C.04.01-Abstract_W912EP24B0005 Flagler Beach.pdf
PDF 117 KB Posted
- Solicitation number
- W912EP24B0005
About this file
This document is an Abstract of Offers for Solicitation Number W912EP24B0005, a solicitation by the U.S. Army Corps of Engineers Engineering District Jacksonville for the COASTAL STORM RISK MANAGEMENT PROJECT INITIAL CONSTRUCTION AND NORTH AND SOUTH REACHES BEACH DUNE RESTORATION FLAGLER BEACH 2024 in Flagler County, FL.
The project will restore approximately 3.4 miles of beach and dune along the Flagler County shoreline, with material dredged from Borrow Area 3A offshore. The work includes beach fill, dune vegetation planting, vibration control, environmental monitoring, and other related activities. The solicitation is unrestricted, with a magnitude of construction between $25 million and $100 million. Bids were due on April 4, 2024, and the period of performance is 320 calendar days after the Notice to Proceed. The Abstract shows bid prices from 4 offerors for the various contract line items.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Pre-Bid Site Visit Memo Solicitation W912EP24B0005 03-15-2024.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOLICITATION NUMBER: W912EP24B0005
USA ENGINEER DISTRICT, JACKSONVILLE
PRUDENTIAL OFFICE BUILDING
701 SAN MARCO BLVD
ATTN: CESAJ-CT
JACKSONVILLE FL 32207-8175 BIDS
NO. 1 NO. 2 NO. 3 NO. 4 NO. 5
BIDDER: BIDDER: BIDDER: BIDDER: BIDDER:
B. BID SECURITY B. BID SECURITY B. BID SECURITY B. BID SECURITY B. BID SECURITY
(Type & amount) (Type & amount) (Type & amount) (Type & amount) (Type & amount)
C. BUSINESS SIZE: C. BUSINESS SIZE: C. BUSINESS SIZE: C. BUSINESS SIZE: C. BUSINESS SIZE:
D. ADDENDA D. ADDENDA D. ADDENDA D. ADDENDA D. ADDENDA
NUMBER OF AMENDMENTS ISSUED: 2 ACKNOWLEDGED: ACKNOWLEDGED: ACKNOWLEDGED: ACKNOWLEDGED: ACKNOWLEDGED:
CLIN NO. 7B DESCRIPTION OF OFFERED ITEM:
QUANTIT
Y UNIT UNIT PRICE AMOUNT UNIT PRICE AMOUNT UNIT PRICE AMOUNT UNIT PRICE AMOUNT UNIT PRICE AMOUNT UNIT PRICE AMOUNT
BASE
0001 MOBILIZATION AND DEMOBILIZATION 1 JOB 5,335,000.00$ $5,335,000.00 9,175,000.00$ $9,175,000.00 8,450,000.00$ $8,450,000.00 5,250,000.00$ $5,250,000.00 -$ $0.00 -$ $0.00
BEACH FILL FROM UPLAND
(ESTIMATED QUANTITY) ACCESS AREA AT R-95
14,000 ACTUAL TON 52.80$ $739,200.00 79.00$ $1,106,000.00 100.00$ $1,400,000.00 0.10$ $1,400.00 -$ $0.00 -$ $0.00
BEACH FILL FROM UPLAND
(ESTIMATED QUANTITY) ACCESS AREAS NEAR PIER
22,000 ACTUAL TON 52.80$ $1,161,600.00 79.00$ $1,738,000.00 100.00$ $2,200,000.00 5.00$ $110,000.00 -$ $0.00 -$ $0.00
BEACH FILL (ESTIMATED QUANTITY)
STA. 775+50 TO STA. 803+50
NON-FEDERAL NORTH REACH
150,000 CUBIC YARD 12.65$ $1,897,500.00 18.30$ $2,745,000.00 40.00$ $6,000,000.00 10.00$ $1,500,000.00 -$ $0.00 -$ $0.00
BEACH FILL (ESTIMATED QUANTITY)
STA. 803+50 TO STA. 937+50FEDERAL REACH
1,340,000 CUBIC YARD 12.65$ $16,951,000.00 17.45$ $23,383,000.00 25.00$ $33,500,000.00 10.50$ $14,070,000.00 -$ $0.00 -$ $0.00
BEACH FILL (ESTIMATED QUANTITY)
STA. 937+50 TO STA. 952+00
NON-FEDERAL SOUTH REACH
110,000 CUBIC YARD 12.65$ $1,391,500.00 17.45$ $1,919,500.00 25.00$ $2,750,000.00 11.00$ $1,210,000.00 -$ $0.00 -$ $0.00
BEACH TILLING (ESTIMATED QUANTITY)
NON-FEDERAL NORTH REACH
4 ACRE 1,900.00$ $7,600.00 600.00$ $2,400.00 1,200.00$ $4,800.00 750.00$ $3,000.00 -$ $0.00 -$ $0.00
BEACH TILLING (ESTIMATED QUANTITY)
FEDERAL REACH
24 ACRE 1,900.00$ $45,600.00 600.00$ $14,400.00 950.00$ $22,800.00 750.00$ $18,000.00 -$ $0.00 -$ $0.00
BEACH TILLING (ESTIMATED QUANTITY)
NON-FEDERAL SOUTH REACH
2 ACRE 1,900.00$ $3,800.00 600.00$ $1,200.00 950.00$ $1,900.00 750.00$ $1,500.00 -$ $0.00 -$ $0.00
COASTAL VEGETATION (ESTIMATED QUANTITY)
NON-FEDERAL NORTH REACH
12,000 EACH 1.75$ $21,000.00 1.35$ $16,200.00 4.00$ $48,000.00 1.15$ $13,800.00 -$ $0.00 -$ $0.00
COASTAL VEGETATION (ESTIMATED QUANTITY)
FEDERAL REACH
300,000 EACH 1.75$ $525,000.00 1.35$ $405,000.00 3.00$ $900,000.00 1.15$ $345,000.00 -$ $0.00 -$ $0.00
COASTAL VEGETATION (ESTIMATED QUANTITY)
NON-FEDERAL SOUTH REACH
8,000 EACH 1.75$ $14,000.00 1.35$ $10,800.00 3.00$ $24,000.00 1.15$ $9,200.00 -$ $0.00 -$ $0.00
SCREENING OF DREDGE MATERIAL
NON-FEDERAL NORTH REACH
150,000 CUBIC YARD 0.90$ $135,000.00 3.60$ $540,000.00 3.50$ $525,000.00 1.75$ $262,500.00 -$ $0.00 -$ $0.00
SCREENING OF DREDGE MATERIAL
FEDERAL REACH
1,340,000 CUBIC YARD 0.90$ $1,206,000.00 2.95$ $3,953,000.00 2.50$ $3,350,000.00 1.75$ $2,345,000.00 -$ $0.00 -$ $0.00
SCREENING OF DREDGE MATERIAL
NON-FEDERAL NORTH REACH
110,000 CUBIC YARD 0.90$ $99,000.00 2.95$ $324,500.00 2.50$ $275,000.00 1.75$ $192,500.00 -$ $0.00 -$ $0.00
TRANSPORTATION AND DISPOSAL OF
UNACCEPTABLE MATERIAL (ESTIMATED QUANTITY)
1,200 CUBIC YARD 155.00$ $186,000.00 150.00$ $180,000.00 450.00$ $540,000.00 45.00$ $54,000.00 -$ $0.00 -$ $0.00
0017 BLENDING OF NONCOMPLIANT MATERIAL) 1 ACRE 7,500.00$ $7,500.00 10,000.00$ $10,000.00 20,000.00$ $20,000.00 25,000.00$ $25,000.00 -$ $0.00 -$ $0.00
0018 VIBRATION CONTROL AND MONITORING 1 JOB 172,500.00$ $172,500.00 215,000.00$ $215,000.00 40,000.00$ $40,000.00 125,000.00$ $125,000.00 -$ $0.00 -$ $0.00
0019 ENVIRONMENTAL SPECIES MONITORING 1 JOB 403,000.00$ $403,000.00 550,000.00$ $550,000.00 200,000.00$ $200,000.00 175,000.00$ $175,000.00 -$ $0.00 -$ $0.00
MOBILIZATION AND DEMOBILIZATION SEA TURTLE TRAWL
SWEEPING AND RELOCATION (HOPPER DREDGE ONLY,(SEE NOTE 2)
1 JOB 11,600.00$ $11,600.00 30,000.00$ $30,000.00 40,000.00$ $40,000.00 25,000.00$ $25,000.00 -$ $0.00 -$ $0.00
SEA TURTLE TRAWL AND RELOCATION (HOPPER DREDGE ONLY, SEE
NOTE 2)
15 DAY 580.00$ $8,700.00 5,000.00$ $75,000.00 6,000.00$ $90,000.00 7,000.00$ $105,000.00 -$ $0.00 -$ $0.00
0022 TURBIDITY MONITORING 1 JOB 278,000.00$ $278,000.00 195,000.00$ $195,000.00 200,000.00$ $200,000.00 100,000.00$ $100,000.00 -$ $0.00 -$ $0.00
0023 STANDBY TIME (SEE NOTE 3) 72 HOUR 6,100.00$ $439,200.00 9,500.00$ $684,000.00 12,000.00$ $864,000.00 12,500.00$ $900,000.00 -$ $0.00 -$ $0.00
0024 PARTNERING REGROUP 1 EACH 7,600.00$ $7,600.00 10,000.00$ $10,000.00 8,000.00$ $8,000.00 2,500.00$ $2,500.00 -$ $0.00 -$ $0.00
0025 MEC CONSTRUCTION SUPPORT 1 JOB 207,000.00$ $207,000.00 650,000.00$ $650,000.00 350,000.00$ $350,000.00 165,000.00$ $165,000.00 -$ $0.00 -$ $0.00
GOPHER TORTOISE, SURVEY, PERMITTING, AND REPORTING
1 JOB 8,000.00$ $8,000.00 22,000.00$ $22,000.00 8,000.00$ $8,000.00 17,500.00$ $17,500.00 -$ $0.00 -$ $0.00
GOPHER TORTOISE CAPTURE AND RELOCATION (ESTIMATED
QUANTITY) 2 EACH 11,550.00$ $23,100.00 22,000.00$ $44,000.00 30,000.00$ $60,000.00 35,000.00$ $70,000.00 -$ $0.00 -$ $0.00
TOTAL BASE (LINE ITEMS 0001 THROUGH 0027) $31,285,000.00 47,999,000.00$ $61,871,500.00 $27,095,900.00 $0.00 $0.00
ABSTRACT OF OFFERS
DATE ISSUED DATE CLOSED
I CERTIFY that I have opened, read, and recorded on this abstract all offers received in response to this solicitation: ->
ISSUING OFFICE
February 29, 2024 April 4, 2024
COASTAL STORM RISK MANAGEMENT PROJECT FLAGLER BEACH INITIAL
CONSTRUCTION AND NORTH AND SOUTH REACHES BEACH
DUNE RESTORATION 2024 FLAGLER COUNTY, FL
Independent Government Estimate
PROJECT TITLE
IGE BIDS (Continued)
Weeks Marine incorpoated Great Lakes Dredge & Dock Company Manson Construction Company
20%
Yes Yes
20%
Yes
20%
NAME AND TITLE OF CERTIFYING OFFICIAL:
William J. Wallace
Signature
BIDSBIDS (Continued)
| 2024-04-05T14:14:12-0400 | |
| WALLACE.WILLIAM.JR.1149496757 |
File details come from the government source that posted it. Updated .