Broward Segment II- Pre Bid Site Visit Memo (SIGNED).pdf
PDF 518 KB Posted
- Attached to
- Shore Protection Project, Segment II, Beach Renourishment 2020-2021, Broward County, Florida
- Solicitation number
- W912EP21B0001
About this file
This memorandum documents a pre-bid site visit for a federal beach renourishment contract in Broward County, Florida. The U.S. Army Corps of Engineers will accept bids until November 30, 2020 for the placement of approximately 210,000 cubic yards of sand along 8.9 miles of shoreline between Hillsboro Inlet and Port Everglades Inlet. Bidders were given the opportunity to inspect three project areas and ask questions by November 29th. The base work involves renourishing from Range Monuments R-36 to R-72, while the optional work is from R-25 to R-36 for approximately 177,000 cubic yards. The period of performance is 250 calendar days after notice to proceed.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CESAJ-CD-RC 23 NOV 2020
MEMORANDUM FOR RECORD
SUBJECT: W912EP21B0001 – Shore Protection Project—Beach Renourishment, Broward Segment II
1. A pre-bid site visit was held for subject project on 23 November 2020 at 11:00 A.M. in order to give the prospective contractors or bidders a chance to see the worksite prior to submitting a bid.
2. The list of those attending the site visit is attached.
3. Prior to the visit, all contractors that expressed interest in the subject project pre-bid site visit were provided with the address for Hillsboro Inlet Park, to meet with USACE personnel.
4. The contractors were advised to write down any questions they may have and submit them via ProjNet no later than 29 November 2020 (End of Day). The solicitation Section 00010A, Attachment A - Instructions for
Technical Inquiries and Questions states that inquiries shall be submitted no later than 29 November 2020.
They were also reminded that the pre-bid conference was to be held tomorrow, 24 November 2020.
5. The site visit began at the northern end of the project with a description of the overall project area. The contractors were able to physically inspect three project areas such as: the access area by the Pompano Pier on SE 4th Street, as seen on Drawing C-05; the access area on NE 27th Street, as described in Drawing C-14;
and the staging area at the southern end of the project, near the intersection of SR A1A and Sunrise Blvd, as depicted in drawings C-17 and C-18. The contractors were advised to take pictures of the site in order to capture the existing site conditions, and accurately prepare their bids.
6. Prior to adjourning, the contractors were reminded to read through all of the requirements in the contract, to submit any questions they may have in ProjNet, and to look out for any forthcoming amendments to the solicitation, and ensure they were taken into consideration in the development of their proposal.
7. Finally, the contractors were advised to prepare their proposal in accordance with contract specifications and drawings as provided in the solicitation.
8. The POC for this action is the undersigned at 561-319-4803.
Leopoldo A. Bastante, P.E.
Project Engineer
Construction Division
Miami Resident Office
W912EP2180001- Shore Protection Project, Beach Renourishment, Broward County Segment II
SUBJECT: Pre-bid Site Visit
Name Organization Telephone#
CH <-'C..K.. H llKOX
Ar2v- JeN1/
U5ACE- 5� I • 3 \ q , 4 f5 O 3
U5ACG::
Monday, November 23, 2020
| Broward Segment II- Pre Bid Site Visit Memo |
| scannedDoc.pdf |
| 2020-11-24T07:55:37-0500 | |
| BASTANTE.LEOPOLDO.ALEXANDER.1268214077 |
File details come from the government source that posted it. Updated .