CHANGES TO THE TECHNICAL INFORMATION AND SPECIFICATIONS VOLUME 2 OF 2
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 7-9-TCC_Site-Visit_Sign_in_SHeet.pdf | ||
| W912EP-13-R-0001-0001.doc | DOC document | |
| Vol2of2_13R0001.pdf | ||
| HHD_-_TCC_Abandonment_10.15.12.pdf | ||
| Vol1of2___13R0001.pdf | ||
| HHD_-_C-09_Abandonment_10.15.12.pdf | ||
| HHD_-_C-07_Abandonment_10.15.12.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
HHD Rehabilitation Project, Culvert 7, Culvert 9, and Taylor Creek Culvert Abandonment
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 30 00
ADMINISTRATIVE PROCEDURES
PART 1 GENERAL
1.1 SUMMARY
1.2 SUBMITTALS
1.3 PROJECT COORDINATION
1.3.1 Resident Management System (RMS)
1.3.2 Coordination with Other Contracts
1.3.2.1 Adjacent Contractors
1.3.2.2 Work by Others
1.3.3 Access to Others
1.3.4 Inspections by Others
1.3.5 Work Schedule Coordination
1.4 PROJECT MEETINGS
1.5 PRECONSTRUCTION CONFERENCE
1.5.1 Preconstruction Conference Minutes
1.5.2 Preconstruction Conference Submittals
1.5.2.1 Other Division 01 Submittals
1.5.2.2 Divisions 02 through 48 Submittals
1.6 PARTNERING
1.6.1 Initial Partnering Meeting
1.6.2 Partnering Regroups
1.7 NOTICE TO PROCEED
1.8 COORDINATION MEETING
1.9 PROGRESS MEETINGS
1.9.1 Progress Meeting Participants
1.10 CONTRACTOR PERFORMANCE EVALUATIONS
1.10.1 Training
1.11 PRECONSTRUCTION SURVEY
PART 2 PRODUCTS (NOT APPLICABLE)
PART 3 EXECUTION
3.1 GENERAL MEETING REQUIREMENTS
3.2 PROGRESS MEETING AGENDA
-- End of Section Table of Contents --
W912EP-13-R-0001 SECTION 01 30 00 Page 1 Am0001
SECTION 01 30 00
ADMINISTRATIVE PROCEDURES
PART 1 GENERAL
1.1 SUMMARY
Manage project and coordinate activities of own employees, subcontractors, suppliers and offsite fabricators. Contractor shall use computers, E-mail, and Internet resources for administrative work. Notify Contracting Officer of important meetings, schedule events and activities. Furnish labor and materials and equipment required to plan and execute project management functions and coordination. Coordinate activities and manage resources to construct project conforming to contract, on time and within budget.
Related Sections are 01 32 01 PROJECT SCHEDULE, and 01 45 04 CONTRACTOR
QUALITY CONTROL.
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Transmit submittal items in accordance with Section 01 33 00 SUBMITTAL PROCEDURES. Bring following administrative submittal items to Preconstruction Conference:
SD-01 Preconstruction Submittals
List of Subcontractors
Documentation of compliance with Clauses SUBCONTRACTS (LABOR STANDARDS) and LIMITATIONS ON SUBCONTRACTING of Section 00700 CONTRACT CLAUSES in Volume 1, and, if included, paragraph
LIMITATIONS ON SUBSTITUTIONS FOR CERTAIN POSITIONS AND/OR
SUBCONTRACTORS of Section 00800 SPECIAL REQUIREMENTS in Volume 1.
Submit a list of proposed subcontractors with company name, person to contact, street address, mail address, phone number, type of specialty and estimated subcontract quote.
SD-07 Certificates
Signature Authority
Furnish a power of attorney or a notarized letter of authority from Contractor identifying local representatives authorized to sign contract documents.
Drug-Free Work Place Record
Documentation of compliance with Clause DRUG-FREE WORKPLACE of Section 00700 CONTRACT CLAUSES in Volume 1 (see subparagraphs (b)(1) through (b)(7)).
Work Schedule; G|RO
W912EP-13-R-0001 SECTION 01 30 00 Page 2 Am0001
Furnish work schedule which shall include days and hours scheduled for work.
1.3 PROJECT COORDINATION
1.3.1 Resident Management System (RMS)
Contractor shall use Corps of Engineers' Resident Management System, referred to as Quality Control System (QCS), for construction information management. See Section 01 45 04 CONTRACTOR QUALITY CONTROL.
1.3.2 Coordination with Other Contracts
1.3.2.1 Adjacent Contractors
Active construction near project site may impact Contractor work.
Coordinate activities to avoid impact to adjacent Contractors and prevent problems from adjacent contracts. The Contractor's work limits from the public right of way to the site are limited to the crest of the embankment. The crest of the embankment will be shared with other contractors.
1.3.2.2 Work by Others
During construction period, construction or maintenance work will be performed by others within construction limits. Coordinate work by others with Contracting Officer and schedule activities to avoid problems.
1.3.3 Access to Others
Maintain access to Government operations personnel for scheduled inspections of the dike. Maintain access to power poles and other items owned or operated by utility companies. Coordinate with utility companies as required for line marking, hookups, and relocations as needed to perform work. Incoming electrical utilities become the responsibility of Contractor at transformers. Coordinate emergency incident response with local law enforcement and fire rescue authorities. Notify Contracting Officer in writing of coordination problems encountered affecting work.
1.3.4 Inspections by Others
During construction period, inspection or maintenance work will be performed by others within the construction limits. The Contractor will be responsible for neatly mowing all grass and vegetation (not to include established trees or other protected vegetation designated as wetland areas) within the construction limits during the duration of the contract.
Areas not accessible to mowers shall be edged or trimmed neatly. Mowing or trimming shall be performed every three week or when vegetation exceeds twelve inches in height.
1.3.5 Work Schedule Coordination
During construction period, Contractor shall give 48 hours notice if they are to change or deviated from the approved work schedule.
1.4 PROJECT MEETINGS
Contracting Officer requires following types of project meetings:
W912EP-13-R-0001 SECTION 01 30 00 Page 3 Am0001
-- Preconstruction Conference -- Partnering Meeting -- Partnering Regroup Meetings -- Coordination Meeting -- Preparatory and Initial Phase meeting for each feature of work -- Project Progress Meetings
Project meetings are described in detail in subparts below.
1.5 PRECONSTRUCTION CONFERENCE
Contracting Officer will conduct a Preconstruction Conference for this project in accordance with Clause PRECONSTRUCTION CONFERENCE of Section 00700 CONTRACT CLAUSES in Volume 1. Preconstruction Conference will be after Notice of Award (NOA) but prior to Notice to Proceed (NTP). (Refer to subparagraph "Preconstruction Conference Submittals" below.)
Contracting Officer will notify Contractor of time, place, and agenda.
Contractor shall notify key subcontractors and suppliers to attend.
Contracting Officer will discuss contract "ground rules" and general issues including:
-- Lines of Contracting Officer authority -- Lines of Contractor authority -- 00700 Contract Clauses -- 00800 Special Contract Requirements -- Contract Administration -- Progress Payment -- Correspondence Procedures -- Project Schedule -- Submittal Register -- Labor requirements -- General Site Safety
1.5.1 Preconstruction Conference Minutes
Contracting Officer will take detailed minutes of Preconstruction Conference discussions and may use an audio or video tape. Copies of typed minutes will be provided to the Contractor to review for accuracy, sign and return. Signed minutes become part of the contract file. Audio or video tapes if used will be made available for Contractor to review or copy at Area Office.
1.5.2 Preconstruction Conference Submittals
The timing of submission of submittals and completion of the Preconstruction Conference is intended to allow the Contractor and the Government adequate time to prepare for commencement of work. However, should the Contractor fail to submit required items within the times stated, the Contracting Officer may issue NTP prior to receipt of submittals and prior to the Preconstruction Conference. If NTP is issued prior to the Contractor's compliance with submittal requirements and prior to the Preconstruction Conference, the Contractor will not be permitted to commence work until these requirements have been satisfied. Any delays attributable to the Contractor's failure to comply with these pre-work requirements shall be at the Contractor's expense and may be cause for remedial action by the Contracting Officer. Submittals required by this Section are described in paragraph SUBMITTALS above.
W912EP-13-R-0001 SECTION 01 30 00 Page 4 Am0001
1.5.2.1 Other Division 01 Submittals
In addition to the above, bring listed Division 01 submittals in draft form to Preconstruction Conference:
-- Network Analysis Schedule - See Section 01 32 01 PROJECT SCHEDULE -- Submittal Register - See Section 01 33 00 SUBMITTAL PROCEDURES -- Quality Control Plan - See Section 01 45 04 CONTRACTOR QUALITY
CONTROL
-- Temporary Facilities Plan - See Section 01 50 02 TEMPORARY
CONSTRUCTION FACILITIES
Contracting Officer reviews submitted draft plans to prepare Coordination Meeting agenda and understand Contractor procedures. Submit the Accident Prevention Plan in accordance with Section 01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS. Submit the Environmental Protection Plan in accordance with Section 01 57 20 ENVIRONMENTAL PROTECTION.
1.5.2.2 Divisions 02 through 48 Submittals
In addition to the above, bring submittal items for materials, workmanship, plans or events required early in project schedule which are ready for transmittal to Contracting Officer. Prepare transmittal of submittal items in accordance with Section 01 33 00 SUBMITTAL PROCEDURES.
1.6 PARTNERING
Contracting Officer wants to have a bilateral project partnership with Contractor that draws on strengths of both organizations to identify and achieve common goals. Typical partnering goals include:
-- Effective and efficient contract performance -- Project completion on time and within budget -- Construction completed according to plans and specifications -- Development of cooperative management teams -- Project success with customer (stakeholders) satisfaction -- Improved Project communication
1.6.1 Initial Partnering Meeting
Contractor, key subcontractors and suppliers shall attend a one-day project "Partnering Meeting". The Partnering Meeting is a project team building workshop facilitated by qualified persons. Contracting Officer attendees and invited persons may include:
Administrative Contracting Officer Representative (Area Engineer) Construction Quality Assurance Representatives Jacksonville District - Construction Branch persons Jacksonville District - Engineering Division Designers Local Sponsor (Owner) - Operations Division personnel
Goal of initial Partnering Meeting is to build trust, identify common goals, and understand individual project members expectations and organizational values. Usual results include better communication between contract parties, shortened project learning curve and a cohesive two party contract partnership. Participants usually sign a voluntary partnering agreement generally describing mutual obligation to cooperate to achieve project goals and maintain effective communication. Contracting Officer will pay costs for workshop site rental and facilitator fees.
W912EP-13-R-0001 SECTION 01 30 00 Page 5 Am0001
1.6.2 Partnering Regroups
After initial Partnering Meeting participation will be voluntary in accordance with a signed Partnering Agreement. After initial Partnering Workshop, partnering sessions will be hosted by both parties on an alternating basis with the hosting party being responsible for all costs associated with their meeting. At no time will these costs be used to change the contract price. Partnering Agreements include provisions for Contracting Officer and Contractor to request "Partnering Regroups" when needed. A "Partnering Regroup" is usually a short (4 hours - 1 day) informal partnering session where senior level Contractor and Contracting Officer project members and other interested parties review project issues of concern. Issues of conflict are reviewed, attempt to affirm common project goals and understand concerns of other partner.
1.7 NOTICE TO PROCEED
Notice to proceed (NTP) will be issued shortly after completion of the preconstruction conference. If the Contractor has failed to submit specified plans, including, but not limited to, Accident Prevention Plan - Section 01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS, Quality Control Plan - Section 01 45 04 CONTRACTOR QUALITY CONTROL, and Environmental Protection Plan - Section 01 57 20 ENVIRONMENTAL PROTECTION, or has not yet received the Contracting Officer's conditional approval to work under an interim plan, the Contractor shall not proceed with the work and shall consider the work to be suspended in accordance with the Suspension Of Work clause of the contract. While the Contractor is working under a conditionally accepted interim plan, funds may be retained from progress payments in accordance with the Payments Under Fixed-Price Construction Contracts clause of this contract until such time as the Contractor submits an acceptable plan. If the Contractor does not submit an acceptable plan within a reasonable time, as determined by the Contracting Officer, the Contracting Officer may order the Contractor to suspend work. Any suspension order issued for the Contractor's failure to submit an acceptable plan will not constitute unreasonable delay under the Suspension Of Work clause and the Contractor will not be entitled to an equitable adjustment of either performance period or contract price.
1.8 COORDINATION MEETING
Coordination Meeting is scheduled, convened and conducted by Contracting Officer after a Preconstruction Conference and prior to starting physical construction. Draft plans submitted after NOA (i.e., Quality Control Plan, Environmental Protection Plan and Accident Prevention Program) will have been reviewed. Coordination Meeting is primarily for on-site Contractor Quality Control staff, including subcontractor and supplier employees performing quality control, to meet and discuss the project in detail with Contracting Officer's Quality Assurance Representatives. Purposes of Coordination Meeting are:
-- Achieve mutual understanding with Contractor of required Quality Control -- Jointly review submitted draft plans; resolve issues of concern -- Discuss project plans and specifications, schedule, documentation -- Establish a good working relationship between the Contractors Quality Control Staff and Quality Assurance Representatives
W912EP-13-R-0001 SECTION 01 30 00 Page 6 Am0001
1.9 PROGRESS MEETINGS
Schedule, convene and preside over progress meetings as required. As project activities increase ("ramp up"), a minimum of one progress meeting per week is typical of a project of this scope. Convene additional meetings as required, or when requested by Contracting Officer. Notify persons needed to be present to discuss agenda issues. Contracting Officer may direct attendance by key Contractor suppliers, or fabricators as needed. A sample meeting agenda is provided in paragraph GENERAL MEETING REQUIREMENTS below. The Contractor shall take minutes of the meetings and distribute copies of the minutes within three working days after the meetings.
1.9.1 Progress Meeting Participants
Typical participants include:
-- Contracting Officer or Contracting Officer's Representative -- Contractor's Site Superintendent -- Contractor's Quality Control Manager -- Contractor's Safety Coordinator -- Subcontractors, as appropriate to the agenda -- Suppliers, as appropriate to the agenda -- Others as appropriate to the agenda
1.10 CONTRACTOR PERFORMANCE EVALUATIONS
Contractors are given an opportunity to provide and/or enter performance evaluation comments directly into the Contractor Performance Assessment Reporting System (CPARS), Architect-Engineer Contract Administration Support System (ACASS), and the Construction Contractor Appraisal Support System (CCASS). The systems are web-enabled applications that support the completion, distribution, and retrieval of contract performance evaluations. Provide to the responsible area office the name and email address of the contractor user that will be accessing CPARS/ACASS/CCASS.
Read this paragraph in conjunction with Paragraph 999.236-4003 CONSTRUCTION CONTRACTOR PERFORMANCE EVALUATIONS of Section 00800 SPECIAL REQUIREMENTS.
1.10.1 Training
Contractor online training is available at the following web site:
http://www.cpars.csd.disa.mil/allapps/cpartrng/onlinetrn.htm. Training will give the student an understanding of the Contractor Representative and Contractor Corporate Senior Management levels of access, the policies and regulations governing CPARS/ACASS/CCASS, and the electronic workflow with particular attention to the Contractor comment function.
1.11 PRECONSTRUCTION SURVEY
The Contractor shall create a video survey of existing site features and conditions to include but is not limited to asphalt pavement along access road, guardrail, fence, gates, posts, etcetera. The survey shall be created and a copy on CD-ROM or DVD shall be given to the Contracting Officer within 15 calendar days from NTP and prior to construction commencement.
W912EP-13-R-0001 SECTION 01 30 00 Page 7 Am0001
PART 2 PRODUCTS (NOT APPLICABLE)
PART 3 EXECUTION
3.1 GENERAL MEETING REQUIREMENTS
See Section 01 45 04 CONTRACTOR QUALITY CONTROL for Preparatory and Initial Phase meeting checklists. Contractor is responsible for phase and progress meetings to include:
Meeting notification to participants Prepare agenda for meetings Use phase checklists for Preparatory and Initial Phase meetings Physical arrangements for meetings Preside at meetings Record minutes recording proceedings and decisions Copy and send minutes to:
Meeting participants Project parties affected by decisions Contracting Officer (No later than 3 working days)
3.2 PROGRESS MEETING AGENDA
Modify agenda as needed for on-going work.
Review minutes from previous progress meetings Review work progress since previous meeting Review current definable features of work:
-- Identify phases of current features of work -- Identify pending phase changes -- Identify features for discussion in next scheduled meeting
Discuss problem prevention:
-- Field observations -- Deficiencies and tracking -- Procedures working well -- Problems, conflicts -- Methods to improve
Review construction schedule:
-- Identify delays -- Discuss proposed corrective actions to regain schedule
Submittals and Requests for Information (design interpretation):
-- Review submittal register -- Identify submittals to expedite as required
Review off-site activities:
-- Fabrications -- Material and equipment delivery schedule
Review Testing:
-- Type, Schedule -- Received Results
Review changes to construction schedule:
-- Planned progress during succeeding work period -- Coordination of various schedules -- Effect of changes on construction and completion date
Review site safety Discuss maintaining contract quality for materials and workmanship Discuss pending modifications, changes and substitutions Discuss other business, as appropriate
-- End of Section --