This is a Standard Form 30 (SF 30) Amendment of Solicitation/Modification of Contract issued by the W07D Endist Rock Island, located at 1 Rock Island Arsenal, Rock Island, IL 61299-5001. The amendment number is 0001 with an effective date of 10 August 2026, issued by contracting officer Eric Gaul. The amendment modifies solicitation W912EK26QA047, originally dated 21 July 2026.

The primary purpose of this amendment is to provide an updated period of performance, request only certain colors of the playground, and specify plastic or metal only for the integrated shade roof(s). The delivery information for CLIN 0001 has been modified, changing from a delivery estimated by 01 November 2026 to a delivery period spanning 08 September 2026 through 30 November 2026. All other terms and conditions of the original solicitation remain unchanged and in full force and effect. Contractors must acknowledge receipt of this amendment prior to the hour and date specified in the original solicitation, using one of the three specified methods outlined in Item 11.

View the file

Other files

File Type Posted
Updated Statement of Work.pdf PDF
W912EK26QA047.pdf PDF
Statement of Work.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER.

If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

16C. DATE SIGNED

Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

Deliveries or Performance

The delivery information for the following CLIN(s) / SLIN(s) / ELIN(s) were modified:

INFORMATION FROM TO

Delivery Delivery Estimated By 01 Nov 2026. Delivery Period PeriodStart = 08

Sep 2026. PeriodEnd = 30 Nov 2026.

W912EK26QA0470001

IDCode: J
Page: 1
Pages: 2
AmendNo: 0001
EffDate: 10 AUG 2026
ReqNo:
ProjNo:
IssCode: W912EK
AdmCode:
IssuedBy: W07V ENDIST ROCK ISLAND

KO CONTRACTING DIVISION, 1 ROCK ISLAND ARSENAL

ROCK ISLAND, IL 61299-5001

UNITED STATES

ERIC GAUL, EMAIL: ERIC.J.GAUL@USACE.ARMY.MIL TELEPHONE: (309) 794-5093

AdminBy:

SCD: PAS:

ContractorNameAdd:
Code:
FacCode:
SolChg: 1
SolNo: W912EK26QA047
SolDate: 21 JUL 2026
AwardChg: Off
AwardNo:
AwardDate:
Amended: 1
OffrExt: 1
OffrNoEx: Off
NoCopies: 1
ApprData: SEE SECTION G - CONTRACT ADMINISTRATION DATA
ChgeOrd: Off
ChgeOrder:
Modify: Off
SuppAgre: Off
SuppAuth:
ModOthr: Off
OthrSpec:
NoReq: Off
Require: Off
Copies:
Descript: The purpose of this Amendment is to provide an updated period of performance, request only certain colors of the playground, and specify plastic or metal only to the integrated Shade Roof(s).

All other terms and conditions of this solicitation remain unchanged by this amendment.

ContNameTitle:
CoNameTitle: RYAN R. LARRISON
ContDate:
CODate: 10 AUG 2026