W912EP18R0018_Volume_2.pdf
PDF 445 KB Posted
- Attached to
- Guajataca Dam Gate Repairs, Puerto Rico
- Solicitation number
- W912EP18R0018
About this file
W912EP18R0018 Volume 2
View the file
Other files
| File | Type | Posted |
|---|---|---|
| W912EP18R0018_Amendment_0003.pdf | ||
| W912EP18R0018_Amendment_0002.pdf | ||
| W912EP18R0018_Amendment_0001.pdf | ||
| W912EP18R0018_Volume_1.pdf | ||
| W912EP18R0018_Plans.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
W912EP-18-R-0018
Jacksonville District
Guajataca Dam Sluice Gate Stem Replacement
Isabela and Quebradillas, Puerto Rico
Construction Solicitation and Specifications Volume 2 of 2
See Volume 1 of 2 for Issue Date
Guajataca Dam Sluice Gate Stem Replacement
PROJECT TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 SUMMARY OF WORK
01 22 00 MEASUREMENT AND PAYMENT
01 30 00 ADMINISTRATIVE PROCEDURES
01 32 01 PROJECT SCHEDULE
01 33 00 SUBMITTAL PROCEDURES
01 35 25 OWNER SAFETY REQUIREMENTS - DIVING
01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)
01 45 04 CONTRACTOR QUALITY CONTROL
01 50 02 TEMPORARY CONSTRUCTION FACILITIES
01 57 20 ENVIRONMENTAL PROTECTION
01 78 02 CLOSEOUT SUBMITTALS
01 78 23 OPERATION AND MAINTENANCE DATA
DIVISION 35 - WATERWAY AND MARINE CONSTRUCTION
35 20 16 SLUICE GATES AND HOISTS
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 1
W912EP-18-R-0018 RTA
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 11 00
SUMMARY OF WORK
PART 1 GENERAL
1.1 REFERENCES
1.2 WORK COVERED BY CONTRACT DOCUMENTS
1.2.1 Project Description
1.2.1.1 Background
1.2.1.2 Definitions
1.2.2 Detailed Description
1.2.2.1 Opening and Securing of Gate C
1.2.2.2 Removal of Intake Tower Gate C Stem and Operator
1.2.2.3 Installation of Intake Tower Gate C Stem and Operator
1.2.3 Diving Video Files
1.2.4 Location
1.2.5 Safety Requirements
1.2.6 Work Performed by Others
1.3 COMMENCEMENT, PROSECUTION AND COMPLETION OF WORK
1.4 LIQUIDATED DAMAGES - CONSTRUCTION
1.5 PHYSICAL DATA
1.5.1 Contractor Investigation
1.6 LAYOUT OF WORK
1.6.1 Layout
1.6.2 Survey
1.7 DAMAGE TO WORK
1.8 EXISTING WORK
1.9 UNITS OF MEASURE
PART 2 PRODUCTS (NOT APPLICABLE)
PART 3 EXECUTION (NOT APPLICABLE)
-- End of Section Table of Contents --
SECTION 01 11 00 Page 1
SECTION 01 11 00
SUMMARY OF WORK
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 Safety and Health Requirements Manual
1.2 WORK COVERED BY CONTRACT DOCUMENTS
1.2.1 Project Description
1.2.1.1 Background
The Guajataca Dam and Reservoir, owned by the Puerto Rico Electric Power Authority (PREPA), supplies domestic water and public irrigation to northwest Puerto Rico. The hydraulic-fill embankment dam was constructed in 1928. It stands 121 feet in height with a crest of approximately 1,037 feet in length, 31.2 feet in width, at an elevation of 664.4 feet.
During Hurricane Maria, the dam's outlet works were damaged and resulted in the loss of ability to maintain water supply deliveries, and affected the ability to draw down the reservoir's pool.
The dam is operated as follows: Water flows from the lake/reservoir into the intake tower via two (2) vertical sluice gates within the concrete structure. Gates are mounted either on the interior or exterior of the structure and may be protected by trash racks. The gates are separately operated manually by a hand crank. A rising stem is connected from each gate to a pedestal operator at the top of the tower. When at least one gate is opened, water flows from the intake tower into the outlet tunnel, where the tunnel branches to a 96 inch pipe which discharges into the river and a 54 inch pipe which discharges into the water supply canal. These may referred to the river outlet and canal outlet. Each of the river and canal outlet is controlled via a high pressure sluice gate, operated by a hydraulic power system. The 54 inch pipe to the water supply canal has an outlet house with a sleeve valve for energy dissipation before the water enters the open channel.
It is assumed the stem is bound within the operator at the stem thread to lifting nut interface, and movement either up or down by the operator is not possible. The gate is stuck approximately half open.
This construction contract is for removal and replacement of the following gate components of Gate C residing underwater in the intake tower: gate stem, stem guides, and operator.
SECTION 01 11 00 Page 2
1.2.1.2 Definitions
Reservoir: The reservoir is the water pool that is held behind the dam.
The reservoir may be referred to as the upstream pool, and its water elevation may be referred to as the headwater.
Canal Outlet: The dam supplies water from the reservoir to two discharges.
The canal outlet, also known as the water supply canal, is used for municipal drinking water supply.
River Outlet: The dam supplies water from the reservoir to two discharges.
The river outlet supplies water to the Rio Guajataca River.
Intake Gates: Sluice gates in the intake tower which resides within the reservoir behind the dam. The gates are cast iron 48 in x 60 in in size.
High Pressure (HP) Gates: Sluice gates are located in the outlet tunnel, which is supplied with water by the intake gates. Gates are seating-head cast iron 48 in x 48 in in size.
1.2.2 Detailed Description
1.2.2.1 Opening and Securing of Gate C
The Contractor must open and secure the gate in the fully open position within 30 calendar days after the Notice to Proceed (NTP) has been issued.
The gate is currently stuck approximately half open and cannot be operated by the existing operator. It is assumed the stem is bound within the operator at the stem thread to lifting nut interface and movement neither up or down is possible. A fully opened gate allows maximum water flow in the event the pool behind the dam needs to be lowered.
1.2.2.2 Removal of Intake Tower Gate C Stem and Operator
The Contractor shall remove a quantity of one (1) gate stem and operator for the gate attached to the intake tower residing within the lake/reservoir behind the dam, known as Gate C.
Two (2) sluice gates, known as Gate A and C, are similar in construction and are cast iron with dimensions of 48 in x 60 in. Gate A is at elevation
167.56 m and Gate C is at 180.53 m. Gate C is of the seating-head type. No work will be performed on Gate A.
Gate C is mounted on the outside of the intake tower, within an intake shaft that has dimensions of 30" x 60". The shaft has a steel trash rack over it which must be removed to access the gate. A new trash rack must be fabricated and installed after work is complete.
Gate C has a 3 3/8" rising cast iron stem with a thread pitch of 2 threads/inch which connects from the sluice gate up to the operator inside the intake tower housing, which is manually operated by a hand crank. The stem assembly and operator equipment shall be removed, including the stem, stem guides and anchors, bearings, and pedestal floor stands and baseplates. The existing concrete anchors for the pedestals shall be cut flush with the concrete floor.
The stem of Gate C is mounted on the exterior of the structure and is approximately 80 ft in length. Work shall be performed in the wet and a dive team is required.
SECTION 01 11 00 Page 3
Flow through Gate C can be stopped by closing both High Pressure gates, operated by a hydraulic system, and must be locked out/tagged out prior to work beginning. The Contractor shall coordinate any equipment operation with the Government. Any system operations must be completed by the Government.
1.2.2.3 Installation of Intake Tower Gate C Stem and Operator
After removal of the stem is completed, the Contractor shall install a new stainless steel stem and operator.
It will be necessary to remove the trash rack, fabricate a new one, and install after the gate has been installed and accepted by the Government.
New trash rack anchors shall be required.
Fabricate and install a new stem, stem guide, stem guide anchors, and operator.
Install one (1) new pedestal floor stand operator, hand crank, and provide one (1) portable electric operator. The floor stands shall be compatible for a rising stem.
1.2.3 Diving Video Files
USACE completed several hours of diving which was used to gather information to aid in the assembling of this contract. Diving took place from 27 to 28 February 2018. Dive videos may be requested from the contracting specialist, who will send download links via the Army's SAFE file exchange platform.
1.2.4 Location
The work is located at the Guajataca Dam in northwest Puerto Rico, approximately 6 miles south of the municipality of Quebradillas.
1.2.5 Safety Requirements
See Section 01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS and EM 385-1-1.
1.2.6 Work Performed by Others
This work shall take place concurrently in an active construction zone with other contractors. Coordination may be required between contractors as to not interfere with each others work. The operating equipment controlling the flow out of the intake tower may undergo maintenance and work will need to be coordinate between both contractors.See paragraph PROJECT COORDINATION of Section 01 30 00 ADMINISTRATIVE PROCEDURES.
1.3 COMMENCEMENT, PROSECUTION AND COMPLETION OF WORK
a. Read this paragraph in conjunction with the Clause COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (FAR 52.211-10) of Section 00700 CONTRACT CLAUSES in Volume 1.
b. The gate must be secured in the fully open position within 30 calendar days after the Notice to Proceed (NTP) has been issued.
SECTION 01 11 00 Page 4
1.4 LIQUIDATED DAMAGES - CONSTRUCTION
Refer to the Clause LIQUIDATED DAMAGES - CONSTRUCTION (FAR 52.211-12) of Section 00700 CONTRACT CLAUSES in Volume 1.
1.5 PHYSICAL DATA
Read this paragraph in conjunction with the Clause PHYSICAL DATA (FAR 52.236-4) of Section 00700 CONTRACT CLAUSES in Volume 1.
1.5.1 Contractor Investigation
Refer to the Clause SITE INVESTIGATION AND CONDITIONS AFFECTING THE WORK (FAR 52.236-3) of Section 00700 CONTRACT CLAUSES in Volume 1.
1.6 LAYOUT OF WORK
Read this paragraph in conjunction with the Clause LAYOUT OF WORK (FAR 52.236-17) of Section 00700 CONTRACT CLAUSES in Volume 1.
1.6.1 Layout
From the monuments, control data and elevations established by the Government, the Contractor shall complete the layout of the work and shall be responsible for all measurements that may be required for the execution of the work to the location and limit marks prescribed in the specifications or on the contract drawings, subject to such modifications as the Contracting Officer may require to meet changed conditions or as a result of necessary modifications to the contract work.
1.6.2 Survey
The Contractor shall furnish, at his own expense, such stakes, templates, platforms, equipment, tools and material, and all labor as may be required in laying out any part of the work from the monuments, control data and elevations established by the Government. It shall be the responsibility of the Contractor to maintain and preserve all stakes and other marks established by the Contracting Officer until authorized to remove them, and if such marks are destroyed by the Contractor or through his negligence, prior to their authorized removal, they may be replaced by the Contracting Officer, at his discretion, and the expense of replacement will be deducted from any amounts due or to become due the Contractor. The Contracting Officer may require that work be suspended at any time when location and limit marks established by the Contractor are not reasonably adequate to permit checking of the work.
1.7 DAMAGE TO WORK
The responsibility for damage to any part of the permanent work shall be as set forth in Clause PERMITS AND RESPONSIBILITIES of Section 00700 CONTRACT CLAUSES in Volume 1. However, if, in the judgment of the Contracting Officer, any part of the permanent work performed by the Contractor is damaged by flood, earthquake, hurricane, or tornado, which damage is not due to the failure of the Contractor to take reasonable precautions or to exercise sound engineering and construction practices in the conduct of the work, the Contractor will make the repairs as ordered by the Contracting Officer and full compensation for such repairs will be made at the applicable contract unit or lump sum prices as fixed and established in the contract. If, in the opinion of the Contracting Officer, there are no
SECTION 01 11 00 Page 5 contract unit or lump sum prices applicable to any part of such work, an equitable adjustment pursuant to Clause CHANGES of Section 00700 CONTRACT CLAUSES in Volume 1 will be made as full compensation for the repairs of that part of the permanent work for which there are no applicable contract unit or lump sum prices. Except as herein provided, damage to all work (including temporary construction), utilities, materials, equipment and plant shall be repaired to the satisfaction of the Contracting Officer at the Contractor's expense, regardless of the cause of such damage.
1.8 EXISTING WORK
In addition to "FAR 52.236-9, Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements":
a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.
b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work shall be in a condition equal to or better than that which existed before new work started.
1.9 UNITS OF MEASURE
The standard U.S. system or the metric systems of measure may be utilized by the Contractor in the performance of his work. All survey records, official documentation, engineering data, and all correspondence, including any submittals and shop drawings, shall clearly denote which system of measure is being utilized, referenced or discussed. Any omission, unprofessional or inaccurate use of a unit of measure on the part of the Contractor shall not relieve him of his responsibilities under the contract terms. The unit of measure used in this specification is the standard U.S.
system. The contract drawings denote both standard U.S. system and metric system where appropriate. If no unit of measure is indicated on the drawing such as on ranges, stations, slope elevations, and distance numbers, then they are to be considered the standard U.S. system.
PART 2 PRODUCTS (NOT APPLICABLE)
PART 3 EXECUTION (NOT APPLICABLE)
-- End of Section --
SECTION 01 11 00 Page 6
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 22 00
MEASUREMENT AND PAYMENT
PART 1 GENERAL
1.1 SUMMARY
1.2 RESIDENT MANAGEMENT SYSTEM (RMS)
1.2.1 Definition
1.2.2 Instructions
1.3 SUBMITTALS
1.4 JOB PAYMENT ITEMS
1.4.1 Opening and Securing of Gate C (Line Item 0001)
1.4.1.1 Payment
1.4.2 Removal of Intake Tower Gate C Stem and Operator (Line Item
0002)
1.4.3 Installation of Intake Tower Gate C Stem and Operator (Line
Item 0003)
1.4.4 Municipal Taxes (Line Item 0004)
PART 2 PRODUCTS (NOT APPLICABLE)
PART 3 EXECUTION
3.1 PAYMENT PROCEDURES
3.1.1 Requesting Progress Payment
3.1.2 Options and Modification CLINS
-- End of Section Table of Contents --
SECTION 01 22 00 Page 1
SECTION 01 22 00
MEASUREMENT AND PAYMENT
PART 1 GENERAL
1.1 SUMMARY
This section describes how Line Items will be measured and paid for when making progress payments. Work to be measured is described in specification sections listed for each Line Item. Measurement procedures for payment, required quantity survey or procurement documentation and payment restrictions are described in applicable specification sections.
Allocate costs for work not specifically mentioned to the Line Item most closely associated with work involved. Unless there is a specific Line Item for administrative costs, such as Quality Control and Safety, allocate such costs proportionally across all Line Items.
1.2 RESIDENT MANAGEMENT SYSTEM (RMS)
1.2.1 Definition
The terms "Contract Line Item Number (CLIN)" and "Line Item" are interchangeable herein (e.g.: CLIN 0001 is Line Item 0001). The term "CLIN" is a contracting term used in the Resident Management System (RMS) payment data base.
1.2.2 Instructions
See Section 01 45 00 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM) for more information on CLINs, schedule of values of pay activities and construction schedule, and payment procedures. The Contractor mode user manual with in-depth instructions can be downloaded from the RMS web site indicated in Section 01 45 00 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE
(RMS CM).
1.3 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Transmit submittal items in accordance with Section 01 33 00 SUBMITTAL PROCEDURES. Submit the following preconstruction submittal items no later than 10 calendar days after Notice to Proceed:
SD-01 Preconstruction Submittals
Schedule of Values; G, RO
Provide a breakdown of lump sum items into proposed pay activities as part of the initial project schedule. Schedule of Values will become basis for CLIN and Pay Activity data in the RMS payment data base.
SECTION 01 22 00 Page 2
SD-07 Certificates
Invoice For Municipal Taxes
Submit invoice for payment under subparagraph "Municipal Taxes (Line Item 0004)" below.
1.4 JOB PAYMENT ITEMS
Payment items for the work of this contract for which contract lump sum payments will be made are listed in the LINE ITEMS AND PRICING SCHEDULE with the unit "JOB" and described below. All costs for items of work, which are not specifically mentioned to be included in a particular lump sum or unit price payment item, shall be included in the listed lump sum item most closely associated with the work involved. The lump sum price and payment made for each item listed shall constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided.
Progress payments for lump sum CLINs will be made in accordance with the Payments Under Fixed-Price Construction Contracts clause of Section 00700 CONTRACT CLAUSES in Volume 1. Submit a list of pay activities, (Schedule of Values) to breakdown bid for each lump sum CLIN. The Schedule of Values shall be submitted for Government approval with the baseline schedule submittal (see Section 01 32 01 PROJECT SCHEDULE). An unbalanced Schedule of Values and Pay Activity Schedule will be returned for revision. If this contract contains either the Continuing Contracts clause or the Continuing Contracts (Alternate) clause, the Contractor should take into account the amount reserved for contract payments when preparing the construction schedule.
1.4.1 Opening and Securing of Gate C (Line Item 0001)
1.4.1.1 Payment
Payment will be made for costs associated with or incidental to mobilization and demobilization, establishment of initial project management and coordination, and fully opening and securing the gate in the opened position within thirty (30) calendar days after the NTP has been issued. This line item does not require full demolition of the stem and operator.
1.4.2 Removal of Intake Tower Gate C Stem and Operator (Line Item 0002)
Payment will be made for costs associated with or incidental to mobilization and demobilization, and removing a quantity of one (1) cast iron sluice gate stem and operator for Gate C residing on the outside of the intake tower. Include costs for removing and disposing of the trash rack over the intake shaft. Costs for the pre-removal and post-removal dive inspections shall be included in this line item.
1.4.3 Installation of Intake Tower Gate C Stem and Operator (Line Item 0003)
Payment will be made for costs associated with or incidental to mobilization and demobilization, and installing a quantity of one new (1) sluice gate stem, stem guides, and operator for the intake tower Gate C.
Include costs for fabricating and installing a new trash rack over the
SECTION 01 22 00 Page 3 intake shaft. Include all costs for testing and closeout.
1.4.4 Municipal Taxes (Line Item 0004)
Pursuant to municipality local regulations, taxes may apply with line items under this contract. See Paragraph 999.229-1 in Section 00100 of this solicitation. The contract price will be adjusted to compensate the Contractor for the amount of construction taxes. No mark-ups will be allowed in this line item. The Contractor will be paid on the basis of proof of payment from the appropriate Commonwealth of Puerto Rico or Municipal authorities.
PART 2 PRODUCTS (NOT APPLICABLE)
PART 3 EXECUTION
3.1 PAYMENT PROCEDURES
Upon receiving initial Resident Management System import file, go to "Pay Activities" and establish a link between bid breakdown schedule of values of "Pay Activities" to contract CLINs using "Schedule Activities" data entry page.
3.1.1 Requesting Progress Payment
For progress payments, ensure "Activity Schedule", "Feature Schedule", submittal register, and punchlists are all up to date. Use "Progress Payments" to "request Activity Earnings" for both "Activity Earnings" data entry page and "Other Earning". Provide hard copies of supporting invoices and quantity measurements to support all requested earnings. Ensure that sum of payment activities do not exceed contract award CLIN funding amounts, or "unbalanced" CLINs error will prevent processing the payment.
3.1.2 Options and Modification CLINS
When additional work is added by modification, existing CLINs funding amounts must be updated, or new CLINs for modification will be created. If contract has option CLINs not yet awarded, option CLINs will appear as zero dollar CLINs until option is awarded by modification. No payment may be requested for Options or Modification CLINs until contract modification has been funded and signed.
-- End of Section --
SECTION 01 22 00 Page 4
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 30 00
ADMINISTRATIVE PROCEDURES
PART 1 GENERAL
1.1 SUMMARY
1.2 SUBMITTALS
1.3 PROJECT COORDINATION
1.3.1 Resident Management System (RMS)
1.3.2 Coordination with Other Contracts
1.3.2.1 Contractor Shared Space or Facilities
1.3.2.2 Adjacent Contractor
1.3.2.3 Future Contract
1.3.2.4 Work by Others
1.3.3 Inspections by Others
1.4 PROJECT MEETINGS
1.5 PRECONSTRUCTION CONFERENCE
1.5.1 Preconstruction Conference Minutes
1.5.2 Preconstruction Conference Submittals
1.5.2.1 Other Division 01 Submittals
1.6 PARTNERING
1.6.1 Initial Partnering Meeting
1.7 NOTICE TO PROCEED
1.8 COORDINATION MEETING
1.9 PROGRESS MEETINGS
1.9.1 Progress Meeting Participants
1.10 CONTRACTOR PERFORMANCE EVALUATIONS
1.10.1 Training
PART 2 PRODUCTS (NOT APPLICABLE)
PART 3 EXECUTION
3.1 GENERAL MEETING REQUIREMENTS
3.2 PROGRESS MEETING AGENDA
-- End of Section Table of Contents --
SECTION 01 30 00 Page 1
SECTION 01 30 00
ADMINISTRATIVE PROCEDURES
PART 1 GENERAL
1.1 SUMMARY
Manage project and coordinate activities of own employees, subcontractors, suppliers and offsite fabricators. Contractor shall use computers, E-mail, and Internet resources for administrative work. Notify Contracting Officer of important meetings, schedule events and activities. Furnish labor and materials and equipment required to plan and execute project management functions and coordination. Coordinate activities and manage resources to construct project conforming to contract, on time and within budget.
Related Sections are 01 32 01 PROJECT SCHEDULE.
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Transmit submittal items in accordance with Section 01 33 00 SUBMITTAL PROCEDURES. Submit the following preconstruction submittal items no later than 10 calendar days after Notice to Proceed:
SD-01 Preconstruction Submittals
List of Subcontractors
Documentation of compliance with Clauses SUBCONTRACTS (LABOR STANDARDS) and LIMITATIONS ON SUBCONTRACTING of Section 00700 CONTRACT CLAUSES in Volume 1, and, if included, paragraph
LIMITATIONS ON SUBSTITUTIONS FOR CERTAIN POSITIONS AND/OR
SUBCONTRACTORS of Section 00800 SPECIAL REQUIREMENTS in Volume 1.
As part of the initial project schedule, submit a list of proposed subcontractors with company name, person to contact, street address, mail address, phone number, type of specialty and estimated subcontract quote.
SD-07 Certificates
Signature Authority
Furnish a power of attorney or a notarized letter of authority from Contractor identifying local representatives authorized to sign contract documents.
Drug-Free Work Place Record
Documentation of compliance with Clause DRUG-FREE WORKPLACE of Section 00700 CONTRACT CLAUSES in Volume 1 (see subparagraphs (b)(1) through (b)(7)).
SECTION 01 30 00 Page 2
1.3 PROJECT COORDINATION
1.3.1 Resident Management System (RMS)
Contractor shall use Corps of Engineers' Resident Management System for construction information management. See Section 01 45 00 RESIDENT
MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM).
1.3.2 Coordination with Other Contracts
1.3.2.1 Contractor Shared Space or Facilities
Employee parking and material storage areas will be shared with other Contractors. Each Contractor is responsible to maintain his portion of shared facilities until contract completion of his contract. Each Contractor is responsible to secure and protect stored materials from theft or damage.
1.3.2.2 Adjacent Contractor
An active construction near project site may impact Contractor work.
Coordinate activities to avoid impact to adjacent Contractors and prevent problems from adjacent contract.
1.3.2.3 Future Contract
During construction period for this project, a future contract may be scheduled to start. Coordinate contract activities with other Contractor to avoid impact to either contract. Notify Contracting Officer of problems caused by other contract.
1.3.2.4 Work by Others
During construction period, construction or maintenance work will be performed by others within construction limits of the intake tower, or on systems and equipment related to dam operations. Coordinate work by others with Contracting Officer and schedule activities to avoid problems.
1.3.3 Inspections by Others
During construction period, inspection or maintenance work will be performed by others within the construction limits.
1.4 PROJECT MEETINGS
Contracting Officer requires following types of project meetings:
-- Preconstruction Conference -- Partnering Meeting -- Partnering Regroup Meetings -- Coordination Meeting -- Preparatory and Initial Phase meeting for each feature of work -- Project Progress Meetings
Project meetings are described in detail in subparts below.
1.5 PRECONSTRUCTION CONFERENCE
Contracting Officer will conduct a Preconstruction Conference for this
SECTION 01 30 00 Page 3 project in accordance with Clause PRECONSTRUCTION CONFERENCE of Section 00700 CONTRACT CLAUSES in Volume 1. Preconstruction Conference will be held within 30 to 60 calendar days after Notice to Proceed (NTP) acknowledgment. (Refer to subparagraph "Preconstruction Conference Submittals" below.) Contracting Officer will notify Contractor of time, place, and agenda. Contractor shall notify key subcontractors and suppliers to attend. Contracting Officer will discuss contract "ground rules" and general issues including:
-- Lines of Contracting Officer authority -- Lines of Contractor authority -- 00700 Contract Clauses -- 00800 Special Contract Requirements -- Contract Administration -- Progress Payment -- Correspondence Procedures -- Project Schedule -- Submittal Register -- Labor requirements -- General Site Safety
1.5.1 Preconstruction Conference Minutes
Contracting Officer will take detailed minutes of Preconstruction Conference discussions and may use an audio or video tape. Copies of typed minutes will be provided to the Contractor to review for accuracy, sign and return. Signed minutes become part of the contract file. Audio or video tapes if used will be made available for Contractor to review or copy at Area Office.
1.5.2 Preconstruction Conference Submittals
The timing of submission of submittals and completion of the Preconstruction Conference is intended to allow the Contractor and the Government adequate time to prepare for commencement of work. However, should the Contractor fail to submit required items and receive acceptance and/or approval within the times stated, the Contractor will not be permitted to commence work until these requirements have been satisfied.
Any delays attributable to the Contractor's failure to comply with these pre-work requirements shall be at the Contractor's expense and may be cause for remedial action by the Contracting Officer. Submittals required by this Section are described in paragraph SUBMITTALS above.
1.5.2.1 Other Division 01 Submittals
The Contracting Officer reviews submitted draft plans to prepare Coordination Meeting agenda and understand Contractor procedures. Submit the following preconstruction submittal items no later than 30 calendar days after Notice to Proceed:
-- Project Schedule - See Section 01 32 01 PROJECT SCHEDULE -- Accident Prevention Plan - See Section 01 35 26 GOVERNMENTAL
SAFETY REQUIREMENTS
-- Quality Control Plan - See Section 01 45 04 CONTRACTOR QUALITY
CONTROL
-- Environmental Protection Plan - See Section 01 57 20
ENVIRONMENTAL PROTECTION
SECTION 01 30 00 Page 4
1.6 PARTNERING
Contracting Officer wants to have a bilateral project partnership with Contractor that draws on strengths of both organizations to identify and achieve common goals. Typical partnering goals include:
-- Effective and efficient contract performance -- Project completion on time and within budget -- Construction completed according to plans and specifications -- Development of cooperative management teams -- Project success with customer (stakeholders) satisfaction -- Improved Project communication
1.6.1 Initial Partnering Meeting
Contractor, key subcontractors and suppliers shall attend a project "Partnering Meeting". The Partnering Meeting is a project team building meeting facilitated by qualified persons. Contracting Officer attendees and invited persons may include:
Administrative Contracting Officer (Area Engineer) Construction Quality Assurance Representatives Jacksonville District - Construction Branch persons Local Sponsor (Owner) - Puerto Rico Electric Power Authority (PREPA)
Goal of initial Partnering Meeting is to build trust, identify common goals, and understand individual project members' expectations and organizational values. Usual results include better communication between contract parties, shortened project learning curve and a cohesive two party contract partnership. Participants usually sign a voluntary partnering agreement generally describing mutual obligation to cooperate to achieve project goals and maintain effective communication. Contractor shall pay costs for workshop site rental and facilitator fees.
1.7 NOTICE TO PROCEED
Notice to proceed (NTP) will be issued 7 calendar days after award or after all required bonds are in place, whichever is later. If the Contractor has failed to submit and receive acceptance and/or approval of specified plans, including, but not limited to, Accident Prevention Plan - Section 01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS, Quality Control Plan - Section 01 45 04 CONTRACTOR QUALITY CONTROL, , and Environmental Protection Plan - Section 01 57 20 ENVIRONMENTAL PROTECTION, or has not yet received the Contracting Officer's conditional approval to work under an interim plan, the Contractor shall not proceed with the work and shall consider the work to be suspended in accordance with the Suspension Of Work clause of the contract. While the Contractor is working under a conditionally accepted interim plan, funds may be retained from progress payments in accordance with the Payments Under Fixed-Price Construction Contracts clause of this contract until such time as the Contractor submits an acceptable plan. If the Contractor does not submit an acceptable plan within a reasonable time, as determined by the Contracting Officer, the Contracting Officer may order the Contractor to suspend work. Any suspension order issued for the Contractor's failure to submit an acceptable plan will not constitute unreasonable delay under the Suspension Of Work clause and the Contractor will not be entitled to an equitable adjustment of either performance period or contract price.
SECTION 01 30 00 Page 5
1.8 COORDINATION MEETING
Coordination Meeting is scheduled, convened and conducted by Contracting Officer after a Preconstruction Conference and prior to starting physical construction. Draft plans submitted after NOA (i.e., Quality Control Plan, Environmental Protection Plan and Accident Prevention Program) will have been reviewed. Coordination Meeting is primarily for on-site Contractor Quality Control staff, including subcontractor and supplier employees performing quality control, to meet and discuss the project in detail with Contracting Officer's Quality Assurance Representatives. Purposes of Coordination Meeting are:
-- Achieve mutual understanding with Contractor of required Quality Control -- Jointly review submitted draft plans; resolve issues of concern -- Discuss project plans and specifications, schedule, documentation -- Establish a good working relationship between the Contractors Quality Control Staff and Quality Assurance Representatives
1.9 PROGRESS MEETINGS
Schedule, convene and preside over progress meetings as required. As project activities increase ("ramp up"), a minimum of one progress meeting per week is typical of a project of this scope. Convene additional meetings as required, or when requested by Contracting Officer. Notify persons needed to be present to discuss agenda issues. Contracting Officer may direct attendance by key Contractor suppliers, or fabricators as needed. A sample meeting agenda is provided in paragraph GENERAL MEETING REQUIREMENTS below. The Contractor shall take minutes of the meetings and distribute copies of the minutes within three working days after the meetings.
1.9.1 Progress Meeting Participants
Typical participants include:
-- Contracting Officer -- Construction Quality Assurance Representatives -- Contractor's Site Superintendent -- Contractor's Quality Control Manager -- Contractor's Safety Coordinator -- Subcontractors, as appropriate to the agenda -- Suppliers, as appropriate to the agenda -- Others as appropriate to the agenda
1.10 CONTRACTOR PERFORMANCE EVALUATIONS
Contractors are given an opportunity to provide and/or enter performance evaluation comments directly into the Contractor Performance Assessment Reporting System (CPARS). The system is a web-enabled application that supports the completion, distribution, and retrieval of contract performance evaluations. Provide to the responsible area office the name and email address of the contractor user that will be accessing CPARS.
1.10.1 Training
Contractor online training is available at the following web site:
https://www.cpars.gov/webtrain.htm. Training will give the student an understanding of the Contractor Representative and Contractor Corporate
SECTION 01 30 00 Page 6
Senior Management levels of access, the policies and regulations governing CPARS, and the electronic workflow with particular attention to the Contractor comment function.
PART 2 PRODUCTS (NOT APPLICABLE)
PART 3 EXECUTION
3.1 GENERAL MEETING REQUIREMENTS
See Section 01 45 04 CONTRACTOR QUALITY CONTROL for Preparatory and Initial Phase meeting checklists. Contractor is responsible for phase and progress meetings to include:
Meeting notification to participants Prepare agenda for meetings Use phase checklists for Preparatory and Initial Phase meetings Physical arrangements for meetings Preside at meetings Record minutes recording proceedings and decisions Copy and send minutes to:
Meeting participants Project parties affected by decisions Contracting Officer (No later than 3 working days)
3.2 PROGRESS MEETING AGENDA
Modify agenda as needed for on-going work.
Review minutes from previous progress meetings Review RMS Contractor Action Item Report Review work progress since previous meeting Review current definable features of work:
-- Identify phases of current features of work -- Identify pending phase changes -- Identify features for discussion in next scheduled meeting
Discuss problem prevention:
-- Field observations -- Deficiencies and tracking -- Procedures working well -- Problems, conflicts -- Methods to improve
Review construction schedule:
-- Identify delays -- Discuss proposed corrective actions to regain schedule
Submittals and Requests for Information (design interpretation):
-- Review submittal register -- Identify submittals to expedite as required
Review off-site activities:
-- Fabrications -- Material and equipment delivery schedule
Review Testing:
-- Type, Schedule -- Received Results
Review changes to construction schedule:
-- Planned progress during succeeding work period -- Coordination of various schedules -- Effect of changes on construction and completion date
Review site safety
SECTION 01 30 00 Page 7
Discuss maintaining contract quality for materials and workmanship Discuss pending modifications, changes and substitutions Discuss other business, as appropriate
-- End of Section --
SECTION 01 30 00 Page 8
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 32 01
PROJECT SCHEDULE
PART 1 GENERAL
1.1 SUBMITTALS
1.2 CONSTRUCTION SCHEDULES
1.2.1 RMS SCHEDULES
1.2.2 Bar Chart with "S"Curve
1.2.2.1 Sample Bar Chart
1.2.2.2 Sample "S" Curve
1.3 UPDATED SCHEDULES
PART 2 PRODUCTS (NOT APPLICABLE)
PART 3 EXECUTION (NOT APPLICABLE)
-- End of Section Table of Contents --
SECTION 01 32 01 Page 1
SECTION 01 32 01
PROJECT SCHEDULE
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES. Submit the following preconstruction submittal items no later than 10 calendar days after Notice to Proceed:
SD-01 Preconstruction Submittals
RMS Schedules; G, RO
Bar Chart; G, RO
"S" Curve; G, RO
1.2 CONSTRUCTION SCHEDULES
Use work breakdown structure of "CLINs", "Features" and "Pay Activities".
"CLINs" are Contract Line Item Numbers from bid schedule. "Features" are quality control grouping of like "Pay Activities" requiring similar quality control. "Pay Activities" are scheduled work activities or events. Most "Pay Activities" have resources (time, money, labor, material and equipment). Use "Pay Activities" with no dollars allocate to schedule administrative work activities or events.
1.2.1 RMS SCHEDULES
See Section 01 45 04 CONTRACTOR QUALITY CONTROL. After receipt of Notice of Award, create "Activity Schedule" and "Feature Schedule" in RMS, in accordance with the terms of FAR 52.236-15 SCHEDULES FOR CONSTRUCTION CONTRACTS. Submit RMS Schedules as part of initial RMS export. Data can be entered manually or Contractor has option to use standard data exchange format (SDEF.txt file). Cost allocate each "Pay Activity" to an assigned CLIN. Sum of "Pay Activities" must equal CLIN totals so there is no variance. "Features" duration is early start of first "Pay Activity" to late finish date of last "Pay Activity". Primavera P6 v6.x and later versions (v7.x and v8.x) allow export of a file for conversion to standard data exchange format (SDEF.txt) file format. Primavera provides a utility that will convert the export file to an SDEF.txt file. An SDEF.txt file can then be used to directly import the Primavera schedule into RMS. The Contractor shall be responsible for providing all programs and hardware necessary to prepare initial and progress schedules. The required Primavera P6 Activity Code Structure is as follows:
SECTION 01 32 01 Page 2
Field # Code Length Field Description 1 WRKP 3 Workers per day 2 RESP 4 Responsibility 3 AREA 4 Area 4 MODF 6 Modification or Claim # 5 BIDI 6 Bid Item 6 PHAS 2 Phase 7 CATW 1 Category of Work 8 FOW 20 Feature of Work
1.2.2 Bar Chart with "S"Curve
Submit the initial Bar Chart with target "S" Curve no later than 20 calendar days after award or 5 calendar days after Notice to Proceed, whichever is later. Contractor may create a manual Bar Chart and "S" curve or use computer software of his choice. Scheduling software allows for easier updates and changes. See sample Bar Chart and "S" Curve below. The Bar Chart shall include an appropriate level of detail including activities, submittals, Government review periods, material/equipment delivery, utility outages, on-site construction, inspection, testing, and closeout activities. Contractor's submissions shall follow the direction of the Contracting Officer regarding reasonable activity durations.
Reasonable durations are those that allow the progress of activities to be accurately determined between payment periods. All planned durations must take into account weather and climate data, work schedules, and contract restrictions on work periods. No single on-site construction activity shall exceed 30 days in duration without further breakdown in detail.
Contractor has an option to schedule an "early finish" date with "float" until contract required completion date. Schedules with "early finish" are for the benefit of the Contractor, and the Contracting Officer may elect to continue to make balanced progress payments based on funds availability.
Neither Contractor nor Contracting Officer own "float" on early finish schedules. Contractor shall not claim added costs for delay for float used. When unit price CLINs have quantity variations and impact weighted percentage of a "Pay Activity" by five percent or more, revise bar chart and "S" Curve to accurately reflect impact of variation of estimated quantities. See the next page for sample Bar Chart and "S" Curve.
SECTION 01 32 01 Page 3
1.2.2.1 Sample Bar Chart
Sample Bar Chart has early finish at week 16 +/-.
Feature A CLIN1/Act 1| AAAA CLIN1/Act 2| AAAAAAAAAAAA Feature B CLIN2/Act 3| BBBBBBB CLIN2/Act 4| BBBBBBBBBBB CLIN2/Act 5| BBBBBBBBBBB Feature C CLIN3/Act 6| CCCCCCCCCCCCCC CLIN3/Act 7| CCCCCCCCCCC Feature D CLIN4/Act 8| DDDDDDDDDDDDDDDDD CLIN4/Act 9| DDDDDDDDDDDDDD |<-- Float->| CLIN4/Act 10 DDDDDD 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
TIME SCALE
1.2.2.2 Sample "S" Curve
Sample "S" curve is early finish at week 16 +/- with actual progress plotted at week 14.
% Complete 100 | +|<---- Float ---->| 95 | + + e 90 | + = Target + e 85 | a = Actual + e 80 | e = Estimated + e 75 | + e 70 | + e 65 | + e 60 | + a 55 | + a 50 | + a 45 | + + a a 40 | + a 35 | + + a 30 | + a 25 | + + a 20 | + + a a 15 | + + + a a 10 | + a a a a 5 | + + a 0 |_ + a a 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 Time Scale
1.3 UPDATED SCHEDULES
Maintain construction progress schedules submission up-to-date. Ensure submittal is updated and includes RMS Schedules, Bar Charts, "S" Curves and progress narrative when requesting progress payment. Submit Bar Chart , "S" Curve schedule when schedule is revised. Reflect any changes occurring
SECTION 01 32 01 Page 4 since the last update.
When work is delayed by causes beyond the Contractor's control, the Contractor is obligated to notify the ACO within 10 days of the beginning of the delay. The Contractor is obligated to submit a cost and time proposal, illustrating the influence of each change or delay on the Contract Completion Date or contract required Milestone. No time extension will be granted nor delay damages paid unless a delay occurs which consumes all available Project Float, and extends the Projected Finish beyond the Contract Completion Date.
PART 2 PRODUCTS (NOT APPLICABLE)
PART 3 EXECUTION (NOT APPLICABLE)
-- End of Section --
SECTION 01 32 01 Page 5
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 33 00
SUBMITTAL PROCEDURES
PART 1 GENERAL
1.1 SUMMARY
1.2 DEFINITIONS
1.2.1 Submittal
1.2.2 Transmittal
1.2.3 Submittal Descriptions (SD)
1.2.4 Approving Authority
1.2.5 Work
1.2.6 Contractor Reviewer
1.2.7 Primary Reviewer
1.2.8 Secondary Reviewer
1.2.9 Reviewer Codes
1.2.10 Review and Action Codes
1.2.11 Review Comments to Contractor
1.3 SUBMITTALS
1.4 SUBMITTAL CLASSIFICATION
1.4.1 Government Approved
1.4.2 Information Only
1.5 APPROVED SUBMITTALS
1.6 DISAPPROVED SUBMITTALS
1.7 WITHHOLDING OF PAYMENT
1.8 GENERAL
1.9 SUBMITTAL REGISTER
1.10 SCHEDULING
1.10.1 Avoiding Delays
1.11 TRANSMITTAL FORM (ENG FORM 4025)
1.11.1 Approving Authority Review Codes
1.12 SUBMITTAL PROCEDURES
1.12.1 Reviewing, Certifying, Approving Authority
1.12.2 Procedures
1.12.3 Number of Copies or Samples
1.12.4 Identifying Submittal Items and Transmittals
1.12.5 Submittal Format
1.12.5.1 Format for Shop Drawings
1.12.5.2 Format for Construction Drawings
1.12.5.3 Format for Computer Aided Design (CAD) Drawings
1.12.5.4 Administrative Submittal Items Format
1.12.6 Deviations
1.12.7 Considering Variations
1.12.8 Proposing Variations
1.12.9 Warranty Variations
1.12.10 Electronic Correspondence
1.13 CONTROL OF SUBMITTALS
1.14 GOVERNMENT APPROVED SUBMITTALS
1.15 INFORMATION ONLY SUBMITTALS
SECTION 01 33 00 Page 1
1.16 REQUEST FOR INFORMATION (RFI)
1.17 SUBMITTAL REGISTER
1.18 STAMPS
PART 2 PRODUCTS (NOT APPLICABLE)
PART 3 EXECUTION (NOT APPLICABLE)
-- End of Section Table of Contents --
SECTION 01 33 00 Page 2
SECTION 01 33 00
SUBMITTAL PROCEDURES
PART 1 GENERAL
1.1 SUMMARY
This section describes submittal procedures in Jacksonville District contracts using Quality Control System submittal procedures in accordance with Section 01 45 00 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM).
It covers submittal item identification, number of copies, review periods, quality control review, QC/QA reviewer coding, and transmittal tracking procedures using Resident Management System (RMS) shared data base.
Contractor shall use RMS software to identify, track and transmit submittal items.
1.2 DEFINITIONS
1.2.1 Submittal
Contract Clauses "FAR 52.236-5, Material and Workmanship," paragraph (b) and "FAR 52.236-21, Specifications and Drawings for Construction," paragraphs (d), (e), and (f) apply to all "submittals."
1.2.2 Transmittal
This is a routine contract correspondence action using a transmittal form (ENG Form 4025) to send submittal items to the Government. The RMS "Transmittal Log" module uses data base entry to create a hard copy of ENG Form 4025.
1.2.3 Submittal Descriptions (SD)
Submittals requirements are specified in the technical sections.
Submittals are identified by SD numbers and titles as follows.
SD-01 Preconstruction Submittals
Submittals which are required prior to start of construction (work) or the start of the next major phase of the construction on a multi-phase contract, includes schedules, tabular list of data, or tabular list including location, features, or other pertinent information regarding products, materials, equipment, or components to be used in the work.
Preconstruction submittals shall be submitted no later than 10 calendar days after Notice to Proceed.
SD-02 Shop Drawings
Drawings, diagrams and schedules specifically prepared to illustrate some portion of the work.
Diagrams and instructions from a manufacturer or fabricator for use in producing the product and as aids to the Contractor for integrating the product or system into the project.
SECTION 01 33 00 Page 3
Drawings prepared by or for the Contractor to show how multiple systems and interdisciplinary work will be coordinated.
SD-03 Product Data
Catalog cuts, illustrations, schedules, diagrams, performance charts, instructions and brochures illustrating size, physical appearance and other characteristics of materials or equipment for some portion of the work.
Samples of warranty language when the contract requires extended product warranties.
SD-06 Test Reports
Report signed by authorized official of testing laboratory that a material, product or system identical to the material, product or system to be provided has been tested in accordance with specified requirements. (Testing must have been within three years of date of contract award for the project.)
Report which includes findings of a test required to be performed by the Contractor on an actual portion of the work or prototype prepared for the project before shipment to job site.
Report which includes finding of a test made at the job site or on sample taken from the job site, on portion of work during or after installation.
Investigation reports.
Daily checklists.
Final acceptance test and operational test procedure.
SD-07 Certificates
Statements signed by responsible officials of manufacturer of product, system or material attesting that product, system or material meets specification requirements. Must be dated after award of project contract and clearly name the project.
Document required of Contractor, or of a supplier, installer or subcontractor through Contractor, the purpose of which is to further quality of orderly progression of a portion of the work by documenting procedures, acceptability of methods or personnel qualifications.
Confined space entry permits.
SD-10 Operation and Maintenance Data
Data that is furnished by the manufacturer, or the system provider, to the equipment operating and maintenance personnel. This data is needed by operating and maintenance personnel for the safe and efficient operation, maintenance and repair of the item.
SD-11 Closeout Submittals
SECTION 01 33 00 Page 4
Documentation to record compliance with technical or administrative requirements or to establish an administrative mechanism.
1.2.4 Approving Authority
Office authorized to approve submittal.
1.2.5 Work
As used in this section, on- and off-site construction required by contract documents, including labor necessary to produce submittals, construction, materials, products, equipment, and systems incorporated or to be incorporated in such construction.
1.2.6 Contractor Reviewer
Contractor…