W912EP23R0026 AM 0002 SF30 Updates.pdf
PDF 2 MB Posted
- Attached to
- New Lock Control Building and Associated Upgrades at Ortona Lock and Dam, Florida, Glades County
- Solicitation number
- W912EP23R0026
About this file
This document outlines a two-phase design-build solicitation for a new lock control building and associated upgrades at Ortona Lock and Dam in Florida. The Army Corps of Engineers seeks proposals for design and construction of a 1,343 square foot hurricane shelter building to house lock and dam control equipment. Phase one will evaluate offeror qualifications and capabilities. Phase two will evaluate price and technical proposals, with award based on best value.
The solicitation is set aside for small businesses and targets completion within 686 days. Phase one proposals are due on November 23, 2023 and must demonstrate experience with similar projects, organizational approach, and key personnel qualifications. Phase two will be invited for up to five highest rated phase one offerors and will involve price and detailed design submissions, with evaluation prioritizing non-price factors. Pricing will be reviewed for fairness and reasonableness against an independent estimate.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
W912EP23R0026 New Lock Control Building and Associated Upgrades at Ortona Lock and Dam, Florida, Glades County
A. See Continuation Sheet for Amendments details.
B. The proposal due date is not extended.
C. All other Terms and Condition main unchanged
1. CONTRACT ID CODE PAGE OF PAGES
1 51
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912EP23R0026
X 9B. DATED (SEE ITEM 11)
31-Oct-2023
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO.
5. PROJECT NO.(If applicable)
6. ISSUED BY
3.EFFECTIVE
DATE
20-Nov-2023
CODE
USA ENGINEER DISTRICT, JACKSONVILLE
CONTRACTING DIVISION
701 SAN MARCO BLVD
JACKSONVILLE FL 32207-8175
W912EP 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
SUMMARY OF CHANGES
SF 30 CONTINUATION SHEET
W912EP23R0026 New Lock Control Building and Associated Upgrades at Ortona Lock and Dam, Glades County, Florida
SUMMARY OF CHANGES
1. SPECIFICATIONS:
The text changes have been updated with additions noted by green text and deletions noted by red line/cross-outs, and pertain only to changes made by this amendment. The entire section is replaced if there is any change. The Project Table of Contents and Submittal Register are replaced without underlines and cross-outs if there are changes to these documents. New sections are added without underlines and cross-outs.
DELETE Section 00100 and REPLACED with the attached updated Section 00100
DELETE Section 00100A and REPLACED with the attached updated Section 00100A.
DELETE Section 00700 and REPLACED with the attached updated Section 00700.
(End of Summary of Changes)
Section 00100 - INSTRUCTIONS TO OFFERORS
CLAUSES INCORPORATED BY REFERENCE
52.204-7 System for Award Management OCT 2018 52.204-22 Alternative Line Item Proposal JAN 2017 52.211-2 Availability of Specifications, Standards, and Data Item
Descriptions Listed in the Acquisition Streamlining and Standardization Information System (ASSIST)
JUL 2021
52.211-14 Notice Of Priority Rating For National Defense, Emergency Preparedness, and Energy Program Use
APR 2008
52.212-1 Instructions to Offerors--Commercial Products and Commercial Services
MAR 2023
52.215-1 Instructions to Offerors--Competitive Acquisition NOV 2021 52.215-1 Alt I Instructions to Offerors--Competitive Acquisition (NOV
2021) - Alternate I
OCT 1997
52.222-5 Construction Wage Rate Requirements--Secondary Site of the Work
MAY 2014
52.222-56 Certification Regarding Trafficking in Persons Compliance Plan.
OCT 2020
52.225-9 Buy American--Construction Materials OCT 2022 52.225-10 Notice of Buy American Requirement--Construction
Materials
MAY 2014
52.225-12 Notice of Buy American Requirement - Construction Materials Under Trade Agreements
MAY 2014
52.225-23 Required Use of American Iron, Steel, and Manufactured Goods--Buy American Statute--Construction Materials Under Trade Agreements
DEC 2022
52.228-17 Individual Surety--Pledge of Assets (Bid Guarantee) FEB 2021 52.236-28 Preparation of Proposals--Construction OCT 1997 252.204-7008 Compliance With Safeguarding Covered Defense Information
Controls
OCT 2016
252.204-7012 Safeguarding Covered Defense Information and Cyber Incident Reporting
JAN 2023
252.204-7016 Covered Defense Telecommunications Equipment or Services -- Representation
DEC 2019
252.204-7017 Prohibition on the Acquisition of Covered Defense Telecommunications Equipment or Services -- Representation
MAY 2021
252.204-7018 Prohibition on the Acquisition of Covered Defense Telecommunications Equipment or Services
JAN 2023
252.215-7008 Only One Offer DEC 2022
CLAUSES INCORPORATED BY FULL TEXT
52.216-1 TYPE OF CONTRACT (APR 1984)
The Government contemplates award of a Firm Fixed Price contract resulting from this solicitation.
(End of provision)
52.217-5 EVALUATION OF OPTIONS (JUL 1990)
Except when it is determined in accordance with FAR 17.206(b) not to be in the Government's best interests, the Government will evaluate offers for award purposes by adding the total price for all options to the total price for the basic requirement. Evaluation of options will not obligate the Government to exercise the option(s).
(End of provision)
52.219-6 NOTICE OF TOTAL SMALL BUSINESS SET-ASIDE (NOV 2020)
(a) Definition. Small business concern, as used in this clause--
(1) Means a concern, including its affiliates, that is independently owned and operated, not dominant in the field of operation in which it is bidding on Government contracts, and qualified as a small business under the size standards in this solicitation.
(2) Affiliates, as used in paragraph (a)(1) of this clause, means business concerns, one of whom directly or indirectly controls or has the power to control the others, or a third party or parties control or have the power to control the others. In determining whether affiliation exists, consideration is given to all appropriate factors including common ownership, common management, and contractual relationships. SBA determines affiliation based on the factors set forth at 13 CFR 121.103.
(b) Applicability. This clause applies only to--
(1) Contracts that have been totally set aside for small business concerns; and
(2) Orders set aside for small business concerns under multiple-award contracts as described in 8.405-5 and 16.505(b)(2)(i)(F).
(c) General. (1) Offers are solicited only from small business concerns. Offers received from concerns that are not small business concerns shall be considered nonresponsive and will be rejected.
(2) Any award resulting from this solicitation will be made to a small business concern.
(End of clause)
52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL
EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)
(a) The offeror's attention is called to the Equal Opportunity clause and the Affirmative Action Compliance Requirements for Construction clause of this solicitation.
(b) The goals for minority and female participation, expressed in percentage terms for the Contractor's aggregate workforce in each trade on all construction work in the covered area, are as follows:
Goals for minority participation for each trade
Goals for female participation for each trade
30.4% 6.9%
These goals are applicable to all the Contractor's construction work performed in the covered area. If the Contractor performs construction work in a geographical area located outside of the covered area, the Contractor shall apply the goals established for the geographical area where the work is actually performed. Goals are published periodically in the Federal Register in notice form, and these notices may be obtained from any Office of Federal Contract Compliance Programs office.
(c) The Contractor's compliance with Executive Order 11246, as amended, and the regulations in 41 CFR 60-4 shall be based on (1) its implementation of the Equal Opportunity clause, (2) specific affirmative action obligations required by the clause entitled "Affirmative Action Compliance Requirements for Construction,'' and (3) its efforts to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade. The Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects. The transfer of minority or female employees or trainees from Contractor to Contractor, or from project to project, for the sole purpose of meeting the Contractor's goals shall be a violation of the contract, Executive Order 11246, as amended, and the regulations in 41 CFR 60-4. Compliance with the goals will be measured against the total work hours performed.
(d) The Contractor shall provide written notification to the Deputy Assistant Secretary for Federal Contract Compliance, U.S. Department of Labor, within 10 working days following award of any construction subcontract in excess of $10,000 at any tier for construction work under the contract resulting from this solicitation. The notification shall list the --
(1) Name, address, and telephone number of the subcontractor;
(2) Employer's identification number of the subcontractor;
(3) Estimated dollar amount of the subcontract;
(4) Estimated starting and completion dates of the subcontract; and
(5) Geographical area in which the subcontract is to be performed.
(e) As used in this Notice, and in any contract resulting from this solicitation, the "covered area" is Glades County, Florida.
(End of provision)
52.228-1 BID GUARANTEE (SEP 1996)
(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.
(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States.
The Contracting Officer will return bid guarantees, other than bid bonds, (1) to unsuccessful bidders as soon as practicable after the opening of bids, and (2) to the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.-
(c) The amount of the bid guarantee shall be 20 percent of the bid price or $3,000,000, whichever is less.-
(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.-
(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.
(End of provision)
52.233-2 SERVICE OF PROTEST (SEP 2006)
(a) Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer by obtaining written and dated acknowledgment of receipt from the person identified in item 9A of the Standard Form 1442, at the address shown in item 7 of the Standard Form 1442.
(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.
(End of provision)
52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) – ALTERNATE I (FEB 1995)
(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.
(b) An organized site visit has been scheduled for 15 November 2023 at 10:00 AM EDT. Participants will meet at Participants will meet at the site located at:
USACE Ortona Lock
1217 Lock Ln, Moore Haven, FL 33471
Participants shall contact Local Site Representative if additional directions needed:
William Keeney
(W) 239-694-5451, or (C) 863-368-9086
All participants must sign in and provide the following information, which will also be used by the Installation to grant access: Full Name, Company, Phone number and Email information. A valid ID is required.
Limit to 5 people per firm at the site visit.
Participants shall park in any designated non-reserved parking spots or as indicated by USACE site manager.
The prospective bidders are responsible for bringing all required documents & equipment to perform the site investigation. The Government will not have plans and specifications during the site visit.
All participants must bring required PPE to the site including: Hardhat, Safety toe shoes, High Visible vest. The Government will not have PPE on hand.
All participants must stay together with the Government escort and visible at all times.
Participants shall contact Chad Manson via email chad.d.manson@usace.army.mil and Courtesy Copy Ms. Maria Torres-Rodriguez maria.torres-rodriguez@usace.army.mil on or before November 13, 2023 @ 1500 PM ESD Time to make RSVP arrangements. ALL participants must provide the following information in the RSVP email:
Full Name, Company, Phone number and Email information. The Government cannot guarantee access to the Site Visit Location if the information is received after November 13, 2023. All participants must sign in and provide the following information, which will also be used by the Installation to grant access: Full Name, Company, Phone number and Email information. A valid ID is required.
(c) A Pre-Proposal Conference Call will be held on 20 November 2023 at 10:00 AM EDT to address any further questions. Callers can call in at: (844) 800-2712, Access Code: 199 98 3645, Attendee Code: PRESS #.
(c) A Pre-Proposal Conference Call will be held on 21 November 2023 at 2:00 PM EDT to address any further questions. Callers can call in at: (844) 800-2712, Access Code: 199 98 3645, Attendee Code: PRESS #
(d) After the site visit, a memorandum summarizing the visit will be posted to Sam.GOV under the solicitation number. This posting will be strictly for informational purposes only. The memorandum will not become a part of the solicitation. If the solicitation needs to be changed as a result of information obtained during the site visit, a written amendment will be made available to all registered vendors. Questions regarding any information given in the memorandum must be directed to the person whose name appears in item 9 of the Standard Form 1442.
(End of provision)
52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)
This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):
https://www.acquisition.gov/content/regulations
(End of provision)
52.252-5 AUTHORIZED DEVIATIONS IN PROVISIONS (NOV 2020)
(a) The use in this solicitation of any Federal Acquisition Regulation (48 CFR Chapter 1) provision with an authorized deviation is indicated by the addition of "(DEVIATION)" after the date of the provision.
(b) The use in this solicitation of any Defense Federal Acquisition Regulation Supplement (48 CFR Chapter 2) provision with an authorized deviation is indicated by the addition of "(DEVIATION)" after the name of the regulation.
(End of provision)
00100A
SECTION 00100B A
PHASE I
SOLICITATION PROVISIONS
A. DESCRIPTION OF THE REQUIREMENT
The Jacksonville District Contracting Division has a requirement from the South Florida Operations Offices (SFOO) – Operations Division to provide a request for proposal for a single award of a Firm Fixed Priced (FFP) contract, utilizing Two-Phase Design-Build Selection Procedures (See FAR 36.303). This single award FFP Contract is issued to obtain design-build services for a proposed new high performance sustainable
K3CTCCM9
Cross-Out
K3CTCCM9
Cross-Out lockhouse building. This building will serve as a lock and spillway control building for the Ortona Lock and Dam. This new building (approximately net conditioned 1,343 square feet including garage) is intended to house equipment that controls the operations of the lock and dam. The overarching building code is UFC 1- 200-01 which has modifications and provisions to the International Building Code, however this building must also be designed as a High-Performance Sustainable Building per UFC 1- 200-02, in particular Chapter 2. The building must be structurally and architecturally designed as a hurricane storm shelter in accordance with ICC
500. The structure including all openings must be inherently missile impact resistant without any additional protection required to be installed by the user, such as shutters. Option work includes conduit runs to be designed and installed around the lock to the control center within this building, to support future installation of a new control system under a separate contract. Other option work includes demolition of the existing control house after occupancy of the new control house.
Design Work includes, but is not limited to, calculations, plans, and specifications. Included in the design is the proper phasing of all activities coordinated among disciplines, and the removal of existing conditions to include utilities and occupants of the affected areas. The Contractor shall take into consideration that the existing structure will remain occupied during construction of new structure and phase demolition accordingly. Design must be signed and sealed by a Registered Professional Architect, Registered Professional Engineer, or other Registered Professional, for the discipline of work required. Design must be in accordance with design standards required within the contract.
This contract will have a period of performance of 686 calendar days. In accordance with FAR 36.204 -- Disclosure of the Magnitude of Construction Projects, the magnitude associated with this requirement is between $1,000,000.00 and $5,000,000.00.
B. BASIS FOR AWARD
Proposals must meet the criteria stated in the RFP to be considered for Phase I qualification. To qualify, proposals must demonstrate capability in accordance with the evaluation criteria in Section 00100A, and responsibility in accordance with FAR 9.104. The most highly qualified proposals are determined by a comparative assessment of Phase I proposals. The Source Selection Authority will select up to five of the most highly qualified Phase 1 offerors to submit proposals for Phase 2. A rating of Unacceptable for any Element will result in a rating of Unacceptable for the entire Factor. Final award will be based upon the Phase 2 evaluation. Phase 2 offerors will submit a price proposal and a design technical and schedule proposal, then Trade-Off procedure will be used to determine overall award. All evaluation factors other than cost or price, when combined, are significantly more important than price.
C. EVALUATION APPROACH
The acquisition will utilize the Two-Phase Design-Build Selection Procedures (See FAR 36.303). In Phase 1 of the two-phase design-build selection procedure, interested firms or joint venture entities (referred to as “offerors”) submit certain specified performance capability proposals, demonstrating their capability to successfully execute the design-build construction contract resulting from this solicitation. The Government will evaluate the performance capability proposals in accordance with the criteria described herein and will short-list the Phase 1 offerors to a maximum of five of the most highly qualified offerors to compete for the design-build contract in Phase 2. The Two-Phase solicitation will be prepared in accordance with FAR Part 15, and with phase 2 evaluation factors developed in accordance with FAR 15.304.
The Government intends to make award without holding discussions with offerors. The Government may hold discussions if the Source Selection Authority later determines them to be necessary. Therefore, offerors are encouraged to include their best terms and conditions in their offers for Phase 1 and Phase 2. By submitting an offer in response to this solicitation, offerors are agreeing to comply with all terms and conditions contained in the solicitation. Unless the solicitation specifically invites the offeror to submit exceptions, the Source Selection Authority may reject any offer that contains exceptions. In this solicitation, the words “offer” and “proposal” are used interchangeably. (See definition of “offer” at FAR 2.101.) Except for any portions of the offeror’s proposal incorporated into the resulting contract by specific reference, the terms and conditions included in the solicitation, including any amendments, shall take precedence over the offeror’s proposal.
D. GENERAL INSTRUCTIONS
In Phase One, only responsible firms that are System for Award Management (SAM) registered small business, Joint Ventures, and Mentor Protégé under the selected NAICS of 236220, Commercial and Institutional Building Construction, are eligible to submit an offer. For Phase Two, only the Offerors that are selected because of Phase One evaluations may submit a Phase Two proposal. Contractors submitting an offer as a joint venture must provide a copy of the executed joint venture agreement with the initial proposal. Also, if the joint venture involves an 8(a)-small business, the offeror shall submit evidence from the offeror’s SBA Servicing Agency that the offeror has notified and discussed the proposed joint venture with the appropriate SBA personnel. The joint venture or Mentor Protege must be registered in the System for Award Management (SAM) as a joint venture for an award to be made.
Offerors are reminded that if it is an 8(a) or HUBZone joint venture, it shall ensure that it complies with the applicable requirements of 13 CFR Parts 124 and 126, respectively.
E. OTHER GENERAL REVIEW
Debarred List
Offerors will be checked in SAM to ensure there are no exclusions listed. Any Offeror who is listed with exclusions will be eliminated without further consideration.
Minor Informalities
Proposals will be checked for minor informalities or irregularities. The Contracting Officer will follow guidance at FAR 15.305 when resolving minor informalities or irregularities. The Contracting Officer either will give the Offeror an opportunity to cure any defect resulting from a minor informality or irregularity or waive the defect, whichever is to the advantage of the Government.
F. PHASE 1 PROPOSAL AND RELATED EVALUATION FACTORS
1. Factor 1 – Technical Merit- Technical Merit is significantly more important than Past Performance.
Technical merit consists of three subfactors as shown below:
Element 1 - Specialized Experience Element 2 – Organization and Technical Approach Element 3 – Key Subcontractors
2. Factor 2 – Past Performance – Second most important factor, slightly less important than Factor 1.
G. PHASE 1 FACTOR SUBMISSION REQUIREMENTS AND
EVALUATION METHODS FACTOR 1 – TECHNICAL MERIT
In responding to this factor, the objective should be to instill confidence that the offeror thoroughly understands the requirements and complexities of this project, has the knowledge, expertise, and experience required to meet or exceed the terms and conditions of these specifications, and the ability to successfully accomplish and complete the requirements of this contract within the required time frames as specified.
ELEMENT 1 – SPECIALIZED EXPERIENCE
Specialized Experience -Submission Requirements
The prime contractor and the design firm(s) (or prime contractor if design is to be self-performed) shall each demonstrate recent, relevant experience on projects that are similar in nature, magnitude, and complexity to the work described in this solicitation, using Construction – Specialized Experience form – (Attachment 2), and Design – Specialized Experience Form – (Attachment 3) at the end of the section. Offerors may identify projects that are similar to the types listed below in Relevant Specialized Experience. If the Offeror is a joint venture, each firm shall provide information, demonstrating experience relevant to their role on this project.
Submit projects that are currently well underway or completed and turned over no longer than ten (10) years preceding the date of this solicitation. A well underway project is defined as 100% designed and at least 80% construction progress completed. If a project is presented and has not been completed, the offeror shall explain which elements of the work are not completed and the completion percentage. If any firm has multiple functions or divisions, limit the project examples to those performed by the division or unit submitting the offer or by the team member. Design firms may list prime contractors they have worked for or government, private, or commercial customers. The Offeror shall select the design firm(s), if projects were design-build, so identify them.
Relevant Specialized Experience for Evaluation Consideration:
General construction projects for commercial or industrial new facility construction not less than 1,250 SF, to include high- performance green buildings, including buildings conforming to ASHRAE 90.1, IgCC, and ICC 500 storm shelter design and construction, including work related to civil-site design and construction, geotechnical investigations, shallow foundation design and construction, concrete and CMU structural design and construction, architectural design and construction including large missile- impact resistant architectural finishes and fenestrations, mechanical, electrical, and plumbing design and construction. Contractor must demonstrate strong experience in executing and managing design-build projects. Contractor must also demonstrate experience applying UFC requirements to design and construction.
Using the Construction – Specialized Experience Form, the offeror shall submit five (5) projects similar to the type described in Relevant Specialized Experience. Construction experience not related to Relevant Specialized Experience will not be evaluated. The maximum number of submitted projects that will be evaluated is five (5) projects. If more than 5 projects are submitted, only the first 5 projects will be evaluated.
Using the Design – Specialized Experience Form, the offeror shall submit five (5) projects similar to the type described in Relevant Specialized Experience. Design experience not related to Relevant Specialized Experience will not be evaluated. The maximum number of submitted projects that will be evaluated is five (5) projects. If more than 5 projects are submitted, only the first 5 projects will be evaluated.
SPECIALIZED EXPERIENCE -EVALUATION CRITERIA
The Government will evaluate the extent of recent, related experience of the prime contractor and design firms in design, construction, or design-build, as relevant to their role on this project. The design firm(s) or the design capabilities of the prime contractor will be evaluated only for experience in Relevant Specialized Experience. Higher evaluation ratings will be given for construction projects examples which are similar in function, scope, complexity, location, and size to this solicitation and clearly demonstrate the offeror’s abilities to execute the projects successfully while maintaining cost and schedule. In addition, this criterion will be evaluated for the quantity and quality of experience demonstrated. The greater the relevance and the more recent the prior project experience, the higher the rating assigned during evaluations. Demonstration of experience in completing projects that had the unique characteristics of the proposed project will be evaluated favorably.
Higher evaluation ratings will be given for projects where the Offeror has previously worked with the A-E firm.
The Government may place greater importance on projects performed as a prime contractor than as a subcontractor, depending upon overall role and relevancy considerations. Federal Government project experience will not be inherently more important than non- Federal Government project experience.
The offeror must submit the requested information to demonstrate a record of recent, related experience in both design and construction, for projects that are similar to the Relevant Specialized Experience (which may include similar state or local government or private counterparts) included in this solicitation. Recent experience includes projects well underway (see above criteria) or those completed and turned over within ten (10) years of the proposal issue date for this solicitation for design or construction experience. Joint Venture partners should each demonstrate experience commensurate with their role on this project or explain in a detailed narrative how their experience qualifies them for their role on this project.
To receive credit for extent (amount) of experience, the offeror and its proposed design firm(s) shall demonstrate a history of recent, relevant experience.
The Government will consider extent of recent experience, degree of relationship of such experience, demonstrated familiarity with applicable codes and local conditions. Some examples of relevancy may include, but not be limited to:
Nature, magnitude, complexity, and location Dates (80% completed or completed no more than ten (10) years preceding date of Solicitation)
Firm’s role and extent of work self-performed (brokering out all work and simply “placing the sidewalks” on a cited project are examples of less relevant experience)
The Government does consider previous D-B experience a strength, even if the experience is on different type projects than this project. Similarly, the Government considers previous recent teaming experience among the team members as value added, even if on different type design and, or construction projects than this project.
The more relevant the experience, the more credit will be given.
The firm(s) or prime contractor preparing the design must demonstrate qualifications and experience in design considerations and development of designs of the types listed in Relevant Specialized Experience.
ELEMENT 2 – ORGANIZATION AND TECHNICAL APPROACH
SUBMISSION REQUIREMENTS
Provide information that describes the offeror’s organization and intended technical approach to executing the design-build contract per the detailed requirements herein. Concisely and clearly, describe the organizational and technical approach to project management, design, and construction execution.
Organization: Describe what firms, their resources and how their resources will be utilized, their roles and responsibilities and any contractual arrangements that have been established. Identify the design firm(s) chosen, if not to be self-performed. Clearly describe any teaming or joint venture arrangements, including a clear description of each firm’s roles and responsibilities on the project. The offeror shall document unequivocal teaming arrangements with its design firms(s) using the format in (Attachment 7). Include an organizational chart illustrating the organization, including key personnel and the proposed quality control group(s). The chart shall depict the key positions and names of personnel, their firm affiliations and their job locations (function or physical location), their job/position title within the organization. Describe the proposed management structure for the team, describing how the design and construction process will be managed and the authorities and delegations of authority within the team.
Key Project Personnel Capabilities and Experience: Provide a consolidated list of key personnel with name, position title and description of project responsibility for each. Indicate whether each individual has had a significant role in any of the cited project examples. If alternates are proposed for key personnel, the rating will consider the lesser qualified or experienced person, if there is a difference. Include key designers, whether employed by the prime or by a design subcontractor. For each person provide a brief resume, using the Key Personnel Resume forms (Attachment 5) at the end of this section. The following personnel must be identified:
Project Manager
Design Quality Control Manager
Special Inspector of Record
Architect
Landscape Architect
Interior Designer
Civil Engineer
Structural Engineer
Geotechnical Engineer
Mechanical Engineer
Fire Protection Engineer
Electrical Engineer
Telecommunications Engineer
Specifications Technician
Construction Quality Control Manager
Site Superintendent
Site Safety and Health Officer
All designers of record must be registered in accordance with contract clause: 52.236-25, Requirements for Registration of Designers.
In accordance with the non-substitution clause in Section 00800, Limitations on Substitutions for Certain Positions and, or Subcontractors, a letter of commitment must be provided for any proposed major subcontractor or key personnel.
A major subcontractor is defined as any subcontractor that is crucial for successfully completing the project.
The key subcontractor identified for this project is for electrical installations, controls, and fire protection installation.
Key Personnel for this project are all the disciplines identified in paragraph “Key Project Personnel Capabilities and Experience” above.
A letter of commitment is defined as a letter from the subcontractor or key person on official Company letterhead (1) addressed to the prime contractor, (2) identifying the work they intend to perform, and (3) stating that they are willing to be bound to perform the identified work if the prime receives this contract. Failure to provide a letter of commitment from proposed major subcontractor or key personnel will be noted as a weakness. Use the form letter (attachment 6) at the end of this section to provide letters of commitment.
Quality Control: Describe the team’s quality control approach, corporate systems and capabilities to maintain quality control of the design and construction. Describe the proposed quality control organization, including the proposed staffing plan. Provide specific information on how you will manage design quality control, track the design evolution and changes during design to meet the schedule and to facilitate Government reviews.
Provide information on how you will handle internal and external requests for information, shop drawings, submittal reviews and approvals, progress meetings, site visits, contract completion, closeout, as-builts, and completion documentation. In addition to the required designer-of-record (DOR) roles specified within the RFP for maintaining integrity of the design, describe any other DOR involvement in the quality control process, if any. There is no need to submit a quality control plan as the successful offeror will provide that after award. In Phase 1, the Government is interested in demonstrable capabilities to assure and control quality and how the offeror can achieve or exceed the contract’s minimum quality control system requirements.
EVALUATION CRITERIA:
Organization: The Government will evaluate the strengths, weaknesses and any deficiencies in the organization and technical approach. The Government will evaluate the firm’s understanding of the design-build process (and the requirements described in the Division 01 requirements of the Solicitation) and the capability to execute the project.
The Government will evaluate clarity and strength of the overall organization, the structure and staffing to execute the entire scope of work. The Offeror is required to select and commit to design firms to achieve an “acceptable” rating. Joint venture participant’s contribution to the organization should be commensurate with their skills and background.
Key Personnel Capabilities and Experience: The Government will evaluate the required information to determine how well the offeror identifies and demonstrates that its key personnel meet or exceed minimum qualifications necessary, which includes previous satisfactory experience in similar type work, to manage, control and perform the design, and to perform construction. Use the Letter of Commitment (attachment 6). Performance of key personnel proposed for this project may be taken into account when it comes to the attention of the Government. The Government will evaluate how well the offeror demonstrates that it has the necessary structure and experienced, qualified personnel within its organization to effectively manage, control, administer and execute the integrated design and construction operations, quality control program and subcontracts. This shall be achievable with other projected on-going work. The Government will give additional consideration to previous design-build experience. Evaluate whether designers of record are registered (a requirement), experienced and qualified.
Project Manager: This is the individual who has the direct responsibility for all operations on the site. This individual shall have a recognized four-year college degree in engineering or related technical field or business/management, minimum experience of five years (or minimum experience of ten years in lieu of a four-year degree) in managing and supervising construction and, or engineering.
for projects similar in scope of the contract. Professional(s) shall be familiar and conversant with the various codes and standards applicable to the scope of work. The Project Manager for a contract shall oversee task accomplishment, administer all instructions, and answer all questions from the Contracting Officer pertaining to the tasks during the life of the contract.
Design Quality Control Manager: This individual must be a person who has verifiable engineering or architectural design experience and is a registered professional engineer or architect with a minimum of 5 years’ experience overseeing design projects.
Special Inspector of Record: The SIOR must be a registered Professional Engineer with five years of related experience overseeing special inspections of new vertical construction.
Architect: The Architect must be a registered architect, active within any state, with at least 5 years licensed design experience in similar projects.
Landscape Architect: The Landscape Architect must be a registered landscape architect, active within any state, with at least 5 years licensed design experience in similar projects.
Interior Designer: The Interior Designer must possess at minimum a NCIDQ certification with a minimum 5 years design experience, or be a state licensed Interior Designer within any state.
Civil Engineer: The Civil Engineer must be a registered Professional Engineer, active within any state, with at least 5 years licensed design experience in similar projects.
Structural Engineer: The Structural Engineer must be a registered Professional Engineer, active within any state, with at least 5 years licensed design experience in similar projects.
Geotechnical Engineer: The Geotechnical Engineer must be a registered Professional Engineer, active within any state, with at least 5 years licensed design experience in similar projects.
Mechanical Engineer: The Mechanical Engineer must be a registered Professional Engineer, active within any state, with at least 5 years licensed design experience in similar projects to this scope of work.
Fire Protection Engineer: The Fire Protection DOR must be a registered Professional Engineer, active within any state, who has passed the fire protection engineering written examination administered by the National Council of Examiners for Engineering and Surveys (NCEES) with at least 10 years of licensed design experience.
Electrical Engineer: The Electrical Engineer must be a registered Professional Engineer, active within any state, with at least 5 years licensed design experience in similar projects.
Telecommunications Engineer: The Telecommunications Engineer must be a registered Professional Engineer, active within any state with a minimum 2 years of licensed design experience, or a Building Industry Consulting Services International (BICSI) Registered Communications Distribution Designer (RCDD) with at least 5 years related experience.
Specifications Technician: The specifications writer must have a minimum of two (2) years’ experience on a minimum of four (4) projects writing construction specifications in UFGS format using SpecsIntact software.
Construction Quality Control Manager: The minimum requirements for the key person identified by the offeror to perform the Quality Control during the construction are at least 5 years’ experience in Quality Control during the construction of the types listed in Relevant Specialized Experience or commercial or industrial type experience of similar size, scope, and technical consideration.
Site Superintendent: The minimum experience requirements for the Superintendent are at least five years of experience , superintendent, managing multiple trades and subcontractors during the construction of the types listed in Relevant Specialized Experience of commercial or industrial type experience of similar size, scope, and technical consideration.
Site Safety and Health Officer: The SSHO is required to have a minimum of five years of construction industry safety experience. If the individual possesses a Third-Party, Nationally Accredited (ANSI or National Commission for Certifying Agencies - NCCA) SOH-related certification, only four years of experience is needed. The SSHO is required to have completed the 30-hour OSHA General Industry safety class. The SSHO shall report to an officer of the company, and not the project manager.
ELEMENT 3 – KEY SUBCONTRACTORS
Submission Requirements:
Identify the Key Subcontractor chosen for site/civil, structural, architectural, mechanical, electrical, and fire protection, describing the extent of their involvement on past projects similar to the project types listed in the Relevant Specialized Experience. Submit no more than five (5) Specialized Experience forms (attachment 2), using the same requirements as described in the Phase 1 Specialized Experience submission requirements, including past performance ratings. The ratings may be from either the owner or the prime contractor if the firms were subcontractors on the cited projects. The offeror shall document unequivocal teaming arrangements with its key subcontractors. Use the Letter of Commitment (attachment 8) at the end of this section. Contractors who will self-perform may submit five additional specialized experience forms in this section.
Any construction work to be self-performed by the offeror must be clearly identified. Include description of in-house labor crews and a list of equipment owned or leased by the offeror which is expected to be used within the project.
In accordance with the non-substitution clause in Section 00800, Limitations on Substitutions for Certain Positions and, or Subcontractors, a letter of commitment must be provided for any proposed major subcontractor or key personnel.
Evaluation Criteria:
The Government will evaluate the specialized experience of the Key Subcontractors required above, using the same criteria as in the Factor 1 Technical Merit, Element 1 Specialized Experience in Phase 1 evaluation, as applicable to their role on this project. No substitution will be allowed without contracting officer approval below:
LIMITATIONS ON SUBSTITUTIONS FOR CERTAIN POSITIONS AND, OR SUBCONTRACTORS
The award decision for this contract was based, in part, on an evaluation of the personnel and, or subcontractors the Contractor included in its proposal for the positions and, or items of subcontracted work identified at the end of this paragraph. The Contractor agrees these personnel and, or subcontractors will be employed as described in its proposal and no substitutes will be employed without prior written approval of the Contracting Officer or Administrative Contracting Officer. The Contractor further agrees that any proposed substitutes shall meet or exceed the qualifications of the original personnel and, or subcontractors. If the Contractor’s proposal did not name a subcontractor for an identified item of work, the Contractor will not be allowed to subcontract that item of work without prior approval of the Contracting Officer or Administrative Contracting Officer. The limitations described herein shall apply to the following positions and, or items of subcontracted work: Project Manager, Design Quality Control Manager, Special Inspector of Record, Architect, Landscape Architect, Interior Designer, Civil Engineer, Structural Engineer, Geotechnical Engineer, Mechanical Engineer, Fire Protection Engineer, Electrical Engineer, Telecommunications Engineer, Construction Quality Control Manager Site Superintendent, Site Safety and Health Officer.
Once the individual rating for Sub-Factor 1, Specialized Experience, the rating for Sub-Factor 2, Organizational and Technical Approach and Sub-Factor 3, Key Subcontractors, are assigned, an overall Technical Merit Rating will be assigned.
FACTOR 2 – PAST
PERFORMANCE SUBMISSION
REQUIREMENTS
Offerors shall submit one NAVFAC/USACE Past Performance Questionnaire (Attachment 4), completed and signed by an Owner of the Project (Client) point of contact or “POC” for each of the projects submitted under Element 1, Specialized Experience and Element 3, Key Subcontractors. All pages of each NAVFAC/USACE Past Performance Questionnaire must be initialed and dated on the bottom right-hand corner by the POC. Failure to provide a completed and signed NAVFAC/USACE Past Performance Questionnaire for each project as described above may be noted as a deficiency. If a Contractor Performance Assessment Reporting System (CPARS) record is available for any of the projects submitted under Element 1 - Demonstrated Experience, and Element 3 Key Subcontractor, the CPARS record may be submitted in lieu of the completed Past Performance Questionnaire or an official Performance Evaluation from a non-federal agency.
The Owner of the Project (Client) or “POC” is defined as the entity that took ownership of the project after construction was complete.
If the offeror is unable to obtain a completed Past Performance Questionnaire from the Owner of the Project (Client), before the proposal receipt date, the Offeror shall complete and submit with the proposal the first page of the Questionnaire (Blocks 1-8) that contains contract and client information for the submitted project. Note: it is the Offeror’s responsibility to ensure that the client’s point of contact information is current and correct. The client POC reflected in Blocks 1-8 should also be familiar with the past performance they are being asked to verify and informed that they will be contacted by the Government to verify past performance.
The Government reserves the right to obtain copies of all CPARS records contained in the Federal Government’s CPARS database for the offeror or offeror’s major subcontractors.
EVALUATION METHOD
The past performance evaluation is an assessment of the offeror’s probability of meeting the solicitation requirements. The assessment considers each offeror's demonstrated recent and relevant past performances in supplying services that meet the solicitation requirements. There are two aspects to the past performance evaluation.
The first evaluates whether the Offeror’s past performance is relevant or not relevant to the effort to be acquired.
The technical evaluation team will evaluate the demonstrated experiences provided by the offeror under Element 1 and Element 3 above.
Relevancy will be determined based on the timeframe for project completion given under Element 1 and Element 3 and the level of similarity between…