W912EK25BA009 - Statement of Work.pdf
PDF 10 MB Posted
- Solicitation number
- W912EK25BA009
About this file
This Statement of Work (SOW) details a roof replacement and masonry restoration project for the U.S. Army Corps of Engineers at Lock 19 in Keokuk, Iowa. The base bid includes work on the Upper Land Wall Switch Board and Upper River Wall Switch Board Buildings, with the adjacent Scooter Shed, and an optional additional scope for the Office Building. The project requires replacing existing ballasted roofs with EPDM roofing, including new gutters, scuppers, downspouts, and splash blocks. Masonry restoration involves replacing exterior brick masonry parapets, spalled bricks, and stone coping, with all work to conform to the Secretary of Interior Standards for Rehabilitation of Historic Structures.
The project scope encompasses comprehensive roof and masonry repairs across three buildings, with specific technical requirements including: installing 2 layers of 2" polyisocyanurate foam board insulation (R-30 value), a 90-mil EPDM membrane, new copper gutters and accessories, and detailed masonry restoration. The base bid contract work shall be completed within 90 calendar days from Notice to Proceed, with a potential 30-day extension if Option A (Office Building) is awarded. The contractor must provide experienced personnel, submit detailed quality control plans, and follow strict preservation guidelines to maintain the historical integrity of the structures.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
Lock 19 Roof Replacement and Masonry
Repair 525 N Water Street
Keokuk IA 52632
SECTION 1 PROJECT DESCRIPTION
1.1 Summary of Work
1.2 The U.S. Army Corps of Engineers requires the services of a Contractor to provide roofing maintenance and exterior masonry restoration at (3) buildings at Lock 19. The
Contractor shall perform all necessary services, to include furnishing all material, equipment, and labor to maintain and restore the roofing systems and exterior masonry, as shown in the attached drawings and described herein. The base bid includes work at the Upper Land Wall Switch Board and Upper River Wall Switch Board
Buildings. The scope of work for the Upper River Wall Switch Board Building shall also include the adjacent Scooter Shed, which is structurally connected to this building. The Office Building is included as an Option. Project Narrative
The Upper Land Wall Switch Board and Upper River Wall Switch Board Buildings
(Base Bid) and the Office Building (Option A) have existing ballasted roof which shall be replaced with EPDM roofing. The scope of services also includes replacement of existing gutters, scuppers, downspouts and splash blocks on these buildings. Masonry restoration services include replacing exterior brick masonry parapets, spalled bricks and stone coping cap as shown on attached drawings.
Gutters, downspouts and masonry restoration shall match existing building elements in color, texture and profile, this work shall conform with the Secretary of Interior
Standard for Rehabilitation for Historic Structures. Visit The Secretary of the
Interior's Standards for the Treatment of Historic Properties - Technical
Preservation Services (U.S. National Park Service) for more information. These services are required to restore the watertight integrity of the building envelopes.
1.3 Objectives
The Contractor shall perform all tasks defined within this Performance Work
Statement and provide all deliverables listed in the scope of work, drawings and specification product requirement.
1.4 Bid Schedule: See SF1442.
NOTE: SQUARE FOOT MASONRY COST SHALL INCLUDE ALL WYTHES OF BRICK.
1.5 Existing Reference Drawings- Appendix B
1.6 Asbestos Test Results- Appendix C.
SECTION 2 GENERAL REQUIREMENTS
2.1 Period of Performance
The base bid contract work shall be completed within ninety (90) calendar days from Notice to Proceed (NTP) with a 30-day time extension should Option A be awarded.
2.1.2 Hours of Operation
The locks are open 24/7.
Work schedule shall be coordinated with the Contracting Officer (KO) or the
Contracting Officer’s Representative (COR) in writing prior to commencement.
2.1.3 Federal Holidays
The U.S Army Corps of Engineers offices are closed for the observance of Federal
Holidays listed below. These are non-workdays.
New Year’s Day Labor Day
Martin Luther King’s Day Columbus Day
President’s Day Veterans Day
Memorial Day Thanksgiving Day
Juneteenth National Holiday Christmas Day
Independence Day
This includes any other day designated by Federal statute, by Executive Order or by the President’s proclamation. When a holiday falls on a non-workday, Saturday or
Sunday, the holiday is typically observed on Monday (if the holiday falls on
Sunday) or Friday (if the holiday falls on Saturday).
2.2 Submittals
The Contractor is required to submit all documents related to the execution of this contract to the KO in accordance with the submittal requirements outlined in section
3.1 Required Submittals, of PART 3 SPECIAL REQUIREMENTS.
2.2.1 Work Submittals
Documentation required to be submitted to the KO and approved (if required), at any phase of work during which they are completed and ready for review and acceptance.
2.3 Contractor Business Relations
The Contractor shall successfully integrate and coordinate all activity needed to execute the requirement. The Contractor shall manage the timeliness, completeness, and quality of problem identification. The Contractor shall provide corrective action plans, proposal submittals, timely identification of issues, and effective management of subcontractors. The Contractor shall seek to ensure customer satisfaction and professional and ethical behavior of all Contractor personnel.
2.4 Contractor Administration and Management
The Contractor shall designate one employee to act as the Project Manager. The
Contractor shall submit in writing, the name, and title, office, and mobile telephone number of the Project Manager. The Contractor shall establish clear organizational lines of authority and responsibility to ensure effective management of the resources assigned to the requirement. The Contractor must maintain continuity between the support operations at the job site and the Contractor's corporate offices. This individual shall have full authority to act for the Contractor on all contract matters relating to the daily operation of this Contract. This Designation of Project Manager shall be submitted within three calendar days of contract award to the Contracting
Officer.
The Contractor shall establish processes and assign appropriate resources to effectively administer the requirement. The Contractor shall respond to
Government requests for contractual actions in a timely fashion. The Contractor shall have a single point of contact between the Government and Contractor personnel assigned to support contracts or task orders. The Contractor shall assign work effort and maintaining proper and accurate time keeping records of personnel assigned to work on the requirement.
2.5 Subcontract Management
The Contractor shall be responsible for any subcontract management necessary to integrate work performed on this requirement and shall be responsible and accountable for subcontractor performance on this requirement. The prime contractor will manage work distribution to ensure there are no Organizational
Conflict of Interest (OCI) considerations. Contractors may add subcontractors to their team after notification to the KO or Contracting Officer Representative (COR).
2.6 Contractor Personnel
The Contractor shall accomplish the assigned work by employing and utilizing qualified personnel with appropriate combinations of education, training, and experience. The Contractor shall be required to provide personnel with that meet or exceed a combination of qualifications and experience. Personnel requirements can be found in 3.2 PERSONNEL QUALIFICATIONS, of PART 3 SPECIAL
REQUIREMENTS. The Contractor shall match personnel skills to the work or task with a minimum of under/over employment of resources.
2.7 Contractor Schedule of Services
The Contractor shall perform tasks according to a detailed written performance schedule and plan which is to be prepared by the Contractor, submitted, and accepted by the COR three (3) calendar days prior to commencement of work. The schedule shall include the date the work is to be initiated and completed as well as the amount of work projected to be completed daily. The schedule shall identify the hours when the Contractor will perform the work. Any modification to the Contractor’s Schedule of Services must be submitted in writing to the KO or COR, for review and approval prior to incorporating any proposed changes.
2.8 Quality Control
The Contractor shall develop and maintain an effective quality control program to ensure services are performed in accordance with this PWS. The Contractor shall develop and implement procedures to identify, prevent, and ensure non-recurrence of defective services. The Contractor’s quality control program is how he assures himself that his work complies with the requirement of the contract.
2.9 Quality Assurance
The Government shall evaluate the Contractor’s performance under this contract in accordance with the Performance Requirement Summary (PRS). Additionally, the
Government will use a Quality Assurance Surveillance Plan (QASP), in the inspection of the services. This plan is primarily focused on what the Government must do to ensure that the Contractor has performed in accordance with the performance standards. It defines how the performance standards will be applied, the frequency of surveillance, and the minimum acceptable defect rate(s).
2.9.1 Quality Assurance Surveillance Plan
The Government shall monitor the Contractor's performance under this contract in accordance with the Government's QASP. The QASP for work defined herein is in
Appendix A of this contract.
2.9.2 Government Inspection
All work to be performed under this contract shall conform to the requirements of this contract and shall be approved by the KO. The presence or absence of
Government personnel shall not relieve the Contractor of responsibility for the proper execution of the work in accordance with this contract.
SECTION 3 SPECIAL REQUIREMENTS
3.1 Required Submittals
The approving authority for submittals and deliverables rests with the KO and his/her
Authorized Representative(s). Ensure all submittals and deliverables follow the contract requirements. All schedules, plans and product data submittals required herein must be approved by the KO prior to the start of mobilization on site. Samples must be approved by the KO prior to continuation of work.
3.1.1 Preconstruction Submittals
a. Schedule
b. Quality Control Plan
c. Qualifications
3.1.2 Product Data
a. Roofing membrane
b. Insulation
c. Sealant
d. Flashing
e. Gutter and Downspout
f. Brick
g. Mortar
h. Prefinished Stone Cap
3.1.3 Samples
a. Brick and Mortar Mock-up
b. Brick Masonry
c. Prefinished Stone Cap
3.1.4 Shop Drawings
a. Prefinished Stone Cap
b. Gutter and Downspout
c. Roofing
3.1.5 Warranty
a. Roofing and Masonry Repair Work- Contractor’s Warranty
b. Manufacturer’s Standard Warranty and as listed in SOW 4.2 and 4.4
c. As- Built Drawings- paper and electronic formats.
3.2 Quality Control Plan
Prior to beginning the roofing maintenance, restoration and cleaning work, submit a written
Quality Control Plan. Do not proceed without written approval of the plan. At a minimum, include the following items in the Quality Control Plan:
a. Describe the methods of protecting surrounding masonry, windows, doors, and other building features as well as surrounding landscape, mechanical equipment, louvers, vents, intakes, vehicles, and other property and sensitive equipment during masonry restoration.
b. Describe the work procedures, materials, and tools proposed to use for re-pointing, brick replacement, sealant replacement, and application of water repellent.
c. Describe the method and approach to cleaning mortar coating smears from the masonry surfaces.
d. Describe the method and approach to demolition of roof & protecting existing construction before installation of new roof.
3.3 Personnel Qualifications
Employ only competent and satisfactory personnel and provide a sufficient number of employees to perform the required services efficiently. Comply with local, state, and federal codes and regulations.
3.3.1 Masons and Roofers
Masons and roofers must have a minimum of five years’ experience on work similar in material, design, and extent to that indicated and shall demonstrate a record of successful in-service performance.
3.3.2 Field Supervision
Retain an experienced supervisor on the project site responsible for supervising the masonry restoration work throughout the duration of the project.
Submit a resume for the field supervisor which demonstrates qualifications and successful similar past projects.
3.4 Open Flame
No Open Flame Permitted.
3.5 Government Furnished Materials
Hot and cold water and electricity will be provided from existing outlets.
3.6 Clean-up and Disposal Requirements
Provide all containers and hauling required for trash disposal and material recycling.
Government containers and equipment shall not be used. Coordinate locations for dumpsters with the KO. Clean up work areas and dispose of trash at the end of each workday. At completion of all work, remove all remaining material and equipment.
3.7 Access, Work Limits, and Staging
Coordinate project access, work area limits, the location of the staging area, pedestrian and vehicle detours, closures to building doors, on site water and power supply, and other site logistical issues with the Contracting Officer prior to project construction.
3.8 Utilities
Coordinate with the Contracting Officer for the location of existing utilities prior to the start of project construction.
3.9 Environmental Protection
In addition to requirements specified elsewhere for environmental protection, provide coating materials that conform to the restrictions of the local Air Pollution
Control District and regional jurisdiction. Notify Contracting Officer of any paint specified herein which fails to conform.
SECTION 4 PERFORMANCE REQUIREMENTS
4.1 LOCATION
The repair work area is at three (3) structures: Upper River Wall Switch Board Building, Upper Land Wall Switch Board Building (Base Bid); and Office Building (option A) on
Lock 19. Address is 525 N Water Street, Keokuk IA- 52632.
4.2 PERFORMANCE REQUIREMENTS SUMMARY (PRS)
The Contractor will perform the following services for roof maintenance and masonry restoration. See also the drawings for locations and approximate sizes. All work must be done in accordance with the Secretary of Interior Standard for
Rehabilitation for Historic Structures. Alternative methods from those specified herein may be submitted for approval.
See PART 2 PRODUCTS for information on materials required. See PART 3
EXECUTION for additional details of work required.
4.2.1 Masonry Restoration Service -Upper River Wall Switch Board Building including the Scooter Shed (Base Bid), Upper Land Wall Switch Board
Building (Base Bid) and Office Building- OPTION A
a. Remove existing brick masonry as identified on the drawings.
b. Rebuild parapet as identified on the drawings.
c. Replace any spalled brick within identified parapet areas with new to match existing in shape, size color and texture.
d. Clean and finish.
e. See drawings for more information.
f. 2yr general contractor installation warranty.
4.2.2 Roofing Maintenance and Replacement Services- Office Building- OPTION A, Upper River Wall Switch Board Building including Scooter Shed (Base Bid), Upper Land Wall Switch Board Building (Base Bid):
a. Remove and dispose of existing roofing material down to the roof deck, including ballast and insulation, and dispose of it in a legal manner.
b. Existing metal roof edge flashing shall be demolished.
c. Inspect and repair concrete roof deck as needed. Provide vapor barrier.
d. Supply and install 2 layers of 2" polyisocyanurate foam board insulation with an R-value of R-30, to be fastened to existing deck.
e. Install new 5/8” recovery board.
f. Provide fully adhered EPDM membrane, with a minimum thickness of 90 mil. The lap seams shall be fabricated with 6” seam tape and stripped-in with self-adhering, semi-cured EPDM cover strips.
g. The EPDM membrane shall extend up and over the parapet to below the prefinished stone coping and be secured.
h. Roof assemblies to be installed to resist wind uplift loads per ASCE 7, using tested and listed systems appropriate for site conditions.
i. Provide new copper gutters, scuppers, conductor heads and downspouts that are compatible with EPDM membranes and have a clamping ring and a strainer. Match to existing size and profile. Install concrete splash blocks at all down spot terminations. See drawings for more information.
j. Repair existing copper conductor heads & downspouts as shown on the drawings.
k. Flash all walls and penetrations per manufacturer's specifications.
l. Provide a 20yr no dollar limit manufacturer's warranty and 2yr general contractor installation warranty.
m. Provide new prefinished stone wall caps to match existing profile, color and texture.
n. See drawings for more information.
4.2.3 Roof Reconstruction- Scooter Shed (Base Bid):
a. Remove and dispose of parapet cap, ballast, roofing, rigid insulation, plywood decking, 2x6 roof joists, metal flashing and overlay plywood and steel anchors. Remove CMU and brick parapet as needed.
b. Brace existing brick walls as needed during demolition and reconstruction work.
c. Reconstruct new roof structure with 2x6 treated wood joists install
¼”x 1 ¼” steel anchor.
d. Supply and install new vapor barrier.
e. Supply and install 2 layers of 2" Polyisocyanurate Foam Board Insulation with an R-value of R-30, to be fastened to new deck.
f. Supply and install new 5/8” recovery board.
g. Supply and fully adhere EPDM membrane, with a minimum thickness of 90 mil. The lap seams shall be fabricated with 6” seam tape and stripped-in with self-adhering, semi-cured EPDM cover strips.
h. The EPDM membrane shall extend up and over the parapet to below the prefinished stone coping and be secured.
i. Roof assemblies to be installed to resist wind uplift loads per ASCE 7, using tested and listed systems appropriate for site conditions.
j. Provide and install new copper scuppers, conductor heads and downspouts that are compatible with EPDM membranes and have a clamping ring and a strainer where shown on the drawings. Match to existing size and profile.
Install concrete splash blocks at all down spot terminations.
k. Flash all walls and penetrations per manufacturer's specifications.
l. Provide a 20yr NDL manufacturer's warranty and 2yr general contractor warranty.
m. The contractor shall submit cut sheets, shop drawings and product data for the type of insulation, recovery board, and EPDM and how they intend to install it.
n. Provide new prefinished stone wall caps to match existing profile, color and texture.
o. See drawings for more information.
4.3 PART 1 GENERAL
4.3.1 General Ambient Conditions
Masonry, mortar, and water repellents must not be placed when weather conditions detrimentally affect the quality of the finished product.
4.3.2 Sample mock-ups
Provide 3’x3’ sample mock-ups of the brick masonry repair work. Materials and qualifications shall be submitted and approved prior to the creation of mock-ups.
Mock-ups must demonstrate the methods and quality of workmanship to be performed in each masonry treatment. Retain the approved sample in undisturbed condition, suitably marked, as a standard for judging completed work.
The location and of mock-ups will be as directed on inconspicuous sections of actual construction. No masonry or mortar shall be used in the work until the mock-ups and the represented material and workmanship have been approved.
Provide (1) Mock up for Office building (Option A) and (1) for Switch Board
Buildings, Base bids.
4.3.3 Mortar
Mortar materials must be mixed and color matched to the existing mortar. Place a mix proportion of mortar on two extra brick and allow to dry to compare to existing mortar.
The Contractor may provide several mix proportions at one time or one mix proportion at a time for evaluation. The process shall be repeated until a mix proportion matches the color and texture of the existing mortar.
4.4. PART 2 PRODUCTS
4.4.1. Brick Masonry:
Replacement brick must match as closely as possible, the color, shape, size, texture and appearance of the existing brick. Conform to ASTM C216, Grade SW, Type FBX. Test brick using ASTM C67.
4.4.2. Precast Stone Coping:
Provide in accordance with ASTM C1364. Exposed stone surfaces must have a fine-grained texture similar to natural stone, with no air voids in excess of 1/32 inch. The density of such voids must be less than 3 occurrences per any 1 square inch and not obvious under direct daylight illumination at a 5 foot distance. Reinforce the units as necessary for safe handling and structural stress.
4.4.3 Mortar:
Mortar shall conform to ASTM C270 Type N: 1 part Portland cement (ASTM C150/C150M
Types I, IA, II, IIA, III, IIIA or V) less than 6 months old, 1 part hydrated lime (ASTM
C207), and 6 parts sand (ASTM C144). Mortar is to be prehydrated and color matched
(including sand color) to the existing mortar. Type N mortar is to have a minimum compressive strength at 28 days of 750 psi. Compressive strength of the mortar shall be tested in accordance with ASTM C109. Sampling and testing frequency of mortar shall be once for the mockup and then once per each structure.
Water to be clean, potable, and free from substances which could adversely affect the mortar.
4.4.4 Flashing and Termination Bar:
Do not use lead, lead-coated metal, or galvanized steel. Use any metal listed by SMACNA
1793 for a particular item, unless otherwise indicated. Provide materials, thicknesses, and configurations in accordance with SMACNA 1793 for each material. Different items need not be of the same metal, except that contact between dissimilar metals must be avoided.
4.4.5 Joints and Sealants:
Provide ASTM C920, polyurethane, Type S or M, Grade NS, Class 25, Use NT, M and
A. Color(s) of sealant shall be as selected. Use for perimeter sealing of doors, windows, and walls.
4.4.6 Vapor Retarder
6 mil thick polyethylene sheeting conforming to ASTM D4397 and having a water vapor permeance of 5.72 by 10-8g/Pa.s.m2 one Perm or less when tested in accordance with
ASTM E96/E96M.
4.4.7 Polyisocyanurate Foam Board Insulation:
Provide in accordance with ASTM C1289 REV A Type II, fibrous felt or glass mat membrane both sides, with minimum compressive strength 25 pounds per square inch
(psi).
4.4.8 Recovery Board:
ASTM C1177/C1177M, 0 Flame Spread and 0 Smoke Developed when tested in accordance with ASTM E84, 3450 kPa 500 psi, Class A, non-combustible, 5/8 inch thick, 4 by 8 feet board size.
4.4.9 EPDM Roofing:
Ethylene Propylene Diene Terpolymer (EPDM), ASTM D4637/D4637M, Type I, non-reinforced, 0.090 inch nominal thickness for fully adhered application. Provide membrane with minimum thickness not less than minus 10 percent of the specified thickness value. EPDM membrane thickness specified is exclusive of backing material on the EPDM membrane. Principal polymer used in manufacture of the membrane sheet must be greater than 95 percent EPDM. Width and length of sheet must be maximum width attainable as recommended by the manufacturer to minimize field formed seams in the field of the roof.
4.4.10 Gutter, Conductor Heads, Downspouts and Scuppers:
Factory fabricate components required for a complete roofing system, including gutters, downspouts, scupper, conductor heads and similar items. Copper roof accessories shall match existing copper accessories on site in design and profile. Furnish clip bases that have factory punched or drilled holes for attachment. Make clips used with panel width greater than 305 mm 12 inches from multiple pieces with the allowance for the total thermal movement required to take place within the clip. Provide cleats which are interlockable with the panels and of type and size to meet design requirements.
Accessories must be fabricated of type and thickness of sheet copper complying with
CDA A4050. Submit one sample of each type of flashing, trim, closure, cap, and similar items. Size must be sufficient to show construction and configuration. Copper solder must conform to ASTM B32. Flux must be rosin, muriatic acid neutralized with zinc or an approved soldering paste.
4.5. PART 3 EXECUTION
4.5.1. Demolition:
Comply with federal, state, and local hauling and disposal regulations, and "Contract
Clauses," in accordance with ASSE/SAFE A10.6. Furnish timely notifications of demolition projects to Federal, State, regional, and local authorities in accordance with
40 CFR 61, Subpart M. Notify the Contracting Officer in writing 10 working days prior to commencing work in accordance with 40 CFR 61, Subpart M.
Take necessary precautions to avoid damage to existing items to remain in place, to be reused, or to remain the property of the Government. Repair or replace damaged items as directed. Construct and maintain shoring, bracing, and supports as required. Ensure that structural elements are not overloaded. Increase structural supports or add additional supports required as a result of any cutting, removal, and demolition work performed. Overloading structural elements is prohibited. Furnish supports and reinforcement for existing construction weakened by demolition or removal work.
Repair, reinforce, or structurally replace damage as required and directed at no additional cost to the Government.
Protect electrical and mechanical services, and utilities during construction. Ensure that no elements determined to be unstable are left unsupported and place and secure bracing, shoring, or lateral supports as may be required as a result of any cutting, removal, or demolition work.
Before, during, and after demolition work, continuously evaluate the condition of the structure being demolished and take immediate action to protect all personnel working in and around the project site. Areas, sections, or components of floors, roofs, walls, or other structural elements may not be left standing without sufficient bracing, shoring, or lateral support to prevent collapse or failure while workmen are in the immediate area.
4.5.2. Masonry Repair:
Remove and clean units that have been disturbed after the mortar has stiffened, and relay with fresh mortar. Keep air spaces, cavities, chases, expansion joints, and spaces to be grouted free from mortar and other debris. Select units to be used in exposed masonry surfaces from those having the least amount of chipped edges or other imperfections detracting from the appearance of the finished work. Ensure that units being laid and surfaces to receive units are free of water film and frost. Lay solid units in a no furrowed full bed of mortar. Bevel mortar for veneer wythes and slope down toward the cavity side. Shove units into place so that the vertical joints are tight.
Completely fill vertical joints between solid units with mortar, except where indicated at control, expansion, and isolation joints. Place hollow units so that mortar extends to the depth of the face shell at heads and beds, unless otherwise indicated. Mortar will be permitted to protrude up to 1/2 inch into the space or cells to be grouted.
Provide means to prevent mortar from dropping into the space below or clean grout spaces prior to grouting. In multi-wythe construction with collar joints no more than
3/4 inch wide, bring up the inner wythe not more than 16 inches ahead of the outer wythe. Fill collar joints with mortar during the laying of the facing wythe, and filling shall not lag the laying of the facing wythe by back-buttering each unit as it is laid.
Tool mortar joints when the mortar is thumbprint hard. Tool horizontal joints after tooling vertical joints. Brush mortar joints to remove loose and excess mortar.
Mix and color match to the existing mortar. Place a mix proportion of mortar on two extra brick and allow to dry to compare to existing mortar. Several mix proportions at one time or one mix proportion at a time for evaluation. Repeat process until a mix proportion matches the color and texture of the existing mortar. Multiple colors may be required to match mortar on each building and different sides or areas of the buildings due to the existing mortar being weathered, stained, different install dates or any other conditions that have caused the existing mortar to vary in color throughout the building.
Remove mortar which has softened, loosened, cracked, or loss of depth of 1/4-inch or greater by means of a toothing chisel or pointer's grinder to a uniform depth that is twice the joint width or deeper until sound mortar is reached. Leave a clean, square face at the back of the joint for maximum contact of repointing mortar. Widening of the existing joint(s) is prohibited. Avoid damaging brick edges. Remove dust and debris from the joint by brushing, blowing with air, or rinsing with water.
Wash faces and other exposed surfaces no sooner than 72 hours after completion of the repointing replacement with water applied and a soft bristle brush, then rinsed with clean water. Discolorations which cannot be removed by these procedures, will be considered defective work. Perform cleaning work when temperature and humidity conditions allow the surfaces to dry rapidly. Protect adjacent surfaces from damage during cleaning operations.
Protect from direct sun and high winds for the first 72 hours after installation or from driving rain for the first 24 hours, using plastic sheeting if necessary. Be careful not to create a greenhouse effect by sealing off air movement to protect the wall with plastic.
4.5.3. Re-Roofing:
Remove dusting agents and dirt from membrane and substrate areas where bonding adhesives are to be applied. Apply specified adhesive evenly and continuously to substrate at rates recommended by the roof membrane manufacturer's printed application instructions. When adhesive is spray applied, roll with a paint roller to ensure proper contact and coverage. Do not apply bonding adhesive to surfaces of membrane in seam or lap areas. Allow adhesive to flash off or dry to consistency prescribed by manufacturer before adhering sheets to the substrate. Roll each sheet into adhesive slowly and evenly to avoid wrinkles; broom or roll the membrane to remove air pockets and fish mouths and to ensure full, continuous bonding of sheet to substrate.
Form field lap splices or seams as specified. Check all seams and ensure full lap seal.
Apply lap sealant to all adhesive formed seams and all cut edges of reinforced membrane materials.
Install flashing and flashing accessories as the roof membrane is installed. Apply flashing to cleaned surfaces and as recommended by the roof membrane manufacturer and as specified. Utilize cured EPDM membrane flashing and prefabricated accessory flashings to the maximum extent recommended by the roof membrane manufacturer.
Limit uncured flashing material to reinforcing inside and outside corners and angle changes in plane of membrane, and to flashing scuppers, pourable sealer pockets, and other formed penetrations or unusually shaped conditions as recommended by the roof membrane manufacturer where the use of cured material is impractical.
Extend base flashing not less than 8 inch above roofing surface and as necessary to provide for seaming overlap on roof membrane as recommended by the roof membrane manufacturer.
4.5.4. Cleaning:
No sooner than 72 hours after completion of the re-pointing and masonry replacement work, faces and other exposed surfaces of masonry shall be washed down with water applied with a soft bristle brush, then rinsed with clean water. Discolorations which cannot be removed by these procedures, shall be considered defective work. Perform cleaning work when temperature and humidity conditions allow the surfaces to dry rapidly. Protect adjacent surfaces from damage during cleaning operations.
4.5.5. Protection of Work:
Protect work against damage from subsequent operations.
4.5.6. Defective Work:
Defective work shall be repaired or replaced, as directed, using approved procedures.
4.4.1. Final Inspection:
Following completion of the work, inspect the structure for damage, staining, and other distresses. The patches shall be inspected for cracking, crazing, delamination, unsoundness, staining and other defects.
The finish, texture, color and shade, and surface tolerances of the patches shall be inspected to verify that all requirements have been met. Repair surfaces exhibiting defects as directed.
4.5.7. Site Restoration:
Conduct site restoration. Site restoration to include the removal of construction equipment and materials from the project site and the restoration of the project site to pre-project or better conditions.
SECTION 5 ENVIRONMENTAL PROTECTION REQUIREMENTS
5.1 General Environmental Protection Requirements
Environmental pollution and damage are defined as the presence of chemical, physical, or biological elements or agents that adversely affect human health or welfare; unfavorably alter ecological balances of importance to life; or degrade the environment for aesthetic, cultural or historical purposes. Environmental protection is the prevention and/or control of pollution that develops during execution of this contract. The control of environmental pollution and damage requires consideration of air, water, soil, and land resources; and includes management of visual aesthetics;
noise; solid, chemical, and liquid waste; radiant energy and radioactive materials;
and other pollutants.
5.2 Permits or Licenses
The Contractor shall, without additional expenses to the Government, be responsible for obtaining all necessary licenses and permits. The Contractor shall also be responsible for all damages to persons or property that occur as a result of the Contractor’s negligence and shall take proper safety and health precautions to protect the work, the workers, the public and the property of others. In addition, the
Contractor shall be responsible for all materials delivered and work performed until completion and acceptance of the entire work.
5.3 Hazardous/Carcinogenic Materials
The Contractor, its employees, or subcontractors or their employees shall not bring, produce, use, or store on the job site any hazardous or carcinogenic products without prior written approval by the Government. All hazardous and/or carcinogenic waste transported or generated on-site at any Government facility by the Contractor must be properly disposed of off the site by the Contractor as required by law and at no cost to the Government.
The Contractor shall provide the Government with complete, legible copies of all regulatory notices, violations, citations, etc. received by the Contractor that pertain directly or indirectly to the fulfillment of this contract.
5.4 VOC Requirements
The Contractor shall use on the job site only chemicals and cleaning products which are effective to fulfill the requirements described herein, have the least adverse impact on the environment, that do not exceed the national Volatile Organic
Chemical (VOC) limitations rule(s) published by the U.S. Environmental Protection
Agency (EPA) and comply with all applicable regulatory requirements.
5.5 Hazardous Waste
The Contractor shall initiate Hazardous Waste Management training and enforcement programs to ensure employees are aware that the domestic drains and storm drains shall not be used to dispose of gasoline, paint, thinner, solvents, concentrated cleaning agents, and other toxic material.
The Contractor is responsible for collecting, accumulating, recycling, and/or offsite disposal of its hazardous and toxic waste off the Government’s site in compliance with Federal, state, county and local laws governing hazardous waste storage and disposal.
The Contractor shall provide the KO and the COR with documentation of hazardous materials or wastes that are accumulated, handled, generated, or disposed of by the Contractor’s operations. The documentation shall demonstrate the adequacy of the handling and disposal operations used by the Contractor and will demonstrate that the Contractor activities will not result in contamination of
Government property. The Government shall provide this documentation upon request during periodic environmental inspections of the Contractor’s premises.
The Government shall be copied on all correspondence with regulatory agencies concerning the Contractor’s compliance with environmental regulations.
If the Contractor generates hazardous waste in an amount that makes it subject to state and EPA hazardous waste requirements, the Contractor shall apply for a
Hazardous Waste Generator Identification Number. Hazardous waste shall be shipped off the Government site using the Contractor’s Hazardous Waste Generator
Identification Number documented on a complete and properly signed Uniform
Hazardous Waste Manifest. The Contractor shall be required to submit an Annual
Hazardous Waste Report to the State of which the work is completed.
The Contractor shall at the start of the contract, implement a written hazardous waste spill contingent plan listing material used, spill prevention procedures, containment equipment and procedures to be used in the event of spill, personnel protective equipment requirements, notification procedures, in accordance with the Resource
Conservation and Recovery Act (RCRA) and the Occupational Safety and Health
Administration (OSHA) regulations.
SECTION 6 SAFETY REQUIREMENTS
6.1 General Safety Requirements
All work under this contract shall comply with the latest version of the US Army
Corps of Engineers Safety and Health Requirements Manual, EM 385-1-1 and the
Occupational Safety and Health Act (OSHA) standards in effect on the date of the solicitation. No separate payment will be made for compliance with EM 385-1-1, nor for compliance with any of the other safety-related requirements.
6.2 Safety Regulatory Compliance
The Contractor and each of its employees shall comply with all applicable local, state, and federal rules, regulations, and practices.
6.3 Contractor Negligence
The Contractor shall also be responsible for all injury to persons or damages to property that occurs as a result of the Contractor’s negligence and shall take proper safety and health precautions to protect the work, the workers, the public, and the property of others.
6.4 Responsibility
The Contractor shall perform all its activities pursuant to this contract in a safe manner. The Contractor shall assume responsibility on the job site for the actions of all its personnel and Subcontractor(s) who are associated with performance on this contract.
6.5 Personal Protective Equipment
The Contractor shall provide and ensure that all its personnel at the job site properly wear all applicable safety devices and apparel. These devices and apparel shall be provided by the Contractor at no cost to the Government. Personnel shall have the appropriate personal protection equipment, such as eye protection, gloves, boots, and clothing as mandated by OSHA, Federal, State, and Local standards.
6.6 Government Safety Inspection
The Government shall have the right to inspect all areas for safety violations at its discretion, direct the Contractor to make immediate improvement of conditions and/or procedures, and/or stop the work if other hazards are deemed to exist.
6.7 Work Stoppage
In the event that the Government should elect to stop work because of an existing safety hazard on the job site after the Contractor has been notified and provided ample time to correct, the Contractor shall bear all costs for eliminating the hazard(s) and shall not be granted compensation for the work stoppage. The Contractor shall be responsible for all additional expenses incurred.
6.8 Vehicle Operation
The operation of the Contractor’s vehicles by the Contractor’s employees on or about Government property shall conform to regulations and safe driving practices.
6.9 Equipment and Tool Inspection
The Contractor shall inspect all powered equipment daily before operations for signs of wear as well as potential safety hazards. The Contractor shall immediately remove from service on the job sites all equipment including extension cords which are potentially unsafe, damaged, inoperable and/or do not meet the manufacturers operational specifications.
6.10 Safety Data Sheets
The Contractor shall obtain Safety Data Sheets (SDS) for all materials or supplies as required by Federal, State, or Local regulations and policies and have them available at the job site during performance of the work.
SECTION 7 SECURITY REQUIREMENTS
General security requirements and guidance: The security requirements described below apply to all contract personnel (including employees of the prime
Contractor (“Contractor”) and all subcontractor employees) supporting the performance requirements of this contract. The Contractor is responsible for compliance with these security requirements. Questions regarding security matters shall be addressed to the designated Government representative (e.g., Contracting
Officer Representative (COR), Requiring Activity (RA) representative, or
Contracting Officer (if a COR or other RA representative is not appointed)).
Contract personnel are critical to the overall security and safety of US Army Corps of Engineers (USACE) installations, facilities and activities, and security awareness training contributes to those efforts. The Department of Defense (DoD) and Army security training requirements specified below, if applicable, are performance requirements; all applicable contract personnel shall complete initial training within
30 days of contract award or the date new contract personnel begin performance on the contract. Within five business days from the completion of training, the
Contractor shall provide written documentation (e.g., email or memorandum) to the
Government representative. The documentation shall include the names of contract personnel trained and which training they completed; the Contractor shall maintain training records as part of their contract files and be prepared to provide copies of training certificates to the Government representative. Contractor personnel and vehicles are subject to search when entering federal installations. Additionally, all contract personnel shall comply with Force Protection Condition (FPCON) measures, Random Antiterrorism Measures (commonly referred to as “RAMs”), and Health Protection Condition (HPCON) measures. The Contractor is responsible for meeting performance requirements during elevated FPCON and/or HPCON levels in accordance with applicable RA plans and procedures --this includes identifying mission essential and non-mission essential personnel. In addition to the changes otherwise authorized by the changes clause of this contract, should the
FPCON or HPCON levels at any individual facility or installation change, the
Government may implement security changes that affect contract personnel. The
Contractor shall ensure all contract personnel are aware of their security responsibilities, including any site-specific requirements identified in local policies or procedures.
Antiterrorism (AT) Level I training: All contract personnel requiring routine access to Army installations, facilities, and controlled access areas, or requiring network access shall complete initial and annual refresher AT Level I awareness training. Online AT Level I awareness training is available at https://jko.jten.mil/
(website subject to change).
For Access and General Protection Policy and Procedures. All Contractors and sub- contractor employees shall comply with installation and facility access guidelines and rules as stated herein. Contractor workforce must comply with all personal identity verification requirements as directed by Department of Defense, Department of the Army Headquarters, Rock Island District and/or local policy. In addition to the changes otherwise authorized by the Changes clause of this contract, should the Force Protection Condition (FPCON) at any installation or facility change, the Government may require changes in Contractor security matters or processes.
Suspicious Activity Reporting training (e.g. iWATCH, CorpsWatch, or See
Something, Say Something): All contract personnel shall receive initial and annual refresher training from the RA representative on the local suspicious activity reporting program. This locally developed training provides contract personnel with general information on suspicious behavior, and guidance on reporting suspicious activity to the project manager, security representative or law enforcement entity.
Training requirements for the protection of sensitive information: All contract personnel with access to critical information (as identified in the RA's OPSEC
Program) shall complete initial and annual refresher OPSEC Level I Awareness training, which is available at the following websites: https://www.iad.gov/ioss/, or http://www.cdse.edu/catalog/operations- security.html (websites subject to change).
All contract personnel with access to Controlled Unclassified Information (CUI) shall complete initial and annual refresher CUI training in accordance with applicable Army policy.
Escorting in classified and/or sensitive areas: In accordance with applicable regulations, all contract personnel who do not possess the appropriate security clearance or access privileges will be escorted in areas where they may be exposed to classified information or operations, sensitive information or activities, or restricted areas.
Physical Security and Access Control Requirements
a. Overview: Contractor personnel requiring physical access to a USACE facility must comply with the access control procedures of that location. Contractor personnel requiring unescorted access to meet Contract performance requirements will be vetted by the USACE Rock Island District Security and Law Enforcement
Office (CEMVR-SL) using the National Crime Information Center Interstate
Identification Index (NCIC-III) and Terrorist Screening Database (TSDB).
Contractor personnel must comply with personal identity verification requirements as specified. Contractor personnel who do not meet requirements for unescorted access to Government installations must coordinate escorted access with the
Contracting Officer. Contractor personnel who receive keys, access cards, or lock combinations that provide access to Government-owned property must comply with USACE key and lock control procedures.
b. Contractor personnel requiring unescorted access to the Rock Island Arsenal and not in possession of a DoD ID card, Federal PIV, or an installation access pass must undergo a NCIC-III background check and be issued an installation access pass for up to one year or the period of performance of the Contract, whichever is shorter. Submit a Rock Island Arsenal Access Request Form for
Contractor personnel requiring access to the installation at least three days prior to arriving at the Rock Island Arsenal. The Rock Island Arsenal Access
Request Form can be found at https://home.army.mil/ria/index.php/download_file/force/465/1.
Submit forms via e-mail to usarmy.ria.imcom.mbx.usag-access-request@mail.mil, or mail to:
Visitor Welcome Center
Rock Island Arsenal
23 Prospect Drive
Moline, IL 61265
When arriving at the Rock Island Arsenal for the first time, report to the Rock
Island Arsenal Visitor Welcome Center located just outside the Moline Gate.
Final processing of the visitor badge will take approximately 5 to 8 minutes per employee.
c. Definition: For the purposes of this Contract, USACE facilities are defined as any USACE owned or leased property for which entry is controlled and limited to authorized USACE employees, Contractors, and official visitors.
d. Procedures:
(1) Contractor personnel may have unescorted access within controlled areas upon completion of an adjudication of fitness by CEMVR-SL and entry onto an access control list (ACL) for the facility/project.
Submit background checks conducted by a bonded third party within the last six months of Notice to Proceed and authorize reports to be provided to CEMVR-SL by the third party.
Background checks must consist of a check of NCIC-III and TSDB when available. Individuals may be denied access to Rock Island District controlled facilities and/or property if the results of the third party
NCIC-III equivalent background check gives an indication that a person may present a threat to the good order, discipline, safety, or security of the facility. This information includes, but is not limited to a person who has:
(a) The background investigation contains criminal arrest information about the individual that causes the senior commander to determine that the person presents a threat to the good order, discipline, or health and safety on the installation.
(b) A claimed identity that cannot be verified based on the reasonable belief that the person submitted fraudulent identity information in the attempt to gain access.
(c) Current arrest warrant in NCIC, regardless of the offense or violation.
(d) Current bar from entry or access to another Federal installation or facility.
(e) Conviction of crimes encompassing sexual assault, armed robbery, rape, child molestation, production or possession of child pornography, trafficking in humans, or drug possession with intent to sell or distribute.
(f) Conviction for espionage, sabotage, sedition, treason, terrorism, or murder.
(g) Being registered as a sex offender.
(h) Felony conviction within the last 10 years regardless of the offense or violation.
(i) Felony conviction for a firearms or explosives violation regardless of when the conviction occurred.
(j) Engaged in acts or activities designed to overthrow the U.S.
Government by force.
(k) Been identified as known to be, or is suspected of being, a terrorist or belonging to an organization with known links to terrorism or support of terrorist activity.
(2) Short term Contractor personnel working at the USACE facility or project for less than 15 calendar days may be escorted at the USACE facility by a USACE employee or other Contractor personnel that is on the ACL for the facility or project. Names and dates of work for short term Contractor personnel must be submitted to CEMVR-SL via e-mail at cemvr-sl@usace.army.mil to be added to the ACL for the period they will be working at the facility.
e. In addition to the submitted background checks, supplemental agency checks may be performed at the discretion of CEMVR-SL personnel. Cooperate and ensure that Contractor personnel provide documentation required to complete these checks. Any person lacking proper identification credentials or deemed a security threat may be denied access to the project. Such action in no way relieves the Contractor from performance of the Contract. USACE Rock
Island District retains the right to deny Contractor personnel from working on a
USACE Rock Island District Contract based on final background investigation results.
f. Contractor personnel denied access based upon derogatory information from the NCIC-III or equivalent check may apply to the District Commander for a waiver. To obtain a waiver, Contractor personnel must:
(1) Obtain a certified copy of their complete criminal history including arrests and convictions.
(2) Obtain a letter of support from their USACE sponsor.