BRIP FRP Pre-Proposal Meeting Slides 10-29-2026.pdf

PDF 3 MB Posted

Attached to
Illinois River Basin, Brandon Road L and D, Joliet, Illinois, Flushing Lock and Dam Gates Fabrication
Solicitation number
W912EK27RA001
Issued by

About this file

This document is a pre-proposal meeting presentation for a U.S. Army Corps of Engineers (USACE) Fiber Reinforced Polymer (FRP) supply contract for the Brandon Road Interbasin Project (BRIP) located near Joliet, Illinois. The contract involves design, fabrication, and delivery of ten FRP composite structures including two 15x13.5 ft filling valves, two 15.5x15 ft filling valve bulkheads, two 9.5x7.5 ft flushing valves, two 7.5x7 ft flushing port bulkheads, and two 17x16 ft dam headgates. Delivery is scheduled in two phases: filling valves and bulkheads between May 1 and July 1, 2028, and remaining structures between May 1 and July 1, 2029, with liquidated damages of $9,700 per calendar day for late delivery. Delivery can be by barge or truck to Brandon Road Lock & Dam, with valves and bulkheads requiring final assembly in the shop and headgates permitting partial assembly with final assembly at a secondary location.

The solicitation uses a Low Price Technically Acceptable (LPTA) source selection process reserved for small businesses with 750 employees or fewer. Evaluation criteria include technical capability (requiring offerors to have fabricated at least three FRP structures exceeding 10,000 pounds using vacuum infusion process, with a Professional Engineer experienced in FRP design and a supervisor experienced in FRP fabrication), past performance, and price. Contractors must furnish a performance bond equal to 100 percent of the original contract price per FAR Clause 52.228-16. The solicitation (W912EK27RA001) will be posted on www.sam.gov with questions due via ProjNet no later than 2:00 p.m. Central Time on November 16, 2026, and offers due by 2:00 p.m. Central Time on November 30, 2026, submitted electronically through the Procurement Integrated Enterprise Environment (PIEE). Two separate contracts will be awarded: one for supply (valves and bulkheads fabrication and delivery only) and one for construction (Flushing Lock and Right Descending Bank including general FRP products fabrication, delivery, and installation).

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

BRANDON ROAD INTERBASIN

PROJECT (BRIP)

FRP PRE-PROPOSAL MEETING

Presenters:

Jeff Voss, Adam Helffrich, Eric Johnson Date: October 29, 2026

AGENDA

• Welcome and Administrative Items

• Introductions

• Project Overview

• Project Schedule

• Contract Overview

• Source Selection Overview

• Contracting Overview

• Closing Remarks

• Adjourn

• Attendance

• Jeff Voss, Contracting Officer for this meeting

• Adam Helffrich, PE, Structural Engineer

• Eric Johnson, PE, SE, CCT-VIP, USACE Composites Program Manager

• Samantha Johanson, Contracting Specialist for project

• Nick Moore, Contracting Officer for project

No official questions will be taken during the Pre-Proposal Meeting. We request all questions be submitted via ProjNet. Further information on how to submit questions will be provided at the end of the meeting.

Introductions

Big Picture of FRP Utilization Strategy in USACE

• Objective: HQ E&C and Operations leadership intent is to transition to the use of FRP for replacement, and/or new construction of hydraulic structures where appropriate and cost effective.

• Why? FRP does not corrode, has low life cycle costs, and increases supply chain.

• References:

• ECB 2024-08 Design of Fiber Reinforced Polymer Hydraulic

Composite Structures (https://www.wbdg.org/dod/ecb/usace-ecb-2024-8)

• USACE HQ Memorandum for Record (7/19/2024) Flap Gate (40-ft Head) (LRN Loyall, 2022)

PROJECT OVERVIEW

This Mega Project is a complex ecosystem protection effort designed to prevent upstream movement of invasive carp and other aquatic nuisance species into the Great Lakes from the Illinois Waterway.

The project, located near Joliet, Illinois, has been identified as the critical pinch point where layered technologies could be used to prevent movement of invasive carp populations into the Great Lakes.

Public website:

https://www.mvr.usace.army.mil/brip/

SITE OVERVIEW

Dam Head Gates

General Needs of Composites

• Head Gates x2

• Filling Valve x2

• Flushing Valve x2

• Filling Bulkhead x2

• Flushing Bulkhead x2

• Electric Influence Zone

• Bulkhead Slots and Fillers

• Electric Membrane

This Supply Contract

Delivery & Project Schedule

• Filling valves and filling valve bulkheads delivery:

between 1 May and 1 July of 2028

• Remaining structures delivery: between 1 May and 1 July of 2029.

• Liquidated damages: $9,700 per calendar day

Delivery

• Delivery can be by barge or by truck to Brandon Road Lock & Dam

• Valves and bulkheads must be final assembled in the shop

• Head gates can be shipped partially assembled with final assembly at a secondary location before delivery

This Contract Design, fabrication, and delivery of ten Fiber Reinforced Polymer (FRP) composite structures for Brandon Road Lock and Dam, Joliet, Illinois, Des Plaines River.

• (2) 15x13.5 ft filling valves

• (2) 15.5x15 ft filling valve bulkheads

• (2) 9.5x7.5 ft flushing valves

• (2) 7.5x7 ft flushing port bulkheads

• (2) 17 X 16 ft dam headgates

Filling Valves (Two)

• New valves to alter the flow in the lock

• Contractor designed item

• Filling Valve approx. 15.5’ x 13.5’ each

• Operated by hydraulic cylinder

• UHMW-PE slides (no metal rollers)

• Design must meet loading and deflection requirements

• Contractor design must conform to control dimensions

• Weight between 10,000 and 20,000 lbs

Filling Valve Bulkheads (Two)

• New Bulkheads to close off filling valves for maintenance

• Contractor designed item

• Each a horizontally framed panel

• Filling Bulkhead approx. 15.5’ x 15’ each

• UHMW-PE slides (no metal rollers)

• Design must meet loading and deflection requirements

• Max weight of 20,000 lbs

Flushing Valve (Two)

• New valves to alter the flow in the lock

• Contractor designed item

• Each a horizontally framed panel

• Flushing Valve approx. 9.5’x7.5’ each

• Operated by hydraulic cylinder

• UHMW-PE slides (no metal rollers)

• Design must meet loading and deflection requirements

• Contractor design must conform to control dimensions

• Weight between 5,000 and 8,000 lbs

Flushing Port Bulkhead (Two)

• New Bulkheads to close off flushing valves for maintenance

• Is a port plug instead of a slide gate

• Bolt holes to mechanically fasten it to the pocket

• Contractor designed item

• Each a horizontally framed panel

• Flushing Port Bulkhead approx. 7.5’x7’ each

• Design must meet loading and deflection requirements

• Contractor design must conform to control dimensions

Head Gates (Two)

• Two new FRP panel gates to replace aging steel gates

• Horizontally framed panel

• UHMW-PE Slides (no steel rollers)

• About 17’ x 16’ each

• Operated by hydraulic cylinder

• Design must meet loading and deflection requirements

• Weight between 15,000 and 30,000 lbs.

Source Selection Process:

Low Price Technically Acceptable

• Small business for this industry classification: 750 employees or less

• Evaluation Criteria

• Technical

• Past Performance

• Price

Evaluation Criteria – Technical

• Offeror has fabricated at least three (3) FRP structures weighing more than 10,000 pounds, using the vacuum infusion process

• Professional Engineer who has designed at least one FRP structure weighing more than 10,000 pounds

• One company employee who has supervised detailing, fabrication, and quality control activities for the fabrication of at least one FRP structure weighing more than 10,000 pounds.

Evaluation Criteria – Past Performance

Evaluation Criteria – Price

• Price will be evaluated and considered but not scored or combined with other aspects of the proposal evaluation. An award will be made to the lowest priced, technically acceptable proposal, based on values for the Base Bid.

Contract Bonding Requirements See Solicitation for FAR Clause 52.228-16

• Contractor to furnish a performance bond in an amount equal to

100 percent of the original contract price

Next Steps

• Inquiries and Questions are to be submitted via Bidder Inquiry in ProjNet

(https://www.projnet.org) NLT 2:00pm Central Time, 16 November 2026

• Instructions for ProjNet Bid Inquiry are provided in the Solicitation and Specs document, section MVR.02 available at:

https://sam.gov/workspace/contract/opp/ebdbd71a9257485098e812d4558 b481a/view

• Offers are due NLT 2:00pm Central Time, 30 November 2026 submitted electronically via Procurement Integrated Enterprise Environment (PIEE) Solicitation Module. See Section L of solicitation.

• Solicitation for the BRIP project will be posted on www.sam.gov under "W912EK27RA001"

• Can set up saved searches with keywords “FRP” and “US Army Corps of Engineers”

• Additional pre-contract opportunities for industry input & feedback will also be posted to sam.gov

• Sources Sought

• Industry Days

• Pre-Solicitation notice

• Solicitations

• Two Contracts:

• Supply Contract – Valves and Bulkheads fabrication and delivery only

• Construction Contract - Flushing Lock & Right Descending Bank including General FRP products fabrication, delivery, and installation.

Thank You for your attention!

If any issues with ProjNet Bidder Inquiry or Procurement Integrated Enterprise Environment (PIEE):

Primary POC is Samantha Johanson (samantha.k.johanson@usace.army.mil) Alternative POC is Nicholas Moore (nicholas.m.moore@usace.army.mil)

File details come from the government source that posted it. Updated .