C.04.01 Abstract, Tampa Harbor Upper Channels, Final.pdf

PDF 289 KB Posted

Attached to
Tampa Harbor Maintenance Dredging 34-Foot Project, Upper Channels Hillsborough County, Florida
Solicitation number
W912EP21B0008
Issued by

About this file

This document summarizes an invitation for bid for maintenance dredging projects in Tampa Harbor, Florida. The U.S. Army Corps of Engineers is soliciting bids for dredging various channels to a depth of 34 feet below the mean lower low water mark, with allowances for overdredging. The base project involves an estimated 62,000 cubic yards of dredging in the Upper and Lower Sparkman channels. Option A includes approximately 23,000 cubic yards in the Ybor Channel. Option B covers around 50,000 cubic yards in the East Bay Extension channel. Option C consists of repairing the southern dike slope of the dredge material placement facility. Bids are due by August 16, 2021 for the projects anticipated to be completed within 230 calendar days of the notice to proceed. The solicitation was issued on July 16, 2021 under NAICS code 237990 with a size standard of $30 million.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

USA ENGINEER DISTRICT, JACKSONVILLE

PRUDENTIAL OFFICE BUILDING

701 SAN MARCO BLVD

ATTN: CESAJ-CT

JACKSONVILLE FL 32207-8175 BIDDERS

NO. 1 NO. 2 NO. 3 NO. 4 NO. 5

OFFEROR: OFFEROR: OFFEROR: OFFEROR: OFFEROR:

B. BID SECURITY B. BID SECURITY B. BID SECURITY B. BID SECURITY B. BID SECURITY

(Type & amount) (Type & amount) (Type & amount) (Type & amount) (Type & amount)

C. BUSINESS SIZE: C. BUSINESS SIZE: C. BUSINESS SIZE: C. BUSINESS SIZE: C. BUSINESS SIZE:

D. ADDENDA D. ADDENDA D. ADDENDA D. ADDENDA D. ADDENDA

NUMBER OF AMENDMENTS ISSUED: 3 ACKNOWLEDGED: ACKNOWLEDGED: ACKNOWLEDGED: ACKNOWLEDGED: ACKNOWLEDGED:

CLIN NO. DESCRIPTION OF OFFERED ITEM: QUANTITY UNIT UNIT PRICE AMOUNT UNIT PRICE AMOUNT UNIT PRICE AMOUNT UNIT PRICE AMOUNT UNIT PRICE AMOUNT UNIT PRICE AMOUNT

BASE (UPPER AND LOWER SPARKMAN)

0001 MOBILIZATION AND DEMOBILIZATION 1 JOB $1,739,000.00 $1,739,000.00 $767,000.00 $767,000.00 $1,812,201.00 $1,812,201.00 $4,250,000.00 $4,250,000.00 $3,400,000.00 $3,400,000.00 $0.00

0002 EXCAVATION, UNCLASSIFIED (ESTIMATED QUANTITY, SEE NOTE 2) 62,000 CUBIC YARD $16.80 $1,041,600.00 $12.07 $748,340.00 $7.47 $463,140.00 $30.00 $1,860,000.00 $17.30 $1,072,600.00 $0.00

0003 TURBIDITY MONITORING 1 JOB $17,650.00 $17,650.00 $14,310.00 $14,310.00 $3,200.00 $3,200.00 $25,000.00 $25,000.00 $12,100.00 $12,100.00 $0.00

0004 ENVIRONMENTAL SPECIES MONITORING 1 JOB $28,000.00 $28,000.00 $45,125.00 $45,125.00 $9,074.00 $9,074.00 $5,000.00 $5,000.00 $8,500.00 $8,500.00 $0.00

MOBILIZATION AND DEMOBILIZATION FOR SEA TURTLE TRAWL

SWEEPING (HOPPER DREDGE ONLY, SEE NOTE 3)

1 JOB $0.00 $0.00 $0.00 $0.00 $11,000.00 $11,000.00 $10,000.00 $10,000.00 $7,900.00 $7,900.00 $0.00

0006 SEA TURTLE TRAWL SWEEPING (HOPPER DREDGE ONLY, SEE NOTE 3) 1 DAY $0.00 $0.00 $0.00 $0.00 $4,000.00 $4,000.00 $4,500.00 $4,500.00 $4,000.00 $4,000.00 $0.00

0007 STANDBY TIME (SEE NOTE 5) 24 HOUR $1,500.00 $36,000.00 $1,000.00 $24,000.00 $2,062.00 $49,488.00 $4,500.00 $108,000.00 $2,600.00 $62,400.00 $0.00

0008 BIRD MONITORING (ESTIMATED QUANTITY - SEE NOTE 4) 25 DAY $750.00 $18,750.00 $517.00 $12,925.00 $175.00 $4,375.00 $500.00 $12,500.00 $380.00 $9,500.00 $0.00

0009 PARTNERING REGROUP 1 EACH $7,000.00 $7,000.00 $1,000.00 $1,000.00 $5,000.00 $5,000.00 $10,000.00 $10,000.00 $2,300.00 $2,300.00 $0.00

TOTAL BASE: (LINE ITEMS 0001 THROUGH 0009) $2,888,000.00 $1,612,700.00 $2,361,478.00 $6,285,000.00 $4,579,300.00 $0.00

OPTION A (YBOR)

0010 EXCAVATION, UNCLASSIFIED (ESTIMATED QUANTITY, SEE NOTE 2) 23,000 CUBIC YARD $18.25 $419,750.00 $14.50 $333,500.00 $7.45 $171,350.00 $20.00 $460,000.00 $14.70 $338,100.00 $0.00

0011 TURBIDITY MONITORING 1 JOB $8,250.00 $8,250.00 $7,440.00 $7,440.00 $1,322.00 $1,322.00 $5,000.00 $5,000.00 $5,700.00 $5,700.00 $0.00

0012 ENVIRONMENTAL SPECIES MONITORING 1 JOB $15,000.00 $15,000.00 $23,465.00 $23,465.00 $3,834.00 $3,834.00 $2,500.00 $2,500.00 $4,000.00 $4,000.00 $0.00

0013 BIRD MONITORING (ESTIMATED QUANTITY - SEE NOTE 4) 20 DAY $750.00 $15,000.00 $517.00 $10,340.00 $175.00 $3,500.00 $500.00 $10,000.00 $380.00 $7,600.00 $0.00

TOTAL OPTION A: (LINE ITEMS 0010 THROUGH 0013) $458,000.00 $374,745.00 $180,006.00 $477,500.00 $355,400.00 $0.00

OPTION B (EAST BAY EXTENSION)

0014 EXCAVATION, UNCLASSIFIED (ESTIMATED QUANTITY, SEE NOTE 2) 50,000 CUBIC YARD $16.85 $842,500.00 $15.30 $765,000.00 $6.71 $335,500.00 $20.00 $1,000,000.00 $14.70 $735,000.00 $0.00

0015 TURBIDITY MONITORING 1 JOB $40,000.00 $40,000.00 $14,310.00 $14,310.00 $3,603.00 $3,603.00 $10,000.00 $10,000.00 $9,700.00 $9,700.00 $0.00

0016 ENVIRONMENTAL SPECIES MONITORING 1 JOB $27,500.00 $27,500.00 $45,125.00 $45,125.00 $10,449.00 $10,449.00 $5,000.00 $5,000.00 $6,800.00 $6,800.00 $0.00

0017 BIRD MONITORING (ESTIMATED QUANTITY - SEE NOTE 4) 30 DAY $750.00 $22,500.00 $517.00 $15,510.00 $175.00 $5,250.00 $500.00 $15,000.00 $380.00 $11,400.00 $0.00

TOTAL OPTION B: (LINE ITEMS 0014 THROUGH 0017) $932,500.00 $839,945.00 $354,802.00 $1,030,000.00 $762,900.00 $0.00

OPTION C (DIKE SLOPE REPAIR)

0018 DIKE SLOPE REPAIR 1 JOB $88,500.00 $88,500.00 $230,000.00 $230,000.00 $262,152.00 $262,152.00 $100,000.00 $100,000.00 $250,000.00 $250,000.00 $0.00

0019 RIP RAP 3,852 TONS $270.00 $1,040,040.00 $91.10 $350,917.20 $85.65 $329,923.80 $350.00 $1,348,200.00 $88.00 $338,976.00 $0.00

0020 BEDDING STONE 293 TONS $135.00 $39,555.00 $89.19 $26,132.67 $84.85 $24,861.05 $450.00 $131,850.00 $80.00 $23,440.00 $0.00

0021 BIRD MONITORING (ESTIMATED QUANTITY - SEE NOTE 4) 45 DAY $750.00 $33,750.00 $517.00 $23,265.00 $262.50 $11,812.50 $500.00 $22,500.00 $380.00 $17,100.00 $0.00

TOTAL OPTION C: (LINE ITEMS 0018 THROUGH 0021) $1,201,845.00 $630,314.87 $628,749.35 $1,602,550.00 $629,516.00 $0.00

TOTAL BID: (LINE ITEMS 0001 THROUGH 0021) $5,480,345.00 $3,457,704.87 $3,525,035.35 $9,395,050.00 $6,327,116.00 $0.00

PROJECT TITLE

IGE

ABSTRACT OF BIDDERS

DATE ISSUED DATE CLOSED

I CERTIFY that I have opened, read, and recorded on this abstract all offers received in response to this solicitation: ->

ISSUING OFFICE

July 16, 2021 August 23, 2021

Yes Yes Yes

Tampa Harbor Maintenance Dredging 34-Foot Project, Upper Channels

Hillsborough County, Florida

Original Government Estimate

Orion Marine Construction Cashman Dredging & Marine

Yes Yes

SOLICITATION NUMBER: W912EP21B0008

NAME AND TITLE OF CERTIFYING OFFICIAL: Anelis I. Nazario Castillo, Contract Specialist

Signature

BIDDERS (Continued)

The Dutra Group

Yes

Yes

Weeks Marine

BIDDERS (Continued) BIDDERS (Continued)

Yes

2021-08-23T15:06:16-0400
NAZARIO CASTILLO.ANELIS.I.1368799315

File details come from the government source that posted it. Updated .