B.07 W912EP21B0010 IWW Palm Valley Maint Dredging Pre-bid Virtual Conference Mins.pdf
PDF 91 KB Posted
- Solicitation number
- W912EP21B0010
About this file
This document summarizes a pre-bid teleconference and related federal contract opportunity for maintenance dredging of the Intracoastal Waterway in Florida. The pre-bid teleconference covered pertinent information on the solicitation such as required mowing, clarification of Amendment 0001, and coverage for roadways and bridges. Contractors requested and were granted an extension of the bidder inquiry deadline to ten days before the bid opening date.
The related federal contract opportunity is a total small business set-aside for maintenance dredging of approximately 641,500 cubic yards of shoal material from cuts SJ-01 to SJ-07 of the Intracoastal Waterway in St. Johns County, Florida. All dredged material will be placed in an existing DMMA. A minimum size 16-foot cutter dredge is required. The estimated period of performance is 210 calendar days with bids due on July 19, 2021. The magnitude of construction is between $10-15 million. The solicitation will be issued electronically on Beta.Sam and interested vendors must register as interested vendors to receive amendments.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Pre-Bid Teleconference
W912EP21B0010, Intracoastal Waterway Jacksonville to Miami – Maintenance Dredging, 12-Foot Project, Palm Valley, North Reach St. Johns
County, Florida
W912EP21B0010
Contractor Attendee List Zach Martin, Ahtna Marine Construction Craig Seibert, Southwind Lisa R Curtin Maritime Rebekah Curtin Maritime Ben Cottrell, Cottrell Justin Chorlog, Coastal Dredge Chris Claussen, Gator Dredging
USACE Attendee List Jennifer Carter, USACE Tedra Thompson, USACE Katie Marrette, USACE Shelley Trulock, USACE Nancy Hutton, USACE
Jennifer Carter, Contract Specialist opened the call with the PowerPoint slides and reviewed pertinent information. Several contractors asked great questions to include but not limited to required mowing, clarification regarding amendment 0001, coverage for roadway and bridges and an extension of the bidder inquiry deadline to ten days before the bid opening date. The dialogue was greatly appreciated, and the contractors were advised to upload their questions to ProjNet for official response by the Government.