Abstract of Offers Summary

This is an Abstract of Offers document for solicitation W912EK26BA001 issued by the U.S. Army Corps of Engineers, Rock Island District for the Cedar Rapids FRM Project, Reach 4 Phase 1 Downs. The solicitation was issued on November 14, 2025, with bids opened on March 18, 2026. Five bidders submitted offers: Wendler, Inc. (Government Estimate); Ames Federal Contracting Group, LLC (Bidder #1); McMillen, Inc. (Bidder #2); General Constructors, Inc. of the Quad Cities (Bidder #3); Michels Construction, Inc. (Bidder #4); and an unnamed Bidder #5. All bidders acknowledged four amendments and provided bid security. The document reflects pricing for the base bid covering Volume 401 (Reach 4 Floodwall) and Volume 403 (Reach 4 Pump Station), plus Option A for combined floodwall and pump station work.

The base bid scope includes extensive civil works covering mobilization, demolition, temporary controls, structural concrete, metal sheet piling, excavation, fill materials, concrete paving, storm sewer installation, pump stations, electrical and mechanical systems, site restoration, and water main distribution. Bid prices vary significantly across contractors, with the Government Estimate totaling approximately $47.79 million, while bidder proposals range from $40.39 million (Bidder #4) to $76.50 million (Bidder #1). Key line items include Floodwall Construction (0132), Structural Excavations (0113), and Storm Water Pumps (0309), each representing multi-million-dollar components. Optional work includes Flood Barriers Installation and Flood Emergency Response operations, with pricing structured in tiered quantities for items such as metal sheet piling, riprap, and excavation.

View the file

Other files

Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

US ARMY CORPS OF ENGINEERS, ROCK ISLAND DISTRICT

Bid Opening Officer:

Abstract of Offers

Solicitation No: W912EK26BA001

Item # Description QTY UOM Unit Price Extended Amount Unit Price

Extended Amount Unit Price

Extended Amount Unit Price

Extended Amount Unit Price

Extended Amount Unit Price

Extended Amount

BASE BID: VOL 401 - Reach 4 Floodwall

0101 Mobilization and Demobilization 1 JOB XXXXXXXX $ 1,902,123.60 XXXXXXXX $ 3,000,000.00 XXXXXXXX $ 5,500,000.00 XXXXXXXX $ 5,600,000.00 XXXXXXXX $ 2,900,000.00 XXXXXXXX $ 3,000,000.00

0102 Temporary Construction Controls 1 JOB XXXXXXXX $ 2,415,146.62 XXXXXXXX $ 14,000,000.00 XXXXXXXX $ 6,900,000.00 XXXXXXXX $ 1,700,000.00 XXXXXXXX $ 4,400,000.00 XXXXXXXX $ 4,175,000.00

0103 Demolition and Deconstruction 1 JOB XXXXXXXX $ 2,501,965.24 XXXXXXXX $ 1,500,000.00 XXXXXXXX $ 2,225,000.00 XXXXXXXX $ 1,100,000.00 XXXXXXXX $ 1,300,000.00 XXXXXXXX $ 930,000.00

0104 Temporary Traffic Controls 1 JOB XXXXXXXX $ 79,473.66 XXXXXXXX $ 550,000.00 XXXXXXXX $ 625,000.00 XXXXXXXX $ 47,500.00 XXXXXXXX $ 100,000.00 XXXXXXXX $ 60,000.00

0105 Protection and Dewatering 1 JOB XXXXXXXX $ 278,273.42 XXXXXXXX $ 5,000,000.00 XXXXXXXX $ 5,260,000.00 XXXXXXXX $ 1,250,000.00 XXXXXXXX $ 3,000,000.00 XXXXXXXX $ 5,100,000.00

0106 Clearing, Grubbing, and Stripping 1 JOB XXXXXXXX $ 41,306.50 XXXXXXXX $ 1,050,000.00 XXXXXXXX $ 350,000.00 XXXXXXXX $ 60,000.00 XXXXXXXX $ 350,000.00 XXXXXXXX $ 100,000.00

0107 PCC Paving and Patching Work 1 JOB XXXXXXXX $ 1,001,520.97 XXXXXXXX $ 2,500,000.00 XXXXXXXX $ 1,350,000.00 XXXXXXXX $ 600,000.00 XXXXXXXX $ 1,250,000.00 XXXXXXXX $ 1,000,000.00

0108 CIP Structural Concrete - Gatewells 1 and 2 1 JOB XXXXXXXX $ 295,794.88 XXXXXXXX $ 1,250,000.00 XXXXXXXX $ 430,000.00 XXXXXXXX $ 450,000.00 XXXXXXXX $ 800,000.00 XXXXXXXX $ 330,000.00

0109 Precast Structural Concrete 1 JOB XXXXXXXX $ 8,318.50 XXXXXXXX $ 250,000.00 XXXXXXXX $ 120,000.00 XXXXXXXX $ 100,000.00 XXXXXXXX $ 200,000.00 XXXXXXXX $ 120,000.00

0110 Metal Fabrications - Grating, Handrailing, and Ladders 1 JOB XXXXXXXX $ 68,578.51 XXXXXXXX $ 100,000.00 XXXXXXXX $ 139,000.00 XXXXXXXX $ 90,000.00 XXXXXXXX $ 75,000.00 XXXXXXXX $ 90,000.00

0111 Metal Sheet Piling 0111AA First 100,000 Square Feet 100,000 SF $ 78.27 $ 7,827,000.00 $ 60.00 $ 6,000,000.00 $ 65.15 $ 6,515,000.00 $ 58.00 $ 5,800,000.00 $ 61.00 $ 6,100,000.00 $ 60.00 $ 6,000,000.00

0111AB Over 100,000 Square Feet 22,000 SF $ 78.27 $ 1,721,940.00 $ 60.00 $ 1,320,000.00 $ 42.00 $ 924,000.00 $ 52.00 $ 1,144,000.00 $ 48.00 $ 1,056,000.00 $ 60.00 $ 1,320,000.00

0112 Relief Wells 1 JOB XXXXXXXX $ 757,265.95 XXXXXXXX $ 1,200,000.00 XXXXXXXX $ 1,390,000.00 XXXXXXXX $ 1,015,000.00 XXXXXXXX $ 700,000.00 XXXXXXXX $ 1,000,000.00

0113 Structural Excavations 0113AA First 36,831 Cubic Yards 36,831 CY $ 114.95 $ 4,233,723.45 $ 69.00 $ 2,541,339.00 $ 38.00 $ 1,399,578.00 $ 21.00 $ 773,451.00 $ 70.00 $ 2,578,170.00 $ 18.00 $ 662,958.00

0113AB Over 36,831 Cubic Yards 6,500 CY $ 114.95 $ 747,175.00 $ 69.00 $ 448,500.00 $ 24.00 $ 156,000.00 $ 20.00 $ 130,000.00 $ 70.00 $ 455,000.00 $ 18.00 $ 117,000.00

0114 Embankment/Impervious Fill 0114AA First 22,895 Cubic Yards 22,895 CY $ 39.86 $ 912,594.70 $ 88.00 $ 2,014,760.00 $ 51.00 $ 1,167,645.00 $ 32.00 $ 732,640.00 $ 85.00 $ 1,946,075.00 $ 24.00 $ 549,480.00

0114AB Over 22,895 Cubic Yards 4,040 CY $ 40.40 $ 163,216.00 $ 88.00 $ 355,520.00 $ 51.00 $ 206,040.00 $ 30.00 $ 121,200.00 $ 85.00 $ 343,400.00 $ 24.00 $ 96,960.00

0115 Cleanouts 1 JOB XXXXXXXX $ 70,332.96 XXXXXXXX $ 42,300.00 XXXXXXXX $ 40,000.00 XXXXXXXX $ 20,000.00 XXXXXXXX $ 245,000.00 XXXXXXXX $ 30,000.00

0116 Manholes - Precast 9 Foot 1 EA $ 40,453.03 $ 40,453.03 $ 49,200.00 $ 49,200.00 $ 50,000.00 $ 50,000.00 $ 37,000.00 $ 37,000.00 $ 18,000.00 $ 18,000.00 $ 35,000.00 $ 35,000.00

0117 Manholes - Precast 6 Foot 7 EA $ 18,383.57 $ 128,684.99 $ 18,200.00 $ 127,400.00 $ 23,000.00 $ 161,000.00 $ 11,000.00 $ 77,000.00 $ 16,000.00 $ 112,000.00 $ 14,000.00 $ 98,000.00

0118 Manholes - Precast 5 Foot 4 EA $ 13,802.63 $ 55,210.52 $ 15,600.00 $ 62,400.00 $ 27,000.00 $ 108,000.00 $ 8,000.00 $ 32,000.00 $ 16,000.00 $ 64,000.00 $ 12,000.00 $ 48,000.00

0119 Manholes - Precast 4 Foot 5 EA $ 7,336.85 $ 36,684.25 $ 12,500.00 $ 62,500.00 $ 20,000.00 $ 100,000.00 $ 6,000.00 $ 30,000.00 $ 9,000.00 $ 45,000.00 $ 7,000.00 $ 35,000.00

0120 Manholes - Precast 2 Foot 1 EA $ 7,680.52 $ 7,680.52 $ 12,500.00 $ 12,500.00 $ 22,000.00 $ 22,000.00 $ 2,000.00 $ 2,000.00 $ 9,000.00 $ 9,000.00 $ 3,000.00 $ 3,000.00

0121 End Sections 2 EA $ 2,966.54 $ 5,933.08 $ 6,000.00 $ 12,000.00 $ 11,000.00 $ 22,000.00 $ 3,000.00 $ 6,000.00 $ 7,000.00 $ 14,000.00 $ 4,000.00 $ 8,000.00

0122 RCP Storm Sewer - 42-Inch 687 LF $ 598.11 $ 410,901.57 $ 410.00 $ 281,670.00 $ 575.00 $ 395,025.00 $ 205.00 $ 140,835.00 $ 230.00 $ 158,010.00 $ 300.00 $ 206,100.00

0123 RCP Storm Sewer - 36-Inch 505 LF $ 446.34 $ 225,401.70 $ 360.00 $ 181,800.00 $ 465.00 $ 234,825.00 $ 175.00 $ 88,375.00 $ 215.00 $ 108,575.00 $ 275.00 $ 138,875.00

0124 RCP Storm Sewer - 24-Inch 159 LF $ 253.03 $ 40,231.77 $ 300.00 $ 47,700.00 $ 355.00 $ 56,445.00 $ 115.00 $ 18,285.00 $ 145.00 $ 23,055.00 $ 220.00 $ 34,980.00

0125 RCP Storm Sewer - 18-Inch 32 LF $ 505.58 $ 16,178.56 $ 290.00 $ 9,280.00 $ 845.00 $ 27,040.00 $ 105.00 $ 3,360.00 $ 240.00 $ 7,680.00 $ 215.00 $ 6,880.00

0126 RCP Storm Sewer - 15-Inch 173 LF $ 109.90 $ 19,012.70 $ 270.00 $ 46,710.00 $ 400.00 $ 69,200.00 $ 92.00 $ 15,916.00 $ 125.00 $ 21,625.00 $ 160.00 $ 27,680.00

0127 Non-contact Cooling Sewer - 21- Inch 58 LF $ 233.06 $ 13,517.48 $ 800.00 $ 46,400.00 $ 530.00 $ 30,740.00 $ 125.00 $ 7,250.00 $ 265.00 $ 15,370.00 $ 300.00 $ 17,400.00

0128 Non-contact Cooling Sewer - 18- Inch 32 LF $ 327.56 $ 10,481.92 $ 750.00 $ 24,000.00 $ 735.00 $ 23,520.00 $ 98.00 $ 3,136.00 $ 400.00 $ 12,800.00 $ 350.00 $ 11,200.00

0129 Slide Gate - 24-Inch 4 EA $ 44,976.62 $ 179,906.48 $ 12,600.00 $ 50,400.00 $ 32,800.00 $ 131,200.00 $ 35,000.00 $ 140,000.00 $ 17,500.00 $ 70,000.00 $ 16,000.00 $ 64,000.00

0130 Trench/Toe Drain 1 JOB XXXXXXXX $ 392,722.81 XXXXXXXX $ 400,000.00 XXXXXXXX $ 173,000.00 XXXXXXXX $ 85,000.00 XXXXXXXX $ 750,000.00 XXXXXXXX $ 400,000.00 y Bid Security y y y y y Amendments Acknowledged: 4.00 y y y y

5AP96

Date Opened: 18 March 2026 WCK5W6RK82X1 C3JZNM5ZLAL1 C9JGVNMG4ND3 CDE7H8M86MB5 UKJDFB78JBL4 Date Issued: 14 November 2025 9BA09 41PM4 00XT6 9C1R4

Wendler, Inc.

415 12th Ave SE

Suite 200 Cedar Rapids, IA 52401

Government Estimate Bidder #1 Bidder #2 Bidder #3

Ames Federal Contracting Group, LLC

2500 County Road 42 W Burnsville, MN 55337

McMillen, Inc.

1471 Shoreline Dr.

Suite 100 Boise, ID 83702

General Constructors, Inc. of the Quad Cities

480 42nd St Bettendorf, IA 52722

Michels Construction, Inc.

817 Main Street

Brownsville, WI 53006

Project Title: Cedar Rapids FRM Project, Reach 4 Phase 1 Downs

I certify that I have opened, read, and recorded on this abstract all offers received in response to this soliciation.

Bidder #4 Bidder #5

0131 Geotechnical Instrumentation 1 JOB XXXXXXXX $ 123,242.44 XXXXXXXX $ 200,000.00 XXXXXXXX $ 188,000.00 XXXXXXXX $ 95,000.00 XXXXXXXX $ 300,000.00 XXXXXXXX $ 100,000.00

0132 Flood Wall Construction 1 JOB XXXXXXXX $ 9,465,583.53 XXXXXXXX $ 15,000,000.00 XXXXXXXX $ 16,465,000.00 XXXXXXXX $ 7,400,000.00 XXXXXXXX $ 13,200,000.00 XXXXXXXX $ 10,500,000.00

0133 Chain Link Fencing 245 LF $ 40.24 $ 9,858.80 $ 400.00 $ 98,000.00 $ 125.00 $ 30,625.00 $ 59.00 $ 14,455.00 $ 150.00 $ 36,750.00 $ 70.00 $ 17,150.00

0134 Concrete Curb and Gutter 243 LF $ 59.85 $ 14,543.55 $ 80.00 $ 19,440.00 $ 65.00 $ 15,795.00 $ 90.00 $ 21,870.00 $ 125.00 $ 30,375.00 $ 100.00 $ 24,300.00

0135 Bollards 8 EA $ 1,214.92 $ 9,719.36 $ 5,000.00 $ 40,000.00 $ 3,300.00 $ 26,400.00 $ 4,000.00 $ 32,000.00 $ 3,500.00 $ 28,000.00 $ 3,200.00 $ 25,600.00

0136 Access Gates 2 EA $ 7,920.95 $ 15,841.90 $ 24,600.00 $ 49,200.00 $ 4,700.00 $ 9,400.00 $ 2,120.00 $ 4,240.00 $ 11,000.00 $ 22,000.00 $ 6,000.00 $ 12,000.00

0137 Cast-in-Place Retaining Walls 1 JOB XXXXXXXX $ 683,391.01 XXXXXXXX $ 500,000.00 XXXXXXXX $ 127,000.00 XXXXXXXX $ 77,000.00 XXXXXXXX $ 1,400,000.00 XXXXXXXX $ 300,000.00

0138 Geotextile 3,644 SF $ 0.79 $ 2,878.76 $ 1.00 $ 3,644.00 $ 3.50 $ 12,754.00 $ 0.50 $ 1,822.00 $ 12.00 $ 43,728.00 $ 0.50 $ 1,822.00

0139 Surface Aggregate - IADOT #11 1,740 SF $ 48.33 $ 84,094.20 $ 6.60 $ 11,484.00 $ 9.00 $ 15,660.00 $ 2.00 $ 3,480.00 $ 250.00 $ 435,000.00 $ 1.50 $ 2,610.00

0139AA (Not Used) 0139AB (Not Used) 0140 (Not Used) 0140AA (Not Used) 0140AB (Not Used) 0141 Aggregate - IADOT #35 0141AA First 1,645 Tons 1,645 TN $ 80.38 $ 132,225.10 $ 41.00 $ 67,445.00 $ 45.00 $ 74,025.00 $ 50.00 $ 82,250.00 $ 100.00 $ 164,500.00 $ 25.00 $ 41,125.00

0141AB Over 1,645 Tons 288 TN $ 80.38 $ 23,149.44 $ 41.00 $ 11,808.00 $ 45.00 $ 12,960.00 $ 44.00 $ 12,672.00 $ 100.00 $ 28,800.00 $ 25.00 $ 7,200.00

0142 Bedding Stone 0142AA First 889 Tons 889 TN $ 68.72 $ 61,092.08 $ 69.00 $ 61,341.00 $ 48.00 $ 42,672.00 $ 49.00 $ 43,561.00 $ 80.00 $ 71,120.00 $ 43.00 $ 38,227.00

0142AB Over 889 Tons 297 TN $ 77.68 $ 23,070.96 $ 69.00 $ 20,493.00 $ 48.00 $ 14,256.00 $ 49.00 $ 14,553.00 $ 80.00 $ 23,760.00 $ 43.00 $ 12,771.00

0143 Riprap Class C 0143AA First 10,293 Tons 10,293 TN $ 109.19 $ 1,123,892.67 $ 110.00 $ 1,132,230.00 $ 53.00 $ 545,529.00 $ 59.00 $ 607,287.00 $ 100.00 $ 1,029,300.00 $ 67.00 $ 689,631.00

0143AB Over 10,293 Tons 3,431 TN $ 108.81 $ 373,327.11 $ 110.00 $ 377,410.00 $ 53.00 $ 181,843.00 $ 61.00 $ 209,291.00 $ 100.00 $ 343,100.00 $ 67.00 $ 229,877.00

0144 Topsoil 408 CY $ 58.27 $ 23,774.16 $ 150.00 $ 61,200.00 $ 31.00 $ 12,648.00 $ 74.00 $ 30,192.00 $ 100.00 $ 40,800.00 $ 45.00 $ 18,360.00

0145 Electrical and Communication Distribution Work 1 JOB XXXXXXXX $ 386,905.07 XXXXXXXX $ 500,000.00 XXXXXXXX $ 1,600,000.00 XXXXXXXX $ 1,680,810.00 XXXXXXXX $ 1,100,000.00 XXXXXXXX $ 1,000,000.00

0146 Mechanical Piping and Valves 1 JOB XXXXXXXX $ 156,329.96 XXXXXXXX $ 200,000.00 XXXXXXXX $ 145,000.00 XXXXXXXX $ 158,000.00 XXXXXXXX $ 185,000.00 XXXXXXXX $ 105,000.00

0147 Seeding and Site Restoration 1 JOB XXXXXXXX $ 19,107.83 XXXXXXXX $ 20,000.00 XXXXXXXX $ 170,000.00 XXXXXXXX $ 55,000.00 XXXXXXXX $ 80,000.00 XXXXXXXX $ 6,000.00

0148 Water Main Distribution - Upstream 1 JOB XXXXXXXX $ 657,799.23 XXXXXXXX $ 2,000,000.00 XXXXXXXX $ 2,090,000.00 XXXXXXXX $ 1,100,000.00 XXXXXXXX $ 1,100,000.00 XXXXXXXX $ 1,400,000.00

0149 Water Main Extended Performance Bond 1 JOB XXXXXXXX $ 59,904.08 XXXXXXXX $ 3,000.00 XXXXXXXX $ 15,000.00 XXXXXXXX $ 5,000.00 XXXXXXXX $ 1,000.00 XXXXXXXX $ 5,500.00

0150 PCC Trail and Pads 44,540 SF $ 17.48 $ 778,559.20 $ 35.00 $ 1,558,900.00 $ 16.00 $ 712,640.00 $ 5.00 $ 222,700.00 $ 16.50 $ 734,910.00 $ 15.00 $ 668,100.00

0151 (Not Used) 0152 Trail Safety Rail 2,500 LF $ 212.26 $ 530,650.00 $ 375.00 $ 937,500.00 $ 250.00 $ 625,000.00 $ 385.00 $ 962,500.00 $ 380.00 $ 950,000.00 $ 200.00 $ 500,000.00

0153 Trail Retaining and Parapet Walls 744 LF $ 915.42 $ 681,072.48 $ 900.00 $ 669,600.00 $ 1,000.00 $ 744,000.00 $ 950.00 $ 706,800.00 $ 700.00 $ 520,800.00 $ 1,750.00 $ 1,302,000.00

BASE BID: VOL 403 - Reach 4 Pump Station

0301 (Not Used) 0302 CIP Structural Concrete 1 JOB XXXXXXXX $ 1,377,935.83 XXXXXXXX $ 3,500,000.00 XXXXXXXX $ 3,500,000.00 XXXXXXXX $ 1,700,000.00 XXXXXXXX $ 3,000,000.00 XXXXXXXX $ 1,500,000.00

0303 Precast Structural Concrete 1 JOB XXXXXXXX $ 3,423.28 XXXXXXXX $ 9,400.00 XXXXXXXX $ 4,500.00 XXXXXXXX $ 3,300.00 XXXXXXXX $ 20,000.00 XXXXXXXX $ 5,000.00

0304 Infill Concrete 1 JOB XXXXXXXX $ 22,836.07 XXXXXXXX $ 50,000.00 XXXXXXXX $ 130,000.00 XXXXXXXX $ 22,000.00 XXXXXXXX $ 100,000.00 XXXXXXXX $ 30,000.00

0305 Structural Metal Fabrications 1 JOB XXXXXXXX $ 8,131.53 XXXXXXXX $ 1,600.00 XXXXXXXX $ 37,000.00 XXXXXXXX $ 8,500.00 XXXXXXXX $ 100,000.00 XXXXXXXX $ 60,000.00

0306 Metal Fabrications 1 JOB XXXXXXXX $ 139,280.82 XXXXXXXX $ 200,000.00 XXXXXXXX $ 440,000.00 XXXXXXXX $ 340,000.00 XXXXXXXX $ 350,000.00 XXXXXXXX $ 350,000.00

0307 Metal Sheet Piling 2,275 SF $ 78.27 $ 178,064.25 $ 80.00 $ 182,000.00 $ 94.00 $ 213,850.00 $ 90.00 $ 204,750.00 $ 60.00 $ 136,500.00 $ 60.00 $ 136,500.00

0308 Steel H-Piles 3,075 LF $ 153.39 $ 471,674.25 $ 100.00 $ 307,500.00 $ 250.00 $ 768,750.00 $ 100.00 $ 307,500.00 $ 120.00 $ 369,000.00 $ 115.00 $ 353,625.00

0309 Storm Water Pumps 3 EA $ 329,750.54 $ 989,251.62 $ 200,000.00 $ 600,000.00 $ 150,000.00 $ 450,000.00 $ 300,000.00 $ 900,000.00 $ 200,000.00 $ 600,000.00 $ 150,000.00 $ 450,000.00

0310 Structural Excavation 3,723 CY $ 45.73 $ 170,252.79 $ 69.00 $ 256,887.00 $ 72.00 $ 268,056.00 $ 19.00 $ 70,737.00 $ 60.00 $ 223,380.00 $ 26.00 $ 96,798.00

0311 General Fill 1,983 CY $ 26.65 $ 52,846.95 $ 88.00 $ 174,504.00 $ 118.00 $ 233,994.00 $ 32.00 $ 63,456.00 $ 85.00 $ 168,555.00 $ 17.00 $ 33,711.00

0312 Structural Backfill 335 CY $ 71.81 $ 24,056.35 $ 88.00 $ 29,480.00 $ 130.00 $ 43,550.00 $ 55.00 $ 18,425.00 $ 135.00 $ 45,225.00 $ 125.00 $ 41,875.00

0313 (Not Used) 0314 RCP Storm Sewer - 60-Inch 15 LF $ 1,400.74 $ 21,011.10 $ 1,400.00 $ 21,000.00 $ 1,600.00 $ 24,000.00 $ 850.00 $ 12,750.00 $ 1,000.00 $ 15,000.00 $ 624.00 $ 9,360.00

0315 Slide Gate - 72x72 Inch 2 EA $ 80,555.05 $ 161,110.10 $ 200,000.00 $ 400,000.00 $ 86,500.00 $ 173,000.00 $ 90,000.00 $ 180,000.00 $ 40,000.00 $ 80,000.00 $ 120,000.00 $ 240,000.00

0316 Slide Gate - 72x54 Inch 1 EA $ 69,982.55 $ 69,982.55 $ 175,000.00 $ 175,000.00 $ 70,500.00 $ 70,500.00 $ 69,000.00 $ 69,000.00 $ 40,000.00 $ 40,000.00 $ 50,000.00 $ 50,000.00

0317 Bar Screen 1 JOB XXXXXXXX $ 414,461.19 XXXXXXXX $ 250,000.00 XXXXXXXX $ 252,000.00 XXXXXXXX $ 290,000.00 XXXXXXXX $ 350,000.00 XXXXXXXX $ 250,000.00

0318 Bedding Stone 0318AA First 325 Tons 325 TN $ 76.55 $ 24,878.75 $ 69.00 $ 22,425.00 $ 91.00 $ 29,575.00 $ 42.00 $ 13,650.00 $ 100.00 $ 32,500.00 $ 43.00 $ 13,975.00

0318AB Over 325 Tons 32 TN $ 64.05 $ 2,049.60 $ 69.00 $ 2,208.00 $ 91.00 $ 2,912.00 $ 43.00 $ 1,376.00 $ 100.00 $ 3,200.00 $ 43.00 $ 1,376.00

0319 Riprap Class C

0319AA First 556 Tons 556 TN $ 116.04 $ 64,518.24 $ 110.00 $ 61,160.00 $ 105.00 $ 58,380.00 $ 66.00 $ 36,696.00 $ 200.00 $ 111,200.00 $ 67.00 $ 37,252.00

0319AB Over 556 Tons 55 TN $ 108.19 $ 5,950.45 $ 110.00 $ 6,050.00 $ 105.00 $ 5,775.00 $ 75.00 $ 4,125.00 $ 200.00 $ 11,000.00 $ 67.00 $ 3,685.00

0320 Utilities - Electrical 1 JOB XXXXXXXX $ 818,196.34 XXXXXXXX $ 1,000,000.00 XXXXXXXX $ 545,000.00 XXXXXXXX $ 545,400.00 XXXXXXXX $ 750,000.00 XXXXXXXX $ 500,000.00 OPTION A: VOL 401 and VOL 403

- Reach 4 Floodwall and Pump Station

0401 Flood Barriers Installation 0401AA First 5,000 Linear Feet 5,000 LF $ 51.34 $ 256,700.00 $ 60.00 $ 300,000.00 $ 110.00 $ 550,000.00 $ 46.00 $ 230,000.00 $ 450.00 $ 2,250,000.00 $ 50.00 $ 250,000.00

0401AB Over 5,000 Linear Feet 1,250 LF $ 35.22 $ 44,025.00 $ 60.00 $ 75,000.00 $ 110.00 $ 137,500.00 $ 44.00 $ 55,000.00 $ 450.00 $ 562,500.00 $ 50.00 $ 62,500.00

0402 Flood Emergency Response Operation

0402AA First 450 Hours 450 HR $ 319.05 $ 143,572.50 $ 1,250.00 $ 562,500.00 $ 805.00 $ 362,250.00 $ 90.00 $ 40,500.00 $ 1,200.00 $ 540,000.00 $ 250.00 $ 112,500.00

0402AB Over 450 Hours 150 HR $ 319.05 $ 47,857.50 $ 1,250.00 $ 187,500.00 $ 805.00 $ 120,750.00 $ 90.00 $ 13,500.00 $ 1,200.00 $ 180,000.00 $ 250.00 $ 37,500.00

0403 Flood Emergency Pump Supply 0403AA First 15 Days 15 DA $ 7,749.64 $ 116,244.60 $ 1,400.00 $ 21,000.00 $ 3,500.00 $ 52,500.00 $ 10,000.00 $ 150,000.00 $ 30,000.00 $ 450,000.00 $ 1,600.00 $ 24,000.00

0403AB Over 15 Days 15 DA $ 7,749.64 $ 116,244.60 $ 1,400.00 $ 21,000.00 $ 2,000.00 $ 30,000.00 $ 10,000.00 $ 150,000.00 $ 30,000.00 $ 450,000.00 $ 1,600.00 $ 24,000.00

Total 47,793,751.15$ 76,495,288.00$ 68,681,307.00$ 40,391,096.00$ 62,034,763.00$ 47,496,443.00$

Sheet1

2026-03-19T11:37:49-0500