211-10, Commencement, Prosecution, and Completion of Work Contract duration will commence once NTP is issued Contract includes section 01 32 01 Project Schedule Qualified Project scheduler must be submitted for approval Submit Preliminary Project Schedule (PPS) for the first 90 days within 15 days after NTP Submit Initial Project Schedule (IPS) within 42 days after NTP IPS must be developed utilizing Standard Data Exchange Format (SDEF) codes for Resident Management System (RMS) transfers Submit Schedule of Values (SOV) along with the IPS Work cannot start until key preconstruction submittals are approved Monthly Periodic Schedule Updates

Administrative Procedures Administrative procedures are outlined in contract section 01 30 00 Administrative Requirements Preconstruction conference Preconstruction conference submittals Submittal Register Coordination Meeting Weekly Progress Meetings Coordination with other contracts Do not anticipate starting work without having preconstruction submittals approved and 3-phase control system started

DRAFT

Flamingo Marina Bulkhead Rehabilitation technical inquiries and questions

Technical inquiries and questions relating to this solicitation are to be submitted via Bidder Inquiry in ProjNet at https://www.projnet.org/ no later than December 01, 2025, 3:00 PM EST.

All timely questions and approved answers will be made available through ProjNet.

The Solicitation Number is: W912EP25RA006

The Bidder Inquiry Key is: A5AUBV – MD27D8

Note: Specific Instructions for ProjNet Bid Inquiry Access can be found on the Solicitation image4.png image5.png image10.png image11.png image12.jpeg image13.png image14.jpeg image15.png image16.jpeg image17.jpeg image18.jpeg image19.jpeg image20.jpeg image21.jpeg image22.jpeg image23.jpeg image24.jpeg image25.jpeg image26.jpeg image27.jpeg image28.png image29.png image30.png image31.png image32.png image33.png image34.png image35.png image36.png image37.png image38.png image39.png image40.png image41.png image42.png image43.png image44.png image45.png image46.png image47.png image48.png image49.png image50.jpg image51.png image1.png image2.png image3.png

File details come from the government source that posted it. Updated .