“The views, opinions and findings contained in this report are those of the authors(s) and should not be construed as an official Department of the Army position, policy or decision, unless so designated by other official documentation.”
Puerto Rico Integrated Program Office (IPP) Programs and Project Management Division 17 August 2022
INDUSTRY DAY
PUERTO RICO BIG 3
FLOOD RISK MANAGEMENT
SUPPLEMENTAL PROJECTS
2AGENDA
• Welcome Remarks – Lyan Garcia, Major Jesus Soto
• How to submit questions – Lyan Garcia
• Projects Overview – Lyan Garcia
• Rio Puerto Nuevo
• Rio de La Plata
• Rio Grande de Arecibo
• Projects Updates – Chad Gillan, Stephen Dupries
• Construction Considerations – Maricarmen Crespo, Mark Waddell
• Quality Control Management for Contractors – Mark Waddell
• Inspection & Validation of Laboratories – Michael Wielputz
• Doing Business with CESAJ – Karla Garcia, Anelis Nazario
• Acquisition Approach – Anelis Nazario
• Small Business Opportunities – Kimberly Daniel-Ray
MORNING SESSION
General requirements of the projects and inspection/validation of construction materials
9:00 am – 12:30 pm
3AGENDA
• Opening Remarks – Lyan Garcia
• Projects Overview – Jorge Ayala
• Rio Puerto Nuevo
• Rio de La Plata
• Rio Grande de Arecibo
• Sub-Contracting Opportunities – Jorge Ayala
• Construction Considerations – Mark Waddell
• Testing Requirements– Mark Waddell
• ERDC Inspection & Validation of Laboratories – Michael Wielputz
AFTERNOON SESSION
Specific requirements to be considered by material suppliers/vendors, and heavy equipment dealers.
2:00 pm – 5:00 pm
4HOW TO SUBMIT QUESTIONS
• All questions to be submitted through ProjNet
• Deadline: 5:00 pm, ET on 26 August 2022
• The Solicitation Number is: W912EP22Z0033
• The Bidder Inquiry Key is: 38K5UQ-U5Q2TS https://www.projnet.org
5SAM.gov
• Please visit SAM.gov after Industry Day
• All presentations, the attendance sheet, and the transcript will be posted
Solicitation No.:W912EP22Z0033
Rio Grande de Arecibo
Rio de la Plata
Rio Puerto Nuevo
LOCATIONS
File Name
7RPN CONTRACTS OVERVIEW
8RPN CONTRACTS OVERVIEW
• RPN Supplemental Contract “La Chuleta” Awarded Summer 2022
• RPN Supplemental Contract 1: Advertise: Early Winter 2024
• RPN Supplemental Contract 2: Advertise: Spring 2023
• RPN Supplemental Contract 3: Advertise: Winter 2023
• RPN Supplemental Contract 4: Advertise: Winter 2025
• RPN Supplemental Contract 5A: Advertise: Spring 2024
• RPN Supplemental Contract 5B Advertise: Summer/Fall 2025
• RPN Supplemental Contract 6: Advertise: Winter 2026
• RPN Supplemental Contract 7: Advertise: Summer 2026
*TENTATIVE
Arecibo
Rio de la Plata
10RIO DE LA PLATA
Disposal Area
East Levee
West Levee
Disposal Area
Disposal Area
East Levee
Channel
Channel
Channel
72” Water Line
Dorado Bridge
PR HWY-2
PR HWY-22
PR-2 Bridge and Road Re-alignment
11RDLP CONTRACTS OVERVIEW
• RDLP Supplemental Contract 1: Advertise: Fall 2023
• RDLP Supplemental Contract 3: Advertise: Fall 2026
• Super-Aqueduct Relocation: TBD
Arecibo
Rio de la Plata
13RIO GRANDE DE ARECIBO
East Levee
West Levee
Disposal Area
Disposal Area
East Levee
Channel
Channel
Channel
72” Water Line
Dorado Bridge
PR HWY-2
PR HWY-22
PR-2 Bridge and Road Re-alignment
14RGDA CONTRACTS OVERVIEW
• RGDA Supplemental Contract 1: Advertise: Fall/Winter 2023
*SUPPLEMENTAL CONTRACT 1 CONSISTS OF ORIGINAL CONTRACTS 2A AND 3
RPN Disposal Area – La Chuleta San Juan Harbor
La Chuleta
• Magnitude of Construction: $4.4M
• NTP Issued: August 2022
• Period of Performance: 1 year
La Chuleta
2RPN Supplemental Contract 1 Supplemental Contract 1
• Upper Margarita Channel (Sta. 56+00 to Sta. 89+60)
• Construction of concrete channel to tie to existing stilling basin
Sewer Line Relocation under Concrete Channel
• Magnitude of Construction: $100M to $250M
• Estimated Advertisement: Winter 2024
• Period of Performance: 4.5 years
• 95% design complete
• Limited construction footprint
• Constructability: phased work, sheet pile installation (under bridge) water diversion of existing channel, utilities relocations
• 121,100 cy of soil mixing
• 6,000 tons of steel sheet pile
• 181,000 cy of excavated material for disposal
• 145,000 cy of suitable fill
• 30,000 cy of concrete for
30-foot concrete channel
• 2,000 tons of reinforcing steel
Soil Mixing
Soil Mixing
Sheet Piles for Water DiversionChannel
Construction - Built in Sections
RPN Supplemental Contract 1
• 121,100 cy of soil mixing
• 6,000 tons of steel sheet pile
• 181,000 cy of excavated material for disposal
• 145,000 cy of suitable fill
• 30,000 cy of concrete for
30-foot concrete channel
• 2,000 tons of reinforcing steel
RPN Supplemental Contract 1
Channel Construction - Built in Sections
• Roosevelt Avenue Bridge with a temporary detour bridge construction
• Six-lane, pre-cast pre-stressed concrete beam bridge
• 95% design complete
• Magnitude of Construction: $25M to $100M
• Estimated Advertisement: Spring 2023
• Period of Performance: 4 years
RPN Supplemental Contract 2
Channel Improvement
• 110 Ea. six-foot diameter concrete-drilled shaft piles (~90 feet deep)
• 90 Ea. five-foot diameter concrete-drilled shaft piles (~90 feet deep)
• 19,000 cy of concrete
• 7,000 tons of reinforcing steel
• 119,000 cy of excavated material for disposal
Fl ow
RPN Supplemental Contract 2
Drilled Shaft
• Main channel walls, composite steel pipe pile/steel sheet pile walls
• Magnitude of Construction: $250M to $500M
• Estimated Advertisement: Summer 2023
• Period of Performance: 5.5 years
RPN Supplemental Contract 3
Supplemental Contract 3
• 1,600 six-foot diameter concrete drill shaft piles
(~100 feet deep)
• 200,000 cy of concrete
• 46,000 tons of reinforcing steel
• 600,000 cy of excavated material to be disposed
• 25,000 cy of suitable fill
• 8,000 tons of steel sheet pile
Sheet Piles
Drilled Shafts
Guardrail
Concrete Cap
Drilled Shaft
Sewer Siphon
Utility Bridge Four crews work on a different section of the river at same time
48” Potable Watermain (DI)
Supplemental Contract 4
• Bridge replacement of four major existing bridges over the Piñero Avenue Interchange 4A-1) Las Americas Expressway Bridge 4A-2) Piñero Avenue Bridge East 4A-3) NE Access Ramp Bridge 4A-4) SE Access Ramp Bridge
• Concrete channel construction
• Magnitude of Construction: $250M to $500M
• Estimated Advertisement: Summer 2025
• Period of Performance: 5 years
RPN Supplemental Contract 4
• Replacement design analysis is underway
• Maintenance of traffic
• Six-foot diameter concrete drill shaft for bridge abutments and channel walls
• Channel bottom will be articulated concrete block mattresses (ACBM)
Channel Improvement
• 1,200 Ea. five-foot diameter concrete drilled shaft piles (~90 feet deep)
• 70,000 cy of excavated material for disposal
• 83,000 cy of concrete
• 4,000 tons of reinforcing steel
• 304,000 square feet of ACB
• 3,500 tons of sheet pile
Pi ñe ro Av en ue
• Replacement design analysis is underway
• Maintenance of traffic (~184K vehicles/day in 2017)
Temporary Bridge
Replaced Bridge Deck
Demolished Bridge Deck
Supplemental Contract 5A Notre Dame Bridge
• Notre Dame Bridge replacement
• Channel works underneath bridge
• Temporary one-lane bridge
• Permanent pedestrian bridge
• Maintenance of traffic through Calle Notre Dame
• Magnitude of Construction: $25M - $100M
• Estimated Advertisement: Spring 2024
• Period of Performance: 3 years
CALLE SORBONA
CALLE GALILEO
Temporary one-lane bridge to be transformed into a permanent pedestrian bridge
Notre Dame Bridge replacement
RPN Supplemental Contract 5A
Supplemental Contract 5A Notre Dame Bridge
• Six-foot diameter concrete drill shaft for bridge abutments and channel walls
• Channel bottom will be ACBM
• 100 Ea. 6-foot dia. concrete drilled shaft piles (~106 feet deep)
• 14,000 cy of concrete
• 3,505 tons of reinforcing steel
• 9,000 LCY of excavated material to be disposed.
• 5,000 cy of suitable fill
• 636 tons of steel sheet pile
• 1,000 tons of Riprap
RPN Supplemental Contract 5A
Supplemental Contract 5B Piñero Bridge West and Josefiña Channel
• Piñero Avenue Bridge West replacement
• Channel works underneath bridge and downstream
• Maintenance of traffic on Piñero Avenue
• Magnitude of Construction: $100M - $250M
• Estimated Advertisement: Fall 2025
• Period of Performance: 3.5 years
• 200 Ea. five-foot diameter concrete drilled shaft piles (~90 feet deep)
• 52,000 cy of concrete
• 2,250 tons of reinforcing steel
• 76,000 cy of excavated material to be disposed
• 1,400 LCY of suitable fill
• 14,000 tons of steel sheet pile
• 102,000 square feet of ACBM
RPN Supplemental Contract 5B
Existing Abutment Drilled Shafts
ACBM
Channel Improvement
• Five-foot diameter concrete drill shaft for bridge abutments and channel walls
• Channel bottom will be ACBM
New Bridge Deck
Existing Abutment
Supplemental Contract 5B West Piñero Bridge
Supplemental Contract 6
• Main Channel Improvements (Sta. 147+40 to Sta.
240+00) - PR HWY 1
• Buena Vista Bridges - Two replacement bridges
• Buena Vista Diversion Channel (Sta. 0+00 to Sta.
42+37)
• Five-foot diameter concrete drill shaft for bridge abutments and channel walls
• Channel bottom will be ACBM
• Magnitude of Construction: $250M to $500M
• Estimated Advertisement: Summer 2026
• Period of Performance: 5.25 years
Contract 5A Notre Dame Bridge
RPN Supplemental Contract 6
• 7,000 tons of reinforcing steel
• 2,000,000 LCY of excavated material to be disposed
• 330,000 LCY of suitable fill
• 8,000 tons of steel sheet pile
• 321,000 square feet of ACB
Buena Vista Diversion Canal
• 1,300 Ea. five-foot diameter concrete drilled shaft piles (~80 feet deep)
• 80,000 cy of concrete
Buena Vista Diversion Canal
RPN Supplemental Contract 6
Excavation Limits
Supplemental Contract 7
• Replacement of 10 bridges
• Quebrada Josefiña Channel and Stilling Basins
• Quebrada Doña Ana Channel and Stilling
• Work cannot start until the completion of Contract 3
• Magnitude of Construction: $250M to $500M
• Estimated Advertisement: Spring 2026
• Period of Performance: 5.5 years
RPN Supplemental Contract 7
Supplemental Contract 7
• 75,000 cy of concrete
• 2,000 TN of reinforcing steel
• 300,000 LCY of excavated material to be disposed
• 100,000 LCY of suitable fill
• 3,200 TN of steel sheet pile
RPN Supplemental Contract 7
Constructability (Means and Methods):
• Limited Space: Constructing flood walls under existing bridges with low overhead clearances, limited construction staging, and access.
• Water Diversion and Care: Working within the channel footprint along the rivers while maintaining existing flow.
• Material Disposal and Hauling: Cutting from the channel and disposal.
• Traffic Control: Maintaining traffic during construction in highly urban area.
• Long Lead Items: Steel Sheet Pile, Steel Reinforcement, Large Quantity Concrete, Steel Electric Poles
RPN Challenges
1Rio De La Plata LOCATION: Dorado and Toa Baja, PR, about 11 miles west of San Juan
PROJECT IMPLEMENTATION:
DORADO BRIDGE CWSP PROJECT (Ongoing) River channel widening and modifications (0.46 miles), construction of earthen levee (0.53 miles), and scour protection
SUPPLEMENTAL CONTRACT 1
River channel widening and modifications (1.6 miles), construction of earthen levees (3.1 miles), four concrete culverts through levee, scour protection, and utility relocations
SUPPLEMENTAL CONTRACT 3
River channel widening and modifications (1.4 miles), construction of earthen levee (1.3 miles), scour protection, and utility relocations
SUPPLEMENTAL CONTRACT 4
Relocation of a 72-inch water supply aqueduct
Disposal Area
East Levee
West Levee
Disposal Area
Disposal Area
East Levee
Channel
Channel
72” Water Line
Dorado Bridge
PR HWY-2
PR HWY-22
SUPPLEMENTAL CONTRACT 1
MAIN PROJECT FEATURES:
2,234,000 yd3 channel excavation 1,962,000 yd3 levee fill placement 272,000 yd3 scour protection stone placement 4 – concrete culvert structures through the levees
Pre-cast concrete pipe (5-7 feet in diameter) Cast-in-place concrete inlet and outlet head walls Composite flap gates
ADDITIONAL PROJECT FEATURES:
• Maintenance road on levee crest and within project boundaries
• Drainage ditches
• Utility relocations
Water lines Sewer lines Electrical lines Telecommunication lines
• Disposal areas for excavated material
• Potential for wetland mitigation
Rio De La Plata
Levee
Channel
SUPPLEMENTAL CONTRACT 1
Rio De La Plata
• Magnitude of Construction: $250M to $500M
• Estimated Advertisement: Fall 2023
• Period of Performance: 3.5 years
East Levee Stone Protection
West Levee Stone Protection
Channel Centerline
Centerline
SUPPLEMENTAL CONTRACT 3
MAIN PROJECT FEATURES:
1,222,000 yd3 channel excavation 224,000 yd3 levee fill placement 101,000 yd3 scour protection stone placement
ADDITIONAL PROJECT FEATURES:
• Maintenance road on levee crest and within project boundaries
• Drainage ditches
• Utility relocations Water lines Sewer lines Electrical lines Communication lines
• Disposal area for excavated material
Rio De La Plata
Disposal area
East Levee
Disposal area
SUPPLEMENTAL CONTRACT 3
Rio De La Plata
• Magnitude of Construction: $100M to $250M
• Estimated Advertisement: Fall 2026
• Period of Performance: 3 years
East Levee
Channel Centerline
Seepage Berm
Stone Protection Stone Protection
SUPER-AQUEDUCT RELOCATION
MAIN PROJECT FEATURES:
• Relocate (approx. 1,000 feet) a 72-inch-diameter potable water line below the new channel
• The water line is a Prestressed Concrete Cylinder
Pipe (PCCP)
• Supplies water to 600,000 people
• From Arecibo to San Juan
• Heavy coordination with PRASA
• Water line shall remain in service during relocation Will require hot tapping existing line Will require temporary diversion water line during construction
ADDITIONAL PROJECT FEATURES:
• Channel excavation
• Disposal area for excavated material
Magnitude of Construction: $10M to $25M Estimated Advertisement: 2025 Period of Performance: 2 Years
Rio De La Plata Super-Aqueduct
Disposal area Channel
East Levee
West Levee
Disposal Area
Disposal Area
East Levee
Channel
Channel
Channel
72” Water Line
Dorado Bridge
PR HWY-2
PR HWY-22
PR-2 Bridge and Road Re-alignment
Rio Grande de Arecibo (Arecibo) General Project Overview
Project Features
• 1.3-mile-long levee
• Terminal Floodwall at the mouth
• 350-foot micropile founded wall under
PR-2
• 3 single span bridge replacements and associated road work
• 1.4 miles of channel improvements on the Santiago
• Mitigation area
• Drainage ditching
Status
• Magnitude of Construction: $100M to
$250M
• Advertisement: Fall 2023
• Period of Performance: 5 years
2Levee Details
Levee Alignment
Existing Condition Along Levee Alignment
Levee alignment
3Levee Details Quantities
• Compacted limerock 470,000 CY embankment
• Sand/random fill 50,000 CY
• Riprap and bedding 40,000 TN
• Soil bentonite cutoff wall 10,500 CY
Cutoff wall Stone Protection
Stone Protection
4Channel Details
Santiago Channel Location
Existing Santiago Channel
5Channel Details
• Riprap and bedding 10,000 TN
• Excavation 325,000 CY
Specific Considerations
• Flow in existing channel will need to be maintained.
• Coordination with the completion of the bridges.
• Fill disposal in the borrow site.
Typical Channel Section
Stone Protection
40’
Excavated Material
Terminal Floodwall Details
Terminal Floodwall Location at the Mouth of the Rio Grande de Arecibo
Arecibo Channel at the Floodwall Location
Levee alignment Flood Wall
Levee
Santiago
7PR-2 Floodwall Details
PR 2 Floodwall (in Green) Location Crossing PR 2
PR 2 Bridge at Floodwall Crossing
Fl oo dw al l
Levee
Levee
8PR-2 Floodwall Details
• Reinforced concrete, 4,000 ksi 1,000 CY
• 9.625-inch micropile 16,000 LF
Specific Considerations
• Micropile will be installed for the PR-2 wall under the bridge. Approximately 15-20 feet of clearance will be available.
• Temporary dewatering will be required for the PR-2 wall construction.
Typical PR 2 Floodwall Section
Micropiles
Base
Stem
9Bridge Details
Constitution Bridge 2
PR 10
Bridge
Constitution Bridge 1
Bridge Locations
Existing Constitution 1 Bridge Existing PR 10 Bridge
Levee
10Bridge Details
Typical Bridge Section
Quantities
• Precast prestressed 36-inch
“Florida” beams, 8,000 ksi
3,900 LF
• Reinforced concrete, 5,000 ksi 3,500 CY
• Drilled shafts, 36-42 inches 4,500 LF
Specific Considerations
• Constitution 1 and 2 will be completed concurrently and prior to PR 10.
• Full road closer is anticipated for bridge replacement. Therefore, there will be no temporary bridges.
Drilled Shafts
Super Structure
~102’
11Others - Features
Constitution 2 Bridge Siphon
PR 10 Bridge Siphon
Wetland Mitigation Area
Along the Santiago Channel
• 12- to 42-inch culverts 3,200 LF
• Siphon structures 2 EA
(12- to 36-inch pipes)
Near the East Approach of PR-2
• Mitigation area 13 AC
• Mangrove habitat
PR HWY 2
1< 2Q21 CMR lite new acd > As of: 16-Aug-22
SAJ: Quality Control Management for Contractors (CQM-C)
5 W’s Who: Jacksonville District (SAJ) What: CQM-C Certification Information as required by Contract Specification 01 45 XX When: Offered Monthly by USACE/NAVFAC Where: University of North Florida (UNF) Why (info):
- 2021 HQ Update CQM-C Content
- SAJ CQM-C – University of North Florida facilitates all course signup & payment
- SAJ - 4 classes annually, NAVFAC – 8 classes annually
- Certifications valid for 5 years
- NAVFAC & USACE class certificates qualify for both Army & Navy Project
- Additional class offerings through other USACE districts and UNF
- CEU’s are available for attending
UNF Classroom/Virtual Training
1. SAJ & NAVFAC returned to classroom format in July of 2022, all COVID-19 restrictions have been lifted and normal classroom classes are being offered.
2. Beginning Jan 2023, One (1) virtual class offered annually, recertification students only.
3. SAJ schedule and UNF link are shown on the next slide
2< 2Q21 CMR lite new acd > As of: 16-Aug-22
SAJ/NAFAC: CQM-C FY-2022 Schedule
Construction Quality Management for Contractors (CQM-C) Classes UNF registration website: https://www.unf.edu/ce/construction-and-trade.html
- Completion certificate valid for 5 years. At the end of 5 years, students must take this course again to re-certify.
- Online Recertification for CQM-C is offered once annually by Jacksonville District.
- Google search: University of North Florida Continuing Education or UNF CQM-C to find
Dates: Offered by:
January 2023 (Virtual) USACE February 2023 NAVFAC March 2323 NAVFAC April 2023 USACE May 2023 NAVFAC June 2023 NAVFAC July 2023 USACE August 2023 NAVFAC September 2023 NAVFAC October 2023 USACE November 2023 NAVFAC December 2023 NAVFAC blockedhttps://www.unf.edu/ce/construction-and-trade.html
3< 2Q21 CMR lite new acd > As of: 16-Aug-22
Geotechnical Materials Completion Report
Geotechnical, and Materials Construction Report (GMCR)
– GMCR serves as the permanent record of construction. Report is primary resource for post-construction evaluation and renovation.
– ER 1110-1-1901 (2017): Engineering and Design, Construction Project Geotechnical and Materials Completion Report governs Major USACE Projects
• ER 1110-1-1901 Project Geotechnical and Materials Completion Report for Major USACE Projects (army.mil)
– Final Report Government Responsibility
• Report dependent on Construction Data (i.e. Material Testing Results and As Builts)
Supplemental Projects Require GMCR
GMCR Contractor Effects/Actions
– Significant Material Data Testing Submission
• Under 01 45 08 – Geographic Information System Data Requirements-Quality Control and Quality Assurance Data.
• Not a typical contract requirement, but will be required for the entire supplemental program
– Increased As-Built Drawing and Submittal Surveillance
• Provide foundational knowledge for future analysis
• Directly inserted into final GMCR Report https://www.publications.usace.army.mil/Portals/76/Publications/EngineerRegulations/ER_1110-1-1901.pdf?ver=HFqPQkfpyUOmcAgsJKG2kQ%3d%3d
4< 2Q21 CMR lite new acd > As of: 16-Aug-22
QA/QC Testing Requirement / Information
• QA testing is mandated by USACE regulation ER 1180-1-6 to ensure that each construction contractor implements and maintains an effective Contractor Quality Control program
• QA Testing regulations required USACE to validate varying percentages of performed QC Testing (5%, 10% or even 20%)
• GMCR reports for supplemental work are dependent of QA Testing results
• Stop work orders will occur if the gov’t fails to perform QA testing
• Currently - Puerto Rico doesn’t have a government testing lab to perform QA testing and relies 100% on commercial labs, these labs can only perform the testing they are validated for at the time of testing
• Supplemental Program projects have “NEW” testing requirements that will require USACE Validation. The “Validation” process can take a substantial amount of time and effort
• ERDC Lab Certification Website: https://mtc.erdc.dren.mil/searchvalidation.aspx
• Government & Contractors can not use the same lab on a project
5< 2Q21 CMR lite new acd > As of: 16-Aug-22
QA/QC Testing Requirement / Information
• Jaca & Sierra Testing Laboratories:
• 19 validations of 69
• MGV-GES Lab:
• 17 validations of 69
• Geo-Engineering:
• 18 validations of 69
• Victor E Rivera Associates:
• 4 validations of 69
• Suelos PSC :
• 4 validations of 69
• GEO CIM:
• 16 validations of 69
• SPEC Group PSC:
• 15 validations of 69
• Validated Labs in Puerto Rico.
• 28 of 69 Verification Tests have “NO” “validated lab” in Puerto Rico (41%)
Statistics for Laboratories validated in Puerto Rico
0 20 40 60 80
Validated Lab Not Available Validated Lab Available Total No. Tests Requirements
EXP Date Estate Testing Lab Validated 12/16/2323 PR Jaca & Sierra Testing Laboratories – Trujillo Alto, PR 4/12/2024 PR MGV-GES Lab Inc. – Vega Baja, PR 6/28/2024 PR Geo Engineering, LLC - San Juan, PR 7/6/2022 PR Victor E. Rivera Associates, LLC - Ponce, PR
3/24/2023 PR Suelos PSC - San Juan, PR 4/9/2023 PR GEO CIM, Inc. - Guaynabo, PR 5/3/2023 PR SPEC Group PSC - San Juan, PR
6< 2Q21 CMR lite new acd > As of: 16-Aug-22
ERDC Inspection & Validation of Laboratories
5 W’s Who: U.S. Army Engineer Research and Development Center (ERDC)
Michael P. Wielputz, P.E. Materials Regional Technical Specialist What: Materials Testing Center (MTC) When: August 17, 2022 Where: Vicksburg, Mississippi Why: (topics)
- Inspection & Validation of Laboratories
- LABORATORY INVESTIGATIONS AND TESTING
- Quality Assurance of Laboratory Testing Procedures
- Validation Program
- Lab Validation
- Laboratory Training Requirements
- Commercial Laboratory Inspection/Testing Issues
7< 2Q21 CMR lite new acd > As of: 16-Aug-22
ER 1110-1-8100 LABORATORY INVESTIGATIONS AND TESTING
ER 1110-1-8100 assigns the inspection and validation of laboratories performing materials testing (aggregate, bituminous materials, concrete, rock, soil, and other construction materials) for the districts to the MTC.
Materials Testing Center (MTC)
A center established at the U. S. Army Engineer Waterways Experiment Station (CEWES) to provide materials testing (soil, rock, concrete, asphalt, and other construction materials) and inspection and validation of:
CQC labs, laboratories utilized by the district, Architect/Engineer (A/E) labs, construction contractor labs, and project materials QA laboratories as required ER 1110-1-261 (superseded by New ER 1110-1-8100).
8< 2Q21 CMR lite new acd > As of: 16-Aug-22
ER 1110-1-261, Quality Assurance of Laboratory Testing Procedures (to be superseded by New ER 1110-1-8100)
An initial validation shall be performed prior to performance of testing and at least every two (2) years thereafter.
(1) Inspection. Inspection shall be performed by the MTC in accordance with American Society for Testing and Materials (ASTM) E329.
(2) Audit. A laboratory may be validated by auditing if it has been accredited by the Concrete and Cement Reference Laboratory (CCRL) or AASHTO Materials Reference Laboratory (AMRL) within the past two years in accordance with ASTM E329. Audit shall be performed by the MTC. Inspection by MTC may be required after auditing if one or more of the critical testing procedures required in the project specification were not included in the CCRL or AMRL inspection report or if there is any concern that the laboratory may not be able to provide required services.
Note: Need to verify that the inspections cover all the test methods required.
9< 2Q21 CMR lite new acd > As of: 16-Aug-22
ERDC Materials Testing Center (MTC) Full Service Materials Testing Lab Manages the Materials Testing Lab Validation
Program
Validation Program Director – Chad Gartrell, P.E.
chad.a.gartrell@erdc.dren.mil Phone: 601-634-2313 Government Cell: 601-618-8154
SAD Materials Testing Regional Technical Specialist Michael P. Wielputz, P.E. michael.p.wielputz@usace.army.mil Phone: 678-354-0310 Government Cell: 470-363-9749
Website Access https://mtc.erdc.dren.mil/
Lab Validation+ Request a Validation Search for a Validation mailto:michael.p.wielputz@usace.army.mil
10< 2Q21 CMR lite new acd > As of: 16-Aug-22
ERDC Slides 1-10
11< 2Q21 CMR lite new acd > As of: 16-Aug-22
Currently, the ACI Certifications that will be required (per ASTM C1077 & D3740), along with the testing methods covered by each, are as follows:
Aggregate Testing Technician Level 1 ---- aggregate testing including ASTM D75, C702, C117, C127, C128, C136, C566, and C40.
Aggregate/Soils Base Testing Technician ---- soils testing including ASTM D75, C702, D421, D422, D4318, D2216, D698, and D1557.
Concrete Strength Testing Technician ---- concrete strength testing including ASTM C617, C1231, C39, and C78.
Concrete Field Testing Technician Grade 1 ---- fresh concrete testing including ASTM C172, C1064, C143, C138, C231 and/or C173, and C31.
Note: Where access to ACI Training is difficult to get, USACE provides ACI workshops and administers the written and performance exams. Contact Mike Wielputz at: michael.p.wielputz@usace.army.mil
Laboratory Training Requirements
12< 2Q21 CMR lite new acd > As of: 16-Aug-22
Laboratory Training Requirements
Agg/Base/Soil 0% Agg L1
16%
Conc Str 9%
Conc Field 75%
PUERTO RICO ACI CERTIFICATIONS
13< 2Q21 CMR lite new acd > As of: 16-Aug-22
ACI Training in Powidz, Poland
14< 2Q21 CMR lite new acd > As of: 16-Aug-22
ACI Training Requirements
Costs Which certifications are requested and how many students each?
Typically, the more students, the less cost per student Desired location for training? (travel, lodging, per diem, etc) Timeline for training?
Logistics Required Classroom of adequate size for group
White board or large writing pad Sufficient power outlets Video projector and screen or video wall screen Lab space or work area for mixing concrete and hands-on demos Adequate light Water Cement, gravel, sand or ready-mix
Interested?
Contact Chad Gartrell or Mike Wielputz for more details.
15< 2Q21 CMR lite new acd > As of: 16-Aug-22
Commercial Laboratory Inspection/Testing Issues
United States Testing Issues Accreditation (AASHTO Materials Reference Laboratory) and/or Validation (USACE) offers only a “snap-shot” in time (2 yr) of Laboratory Capability – often represents the “best of the best”
ERDC - MTC Validation represents a 1st level of basic minimal Quality Assurance – Completely necessary for “even playing field”
Validation by Desk audit of AMRL process is sometimes insufficient to uncover potential issues of non-compliance
2nd level of Quality Assurance is most critical to ensure day-to-day operations are compliant – Project Engineers, Geotech Engineers & Quality Assurance Representatives.
16< 2Q21 CMR lite new acd > As of: 16-Aug-22
Laboratory Validations – Contact the MTC Providing Inspections/Validation Providing Audit/Validation Provides guidance on unusual ASTM or other
Methods such as Rock Testing Handbook (RTH), CRD-C Methods, ACI, Mil Standards, etc.
Review/Validation for adding ASTM methods Cost depends on complexity and quantity of methods (desk audit or inspection) Disputes resolution for conflicting lab data Investigates claims for erroneous/bad data
1CONTRACTING OVERVIEW
Karla M. Garcia, Supervisory Contract Specialist Email: Karla.M.Garcia@usace.army.mil
Anelis I. Nazario Castillo, Lead Contract Specialist Email: Anelis.I.Nazario-Castillo@usace.army.mil
2Doing Business with CESAJ
• System for Award Management (SAM) - the Official U.S. Government System for contract opportunities. Every contract announcement is posted in the SAM.gov website. In order to receive and award with us you must be registered in SAM.
• Federal Acquisition Regulations System (FAR 1.101) - is established for the codification and publication of uniform policies and procedures for acquisition by all executive agencies.
o The Federal Acquisition Regulations System consists of the Federal Acquisition Regulation (FAR), which is the primary document, and agency acquisition regulations that implement or supplement the
FAR.
o https://www.acquisition.gov/browse/index/far
3Doing Business with CESAJ
• FAR Part 9 - Contractor Qualifications o Purchases shall be made from, and contracts shall be awarded to, responsible prospective contractors only.
o To be determined responsible, a prospective contractor must:
Have adequate financial resources to perform the contract, or the ability to obtain them (see 9.104-3(a));
Be able to comply with the required or proposed delivery or performance schedule, taking into consideration all existing commercial and governmental business commitments;
4Doing Business with CESAJ o To be determined responsible, a prospective contractor must (Cont.):
Have a satisfactory performance record (see 9.104-3 (b) and subpart 42.15). A prospective contractor shall not be determined responsible or nonresponsible solely on the basis of a lack of relevant performance history, except as provided in 9.104-2;
Have a satisfactory record of integrity and business ethics (for example, see subpart 42.15);
5Doing Business with CESAJ o To be determined responsible, a prospective contractor must (Cont.):
Have the necessary organization, experience, accounting and operational controls, and technical skills, or the ability to obtain them (including, as appropriate, such elements as production control procedures, property control systems, quality assurance measures, and safety programs applicable to materials to be produced or services to be performed by the prospective contractor and subcontractors). (See 9.104-3(a).)
Have the necessary production, construction, and technical equipment and facilities, or the ability to obtain them (see 9.104- 3(a)); and
6Doing Business with CESAJ o To be determined responsible, a prospective contractor must (Cont.):
Be otherwise qualified and eligible to receive an award under applicable laws and regulations (see also inverted domestic corporation prohibition at 9.108).
7ACQUISITION APPROACH
• Market Research – to be conducted for each acquisition in accordance with (IAW) FAR Part 10 to gather data of the capabilities within the market which helps us determine the best procurement approach that satisfy the agency needs.
o Small Business Set-Asides (FAR Subpart 19.502) - reasonable expectation that offers will be obtained from at least two responsible small business concerns and award will be made at fair market prices.
o Unrestricted - full and open competition without exclusion of sources.
8ACQUISITION APPROACH
• Competition will be promoted, and competitive acquisitions utilized IAW Procedures established in the FAR o FAR Part 14 – Invitation for Bid (IFB). Public opening of bids, or o FAR Part 15 – Request for Proposals (RFP). Best value obtained in negotiated acquisitions by using any one or a combination of source selection approaches, or o Other procedures established in the FAR or supplements pertinent to the requirement.
9ACQUISITION APPROACH
• FAR Part 15 – Contracting by Negotiation, o Source Selection Approaches:
Tradeoff Process (FAR 15.101-1) - This process permits the tradeoff amongst cost or price and non-cost factors and allows the Government to accept other than the lowest priced proposal or the highest technically rated proposal.
Note: Solicitation will state the relative importance of all non-priced factors, and their combined relative importance as they relate to price.
Lowest Price Technically Acceptable or LPTA (FAR 15.101-2) - This source selection process allows the Government to accept the lowest priced proposal, which has been deemed technically acceptable.
Note: Proposals are evaluated for acceptability but not ranked using non -cost/price factors.
10ACQUISITION APPROACH
• Contracting by Negotiation Important References o Army Federal Acquisition Regulation Supplement (AFARS) Part 5115.000
DoD Source Selection Procedures
Army Source Selection Supplement (AS3), Appendix AA
11ACQUISITION APPROACH
• FAR Part 15 – Contracting by Negotiation (Cont.)
o Potential evaluation factors may include, but are not limited to:
Price - in all source selections, the analysis must include a determination of whether the proposed cost or price is fair and reasonable (FAR 15.305(a)(1)).
Demonstrate Corporate Technical Experience – the degree to which the proposed approach meets or does not meet the threshold performance or capability requirements.
Past Performance - an assessment of the offeror’s probability of meeting the solicitation requirements.
Small Business Participation - extent of participation of small business concerns. Proposal indicates an adequate approach and understanding of small business objectives.
Applicable for Unrestricted acquisitions.
12ACQUISITION APPROACH
o Past Performance:
There are three aspects to the past performance evaluation:
Recency - generally expressed as a time period during which past performance references are considered relevant.
Relevance - how relevant a recent effort accomplished by the offeror is to the effort to be acquired. Common aspects of relevancy include, but are not limited to, similarity with the solicitation requirements, complexity, dollar value, contract type, use of key personnel (for services), and extent of subcontracting/teaming.
13ACQUISITION APPROACH
o Past Performance:
There are three aspects to the past performance evaluation (Cont.):
Quality – the past performance evaluation process gathers information from customers on how well the offeror performed those past contracts.
Note: The criteria to establish what prior performance is recent and relevant shall be unique to each source selection and shall be stated in the solicitation.
14ACQUISITION APPROACH
• Type of contract: Firm-fixed-price
• Applicable North American Industry Classification System (NAICS) code is 237990, Heavy and Civil Engineering Construction.
• The Small Business Size Standard for NAICS 237990, Heavy and Civil Engineering Construction, is $39.5 million.
• Executive Order on Use of Project Labor Agreements for Federal Construction Projects, which was issued on February 4, 2022, DOES NOT apply to US territories (American Samoa, Guam, Puerto Rico, the Northern Mariana Islands, and the U.S. Virgin Islands).
• Subcontracting Plan is required from Other than Small Business Firms (FAR Part 19)
ACQUISITION PROCESS FOR EACH PROJECT
Acquisition Strategy
Market Research Sources Sought
Set Aside Determination
Procurement Method Determination RFP vs IFB
Evaluation Criteria for RFP
Solicitation and Award
Receipt of Proposals/Bids
Notice to ProceedAward
Issuance of the Solicitation Pre-Proposal/Bids
Conference and Site Visit *
Evaluations
* Although not mandatory, this is an important event
16KEY WORDS (ACTION VERBS)
• Government communications may include, but is not limited to, the following actions verbs:
o Shall - imposes an obligation to act. May be confused with prediction of future action.
o Will - predicts future action.
o Must - imposes obligation, indicates a necessity to act.
o Must not - indicates a prohibition.
o Should - infers obligation, but not absolute necessity.
o May - indicates discretion to act.
17RESOURCES
Looking for Opportunities in All the Right Places
• Systems for Award Management o www.sam.gov
• Procurement Integrated Enterprise Environment (PIEE) - the primary enterprise procure-to-pay (P2P) application for the Department of Defense and its supporting agencies.
o https://piee.eb.mil/
• USACE Jacksonville District – Antilles Website - covers Puerto Rico and the US Virgin Islands. On this site you’ll find information related to current and upcoming civil works projects, military projects, studies, among others.
o www.usace.saj.army.mil/Antilles
18RESOURCES
Looking for Opportunities in All the Right Places
• Puerto Rico Federal Contracting Center -is a division of the Puerto Rico Department of Commerce focused to assist local business sell their goods and services to the federal government.
o https://www.federalcontractingpr.com
• Dynamic Small Business Search (DSBS)
- is a database where Small Business firms keep a profile current with bonding, past performance, and capabilities.
o http://dsbs.sba.gov/dsbs/search/dsp_d sbs.cfm
19SMALL BUSINESS
Kimberly Daniel Ray, Deputy for Small Business Programs Kimberly.S.DanielRay@usace.army.mil
Nicole Cruz-Batista, Small Business Specialist Nicole.M.Batista-Cruz@usace.army.mil
20SMALL BUSINESS OPPORTUNITIES
• FAR 19.201 – Government Policy
(a) It is the policy of the Government to provide maximum practicable opportunities in its acquisitions to small business, veteran-owned small business, service-disabled veteran-owned small business, HUBZone small business, small disadvantaged business, and women-owned small business concerns. Such concerns must also have the maximum practicable opportunity to participate as subcontractors in the contracts awarded by any executive agency, consistent with efficient contract performance.
21SMALL BUSINESS OPPORTUNITIES
• FAR 19.701 Subcontracting Plan o Electronic Subcontracting Reporting System (eSRS) means the Government wide, electronic, web-based system for small business subcontracting program reporting.
o Individual subcontracting plan means a subcontracting plan that covers the entire contract period (including option periods), applies to a specific contract, and has goals that are based on the offeror’s planned subcontracting in support of the specific contract, except that indirect costs incurred for common or joint purposes may be allocated on a prorated basis to the contract o Subcontracting Plan (Large Business concerns only)
22SMALL BUSINESS OPPORTUNITIES
• DFARS 215.304(c)(i) Evaluation factors and significant subfactors:
(c)(i) In acquisitions that require use of the clause at FAR 52.219- 9, Small Business Subcontracting Plan, other than those based on the lowest price technically acceptable source selection process (see FAR 15.101-2), the extent of participation of small businesses to include service-disabled veteran-owned small business concerns, HUBZone small business concerns, small disadvantaged business concerns, and women-owned small business concerns in performance of the contract shall be addressed in source selection. The contracting officer shall evaluate the extent to which offerors identify and commit to small business performance of the contract, whether as a joint venture, teaming arrangement, or subcontractor.
23SMALL BUSINESS OPPORTUNITIES
• What “Maximum Practicable Opportunity” looks like:
o Setting aside requirements for Small Business o Conducting market research to identify qualified Small Business firms o Utilizing Mentor-protégé programs o Utilizing subnet to solicit subcontracting opportunities o Utilizing the Small Business Administration and local Procurement Technical Assistance Centers (PTACs) for assistance
24SMALL BUSINESS OPPORTUNITIES
• Potential Sub-Contracting opportunities exist for:
o Trucking and hauling o Suppliers - concrete, asphalt, aggregates, stone, steel, precast concrete, etc.
o Sheet pile, anchor installation, pile driving o Drilled shaft construction o Utilities - electrical, telecommunications, sewer, and potable water related work o Reinforcing steel o Structural and nonstructural concrete
Note: This list is not all inclusive of potential sub-contracting opportunities
25SMALL BUSINESS OPPORTUNITIES
• Potential Sub-Contracting opportunities exist for (Cont.):
o Stone and armor protection o ACBM installation o Soil reinforcement o Embankment and levee construction o Micro piles, auger cast piles, jet grouting o Services: surveyor, geotechnical and structural consultants, material testing, environmental monitoring, etc.
Note: This list is not all inclusive of potential sub-contracting opportunities
26SMALL BUSINESS OPPORTUNITIES
• Kimberly Daniel-Ray, Deputy for Small Business o (904) 232-1150
• Nicole Cruz-Batista, Small Business Specialist o (904) 232-3275
• Florida Procurement Technical Assistance Center o http://www.fptac.org/contactus.htm
• Jacksonville District Website Page o www.saj.usace.army.mil
27SMALL BUSINESS OPPORTUNITIES
• How do I contact Small Business?
• Upcoming Jacksonville District Business Opportunities
• Frequently Asked Questions
| INDUSTRY DAY�PUERTO RICO Big 3�FLOOD RISK MANAGEMENT �Supplemental PROJECTS�� |
| Slide Number 2 |
| Slide Number 3 |
| Slide Number 4 |
| Slide Number 5 |
| Slide Number 6 |
| Slide Number 7 |
| Slide Number 8 |
| Slide Number 9 |
| Slide Number 10 |
| Slide Number 11 |
| Slide Number 12 |
| Slide Number 13 |
| Slide Number 14 |
| 2-Puerto Rico Industry Day Webinar Presentation RPN_v2.pdf |
| RPN Disposal Area – La Chuleta |
| Slide Number 2 |
| Slide Number 3 |
| Slide Number 4 |
| Slide Number 5 |
| Slide Number 6 |
| Slide Number 7 |
| Slide Number 8 |
| Slide Number 9 |
| Slide Number 10 |
| Slide Number 11 |
| Slide Number 12 |
| Slide Number 13 |
| Slide Number 14 |
| Slide Number 15 |
| Slide Number 16 |
| Slide Number 17 |
| Slide Number 18 |
| Slide Number 19 |
| Slide Number 20 |
| Slide Number 21 |
| Slide Number 22 |
| Slide Number 23 |
| 3-Puerto Rico Industry Day Webinar Presentation RDLP_v2.pdf |
| Slide Number 1 |
| Slide Number 2 |
| Slide Number 3 |
| Slide Number 4 |
| Slide Number 5 |
| Slide Number 6 |
| 4-Puerto Rico Industry Day Webinar Presentation RGDA_v2.pdf |
| Rio Grande de Arecibo (Arecibo)�General Project Overview |
| Slide Number 2 |
| Slide Number 3 |
| Slide Number 4 |
| Slide Number 5 |
| Terminal Floodwall Details |
| Slide Number 7 |
| Slide Number 8 |
| Slide Number 9 |
| Slide Number 10 |
| Slide Number 11 |
| 5-Industry Day CD-ERDC Briefing_v16 Aug2022.pdf |
| SAJ: Quality Control Management for Contractors (CQM-C) |
| SAJ/NAFAC: CQM-C FY-2022 Schedule |
| Geotechnical Materials Completion Report |
| QA/QC Testing Requirement / Information |
| QA/QC Testing Requirement / Information |
| ERDC Inspection & Validation of Laboratories |
| ERDC Inspection & Validation of Laboratories |
| ERDC Inspection & Validation of Laboratories |
| ERDC Inspection & Validation of Laboratories |
| ERDC Slides 1-10 |
| ERDC Inspection & Validation of Laboratories |
| ERDC Inspection & Validation of Laboratories |
| ERDC Inspection & Validation of Laboratories |
| ERDC Inspection & Validation of Laboratories |
| ERDC Inspection & Validation of Laboratories |
| ERDC Inspection & Validation of Laboratories |
File details come from the government source that posted it. Updated .